- CN106975896B CN106975896B CN201710313659.6A CN201710313659A CN106975896B CN 106975896 B CN106975896 B CN 106975896B CN 201710313659 A CN201710313659 A CN 201710313659A CN 106975896 B CN106975896 B CN 106975896B
- Authority
- CN
- China
- Prior art keywords
- permanent magnetic
- sleeve
- wind
- electricity generation
- production method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B23—MACHINE TOOLS; METAL-WORKING NOT OTHERWISE PROVIDED FOR
- B23P—METAL-WORKING NOT OTHERWISE PROVIDED FOR; COMBINED OPERATIONS; UNIVERSAL MACHINE TOOLS
- B23P15/00—Making specific metal objects by operations not covered by a single other subclass or a group in this subclass
Landscapes
- Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Rolls And Other Rotary Bodies (AREA)
- Manufacture Of Motors, Generators (AREA)
Abstract
本发明公开了一种6MW风电转子房的生产方法,包括:a、将原料制成半成品工件的步骤;b、将半成品工件在恒温环境下机加工成型的步骤;所述步骤b在夹具中进行,所述夹具包括套筒和卡盘,半成品工件置于套筒中,底部由卡盘卡住,在套筒的顶部设有若干第一永磁吸盘,若干第一永磁吸盘均匀分布在套筒的顶部;在套筒的中部设有若干第二永磁吸盘,第二永磁吸盘均匀分布在套筒的中部,且若干第二永磁吸盘在同一个面上,第一永磁吸盘和第二永磁吸盘吸住半成品工件的外壁。本发明能够有效的保证生产出来的转子房的精度。
Description
技术领域
本发明涉及风电设备领域,尤其是涉及一种6MW风电转子房的生产方法。
背景技术
现有的转子房在机加工时,需要分别通过车床、铣床和钻孔设备来加工,因此根据不同的加工需求,需要更换不同的夹具,而在更换夹具之后,极难保证精度。而且现有的夹具均只是将工件夹住,为了使工件在机加工时能够稳定,夹具需要使用较大的力,尤其是在铣槽时,铣刀从侧面进入铣槽,由于工件为薄壁结构,被大力夹住的工件极容易变形,大大的影响了精度,甚至会使工件报废。
发明内容
本发明为了解决目前转子房生产时容易变形,对精度难以保证的问题,为此提供了一种6MW风电转子房的生产方法,包括: a、将原料制成半成品工件的步骤; b、将半成品工件在恒温环境下机加工成型的步骤; 所述步骤b在夹具中进行,所述夹具包括套筒1和卡盘3,半成品工件2置于套筒1中,底部由卡盘3卡住,在套筒1的顶部设有若干第一永磁吸盘4,若干第一永磁吸盘4均匀分布在套筒1的顶部;在套筒1的中部设有若干第二永磁吸盘5,第二永磁吸盘5均匀分布在套筒1的中部,且若干第二永磁吸盘5在同一个面上,第一永磁吸盘4和第二永磁吸盘5吸住半成品工件2的外壁。
本发明6MW风电转子房的生产方法,所述步骤a包括:原料下料→筒体卷圆→卷两个锥度不同的锥度盘→粗车出内、外锻件→将两个锥度盘的内圈和外圈分别与内、外锻件焊接→将外锻件与筒体焊接→热处理。
本发明6MW风电转子房的生产方法,两个锥度盘的锥度分别为9.1和20.5。
本发明6MW风电转子房的生产方法,所述热处理温度在500℃-600℃之间。
本发明6MW风电转子房的生产方法,机加工包括车筒体上表面和内锻件表面→筒体内壁铣梯形斜槽→内锻件钻孔。
本发明6MW风电转子房的生产方法,梯形斜槽通过铣刀由上往下倾斜1.6°铣出。
本发明6MW风电转子房的生产方法,所述第一永磁吸盘4的数量是第二永磁吸盘5的两倍。
本发明的有益效果是:
本发明将半成品工件放置在恒温环境下的夹具中进行机加工,通过卡盘和两组永磁吸盘的配合,将工件向外拉紧,再从上往下进行机加工时,工件能够保证不变形,而且通过该夹具固定之后,能在该夹具内完成机加工所有工序,无需再另外更换位置加工,从而保证了工件的精度。而且在恒温条件下,能够保证无论是在何种加工方式下,温度始终一致,避免了热变形,进一步提高了工件的精度。
附图说明
本发明将通过例子并参照附图的方式说明,其中:
图1是夹具吸住工件后的示意图;
图2是图1的剖视图。
具体实施方式
现在结合附图对本发明作进一步详细的说明。这些附图均为简化的示意图,仅以示意方式说明本发明的基本结构,因此其仅显示与本发明有关的构成。
一种6MW风电转子房的生产方法,包括:a、将原料制成半成品工件的步骤;b、将半成品工件在恒温环境下机加工成型的步骤。
上述步骤a包括:原料下料→筒体卷圆→卷锥度分别为9.1和20.5的两个锥度盘→粗车出内、外锻件→将两个锥度盘的内圈和外圈分别与内、外锻件焊接→将外锻件与筒体焊接→在500℃-600℃之间热处理。
步骤b在夹具中进行,如图1和图2所示,夹具包括套筒1和卡盘3,半成品工件2置于套筒1中,底部由卡盘3卡住,在套筒1的顶部设有若干第一永磁吸盘4,若干第一永磁吸盘4均匀分布在套筒1的顶部;在套筒1的中部设有若干第二永磁吸盘5,第二永磁吸盘5均匀分布在套筒1的中部,且若干第二永磁吸盘5在同一个面上,所述第一永磁吸盘4的数量是第二永磁吸盘5的两倍,第一永磁吸盘4和第二永磁吸盘5吸住半成品工件2的外壁。
机加工包括车筒体上表面和内锻件表面→筒体内壁铣梯形斜槽→内锻件钻孔,分别使用车刀、铣刀和钻头,梯形斜槽则通过铣刀由上往下倾斜1.6°铣出。
本发明将半成品工件放置在夹具中进行机加工,通过卡盘和两组永磁吸盘的配合,将工件向外拉以张紧,再从上往下进行机加工时,工件能够保证不变形,而且通过该夹具固定之后,能在该夹具内完成机加工所有工序,无需再另外更换位置加工,从而保证了工件的精度。而且在恒温的条件下,能够保证无论是在何种加工方式下,温度始终一致,避免了热变形,进一步提高了工件的精度。
上述依据本发明为启示,通过上述的说明内容,相关工作人员完全可以在不偏离本项发明技术思想的范围内,进行多样的变更以及修改。本项发明的技术性范围并不局限于说明书上的内容,必须要根据权利要求范围来确定其技术性范围。
Claims (6)
1.一种6MW风电转子房的生产方法,其特征在于,包括:
a、将原料制成半成品工件的步骤;
b、将半成品工件在恒温环境下机加工成型的步骤;
所述步骤a包括:原料下料→筒体卷圆→卷两个锥度不同的锥度盘→粗车出内、外锻件→将两个锥度盘的内圈和外圈分别与内、外锻件焊接→将外锻件与筒体焊接→热处理;
所述步骤b在夹具中进行,所述夹具包括套筒(1)和卡盘(3),半成品工件(2)置于套筒(1)中,底部由卡盘(3)卡住,在套筒(1)的顶部设有若干第一永磁吸盘(4),若干第一永磁吸盘(4)均匀分布在套筒(1)的顶部;在套筒(1)的中部设有若干第二永磁吸盘(5),第二永磁吸盘(5)均匀分布在套筒(1)的中部,且若干第二永磁吸盘(5)在同一个面上,第一永磁吸盘(4)和第二永磁吸盘(5)吸住半成品工件(2)的外壁。
2.根据权利要求1所述的6MW风电转子房的生产方法,其特征在于,两个锥度盘的锥度分别为9.1和20.5。
3.根据权利要求1所述的6MW风电转子房的生产方法,其特征在于,所述热处理温度在500℃-600℃之间。
4.根据权利要求1所述的6MW风电转子房的生产方法,其特征在于,机加工包括车筒体上表面和内锻件表面→筒体内壁铣梯形斜槽→内锻件钻孔。
5.根据权利要求4所述的6MW风电转子房的生产方法,其特征在于,梯形斜槽通过铣刀由上往下倾斜1.6°铣出。
6.根据权利要求1所述的6MW风电转子房的生产方法,其特征在于,所述第一永磁吸盘(4)的数量是第二永磁吸盘(5)的两倍。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710313659.6A CN106975896B (zh) | 2017-05-05 | 2017-05-05 | 6mw风电转子房的生产方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710313659.6A CN106975896B (zh) | 2017-05-05 | 2017-05-05 | 6mw风电转子房的生产方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106975896A CN106975896A (zh) | 2017-07-25 |
CN106975896B true CN106975896B (zh) | 2019-04-23 |
Family
ID=59341119
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710313659.6A Active CN106975896B (zh) | 2017-05-05 | 2017-05-05 | 6mw风电转子房的生产方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106975896B (zh) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108436136B (zh) * | 2018-05-18 | 2023-10-03 | 江苏振江新能源装备股份有限公司 | 3mw永磁风力发电机的定子支架钻孔装置 |
CN110434636A (zh) * | 2019-08-12 | 2019-11-12 | 江苏振江新能源装备股份有限公司 | 一种用于加工转子的车铣夹具 |
CN113878280B (zh) * | 2021-09-22 | 2023-05-02 | 江苏振江新能源装备股份有限公司 | 一种大兆瓦转子房锥体的防焊接变形装置 |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP5366651B2 (ja) * | 2009-05-19 | 2013-12-11 | 東芝機械株式会社 | 薄肉円筒状ワークの保持治具および薄肉円筒状ワークの加工方法およびシート・フィルム成形ロール |
CN202780539U (zh) * | 2012-07-25 | 2013-03-13 | 南车戚墅堰机车有限公司 | 薄壁环类工件内孔加工装置 |
CN202985151U (zh) * | 2012-12-20 | 2013-06-12 | 贵州航天乌江机电设备有限责任公司 | 一种加工薄壁环形零件的工装 |
CN203141365U (zh) * | 2013-04-07 | 2013-08-21 | 长春大学 | 大型薄壁圆筒定形构件 |
CN203542168U (zh) * | 2013-09-18 | 2014-04-16 | 中国电子科技集团公司第四十八研究所 | 一种大口径薄壁筒外圆加工工装 |
KR101553168B1 (ko) * | 2014-06-24 | 2015-09-14 | 최태광 | 잔류 자기를 최소화한 자성체 홀딩 장치 |
-
2017
- 2017-05-05 CN CN201710313659.6A patent/CN106975896B/zh active Active
Also Published As
Publication number | Publication date |
---|---|
CN106975896A (zh) | 2017-07-25 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106975896B (zh) | 6mw风电转子房的生产方法 | |
CN104295608B (zh) | 关节轴承内圈加工方法 | |
WO2011093215A1 (ja) | ころの製造方法 | |
CN104148894A (zh) | 薄壁深孔焊接件加工方法 | |
CN103522011B (zh) | 一种针织圆机大盘的加工工艺 | |
CN103447566A (zh) | 一种定位器 | |
CN105834481B (zh) | 采用加长镗刀杆在普通镗床加工超长同心阶梯通孔的方法 | |
CN103978256A (zh) | 一种利用车床批量加工弧形槽的方法及工装 | |
CN103028907A (zh) | 一种端盖加工工艺 | |
CN104128759A (zh) | 一种有利于主轴表面硬度的车床主轴加工工艺 | |
CN104014989A (zh) | 一种半圆孔加工方法 | |
WO2018143606A3 (ko) | 브로칭 머신 및 이를 포함하는 선반 | |
CN111299967B (zh) | 一种金属螺旋筋的加工方法 | |
CN106392485A (zh) | 圆兜孔保持架加工方法 | |
CN103084809A (zh) | 一种三棱孔加工方法 | |
CN105345057B (zh) | 一种减小切削扭矩的中心孔基准修正方法 | |
CN206010005U (zh) | 一种新型可加工角度键槽的拉床胎具 | |
CN104400634A (zh) | 一种薄壁轴承端面的磨削装置及方法 | |
CN104476127B (zh) | 一种缸头加工工艺 | |
CN103433689A (zh) | 一种棒形铁心的加工工艺 | |
CN105302060B (zh) | 一种内回转表面正交车铣加工刀具长度补偿算法 | |
CN103692154A (zh) | 圆柱形轴上加工径向通孔或径向盲孔的方法 | |
CN102528076A (zh) | 特大型铜保持架成型加工的优化工艺 | |
CN105643209A (zh) | 一种弧面曲柄的加工方法 | |
CN105743305A (zh) | 小型电机壳体的加工工艺 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |