CN106884384B - 一种山区叠合梁斜拉桥桥面吊机法 - Google Patents

一种山区叠合梁斜拉桥桥面吊机法 Download PDF

Info

Publication number
CN106884384B
CN106884384B CN201710118437.9A CN201710118437A CN106884384B CN 106884384 B CN106884384 B CN 106884384B CN 201710118437 A CN201710118437 A CN 201710118437A CN 106884384 B CN106884384 B CN 106884384B
Authority
CN
China
Prior art keywords
steel girder
sections
steel
girder
crane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710118437.9A
Other languages
English (en)
Other versions
CN106884384A (zh
Inventor
赵伟
张胜林
樊永波
王骞
李忠贤
许高
虞海
欧阳斌
张乙彬
谭继光
张营
岳琳
肖世钦
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUIZHOU BRIDGE CONSTRUCTION GROUP CO Ltd
Original Assignee
GUIZHOU BRIDGE CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUIZHOU BRIDGE CONSTRUCTION GROUP CO Ltd filed Critical GUIZHOU BRIDGE CONSTRUCTION GROUP CO Ltd
Priority to CN201710118437.9A priority Critical patent/CN106884384B/zh
Publication of CN106884384A publication Critical patent/CN106884384A/zh
Application granted granted Critical
Publication of CN106884384B publication Critical patent/CN106884384B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D11/00Suspension or cable-stayed bridges
    • E01D11/04Cable-stayed bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

本发明公开了一种山区叠合梁斜拉桥桥面吊机法,该发明在钢主梁0﹟段、钢主梁1﹟段和钢主梁2﹟段的节段上设置桥面钢主梁预拼场,并将钢主梁部件运输至桥面钢主梁预拼场上,龙门吊将钢主梁部件预拼成整节段,轨道运梁平车运输至主梁前端,悬臂吊机整体起吊、旋转、安装钢主梁标准节段,中跨侧和边跨侧各自完成预拼和整体安装作业,互不干扰,桥面钢主梁整体安装方法不仅解决了施工安全、质量和进度问题,还解决辅助墩对整体安装的干扰问题。该发明的施工方式在现有技术的基础上预计节约工期两天,效率高、减少施工成本、工程量小、施工安全、施工质量高。

Description

一种山区叠合梁斜拉桥桥面吊机法
技术领域
本发明涉及一种桥面吊机法,特别是一种山区叠合梁斜拉桥桥面吊机法。
背景技术
随着我国交通建设的发展,大跨度钢结构斜拉桥出现得越来越多,由于斜拉桥因其跨越能力大,造型美观,今年来得到飞速发展,而桥面吊机架设施工是大跨度斜拉桥钢主梁施工非常常见的一种施工方式,尤其在山区跨度施工时,由于主塔附件场地狭小,只能作为材料堆放场地,难以提供较好的预拼装场地。同时,由于部件运输和悬臂拼装作业高度达上百米甚至更高,塔下预拼作业危险性较高。且架设高度大、施工困难,还存在安全防护困难,成本投入极大的问题,对于大跨度斜拉桥钢主梁采用桥面吊机悬臂架设施工方法,常规方法为:桥面吊机从材料堆放场地将钢主梁部件吊运至桥面上,对各个钢部件悬臂逐次拼装成整节段,这样的施工方式施工工期较长、效率低、成本高、工序较为繁琐、困难,而且施工工程量大,安全风险高。
发明内容
本发明的目的在于,提供了一种山区叠合梁斜拉桥桥面吊机法,该山区叠合梁斜拉桥桥面吊机法具有减少工期、降低施工成本和提高施工安全和质量的特点。
本发明的技术方案:具体包括以下步骤:
(a)安装钢主梁0﹟段;
(b)在边跨平台位置处用钢主梁部件拼装成多个钢主梁;
(c)从边跨处以钢主梁0﹟段为起点,依次整体吊装、运输、安装边跨侧和中跨侧钢主梁(3)1--N﹟段,同时依次安装斜拉索,其中N≥2;
(d)在钢主梁0﹟段、钢主梁1﹟段和钢主梁2﹟段的节段上设置桥面钢主梁预拼场,并将钢主梁部件运输至桥面钢主梁预拼场上;
(e)在桥面钢主梁预拼场上用钢主梁部件拼装钢主梁N+1﹟段,然后通过轨道运梁平车运输至钢主梁N﹟段前端,再通过悬臂吊机起吊、旋转,安装钢主梁N+1﹟段;
(f)重复步骤e,完成N+2、N+3……﹟段的安装,直至整个桥面拼装完成。
前述的山区叠合梁斜拉桥桥面吊机法,所述步骤中,钢主梁1--N﹟段的安装方法为:钢主梁0﹟段上安装悬臂吊机和悬臂吊机小车,由边跨侧先起吊中跨侧的钢主梁1﹟段至桥面位置,将钢主梁1﹟段旋转90度,悬臂吊机小车移动到中跨侧,钢主梁1﹟段再旋转90度,放置钢主梁1﹟段就位后与钢主梁0﹟段对接,同时预先将桥面板吊至桥面处,并安装钢主梁1﹟段的斜拉索,悬臂吊机安装桥面板并现浇湿接缝,张拉钢主梁1﹟段的斜拉索;并以同样的方法安装钢主梁N﹟段。
前述的山区叠合梁斜拉桥桥面吊机法,所述步骤中,钢主梁N+1﹟段在钢主梁预拼场内进行整体拼装,钢主梁N+1﹟段整体由轨道运梁平车运输至钢主梁N﹟段前端,由悬臂吊机的悬臂吊机小车整体起吊、运输至安装位置,将钢主梁3N+1﹟段旋转90度,下放钢主梁N+1﹟段就位,并与已架设钢主梁N﹟段进行对接,安装钢主梁N+1﹟段的斜拉索,悬臂吊机安装桥面板并现浇湿接缝,张拉钢主梁N+1﹟段的斜拉索。
前述的山区叠合梁斜拉桥桥面吊机法,所述钢主梁N﹟段安装完成后的混凝土养护期间,安装桥面钢主梁预拼场设施和悬臂运输门架,运转钢主梁部件至桥面进行悬臂安装作业。
前述的山区叠合梁斜拉桥桥面吊机法,所述桥面钢主梁预拼场上安装龙门吊,钢主梁M+1﹟段上设置悬臂运输门架,其中M≥1。
前述的山区叠合梁斜拉桥桥面吊机法,所述钢主梁0﹟段设置于钢平台的上部。
本发明的有益效果:在钢主梁0﹟段、钢主梁1﹟段和钢主梁2﹟段上设置桥面钢主梁预拼场,桥面钢主梁预拼场设置于桥面上,龙门吊将钢主梁部件预拼成整节段,轨道运梁平车运输至主梁前端,悬臂吊机整体起吊、旋转、安装钢主梁,中跨侧和边跨侧各自完成预拼和整体安装作业,互不干扰,桥面钢主梁预拼场整体安装方法不仅解决了施工安全、质量和施工进度问题,还解决辅助墩对整体安装的干扰问题。该发明的施工方式在现有技术的基础上节约工期两天,效率高、减少施工成本、工程量小、施工安全、施工质量高。
附图说明
图1是本发明钢主梁整体安装工艺结构示意图;
图2是本发明钢主梁2~5﹟段安装示意图;
图3是本发明钢主梁1﹟段安装示意图;
图4是本发明桥面钢主梁预拼场平面结构示意图。
图5是本发明钢主梁整体悬臂安装图;
图6是本发明钢主梁整体悬臂安装工艺流程图。
附图中的标记为: 1-桥面钢主梁预拼场,2-悬臂吊机,3-钢主梁,31-钢主梁0﹟段,32-钢主梁1﹟段,33-钢主梁2﹟段,4-悬臂运输门架,5-钢主梁部件,6-斜拉索,7-钢平台,8-龙门吊,9-悬臂吊机小车,10-运梁轨道小车,a-边跨,b-中跨,c-运输方向,d-旋转方向。
具体实施方式
下面结合附图和实施例对本发明作进一步的说明,但并不作为对本发明限制的依据。
一种山区叠合梁斜拉桥桥面吊机法,构成如图1-6所示,具体包括以下步骤:
(a)安装钢主梁0﹟段31;
(b)在边跨平台位置处用钢主梁部件5拼装成多个钢主梁3;边跨平台为在边跨位置处设置钢主梁部件5拼装平台;
(c)从边跨处以钢主梁0﹟段31为起点,依次整体吊装、运输、安装边跨侧和中跨侧钢主梁(3)1--N﹟段,同时依次安装斜拉索6,其中N≥2;
(d)在钢主梁0﹟段31、钢主梁1﹟段32和钢主梁2﹟段33的节段上设置桥面钢主梁预拼场1,并将钢主梁部件5运输至桥面钢主梁预拼场1上;
(e)在桥面钢主梁预拼场1上用钢主梁部件5拼装钢主梁3N+1﹟段,然后通过轨道运梁平车10运输至钢主梁3N﹟段前端,再通过悬臂吊机2起吊、旋转,安装钢主梁3N+1﹟段;
(f)重复步骤e,完成N+2、N+3……﹟段的安装,直至整个桥面拼装完成。
所述步骤c中,钢主梁31-N﹟段的安装方法为:钢主梁0﹟段31上安装悬臂吊机2和悬臂吊机小车9,由边跨侧先起吊中跨侧的钢主梁1﹟段32至桥面位置,将钢主梁1﹟段32旋转90度,悬臂吊机小车9移动到中跨侧,钢主梁1﹟段32再旋转90度,放置钢主梁1﹟段32就位后与钢主梁0﹟段31对接,同时预先将桥面板吊至桥面处,并安装钢主梁1﹟段32的斜拉索6,悬臂吊机2安装桥面板并现浇湿接缝,张拉钢主梁1﹟段32的斜拉索6;并以同样的方法安装钢主梁3N﹟段。
所述步骤e中,钢主梁3N+1﹟段在钢主梁预拼场1内进行整体拼装,钢主梁3N+1﹟段整体由轨道运梁平车10运输至钢主梁3N﹟段前端,由悬臂吊机2的悬臂吊机小车9整体起吊、运输至安装位置,将钢主梁3N+1﹟段旋转90度,下放钢主梁3N+1﹟段就位,并与已架设钢主梁3N﹟段进行对接,安装钢主梁3N+1﹟段的斜拉索6,悬臂吊机2安装桥面板并现浇湿接缝,张拉钢主梁3N+1﹟段的斜拉索6。
所述钢主梁N﹟段安装完成后的混凝土养护期间,安装桥面钢主梁预拼场1设施和悬臂运输门架4,运转钢主梁部件5至桥面进行悬臂安装作业。
所述桥面钢主梁预拼场1上安装龙门吊8,钢主梁M+1﹟段上设置悬臂运输门架,其中M≥1。
所述钢主梁0﹟段设置于钢平台7的上部。
本发明的工作原理为:本发明在钢主梁0﹟段31、钢主梁1﹟段32和钢主梁2﹟段33的节段上设置桥面钢主梁预拼场1,并将钢主梁部件5运输至桥面钢主梁预拼场1上,首先,先安装钢主梁0﹟段31,从边跨处以钢主梁0﹟段31为起点,依次整体吊装、运输、安装边跨侧和中跨侧钢主梁31--N﹟段,同时依次安装斜拉索6,其中N≥2;在桥面钢主梁预拼场1上用钢主梁部件5拼装钢主梁3N+1﹟段,通过轨道运梁平车10运输至钢主梁3N﹟段前端,通过悬臂吊机2起吊、旋转,安装钢主梁3N+1﹟段;如,钢主梁1﹟段32的安装方法为:钢主梁0﹟段31上安装悬臂吊机2和悬臂吊机小车9,由边跨侧先起吊中跨侧的钢主梁1﹟段32至桥面位置,旋转90度,悬臂吊机小车9移动到中跨侧,再旋转90度,放置钢主梁1﹟段32就位后与钢主梁0﹟段31对接,同时预先将桥面板吊至桥面处,并安装钢主梁1﹟段32的斜拉索6,悬臂吊机2安装桥面板并现浇湿接缝,张拉钢主梁1﹟段32的斜拉索6;以钢主梁3的N+1﹟段的安装方法相同,完成N+2、N+3……﹟段的安装,直至整个桥面拼装完成。
具体工艺步骤如下:
(1)安装钢主梁0﹟段31成型;
(2)钢主梁0﹟段31上安装边跨及中跨悬臂吊机2,从边跨方向以“先中后边”顺序整体吊装钢主梁1﹟段32,同时预先将桥面板吊至桥面处;
(3)塔吊安装钢主梁1﹟段32的斜拉索6,悬臂吊机2安装桥面板并现浇湿接缝,张拉斜拉索;
(4)边跨及中跨悬臂吊机2解除临时连接并前移,以钢主梁1﹟段32施工方法进行钢主梁2﹟段33施工,其间依靠轨道运梁平车10转运整节段钢主梁3和桥面板;
(5)塔吊及悬臂吊机2配合安装钢主梁2﹟段33的斜拉索6,悬臂吊机2安装桥面板并现浇湿接缝,张拉斜拉索6;
(6)以2﹟段33施工方法循环至钢主梁N﹟段施工完成,悬臂吊机2前移至钢主梁N﹟段端部锚固,钢主梁0﹟段31、钢主梁1﹟段32和钢主梁2﹟段33上设置钢主梁预拼场,钢主梁2+N﹟段上设置悬臂运输门架4转运钢结构部件、桥面板、斜拉索等;
(7)钢主梁N+1﹟段钢主梁从桥面钢主梁预拼场1整体吊放到轨道运梁平车10上,运送至钢主梁N﹟段前端,悬臂吊机将钢主梁N+1﹟段整体起吊、旋转、就位、安装,安装钢主梁N+1﹟段斜拉索6,悬臂吊机2安装桥面板并现浇湿接缝,张拉斜拉索;循环施工其他钢主梁3标准节段,直至施工完成;
(8)拆除悬臂吊机2、桥面钢主梁预拼场1等临时设施,完成桥面系及附属工程施工,全桥交工验收。

Claims (5)

1.一种山区叠合梁斜拉桥桥面吊机法,其特征在于:具体包括以下步骤:
(a)安装钢主梁0﹟段(31);
(b)在边跨平台位置处用钢主梁部件(5)拼装成多个钢主梁(3);
(c)从边跨处以钢主梁0﹟段(31)为起点,依次整体吊装、运输、安装边跨侧和中跨侧钢主梁(3)1--N﹟段,同时依次安装斜拉索(6),其中N≥2;
(d)在钢主梁0﹟段(31)、钢主梁1﹟段(32)和钢主梁2﹟段(33)的节段上设置桥面钢主梁预拼场(1),并将钢主梁部件(5)运输至桥面钢主梁预拼场(1)上;
(e)在桥面钢主梁预拼场(1)上用钢主梁部件(5)拼装钢主梁(3)N+1﹟段,然后通过轨道运梁平车(10)运输至钢主梁(3)N﹟段前端,再通过悬臂吊机(2)起吊、旋转,安装钢主梁(3)N+1﹟段;
(f)重复步骤e,完成N+2、N+3……﹟段的安装,直至整个桥面拼装完成;
所述步骤(c)中,钢主梁(3)1--N﹟段的安装方法为:钢主梁0﹟段(31)上安装悬臂吊机(2)和悬臂吊机小车(9),由边跨侧先起吊中跨侧的钢主梁1﹟段(32)至桥面位置,将钢主梁1﹟段(32)旋转90度,悬臂吊机小车(9)移动到中跨侧,钢主梁1﹟段(32)再旋转90度,放置钢主梁1﹟段(32)就位后与钢主梁0﹟段(31)对接,同时预先将桥面板吊至桥面处,并安装钢主梁1﹟段(32)的斜拉索(6),悬臂吊机(2)安装桥面板并现浇湿接缝,张拉钢主梁1﹟段(32)的斜拉索(6);并以同样的方法安装钢主梁(3)2--N﹟段。
2.根据权利要求1所述的山区叠合梁斜拉桥桥面吊机法,其特征在于:所述步骤(e)中,钢主梁(3)N+1﹟段在钢主梁预拼场(1)内进行整体拼装,钢主梁(3)N+1﹟段整体由轨道运梁平车(10)运输至钢主梁(3)N﹟段前端,由悬臂吊机(2)的悬臂吊机小车(9)整体起吊、运输至安装位置,将钢主梁(3)N+1﹟段旋转90度,下放钢主梁(3)N+1﹟段就位,并与已架设钢主梁(3)N﹟段进行对接,安装钢主梁(3)N+1﹟段的斜拉索(6),悬臂吊机(2)安装桥面板并现浇湿接缝,张拉钢主梁(3)N+1﹟段的斜拉索(6)。
3.根据权利要求1所述的山区叠合梁斜拉桥桥面吊机法,其特征在于:所述钢主梁N﹟段安装完成后的混凝土养护期间,安装桥面钢主梁预拼场(1)设施和悬臂运输门架(4),运转钢主梁部件(5)至桥面进行悬臂安装作业。
4.根据权利要求1、2或3所述的山区叠合梁斜拉桥桥面吊机法,其特征在于:所述桥面钢主梁预拼场(1)上安装龙门吊(8),钢主梁M+1﹟段上设置悬臂运输门架(4),其中M≥1。
5.根据权利要求1所述的山区叠合梁斜拉桥桥面吊机法,其特征在于:所述钢主梁0﹟段设置于钢平台(7)的上部。
CN201710118437.9A 2017-03-01 2017-03-01 一种山区叠合梁斜拉桥桥面吊机法 Active CN106884384B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710118437.9A CN106884384B (zh) 2017-03-01 2017-03-01 一种山区叠合梁斜拉桥桥面吊机法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710118437.9A CN106884384B (zh) 2017-03-01 2017-03-01 一种山区叠合梁斜拉桥桥面吊机法

Publications (2)

Publication Number Publication Date
CN106884384A CN106884384A (zh) 2017-06-23
CN106884384B true CN106884384B (zh) 2018-09-28

Family

ID=59179058

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710118437.9A Active CN106884384B (zh) 2017-03-01 2017-03-01 一种山区叠合梁斜拉桥桥面吊机法

Country Status (1)

Country Link
CN (1) CN106884384B (zh)

Families Citing this family (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108149560A (zh) * 2017-12-25 2018-06-12 中交路桥华南工程有限公司 叠合梁节段及其现场拼装方法
CN108203934A (zh) * 2018-02-02 2018-06-26 中交二公局第工程有限公司 基于偏载横移的斜拉桥叠合梁整节段吊装桥面吊机
CN108221712B (zh) * 2018-02-02 2019-05-10 中交二公局第一工程有限公司 基于偏载横移的斜拉桥叠合梁整节段吊装的桥面吊机的施工工艺
CN109137759B (zh) * 2018-09-29 2023-12-19 中铁第四勘察设计院集团有限公司 一种预应力混凝土箱梁节段预制悬臂拼装方法及系统
CN109505243B (zh) * 2018-11-14 2021-04-27 浙江省交通规划设计研究院有限公司 斜拉桥组合梁桥面抗裂方法
CN109629448B (zh) * 2019-01-28 2023-10-20 中铁大桥局集团有限公司 同步架设主梁和桥面板的装置及方法
CN110042768A (zh) * 2019-06-03 2019-07-23 四川公路桥梁建设集团有限公司 一种组合梁斜拉桥主梁双节段循环施工方法
CN111764283B (zh) * 2020-05-26 2021-08-13 中交路桥建设有限公司 一种叠合梁斜拉桥上部结构快速循环施工方法
CN112709140B (zh) * 2020-12-23 2022-08-05 中铁广州工程局集团有限公司 中承式提篮钢管混凝土拱桥混凝土箱梁施工方法
CN112609598B (zh) * 2021-01-12 2022-05-31 中交二公局第一工程有限公司 一种叠合梁斜拉桥上部结构快速循环施工方法
CN113718625B (zh) * 2021-09-29 2022-11-29 中国水利水电第三工程局有限公司 一种叠合梁斜拉桥塔区无索梁段施工方法
CN114232487B (zh) * 2021-12-15 2024-04-19 中交路桥建设有限公司 一种大跨径斜拉桥主梁架设施工系统
CN114232488B (zh) * 2021-12-15 2023-11-28 中交路桥建设有限公司 一种大跨径斜拉桥主梁架设方法
CN114197329B (zh) * 2021-12-15 2024-02-06 中交路桥华南工程有限公司 一种主梁架设方法
CN117782400B (zh) * 2024-02-23 2024-04-26 贵州桥梁建设集团有限责任公司 一种索结构桥梁索力监测预警装置

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0820910A (ja) * 1994-07-05 1996-01-23 Kajima Corp Pc斜張橋の施工法
JP2008025195A (ja) * 2006-07-20 2008-02-07 Mitsubishi Heavy Industries Bridge & Steel Structures Engineering Co Ltd 斜張橋の施工方法
CN102286935A (zh) * 2011-06-01 2011-12-21 中铁大桥勘测设计院有限公司 一种混合式结合梁斜拉桥全新施工方法
CN104594201B (zh) * 2014-12-16 2016-04-20 中铁大桥局集团有限公司 一种利用单侧墩旁托架架设墩顶钢梁的方法

Also Published As

Publication number Publication date
CN106884384A (zh) 2017-06-23

Similar Documents

Publication Publication Date Title
CN106884384B (zh) 一种山区叠合梁斜拉桥桥面吊机法
CN108532465B (zh) 一种下承式钢箱拱桥的主桥的施工方法
CN106087752B (zh) 多跨提篮拱桥施工方法
CN104195952A (zh) 应用于钢混混合梁斜拉桥钢箱梁架设方法
JP6476426B2 (ja) 揚重装置を用いた部材更新方法
CN105155417B (zh) 一种攀爬式运梁跨车及基于其的隧道口桥梁运架方法
CN104372743B (zh) 栈桥快速施工方法
CN103061506A (zh) 一种钢结构穹顶的施工方法
CN111335178B (zh) 一种小曲线半径钢箱梁架桥机及架设施工方法
CN103882812A (zh) 斜拉索桥中跨主梁的施工方法
CN108149560A (zh) 叠合梁节段及其现场拼装方法
CN109098099A (zh) 连续钢桁柔性拱桥快速施工方法
CN104762882A (zh) 桥梁节段吊装装置及吊装方法
JP2008025195A (ja) 斜張橋の施工方法
CN104670418B (zh) 海洋平台的直升机甲板的总装工艺
JP4361775B2 (ja) 橋梁架設工法および橋梁架設用装置
JP2008248664A (ja) カーテンウォールの揚重方法
CN208219384U (zh) 一种叠合梁节段
CN108625270A (zh) 导梁门吊安装桥梁预制箱梁施工方法
JP2010242308A (ja) コンクリートスラブ構造高層建物の解体工法及びコンクリートスラブ解体装置
CN106120573B (zh) 跨海多跨提篮拱桥自平衡扣挂施工方法
CN105781108B (zh) 一种用于临近场区间大型钢模台车整体转场的施工方法
CN205241086U (zh) 模板吊装和安拆用炮车
CN205529915U (zh) 一种梯型桅杆式悬拼吊机
CN106320181A (zh) 一种采用架桥机安装预制梁板的施工工法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant