CN110042768A - 一种组合梁斜拉桥主梁双节段循环施工方法 - Google Patents

一种组合梁斜拉桥主梁双节段循环施工方法 Download PDF

Info

Publication number
CN110042768A
CN110042768A CN201910474922.9A CN201910474922A CN110042768A CN 110042768 A CN110042768 A CN 110042768A CN 201910474922 A CN201910474922 A CN 201910474922A CN 110042768 A CN110042768 A CN 110042768A
Authority
CN
China
Prior art keywords
binodal
suspension cable
cable
construction
girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910474922.9A
Other languages
English (en)
Inventor
明德江
孙兵
李季
张良隆
郭跃
何良飞
夏仕辉
羊波
周恒�
付利航
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Road and Bridge Group Co Ltd
Original Assignee
Sichuan Road and Bridge Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Road and Bridge Group Co Ltd filed Critical Sichuan Road and Bridge Group Co Ltd
Priority to CN201910474922.9A priority Critical patent/CN110042768A/zh
Publication of CN110042768A publication Critical patent/CN110042768A/zh
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • E01D21/10Cantilevered erection

Abstract

本发明公开了一种组合梁斜拉桥主梁双节段循环施工方法,其特征在于:当主梁塔区钢梁、桥面板及湿接缝施工完毕后,在进行上部结构悬臂施工作业时,采用双节段循环方式进行施工即利用桥面吊机进行1#梁段钢主梁、横梁、小纵梁的拼装,待1#梁段斜拉索“一张”完成后,吊装预制桥面板精确就位,吊机前移并完成1#梁段斜拉索“二张”。继续吊装第2段钢梁,待高栓、标高报验合格后进行2#梁段斜拉索“一张”,安装完2#梁桥面板后吊机前移至2#梁端,在湿接缝钢筋及预应力安装完后进行1#、2#梁段湿接缝砼浇筑。当采用双节段循环安装方式时,可节约工期,减少人员窝工使得劳动力不均衡系数得到改善、同时施工过程中结构安全储备更趋合理。

Description

一种组合梁斜拉桥主梁双节段循环施工方法
技术领域
本发明涉及斜拉桥施工相关领域,具体来讲是一种组合梁斜拉桥主梁悬臂施工方法。
背景技术
随着近几年我国钢混组合梁斜拉桥建设的增加,关于主梁上部结构的安装也呈现出多种方式。一般常用的安装方式有单节段循环安装、三节段循环安装两种,但这几种主梁安装方式在施工工期、人工成本以及施工过程中结构安全储备等方面均未实现很好的平衡。当采用双节段循环安装方式时,可节约工期,减少人员窝工使得劳动力不均衡系数得到改善、同时施工过程中结构安全储备更趋合理。
发明内容
因此,本发明的目的在于克服常规斜拉桥主梁单节段循环施工方法工期较长、劳动力不均衡系数低下、设备摊销高等不足。本发明在此提供一种组合梁斜拉桥主梁双节段循环施工方法;当采用双节段循环安装方式时,可节约工期,减少人员窝工使得劳动力不均衡系数得到改善、同时施工过程中结构安全储备更趋合理。
本发明是这样实现的,构造一种组合梁斜拉桥主梁双节段循环施工方法,其特征在于;按照如下方式实施;
(1),在进行主梁上部结构悬臂施工作业时,采用双节段循环方式进行施工,即利用桥面吊机进行1#梁段钢主梁、横梁、小纵梁的拼装,并配合斜拉索下锚施工;待1#梁段斜拉索“一张”完成后,吊装预制桥面板精确就位,吊机前移并完成1#梁段斜拉索“二张”;
(2),继续吊装第2段钢梁,待高栓、标高报验合格后进行2#梁段斜拉索“一张”,安装完2#梁桥面板后吊机前移至2#梁端,在湿接缝钢筋及预应力安装完后进行1#、2#梁段湿接缝砼浇筑;待强度及龄期达到规定要求后进行2#斜拉索“二张”;重复上述步骤至悬臂拼装完成。
本发明具有如下优点:本发明公开了一种组合梁斜拉桥主梁双节段循环施工方法,其特征在于:当主梁塔区钢梁、桥面板及湿接缝施工完毕后,在进行上部结构悬臂施工作业时,采用双节段循环方式进行施工即利用桥面吊机进行1#梁段钢主梁、横梁、小纵梁的拼装,并配合斜拉索下锚施工。待1#梁段斜拉索“一张”完成后,吊装预制桥面板精确就位,吊机前移并完成1#梁段斜拉索“二张”。继续吊装第2段钢梁,待高栓、标高报验合格后进行2#梁段斜拉索“一张”,安装完2#梁桥面板后吊机前移至2#梁端,在湿接缝钢筋及预应力安装完后进行1#、2#梁段湿接缝砼浇筑。待强度及龄期达到规定要求后进行2#斜拉索“二张”。重复上述步骤至悬臂拼装完成。本发明克服常规斜拉桥主梁单节段循环施工方法工期较长、劳动力不均衡系数低下、设备摊销高等不足。本发明在此提供一种组合梁斜拉桥主梁双节段循环施工方法;当采用双节段循环安装方式时,可节约工期,减少人员窝工使得劳动力不均衡系数得到改善、同时施工过程中结构安全储备更趋合理。
附图说明
图1是本发明双节段循环施工流程图;
图2是桥面吊机处于N-1梁段示意图;
图3是拼装N段主纵梁示意图;
图4是拼装N段横梁示意图;
图5是拼装N段小纵梁,N段斜拉索一张示意图;
图6是安装N段桥面板示意图;
图7是桥面吊机前移至N段,N段斜拉索二张示意图;
图8是拼装N+1段钢梁,N+1段斜拉索一张示意图;
图9是安装N+1段桥面板示意图;
图10是桥面吊机前移至N+1段示意图;
图11是浇筑N及N+1段桥面板湿接缝,N+1段斜拉索二张示意图。
具体实施方式
下面将结合附图1-图11对本发明进行详细说明,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。
本发明通过改进在此提供一种组合梁斜拉桥主梁双节段循环施工方法,其特征在于;按照如下方式实施;
(1),在进行主梁上部结构悬臂施工作业时,采用双节段循环方式进行施工,即利用桥面吊机进行1#梁段钢主梁、横梁、小纵梁的拼装,并配合斜拉索下锚施工;待1#梁段斜拉索“一张”完成后,吊装预制桥面板精确就位,吊机前移并完成1#梁段斜拉索“二张”;
(2),继续吊装第2段钢梁,待高栓、标高报验合格后进行2#梁段斜拉索“一张”,安装完2#梁桥面板后吊机前移至2#梁端,在湿接缝钢筋及预应力安装完后进行1#、2#梁段湿接缝砼浇筑;待强度及龄期达到规定要求后进行2#斜拉索“二张”;重复上述步骤至悬臂拼装完成。
本发明克服常规斜拉桥主梁单节段循环施工方法工期较长、劳动力不均衡系数低下、设备摊销高等不足。本发明在此提供一种组合梁斜拉桥主梁双节段循环施工方法;当采用双节段循环安装方式时,可节约工期,减少人员窝工使得劳动力不均衡系数得到改善、同时施工过程中结构安全储备更趋合理。
对所公开的实施例的上述说明,使本领域专业技术人员能够实现或使用本发明。对这些实施例的多种修改对本领域的专业技术人员来说将是显而易见的,本文中所定义的一般原理可以在不脱离本发明的精神或范围的情况下,在其它实施例中实现。因此,本发明将不会被限制于本文所示的这些实施例,而是要符合与本文所公开的原理和新颖特点相一致的最宽的范围。

Claims (1)

1.一种组合梁斜拉桥主梁双节段循环施工方法,其特征在于;按照如下方式实施;
(1),在进行主梁上部结构悬臂施工作业时,采用双节段循环方式进行施工,即利用桥面吊机进行1#梁段钢主梁、横梁、小纵梁的拼装,并配合斜拉索下锚施工;待1#梁段斜拉索“一张”完成后,吊装预制桥面板精确就位,吊机前移并完成1#梁段斜拉索“二张”;
(2),继续吊装第2段钢梁,待高栓、标高报验合格后进行2#梁段斜拉索“一张”,安装完2#梁桥面板后吊机前移至2#梁端,在湿接缝钢筋及预应力安装完后进行1#、2#梁段湿接缝砼浇筑;待强度及龄期达到规定要求后进行2#斜拉索“二张”;重复上述步骤至悬臂拼装完成。
CN201910474922.9A 2019-06-03 2019-06-03 一种组合梁斜拉桥主梁双节段循环施工方法 Pending CN110042768A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910474922.9A CN110042768A (zh) 2019-06-03 2019-06-03 一种组合梁斜拉桥主梁双节段循环施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910474922.9A CN110042768A (zh) 2019-06-03 2019-06-03 一种组合梁斜拉桥主梁双节段循环施工方法

Publications (1)

Publication Number Publication Date
CN110042768A true CN110042768A (zh) 2019-07-23

Family

ID=67284432

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910474922.9A Pending CN110042768A (zh) 2019-06-03 2019-06-03 一种组合梁斜拉桥主梁双节段循环施工方法

Country Status (1)

Country Link
CN (1) CN110042768A (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110512530A (zh) * 2019-09-06 2019-11-29 同济大学建筑设计研究院(集团)有限公司 一种组合梁双节段悬臂施工方法
CN110593101A (zh) * 2019-08-16 2019-12-20 中铁大桥科学研究院有限公司 一种组合梁斜拉桥的快速拼装施工方法
CN111424556A (zh) * 2020-04-21 2020-07-17 中铁大桥局第七工程有限公司 一种斜拉桥主梁的架设方法和斜拉桥主梁
CN111764283A (zh) * 2020-05-26 2020-10-13 中交路桥建设有限公司 一种叠合梁斜拉桥上部结构快速循环施工方法
CN112081017A (zh) * 2020-08-20 2020-12-15 河南五建建设集团有限公司 桥梁大跨径节段预制悬臂拼装跨越既有桥梁的施工方法

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102286935A (zh) * 2011-06-01 2011-12-21 中铁大桥勘测设计院有限公司 一种混合式结合梁斜拉桥全新施工方法
CN103614973A (zh) * 2013-12-18 2014-03-05 广东省长大公路工程有限公司 一种四索面分体钢箱梁桥梁悬臂施工方法
EP3018255A1 (en) * 2014-10-27 2016-05-11 Rubrica Ingenieria Y Arquitectura, S.L. Cart for building a bridge board forward progressive
CN106884384A (zh) * 2017-03-01 2017-06-23 贵州桥梁建设集团有限责任公司 一种山区叠合梁斜拉桥桥面吊机法
CN108999088A (zh) * 2018-08-14 2018-12-14 张家港市欧微自动化研发有限公司 一种斜拉桥的施工方法
CN109338891A (zh) * 2018-11-14 2019-02-15 安徽省交通控股集团有限公司 一种斜拉桥pk组合箱梁悬臂整体吊装桥面板抗裂方法
CN109505243A (zh) * 2018-11-14 2019-03-22 浙江省交通规划设计研究院有限公司 斜拉桥组合梁桥面抗裂方法

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102286935A (zh) * 2011-06-01 2011-12-21 中铁大桥勘测设计院有限公司 一种混合式结合梁斜拉桥全新施工方法
CN103614973A (zh) * 2013-12-18 2014-03-05 广东省长大公路工程有限公司 一种四索面分体钢箱梁桥梁悬臂施工方法
EP3018255A1 (en) * 2014-10-27 2016-05-11 Rubrica Ingenieria Y Arquitectura, S.L. Cart for building a bridge board forward progressive
CN106884384A (zh) * 2017-03-01 2017-06-23 贵州桥梁建设集团有限责任公司 一种山区叠合梁斜拉桥桥面吊机法
CN108999088A (zh) * 2018-08-14 2018-12-14 张家港市欧微自动化研发有限公司 一种斜拉桥的施工方法
CN109338891A (zh) * 2018-11-14 2019-02-15 安徽省交通控股集团有限公司 一种斜拉桥pk组合箱梁悬臂整体吊装桥面板抗裂方法
CN109505243A (zh) * 2018-11-14 2019-03-22 浙江省交通规划设计研究院有限公司 斜拉桥组合梁桥面抗裂方法

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110593101A (zh) * 2019-08-16 2019-12-20 中铁大桥科学研究院有限公司 一种组合梁斜拉桥的快速拼装施工方法
CN110512530A (zh) * 2019-09-06 2019-11-29 同济大学建筑设计研究院(集团)有限公司 一种组合梁双节段悬臂施工方法
CN111424556A (zh) * 2020-04-21 2020-07-17 中铁大桥局第七工程有限公司 一种斜拉桥主梁的架设方法和斜拉桥主梁
CN111764283A (zh) * 2020-05-26 2020-10-13 中交路桥建设有限公司 一种叠合梁斜拉桥上部结构快速循环施工方法
CN111764283B (zh) * 2020-05-26 2021-08-13 中交路桥建设有限公司 一种叠合梁斜拉桥上部结构快速循环施工方法
CN112081017A (zh) * 2020-08-20 2020-12-15 河南五建建设集团有限公司 桥梁大跨径节段预制悬臂拼装跨越既有桥梁的施工方法

Similar Documents

Publication Publication Date Title
CN110042768A (zh) 一种组合梁斜拉桥主梁双节段循环施工方法
CN101845849B (zh) 新旧建筑物之间架设的大跨度钢结构连廊及其施工方法
CN100503977C (zh) 斜拉桥的塔柱及其施工方法
CN105421248A (zh) 大跨度连续梁跨既有车站转体及合龙施工方法
CN105714683A (zh) 高排架现浇渡槽悬挂式贝雷架的安装和拆除方法
CN108547223A (zh) 钢混叠合的混合梁桥施工方法
CN103882812A (zh) 斜拉索桥中跨主梁的施工方法
CN204716257U (zh) 确保盾构整体始发和车站主体同步施工的可变门洞式支架
CN109736844B (zh) 一种隧道初期支护快速施工方法
CN203947421U (zh) 组合梁斜拉桥横桥向预应力施加装置
CN104060542A (zh) 组合梁斜拉桥横桥向预应力施加装置及其施加方法
CN102635070B (zh) 斜拉桥钢塔互拉式竖向转体施工方法
CN105019357B (zh) 一种拱桥敞口格构式钢梁上异形预制桥面板的安装方法
CN103993739B (zh) 造粒塔喷淋层劲性梁的施工方法
CN203486787U (zh) 一种维金斯式煤气柜柜顶的整体提升装置
CN109629449B (zh) 一种钢箱拱桥拱脚钢混结合段安装定位支架及对位方法
CN204850048U (zh) 辅助高层钢梁快速吊装的搭接结构
CN211141349U (zh) 一种轨排井龙门吊基础固定结构
CN203383221U (zh) 一种钢筋混凝土与钢结构混合的基坑支撑结构
CN105019556A (zh) 辅助高层钢梁快速吊装的搭接结构及其应用
CN207194414U (zh) 一种用于临时支撑的无基础钢平台
CN204940130U (zh) 一种波形钢腹板部件的整体起吊装置
JP5890060B1 (ja) 架設桁を用いた橋梁の解体工法
CN204000639U (zh) 一种大型墩柱混凝土钢筋整体吊装机械对接装置
CN201908665U (zh) 移动式变断面衬砌台车

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination