CN109098099A - 连续钢桁柔性拱桥快速施工方法 - Google Patents
连续钢桁柔性拱桥快速施工方法 Download PDFInfo
- Publication number
- CN109098099A CN109098099A CN201810874745.9A CN201810874745A CN109098099A CN 109098099 A CN109098099 A CN 109098099A CN 201810874745 A CN201810874745 A CN 201810874745A CN 109098099 A CN109098099 A CN 109098099A
- Authority
- CN
- China
- Prior art keywords
- steel
- girder
- pier
- girder steel
- flat string
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
- E01D21/10—Cantilevered erection
Abstract
本发明涉及钢桁柔性拱桥快速施工方法,在拟建桥墩之间同时修建临时支墩,在桥梁跨中修建拼装平台;利用拼装平台拼装平弦钢梁;在平弦钢梁上方设置两台架梁吊机,向两侧对称悬拼平弦钢梁至两侧拟建桥墩的主墩,主墩与钢梁悬拼同时修建;在悬拼平弦钢梁的同时,增设架梁吊机架设拱肋及吊杆;平弦钢梁拼装至两侧边墩之前建成边墩,架梁吊机完成中跨及边跨大部分拱肋与吊杆;拆除一台架梁吊机,利用两台架梁吊机拼装剩余拱肋及吊杆,完成全桥施工。本发明可实现主墩与临时墩、平弦钢梁同时施工,平弦钢梁与拱肋吊杆同时施工,有效缩短工期,可为类似桥梁的设计和施工提供参考。
Description
技术领域
本发明涉及桥梁结构建筑技术领域,具体涉及一种钢桁柔性拱桥快速施工方法。
背景技术
随着我国交通建设的快速发展,大跨度桥梁的建设工期往往会成为控制整条公路或铁路建设总工期的控制因素。钢桁柔性拱桥是公路及铁路建设中跨越大江大河及高级别道路常用的桥型方案。钢桁柔性拱桥合理的建造技术可以有效的缩短工期,避免成为整个项目总工期的控制性工程,为整个项目的开通运营保驾护航,创造可观的经济效益及社会效益。
在钢桁柔性拱桥的施工过程中,考虑综合影响因素,通常采用的施工方法有悬臂拼装法、塔架斜拉索法等。对于某些特殊场地或对影响交通、安全有严格要求的情况下,也可采用顶推法施工。以上施工方法均需采用“先梁后拱”的施工方案,即下部桥墩及平弦钢梁全部施工完成后,再利用完成的钢梁施工拱肋及吊杆,导致下部桥墩与钢梁无法同时施工,平弦钢梁及拱肋无法同时施工,从而耽误施工工期。因此研究一种下部及梁部同时施工、平弦钢梁与拱肋同时施工的施工方法是十分必要的。
发明内容
本发明的目的是提供一种钢桁柔性拱桥快速施工方法,以实现下部及梁部同时施工、平弦钢梁与拱肋同时施工,从而最大限度的缩短施工工期。
本发明所采用的技术方案为:
钢桁柔性拱桥快速施工方法,其特征在于:
包括以下步骤:
步骤一:在施工拟建桥墩的同时,在拟建桥墩之间修建多座临时支墩,在桥梁跨中修建拼装平台;
步骤二:利用拼装平台拼装平弦钢梁;
步骤三:在平弦钢梁上方左右设置两台架梁吊机,分别为1号架梁吊机和2号架梁吊机,利用两台架梁吊机向两侧对称悬拼平弦钢梁至两侧拟建桥墩的主墩,主墩与钢梁悬拼同时修建,并于钢梁悬拼到位前建成;
步骤四:利用1号架梁吊机和2号架梁吊机悬拼平弦钢梁的同时,在两台架梁吊机之间已建成的中跨平弦钢梁上增设3号架梁吊机;
步骤五:利用3号架梁吊机架设拱肋及吊杆;
步骤六:平弦钢梁拼装至两侧边墩之前,利用钢梁拼装时间建成边墩,平弦钢梁完成施工,3号架梁吊机完成中跨及边跨大部分拱肋与吊杆;
步骤七:拆除一台架梁吊机,利用两台架梁吊机拼装剩余拱肋及吊杆,完成全桥施工;
步骤八:施工完成后后,拆除临时支墩、拼装平台及架梁吊机。
临时支墩由竖向的钢管桩和横向的分配梁组装,钢管桩为下部基础,钢管桩上设置分配梁,钢管桩之间连接系均为钢管和槽钢组合焊接而成。
平弦钢梁的上弦杆上安装有轨道,1号架梁吊机和2号架梁吊机在上弦杆轨道上移动。
平弦钢梁上平联节点板上安装有轨道,3号架梁吊机在上平联节点板轨道上移动。
本发明具有以下优点:
本发明所涉及的钢桁柔性拱施工方法可实现主墩与临时墩、平弦钢梁同时施工,平弦钢梁与拱肋吊杆同时施工,可有效的缩短工期,具有很强的创新性和实用性,可为类似桥梁的设计和施工提供参考。
附图说明
图1为步骤一示意图。
图2为步骤二示意图。
图3为步骤三示意图。
图4为步骤四示意图。
图5为步骤五示意图。
图6为步骤六示意图。
图7为步骤七示意图。
图8为步骤八示意图。
图中,1-临时支墩,2-拼装平台,3-拟建桥墩,4-平弦钢梁,5-1号架梁吊机,6-2号架梁吊机,7-3号架梁吊机,8-主墩,9-拱肋,10-吊杆,11-边墩。
具体实施方式
下面结合具体实施方式对本发明进行详细的说明。
连续钢桁柔性拱桥结构是指在连续钢桁梁的顶面增加拱肋结构,拱肋与钢桁梁之间采用吊杆连接,支点位置采用平弦或者加劲弦结构最终形成的连续钢桁柔性拱桥。
本发明涉及的钢桁柔性拱桥快速施工方法,包括以下步骤:
步骤一:在施工拟建桥墩3的同时,在拟建桥墩3之间修建多座临时支墩1,在桥梁跨中修建拼装平台2;
步骤二:利用拼装平台2拼装平弦钢梁4;
步骤三:在平弦钢梁4上方左右设置两台架梁吊机,分别为1号架梁吊机5和2号架梁吊机6,利用两台架梁吊机向两侧对称悬拼平弦钢梁4至两侧拟建桥墩3的主墩8,主墩8与钢梁悬拼同时修建,并于钢梁悬拼到位前建成;
步骤四:利用1号架梁吊机5和2号架梁吊机6悬拼平弦钢梁4的同时,在两台架梁吊机之间已建成的中跨平弦钢梁4上增设3号架梁吊机7;
步骤五:利用3号架梁吊机7架设拱肋9及吊杆10;
步骤六:平弦钢梁4拼装至两侧边墩11之前,利用钢梁拼装时间建成边墩11,平弦钢梁4完成施工,3号架梁吊机7完成中跨及边跨大部分拱肋9与吊杆10;
步骤七:拆除一台架梁吊机,利用两台架梁吊机拼装剩余拱肋9及吊杆10,完成全桥施工;
步骤八:施工完成后后,拆除临时支墩1、拼装平台2及架梁吊机。
临时支墩1、拼装平台2均由钢管桩和分配梁组成,临时支墩1下部基础采用钢管桩,钢管桩上设置分配梁。钢管桩之间连接系均为钢管和槽钢组合焊接而成。
平弦钢梁4的上弦杆上安装有轨道,1号架梁吊机5和2号架梁吊机6在上弦杆轨道上移动。平弦钢梁4上平联节点板上安装有轨道,3号架梁吊机7在上平联节点板轨道上移动。3号架梁吊机7选择型号稍小的吊机避开拱肋对吊机移动轨迹的影响。
本发明的内容不限于实施例所列举,本领域普通技术人员通过阅读本发明说明书而对本发明技术方案采取的任何等效的变换,均为本发明的权利要求所涵盖。
Claims (4)
1.钢桁柔性拱桥快速施工方法,其特征在于:
包括以下步骤:
步骤一:在施工拟建桥墩(3)的同时,在拟建桥墩(3)之间修建多座临时支墩(1),在桥梁跨中修建拼装平台(2);
步骤二:利用拼装平台(2)拼装平弦钢梁(4);
步骤三:在平弦钢梁(4)上方左右设置两台架梁吊机,分别为1号架梁吊机(5)和2号架梁吊机(6),利用两台架梁吊机向两侧对称悬拼平弦钢梁(4)至两侧拟建桥墩(3)的主墩(8),主墩(8)与钢梁悬拼同时修建,并于钢梁悬拼到位前建成;
步骤四:利用1号架梁吊机(5)和2号架梁吊机(6)悬拼平弦钢梁(4)的同时,在两台架梁吊机之间已建成的中跨平弦钢梁(4)上增设3号架梁吊机(7);
步骤五:利用3号架梁吊机(7)架设拱肋(9)及吊杆(10);
步骤六:平弦钢梁(4)拼装至两侧边墩(11)之前,利用钢梁拼装时间建成边墩(11),平弦钢梁(4)完成施工,3号架梁吊机(7)完成中跨及边跨大部分拱肋(9)与吊杆(10);
步骤七:拆除一台架梁吊机,利用两台架梁吊机拼装剩余拱肋(9)及吊杆(10),完成全桥施工;
步骤八:施工完成后后,拆除临时支墩(1)、拼装平台(2)及架梁吊机。
2.根据权利要求1所述的钢桁柔性拱桥快速施工方法,其特征在于:
临时支墩(1)由竖向的钢管桩和横向的分配梁组装,钢管桩为下部基础,钢管桩上设置分配梁,钢管桩之间连接系均为钢管和槽钢组合焊接而成。
3.根据权利要求1所述的钢桁柔性拱桥快速施工方法,其特征在于:
平弦钢梁(4)的上弦杆上安装有轨道,1号架梁吊机(5)和2号架梁吊机(6)在上弦杆轨道上移动。
4.根据权利要求3所述的钢桁柔性拱桥快速施工方法,其特征在于:
平弦钢梁(4)上平联节点板上安装有轨道,3号架梁吊机(7)在上平联节点板轨道上移动。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810874745.9A CN109098099A (zh) | 2018-08-03 | 2018-08-03 | 连续钢桁柔性拱桥快速施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810874745.9A CN109098099A (zh) | 2018-08-03 | 2018-08-03 | 连续钢桁柔性拱桥快速施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109098099A true CN109098099A (zh) | 2018-12-28 |
Family
ID=64848220
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810874745.9A Pending CN109098099A (zh) | 2018-08-03 | 2018-08-03 | 连续钢桁柔性拱桥快速施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109098099A (zh) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109680619A (zh) * | 2019-01-18 | 2019-04-26 | 中铁三局集团有限公司 | 一种适用于环境限制大的钢桁梁吊索拱桥施工方法 |
CN110468721A (zh) * | 2019-08-29 | 2019-11-19 | 中铁大桥局集团有限公司 | 一种大跨度栈桥悬臂施工方法 |
CN111119070A (zh) * | 2019-12-24 | 2020-05-08 | 江苏中铁山桥重工有限公司 | 一种采用对称门吊悬拼架设w形钢桁梁的方法 |
CN111593673A (zh) * | 2020-06-12 | 2020-08-28 | 安徽省公路桥梁工程有限公司 | 一种钢桁拱桥及施工方法 |
CN112900232A (zh) * | 2021-01-19 | 2021-06-04 | 同济大学 | 一种高速磁悬浮大跨度组合式钢桁架拱桥 |
CN114293473A (zh) * | 2021-12-22 | 2022-04-08 | 中铁九桥工程有限公司 | 提篮拱桥施工方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20020060520A (ko) * | 2001-01-11 | 2002-07-18 | 신영균 | 아치교 분할 가설 공법 |
CN102373671A (zh) * | 2011-11-18 | 2012-03-14 | 中铁四局集团有限公司 | 钢桁梁柔性拱桥带拱顶推施工方法 |
JP4985540B2 (ja) * | 2008-05-19 | 2012-07-25 | 鹿島建設株式会社 | 片持架設用移動作業車の上下梁システム |
CN104612058A (zh) * | 2014-12-26 | 2015-05-13 | 中铁大桥勘测设计院集团有限公司 | 一种刚性梁柔性拱桥的施工方法 |
-
2018
- 2018-08-03 CN CN201810874745.9A patent/CN109098099A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR20020060520A (ko) * | 2001-01-11 | 2002-07-18 | 신영균 | 아치교 분할 가설 공법 |
JP4985540B2 (ja) * | 2008-05-19 | 2012-07-25 | 鹿島建設株式会社 | 片持架設用移動作業車の上下梁システム |
CN102373671A (zh) * | 2011-11-18 | 2012-03-14 | 中铁四局集团有限公司 | 钢桁梁柔性拱桥带拱顶推施工方法 |
CN104612058A (zh) * | 2014-12-26 | 2015-05-13 | 中铁大桥勘测设计院集团有限公司 | 一种刚性梁柔性拱桥的施工方法 |
Non-Patent Citations (1)
Title |
---|
吴海勃: "连续钢桁梁双悬臂对称架设快速施工的施工技术研究", 《中外建筑》 * |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109680619A (zh) * | 2019-01-18 | 2019-04-26 | 中铁三局集团有限公司 | 一种适用于环境限制大的钢桁梁吊索拱桥施工方法 |
CN110468721A (zh) * | 2019-08-29 | 2019-11-19 | 中铁大桥局集团有限公司 | 一种大跨度栈桥悬臂施工方法 |
CN110468721B (zh) * | 2019-08-29 | 2021-04-20 | 中铁大桥局集团有限公司 | 一种大跨度栈桥悬臂施工方法 |
CN111119070A (zh) * | 2019-12-24 | 2020-05-08 | 江苏中铁山桥重工有限公司 | 一种采用对称门吊悬拼架设w形钢桁梁的方法 |
CN111119070B (zh) * | 2019-12-24 | 2022-02-11 | 江苏中铁山桥重工有限公司 | 一种采用对称门吊悬拼架设w形钢桁梁的方法 |
CN111593673A (zh) * | 2020-06-12 | 2020-08-28 | 安徽省公路桥梁工程有限公司 | 一种钢桁拱桥及施工方法 |
CN112900232A (zh) * | 2021-01-19 | 2021-06-04 | 同济大学 | 一种高速磁悬浮大跨度组合式钢桁架拱桥 |
CN112900232B (zh) * | 2021-01-19 | 2022-06-21 | 同济大学 | 一种高速磁悬浮大跨度组合式钢桁架拱桥 |
CN114293473A (zh) * | 2021-12-22 | 2022-04-08 | 中铁九桥工程有限公司 | 提篮拱桥施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109098099A (zh) | 连续钢桁柔性拱桥快速施工方法 | |
Hu et al. | Recent development of design and construction of medium and long span high-speed railway bridges in China | |
CN102121234B (zh) | 一种双塔五跨钢桁梁斜拉桥的快速施工方法 | |
CN101195987B (zh) | 斜拉桥中跨顶推辅助合龙工艺 | |
CN103643640B (zh) | 一种先顶进后加固线路的框架桥顶进施工方法 | |
CN103882812B (zh) | 斜拉索桥中跨主梁的施工方法 | |
CN101324053A (zh) | 双线箱梁下行式移动模架造桥机及其施工方法 | |
CN104612058A (zh) | 一种刚性梁柔性拱桥的施工方法 | |
CN209652741U (zh) | 一种跨铁路站场大跨度高架桥 | |
CN201106155Y (zh) | 斜拉索辅助全悬臂架设钢桁梁装置 | |
CN104372743A (zh) | 栈桥快速施工方法 | |
CN104018426B (zh) | 一种钢桁梁安装方法 | |
CN110468743B (zh) | 一种用于旧桥墩帽改造的移动式吊架及施工方法 | |
CN101324054B (zh) | 桥梁节段梁临时墩的顶推就位施工方法 | |
CN109371852A (zh) | 一种跨铁路站场的高架桥施工方法 | |
CN110130201A (zh) | 一种半漂浮桁架式桥塔的斜拉桥 | |
CN210827111U (zh) | 一种环境友好型下行自行式钢栈桥结构 | |
CN105696470B (zh) | 一种钢箱梁原位顶推和塔柱同步快速施工方法 | |
CN209338005U (zh) | 一种架梁施工用移动式高低腿龙门吊 | |
CN104110002A (zh) | 一种更换钢桁梁桥桥面板的方法 | |
Russell et al. | Prefabricated bridge elements and systems in Japan and Europe | |
CN110820519A (zh) | 一种便于快速施工的隧间拱桥及其施工方法 | |
CN102392421B (zh) | 基于潮汐交通流特征的小城镇拱桥局部加宽加固方法 | |
CN102277839A (zh) | 既有电化铁路增建明洞构造及其快速施工方法 | |
CN113322819B (zh) | 一种隧道出口处首跨t梁架设方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181228 |