CN106709703A - Method and system of decoration project construction management based on technology of internet of things - Google Patents

Method and system of decoration project construction management based on technology of internet of things Download PDF

Info

Publication number
CN106709703A
CN106709703A CN201710114439.0A CN201710114439A CN106709703A CN 106709703 A CN106709703 A CN 106709703A CN 201710114439 A CN201710114439 A CN 201710114439A CN 106709703 A CN106709703 A CN 106709703A
Authority
CN
China
Prior art keywords
dpm
construction
information
region
management system
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710114439.0A
Other languages
Chinese (zh)
Inventor
刘群
高仲杰
阎美怡
郁秋梅
刘永明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
TIANJIN HUAHUI ANDERSON DECORATION ENGINEERING Co Ltd
Original Assignee
TIANJIN HUAHUI ANDERSON DECORATION ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by TIANJIN HUAHUI ANDERSON DECORATION ENGINEERING Co Ltd filed Critical TIANJIN HUAHUI ANDERSON DECORATION ENGINEERING Co Ltd
Priority to CN201710114439.0A priority Critical patent/CN106709703A/en
Publication of CN106709703A publication Critical patent/CN106709703A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06KGRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
    • G06K17/00Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations
    • G06K17/0022Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations arrangements or provisious for transferring data to distant stations, e.g. from a sensing device
    • G06K17/0029Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations arrangements or provisious for transferring data to distant stations, e.g. from a sensing device the arrangement being specially adapted for wireless interrogation of grouped or bundled articles tagged with wireless record carriers
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06KGRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
    • G06K7/00Methods or arrangements for sensing record carriers, e.g. for reading patterns
    • G06K7/10Methods or arrangements for sensing record carriers, e.g. for reading patterns by electromagnetic radiation, e.g. optical sensing; by corpuscular radiation
    • G06K7/10544Methods or arrangements for sensing record carriers, e.g. for reading patterns by electromagnetic radiation, e.g. optical sensing; by corpuscular radiation by scanning of the records by radiation in the optical part of the electromagnetic spectrum
    • G06K7/10821Methods or arrangements for sensing record carriers, e.g. for reading patterns by electromagnetic radiation, e.g. optical sensing; by corpuscular radiation by scanning of the records by radiation in the optical part of the electromagnetic spectrum further details of bar or optical code scanning devices
    • G06K7/10861Methods or arrangements for sensing record carriers, e.g. for reading patterns by electromagnetic radiation, e.g. optical sensing; by corpuscular radiation by scanning of the records by radiation in the optical part of the electromagnetic spectrum further details of bar or optical code scanning devices sensing of data fields affixed to objects or articles, e.g. coded labels
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Engineering & Computer Science (AREA)
  • Physics & Mathematics (AREA)
  • Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Strategic Management (AREA)
  • Human Resources & Organizations (AREA)
  • Theoretical Computer Science (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Business, Economics & Management (AREA)
  • Electromagnetism (AREA)
  • Health & Medical Sciences (AREA)
  • Economics (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Computer Vision & Pattern Recognition (AREA)
  • Toxicology (AREA)
  • General Engineering & Computer Science (AREA)
  • Computer Networks & Wireless Communication (AREA)
  • Data Mining & Analysis (AREA)
  • Artificial Intelligence (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention discloses a method and system of decoration project construction management based on the technology of internet of things. The decoration and fitment product data is standardized, the connection with a DPM management system is established, the site collection and the real-time monitoring are realized based on the technology of internet of things, the real-time monitoring comprises construction material storage/retrieval and usage condition monitoring, construction schedule track, construction quality monitoring and analysis, and site worker construction task completion condition monitoring and analysis, and the project dynamic construction cost track is realized. The technology of the internet of things, the two-dimensional barcode technology and the RFID technology are employed, a laser scanner and a wireless sensor are used, the information of people, materials and machines on the construction site is collected to a route device through the ZigBee protocol and is transmitted to a central information system through adoption of the internet to realize the real-time transmission and sharing of the information such as the decoration project cost, the schedule, the quality and the safety and solve the problem of the timeliness and the accuracy of the information collection of the DPM system.

Description

A kind of decoration project work progress management method and system based on technology of Internet of things
Technical field
The invention belongs to decoration industry administrative skill field, it is related to a kind of decoration project work progress pipe based on Internet of Things Reason method and system.
Background technology
As country continues to increase infrastructure construction, various buildings rising sheer from level ground like the mushrooms after rain, building is applied Industrial and commercial bank's industry has also welcome new opportunity to develop, while being also faced with bigger challenge.Aesthetic property, practicality of the people to building decoration Property, the requirement more and more higher of the aspect such as quality, design concept and construction technology, make rapid progress, weed out the old and bring forth the new, not only quantities by Year increases, and difficulty of construction also climbs up and up, construction material enormous variety, using traditional extensive style management, can not meet The requirement of enterprise development.Decoration Construction Enterprise, sizes up the current situation, combining information technology, promotes construction industry DPM management systems Using DPM systems can solve the problem that management and control of the project management process at aspects such as cost, progress, quality, safety, realize to project People, wealth, the management of machine three elements, information transmission and shared, but in information ground promptness, accuracy aspect need to be improved.
In order to solve the problems, such as information promptness and accuracy, for data analysis provides accurate big data with excavation Basis, it is necessary to design a kind of decoration project work progress management method and system based on Internet of Things, realize decoration project cost, The real-time transmission of the information such as progress, quality, safety and shared, makes that DPM system informations collect promptness and accuracy problem is landed.
The content of the invention
The present invention provides a kind of decoration project work progress management method and system based on technology of Internet of things, it is intended to solve Project under construction extensive style management mode, cause information not in time with inaccurate problem, carry out project under construction standardization pipe Reason, collects information of the job site in terms of progress control, quality management etc. immediately, and process data is received in solving project management Collection, the problem for excavating hardly possible, for decoration project management provides accurate information data basis.
To reach above-mentioned purpose, the technical proposal of the invention is realized in this way:A kind of decoration based on technology of Internet of things Project construction process control method, including:
Decorations product data standardization in DPM management systems;Set up job site harvester and set up and DPM The connection of management system;Field data is gathered and monitor in real time;
Wherein, the field data collection includes with monitor in real time:Construction material enter outbound and service condition monitoring;Apply Work progress is followed the trail of;Construction quality control and analysis;Field worker construction task performance is monitored and analysis;Project Dynamic Construction Cost tracing.
Further, the decorations standardization of products includes:
By norm, the Discourse of Enterprise's ration is classified according to construction technology for S101, foundation and perfect enterprise, setting unit construction In engineering, people, machine, the quantity and Price Range of material, and historical information is collected automatically;
S102, based on Discourse of Enterprise's ration, carry out the data normalization of decorations product, i.e., according to customer requirement, knot The unit constructor of associated construction setting, machine, the quantity and price of material in Discourse of Enterprise's ration are closed, material mark is unified with purchasing department Standard, sets up the list of decorations product and construction drawing, divides construction area, forms corresponding management unit.
Further, the enter outbound and service condition monitoring of the construction material includes:
S201, by the scanning that is identified to bar code, Quick Response Code or RFID read when outbound is entered Write, recording materials enter outbound state;
S202, internet long-distance Log server to DPM data servers is used by the interface that is connected with DPM management systems;
S203, information data is processed by DPM management systems, shown by graph mode.
Further, the construction speed is followed the trail of and included:
S301, unit division is carried out to project construction region, and carry out corresponding encoded, project site administrator will generate Bar code, Quick Response Code mark or RFID electronic marks, paste or be embedded into corresponding construction area, be easy to workmen lead to Overscan imaging apparatus are scanned;
S302, a certain construction task of certain unit construction area, constructor are completed according to construction plan as workmen Member scans paste or is embedded into the electronic mark in the region by scanning means, confirms that construction task is completed, long-range by interconnection Reach DPM data servers on the net;
S303, information data is processed by DPM management systems, statistics and tabulating unit region construct performance and Total body construction performance, and the either simplex kind efficiency of construction bond quality situation of each unit area is contrasted, and by figure Table mode shows.
Further, the construction quality control includes with analysis:
S401, pasted by bar code, Quick Response Code or RFID electronic marks or be embedded into job site, site operation personnel After completing a certain construction task of certain unit construction area, workmen scans paste or is embedded in the area by scanning means The electronic mark in domain, remotely by DPM management system interfaces, will confirm that information uploads to DPM data servers using internet. DPM management systems collect the information that job site uploads, and after being processed, system utilizes Work-flow control function, existing from trend Field administrative staff push quality inspection application;
S402, by DPM management system interfaces, site administrator receive a certain construction from unit construction area appoint Business quality inspection application information, within the time of regulation, site administrator is arranged into designated area and carries out quality inspection;
S403, quality inspection personnel at the scene, scan paste or are embedded into the electronic mark in the region, remotely using scanning means Corresponding quality inspection application is found using internet by DPM management system interfaces, quality information is confirmed, including quality inspection people name, There is problem in quality inspection time, quality inspection result, quality information is uploaded into DPM data servers;
S404, DPM management system are processed the data collected, every underproof region of quality inspection, and system passes through work Make flow control function, pushing rectification from the site operation personnel in the trend region applies, the corresponding workmen in the region, remotely The rectification application of a certain construction task from unit construction area, site operation people can be received by DPM management system interfaces Rectification requirement of the member in rectification application, arranges the rectification construction in the unqualified region of quality inspection, and is starting to rectify and improve and completing During rectification, the electronic mark for pasting or being embedded into the region is all scanned using scanning means, remotely connect by DPM management systems Mouthful, corresponding rectification application is found using internet, information is uploaded to DPM data servers;
S405, DPM management system are processed the data collected, and system is existing from trend by Work-flow control function Field administrative staff are pushed and recheck application, remotely pass through DPM management system interfaces, and site administrator is received from unit construction area The reinspection application information of a certain rectification task in domain.Within the time of regulation, site administrator is arranged into designated area and carries out matter Amount is rechecked;
S406, quality inspection personnel at the scene, scan paste or are embedded into the electronic mark in the region, remotely using scanning means Corresponding reinspection is found using internet to apply, reinspection information is uploaded to DPM data, services by DPM management system interfaces Device;
S407, DPM management system repeat rectification application, application process are rechecked, until inspection by Work-flow control function It is qualified;
S408, complete construction task in subregion or Zone Full, and after quality inspection is all qualified, DPM management systems are led to Work-flow control function is crossed, sampling observation application, remotely by DPM management system interfaces, quality are pushed from trend QA Supervisor department Authorities can receive the sampling observation application information that construction task region has been completed from project management department, within the time of regulation, quality Authorities are arranged into completion construction area and carry out sampling check for quality;
S409, sampling observation personnel scan the electricity for pasting or being embedded into the region using scanning means in the region inspected by random samples Sub-mark, remotely by DPM management system interfaces, corresponding sampling observation application is found using internet, and sampling observation information is uploaded to DPM data servers.
S410, DPM management system are processed the data collected, and every underproof region of sampling observation, system passes through work Make flow control function, the project manager for being responsible for the region from trend pushes rectification application, is remotely connect by DPM management systems Mouthful, site administrator is received from the rectification application information for inspecting unqualified region by random samples, after confirming through site administrator, automatically Rectification application is pushed to the workmen for being responsible for the region, remotely by DPM management system interfaces, the workmen in the region receives To from the construction rectification for after the rectification application information for inspecting unqualified region by random samples, arranging unqualified region;When start rectification and During completion, workmen scans the electronic mark for pasting or being embedded into the region using scanning means, and long-range management by DPM is System interface, corresponding rectification application is found using internet, and rectification information is uploaded into DPM data servers;
S411, DPM management system are returned by Work-flow control function according to flow original route, and system can be automatic The reinspection application of sampling observation is pushed to project manager, after confirming to scene through project manager, is scanned by onsite application Device scanning pastes or is embedded into the electronic mark in the region, remotely complete by DPM management system interfaces, confirmation rectification task Into being remotely uploaded to DPM data servers by internet.QA Supervisor department is returned to, sampling observation personnel can be according to ibid Flow confirmed, is uploaded to DPM data servers, until all rectification is qualified;
After S412, DPM management system are processed the information for collecting upload, count and tabulating unit region construction quality Qualification rate and overall construction quality qualification rate, Analysis of Quality Problem etc., graphically represent.
Further, the field worker construction task performance monitoring includes with analysis:
S501, by carrying out unit division to project construction region, and carry out corresponding encoded, project site administrator will The bar code of generation, Quick Response Code are identified or RFID electronic marks, paste or be embedded into corresponding construction area;
S502, when workmen starts to carry out construction operation to unit construction area, use scanning means scan paste Or it is embedded into the electronic mark in the region, remotely confirm to start construction information, bag using internet by DPM management system interfaces Time, workmen's name, the construction content for starting construction are included, information is uploaded to DPM data servers;
S503, when workmen completes the construction operation on the same day of unit construction area according to schedule, use scanning dress The electronic mark that the region is pasted or is embedded into scanning is put, remotely confirms to terminate using internet by DPM management system interfaces Construction information, including terminate time, workmen's name, the construction content of construction, it is uploaded to DPM data servers;
After S504, DPM management system process the information for collecting upload, start to apply according to unit area workmen Between man-hour and terminate the engineering time, collect and count field worker construction task complete efficiency, completion rate, graphically Represent.
Further, the project Dynamic Construction cost tracing includes:
When S601, construction material enter outbound, the electronic mark to pasting in advance or be embedded in material is identified, remotely By DPM management system interfaces, recording materials title, enter the information such as outbound state, be uploaded to DPM data servers;
When S602, site operation workman start construction operation and terminate construction operation, construction area is pasted or is embedded in Electronic mark is identified, and records the information such as the start and end time of construction area construction operation, and long-range management by DPM is System interface, is uploaded to DPM data servers;
S603, DPM management system are processed collecting the information for uploading, dynamic in real time to calculate and tabulating unit region Middle people, material, the consumption of machine, so as to count real-time project cost, realize the tracking of project Dynamic Construction cost.
Another aspect of the present invention, additionally provides a kind of decoration project work progress management system based on technology of Internet of things System, including:DPM data servers, and collection in worksite device, electronic tag;The electronic tag includes bar code, Quick Response Code With RFID electronic marks, the collection in worksite device includes reading bar code, the client device of Quick Response Code, and reads RFID The rfid interrogator of electronic mark;
The client device passes through network connection DPM data servers;
The rfid interrogator is controlled by Zigbee terminal management servers by Zigbee network, the Zigbee Terminal management server is provided with DPM management system interfaces, by network connection DPM data servers.
Further, the Zigbee network includes Zigbee telegons and Zigbee routers, the Zigbee terminals Management server, via Zigbee telegons and Zigbee routers, read write command is sent to rfid interrogator by software, Rfid interrogator sends radiofrequency signal, and triggering electronic mark work, electronic mark reads data information transfer RFID according to instruction Device is write, the data that rfid interrogator will be received are uploaded to DPM data servers by Zigbee wireless networks and internet.
Further, the client device is PC equipment or mobile device, and system is logged in for participating in project manager System, is acquired to electronic mark, in the range of corresponding authority, task is checked and is managed;By manually using, scanning electricity Bar code or Quick Response Code in subtab, and by software, DPM data servers are uploaded to through internet.
Relative to prior art, decoration project work progress management method based on technology of Internet of things of the present invention and System has the advantage that:
The present invention by project construction site setup bar code, Quick Response Code, rfid interrogator and electronic mark, before composition End data acquisition system, project construction scene is connected with DPM management systems to realize project construction scene real time data Transmit and shared;Decoration industry management method and system based on Internet of Things realize organization, Work-flow control, authority pipe The visualized managements such as reason, business rule, diagrammatic representation, user UI, with ripe Work Process Management function, by work flow tube Reason, business rule control and real-time tracking perfect adaptation, abundant chart function, in a short time can unite value information Meter collects out, solves problem of the information in terms of promptness, accuracy, for data analysis is provided accurately with excavation Data basis.
Brief description of the drawings
The accompanying drawing for constituting a part of the invention is used for providing a further understanding of the present invention, schematic reality of the invention Apply example and its illustrate, for explaining the present invention, not constitute inappropriate limitation of the present invention.In the accompanying drawings:
Fig. 1 is system structure diagram of the invention.
Wherein:
1st, DPM data servers;2nd, DPM management system interfaces;3rd, client;
4th, Zigbee network terminal management server;5th, Zigbee routers;6th, Zigbee telegons;
7th, rfid interrogator;8th, electronic mark;9th, bar code, two-dimension code label.
Specific embodiment
It should be noted that in the case where not conflicting, the feature in embodiments of the invention and embodiment can be mutual Combination.
The technical name referred in the present invention is explained as follows:
Internet of Things refers to by information such as radio frequency identification (RFID), infrared inductor, global positioning system, laser scanners Sensing equipment, by the agreement of agreement, thing and thing, people and thing, interpersonal, connection is set up by internet, enters row information Exchange and communicate, to realize Weigh sensor, positioning, tracking, monitoring and a kind of information network of management.Internet of Things is divided into perception Layer, Internet, application layer, the core technology of sensing layer is RFID technique, and the core technology of Internet is wireless sensor network Technology, the core technology of application layer is M2M technologies.
Bar code (barcode) technology is the multiple secret notes and blank for not waiting width, is arranged according to certain coding rule Row, are used to express the graphical identifier of a group information.Common bar code is the secret note (abbreviation bar) differed greatly by reflectivity The pattern of parallel lines lined up with informal voucher (referred to as empty).Bar code can mark many information of article.
Quick Response Code (2-dimensional bar code) is according to certain rules in plane with certain specific geometric figure The chequered with black and white graphic recording data symbol information of (on two-dimensional directional) distribution;Dexterously counted using composition on coding The concept of " 0 ", " 1 " bit stream on calculation machine internal logic basis, table is carried out using several geometrical bodies corresponding with binary system Show word numerical information, automatically processed with realizing information by image input device or photoelectric scanning device automatically identifying and reading:It has There are some general character of barcode technology:Every kind of code system has its specific character set;Each character occupies certain width;With certain Verifying function etc..Also there is the information automatic identification function and the treatment rotationally-varying point of figure to not going together simultaneously.
RFID technique is to couple to realize contactless information transmission by spatial electromagnetic using radiofrequency signal, and passes through to be transmitted Information realization object identification.The interoperability information of specification is store in RFID label tag, by wired or wireless mode them Automatic data collection realizes the identification to article to CIS, so as to realize that information is exchanged and shared by internet, realizes " transparent " management to article.
ZigBee is the low-power consumption LAN protocol based on IEEE802.15.4 standards.Specified according to international standard, ZigBee technology is the wireless communication technology of a kind of short distance, low-power consumption.This title (also known as ZigBee protocol) derives from honeybee Eight words dance, due to honeybee (bee) be by circle in the air and " drone " (zig) shake wing " dancing " come and companion transmission pollen Place azimuth information, that is to say, that honeybee constitutes the communication network in colony by such mode.Be characterized in closely, Low complex degree, self-organizing, low-power consumption, low data rate.It is mainly suitable for, for automatically controlling and remote control field, to be embedded in Various equipment.In brief, ZigBee is exactly a kind of cheap, the near radio networking mechanics of communication of low-power consumption.ZigBee It is a kind of wireless network protocol of low speed short-distance transmission.Zigbee protocol is respectively physical layer, media interviews control from top to bottom Preparative layer, transport layer, Internet, application layer etc..Wherein physical layer and MAC layer follow IEEE 802.15.4 standards Regulation.
Automatic identification technology refers to obtain identification information or feature letter that identified object is included by unartificial means Breath, and data are input into computer or other microprocessor controlled apparatus technologies in real time by not using keyboard.
Decoration construction industry DPM management systems, are exactly the manager of project, under limited resource constraint, with system Viewpoint, method and theory, combining information technology and internet, the whole work being related to project are effectively managed.I.e. The overall process terminated to project since the bid of project is planned, is organized, is commanded, is coordinated, controlled and is evaluated, to realize item Purpose target and management.
Describe the present invention in detail below with reference to the accompanying drawings and in conjunction with the embodiments.
The present invention devises a kind of decoration project work progress management method based on technology of Internet of things, management method step Rapid flow includes:Carry out the decorations standardization of products, set up with the connection of DPM management systems, construction material enter outbound and Service condition monitoring, construction speed are followed the trail of, construction quality control and analysis, field worker construction task performance are monitored and divided Analysis, project Dynamic Construction cost tracing.
The decorations standardization of products refers to set up with perfect enterprise by norm, and wherein Discourse of Enterprise's ration is carried out according to construction technology Classification, in setting unit construction work, people, machine, the quantity and Price Range of material, and historical information is collected automatically.Normalized number According to being engaged with design by buying, careful calculation, project, based on Discourse of Enterprise's ration, the standard of the decorations product for carrying out Change data procedures.First by design department according to customer requirement, the unit constructor that is set with reference to associated construction in Discourse of Enterprise's ration, The quantity and price of machine, material, material standard is unified with purchasing department, sets up the list of decorations product and construction drawing.
It refers to be connected to realize information transmission with DPM management systems by foundation that described foundation is connected with DPM management systems, The information transmission that will be collected to DPM data Layers, for the treatment of data provides basis with analyzing.
DPM management systems refer to realize the platform of decoration construction Whole Life Cycle of Projects management, by integrating applying for enterprise Work plan, goods and materials plan, resource planning, management and control is carried out to project to repair and maintenance overall process again from setting up the project to constructing, and is set up and enterprise The implementation method of DPM management systems connection includes:Set up independent data transmission interface;The data for developing DPM management systems are led Enter functional module.
The present invention realizes collection in worksite and monitor in real time by setting up with the connection of DPM management systems, and collection in worksite is Refer to the various operation information data gathered from during project site operation;Monitor in real time refers to by based on platform of internet of things reality When the information data of various project on-site construction operations states collected, information data is processed by DPM management systems, lead to Cross graph mode to show, reach the purpose for entering outbound state and service condition monitor in real time to construction material.
Collection in worksite and monitor in real time include:
First, construction material enter outbound and service condition monitoring:
Refer to the state status of storage by platform of internet of things remote real-time monitoring job site material and outbound, so that The service condition of analysis of material.Scanning is identified by bar code, Quick Response Code using scanning means, or to RFID Read-write, the information such as title, model, specification, the credit rating of recording materials is when outbound is entered by bar code, Quick Response Code mark The scanning of knowledge is written and read to high frequency RFID, and recording materials enter outbound state, are connect by DPM management systems Mouthful, use internet long-distance Log server to DPM data servers.Information data is processed by DPM management systems, by figure Table mode shows, reaches the purpose for entering outbound state and service condition monitor in real time to construction material.
2nd, construction speed tracking:
Refer to, by carrying out unit division to project construction region, and to carry out corresponding encoded, project site administrator will The bar code of generation, Quick Response Code are identified or RFID electronic marks, paste or be embedded into corresponding construction area, are easy to constructor Member is scanned by scanning means.When workmen completes a certain construction task of certain unit construction area according to construction plan, Workmen scans paste or is embedded into the electronic mark in the region by scanning means, confirms that construction task is completed, long-range logical Cross internet and be uploaded to DPM data servers.Information data is processed by DPM management systems, is counted and tabulating unit Region is constructed performance and total body construction performance, and it is right that the either simplex kind efficiency of construction bond quality situation of each unit area is carried out Than, shown by graph mode, reach the real-time tracing to current workmen and construction speed.3rd, construction quality prison Control and analysis:
Refer to be pasted by bar code, Quick Response Code or RFID electronic marks and be embedded into job site, site operation personnel After completing a certain construction task of certain unit construction area, workmen scans paste or is embedded in the area by scanning means The electronic mark in domain, remotely by DPM management system interfaces, will confirm that information uploads to DPM data servers using internet. DPM management systems collect the information that job site uploads, and after being processed, system utilizes Work-flow control function, existing from trend Field administrative staff push quality inspection application.
By DPM management system interfaces, site administrator can receive a certain construction task from unit construction area Quality inspection application information, within the time of regulation, site administrator is arranged into designated area and carries out quality inspection.
If quality inspection is qualified, quality inspection personnel at the scene, scans paste or is embedded into the region using scanning means Electronic mark, remotely by DPM management system interfaces, corresponding quality inspection application is found using internet, confirms such as quality inspection people's surname The information such as name, quality inspection time, quality inspection result, are uploaded to DPM data servers.
If quality inspection is unqualified, quality inspection personnel at the scene, is scanned using scanning means and pastes or be embedded into the region Electronic mark, remotely by DPM management system interfaces, corresponding quality inspection application is found using internet, confirm such as quality inspection people Name, quality inspection time, there is the information such as problem, upload to DPM data servers.
DPM management systems are processed the data collected, every underproof region of quality inspection, and system passes through workflow control Function processed, rectification application is pushed from the site operation personnel in the trend region, and the corresponding workmen in the region remotely passes through DPM management system interfaces, can receive the rectification application of a certain construction task from unit construction area, site operation personnel's root According to the rectification requirement in rectification application, the rectification construction in the unqualified region of quality inspection is arranged.
When rectification is started to the unqualified region of quality inspection, the scanning of site operation librarian use scanning means is pasted or is embedded into The electronic mark in the region, remotely by DPM management system interfaces, corresponding rectification application is found using internet, is confirmed out The information such as rectification time beginning, rectification people, rectification content, are uploaded to DPM data servers.
When workmen requires according to rectification, the rectification task of certain unit construction area is completed, workmen is by sweeping Imaging apparatus scanning pastes or is embedded into the electronic mark in the region, remotely by DPM management system interfaces, confirms that rectification task is complete Into being remotely uploaded to DPM data servers by internet.
DPM management systems are processed the data collected, and system passes through Work-flow control function, from trend field management Personnel push and recheck application, and remotely by DPM management system interfaces, site administrator receives a certain from unit construction area The reinspection application information of rectification task.Within the time of regulation, site administrator is arranged into designated area and carries out quality reinspection.
If reinspection is qualified, quality inspection personnel at the scene, scans paste or is embedded into the electronics in the region using scanning means Mark, remotely by DPM management system interfaces, finds corresponding reinspection and applies using internet, confirms such as quality inspection people name, matter The information such as inspection time, quality inspection result, are uploaded to DPM data servers.
If reinspection is unqualified, quality inspection personnel scans paste or is embedded into the electronics in the region using scanning means at the scene The mode of mark, remotely by DPM management system interfaces, confirms such as quality inspection people name, quality inspection time, exists and ask using internet The information such as topic, upload to DPM data servers.
DPM management systems repeat rectification application, recheck application process by Work-flow control function, qualified until checking.
Construction task is completed in subregion or Zone Full, and after quality inspection is all qualified, DPM management systems pass through work Flow control function, sampling observation application, remotely by DPM management system interfaces, QA Supervisor portion are pushed from trend QA Supervisor department Door can receive the sampling observation application information that construction task region has been completed from project management department.Within the time of regulation, QA Supervisor portion Door is arranged into completion construction area and carries out sampling check for quality.
If sampling observation is qualified, sampling observation personnel are scanned using scanning means and paste or be embedded into this in the region inspected by random samples The electronic mark in region, remotely by DPM management system interfaces, corresponding sampling observation application is found using internet, and confirmation is such as taken out The information such as inspection people name, sampling observation time, Examined, are uploaded to DPM data servers.
If sampling observation is unqualified, sampling observation personnel scan the electronics for pasting or being embedded into the region using scanning means at the scene Mark, remotely by DPM management system interfaces, corresponding sampling observation application is found using internet, is confirmed such as sampling observation people name, is taken out The information such as inspection time, sampling observation problem, upload to DPM data servers.
DPM management systems are processed the data collected, unqualified when inspecting by random samples, and system passes through Work-flow control function, The project manager for being responsible for the region from trend pushes rectification application, remotely by DPM management system interfaces, field management people Member is received from the rectification application information for inspecting unqualified region by random samples, after confirming through site administrator, the region is responsible for from trend Workmen push rectification application, remotely by DPM management system interfaces, the workmen in the region is received from sampling observation not After the rectification application information in qualified region, the construction rectification in unqualified region is arranged.
When rectification is started to inspecting unqualified region by random samples, workmen is scanned using scanning means and pastes or be embedded into the area The electronic mark in domain, remotely passes through DPM management system interfaces, and corresponding rectification application is found using internet, confirms that beginning is whole Change the information such as time, rectification people, rectification content, be uploaded to DPM data servers.
When workmen according to rectification require, complete rectification task when, workmen by scanning means scan paste or It is embedded into the electronic mark in the region, remotely by DPM management system interfaces, confirms that rectification task is completed, it is long-range by interconnection Reach DPM data servers on the net.
DPM management systems are returned by Work-flow control function according to flow original route, and system meeting automatic push are taken out The reinspection application of inspection after confirming to scene through project manager, is swept to project manager by onsite application scanning means Retouch paste or be embedded into the electronic mark in the region, remotely by DPM management system interfaces, confirm that rectification task is completed, remotely DPM data servers are uploaded to by internet.QA Supervisor department is returned to, sampling observation personnel can be carried out according to flow ibid Confirm, be uploaded to DPM data servers, until all rectification is qualified.
Identification by front end sensing layer to electronic mark, relevant information is collected and DPM data servers are uploaded to, After DPM management systems are processed the information for collecting upload, count and tabulating unit region construction quality qualification rate and totality Construction quality qualification rate, Analysis of Quality Problem etc., graphically show, reach to the monitoring of project construction quality with Analysis.
4th, the monitoring of field worker construction task performance and analysis:
Refer to, by carrying out unit division to project construction region, and to carry out corresponding encoded, project site administrator will The bar code of generation, Quick Response Code are identified or RFID electronic marks, paste or be embedded into corresponding construction area, are easy to constructor Member is scanned by scanning means.
When workmen starts to carry out construction operation to unit construction area, paste or embedded is scanned using scanning means To the electronic mark in the region, remotely by DPM management system interfaces, confirm to start the time of construction, construction using internet The information such as personnel's name, construction content, DPM data servers are uploaded to by information.
When workmen completes the construction operation on the same day of unit construction area according to schedule, scanned using scanning means The electronic mark in the region is pasted or be embedded into, remotely by DPM management system interfaces, confirms to terminate construction using internet The information such as time, workmen's name, construction content, are uploaded to DPM data servers.
Identification by sensing layer to electronic mark, relevant information is corresponding with zone number, and collection information is simultaneously uploaded To DPM data servers, after DPM management systems are processed the information for collecting upload, according to unit area, workmen opens Begin engineering time and end engineering time, collect and count field worker construction task and complete efficiency, completion rate, with chart Form represents, and reaches the purpose of the monitoring of field worker construction task performance and analysis.
5th, project Dynamic Construction cost tracing:
Refer to that when entering outbound by construction material, the electronic mark to pasting in advance or be embedded in material is identified, Remotely by DPM management system interfaces, recording materials title, enter the information such as outbound state, be uploaded to DPM data servers.
When starting construction operation and terminate construction operation by site operation workman, construction area is pasted or embedded electricity Sub-mark is identified, and records the information such as the start and end time of construction area construction operation, remotely passes through DPM management systems Interface, is uploaded to DPM data servers.
DPM management systems can be processed collecting the information for uploading, in real time in dynamic calculating and tabulating unit region People, material, the consumption of machine, so as to count real-time project cost, realize the tracking of project Dynamic Construction cost.
Present invention also offers a kind of decoration project work progress management system based on technology of Internet of things, including:1、DPM Data server, 2, DPM management system interfaces, 3, client computer are divided into PC ends and mobile terminal, 4, Zigbee network terminal Management server, 5, Zigbee routers, 6, Zigbee telegons, 7, rfid interrogator, 8, electronic mark, 9, bar code, two Dimension code label;The various information that DPM data servers 1 are used for the job site to collecting are stored, analyzed and processed;
DPM management system interfaces 2 are connected with DPM data servers, the various information of the job site for that will collect Uploaded, stored, analyzed and processed;
3 points of client is PC ends and mobile terminal, for participating in project manager's login system, electronic mark is adopted Collection, in the range of corresponding authority, is checked and is managed to task;
Zigbee terminal management servers 4 are connected with Zigbee telegons 6, for being sent and received to RFID card reader 7 Control instruction.
The connection Zigbee of Zigbee telegons 6 routers 5, the Zigbee network for setting up project construction scene services real The function of existing data transfer layer;
Client computer mobile terminal 3 coordinates with bar code, two-dimension code label 9, rfid interrogator 7 and electronic mark 8, receives The people at collection project construction scene, material, the data message of machine are acquired.
The present invention takes two kinds of data acquisition modes, the first:Using client computer mobile terminal 3, to zoning The mode that interior bar code, two-dimension code label 9 are scanned, collects data.Second:By Zigbee terminal management servers 4, By Zigbee network service, rfid interrogator 7 is controlled, read the mode of electronic mark 8, collect data.
In collection project construction procedural information such as:During the data such as progress, quality, using first way, by manually using Client computer mobile terminal 3 (equipment such as mobile phone, PDA), scanning is pasted onto the bar code or two-dimension code label 9 of construction area, By mobile terminal software, DPM data servers 1 are uploaded to through internet.
When collection construction material goes out to be put in storage information, using Zigbee network service, assisted through Zigbee by terminal server 4 Device 6 and Zigbee routers 5 are adjusted, rfid interrogator 7 is controlled, the information of reading electronic labels 8 is soft by terminal server Part, DPM data servers 1 are uploaded to through internet.According to project construction field condition, it is also possible to use the first collection side Formula.
The scanning of client 3 bar code, the operation principle of two-dimension code label are the optical signals that will be detected using photoelectric cell Electric signal is converted into, electric signal is converted into data signal by analog-digital converter, after being processed through computer, reduction is corresponding Information.
The operation principle that rfid interrogator 7 reads RFID electronic marks is that terminal server 4 passes through software, via Zigbee Telegon 6 and Zigbee routers 5, read write command is sent to rfid interrogator 7, and rfid interrogator 7 sends radiofrequency signal, triggering RFID electronic marks 8 work, and RFID electronic marks 8 are according to instruction by data information transfer rfid interrogator 7, rfid interrogator 7 The data that will be received are uploaded to DPM data servers 1 by Zigbee wireless networks and internet.
RFID electronic marks 8 are embedded on object correlation, are provided with wireless transmitter, built-in storage chip, The information for being responsible for RFID electronic marks is preserved, built-in dual-mode antenna, for receiving and sending information.When object passes through or is placed into During 7 identification range of rfid interrogator, the radiofrequency signal that rfid interrogator 7 sends, after RFID electronic marks 8 are received, by RFID electricity The information stored in the chip of sub-mark 8 is sent to corresponding rfid interrogator 7.
RFID electronic marks 8 are the information of passive type storage identification object, and passive type RFID electronic marks are passive RFID electronic marks, electric flux is that the electromagnetic signal sent by rfid interrogator 7 is produced.When RFID electronic marks 8 enter During the identification range of rfid interrogator 7, the antenna of RFID electronic marks 8 receives the radio frequency letter sent from rfid interrogator 7 After number, the characteristic transmitted using radiofrequency signal and Space Coupling produces energy, is operated RFID electronic marks 8, so that Rfid interrogator 7 can just receive data message of the storage in the chip of RFID electronic marks 8.The core of RFID electronic marks 8 Piece is made up of holder, modulator, power-supply controller of electric, clock, logic unit, digital circuit.The antenna of RFID electronic marks 8 The bridge that to be rfid interrogator 7 link up with RFID electronic marks 8, antenna receives the radiofrequency signal that rfid interrogator 7 sends and refers to Order, and the data message that RFID electronic marks 8 are stored is sent to rfid interrogator 7.
Rfid interrogator 7 is the equipment for reading and writing the information of RFID electronic marks 8, rfid interrogator 7 by transceiver, memory, Microprocessor, external sensor I/O interfaces, communication interface and power supply composition, it by the read write command of terminal management server 4, RFID electronic marks 8 are sent to by Radio Network System, and data are encrypted, and to letter that RFID electronic marks are beamed back Breath is decrypted, and sends terminal management server 4 to, and the data transfer between them, rfid interrogator 7 are controlled by application software After receiving the instruction of application software, radiofrequency signal is sent to RFID electronic marks 8, RFID electronic marks 8 receive radiofrequency signal Afterwards, relevant information is returned to rfid interrogator 7, and rfid interrogator 7 is received after relevant information processed, by network system Data message is uploaded into terminal management server 4.
Presently preferred embodiments of the present invention is the foregoing is only, is not intended to limit the invention, it is all in essence of the invention Within god and principle, any modification, equivalent substitution and improvements made etc. should be included within the scope of the present invention.

Claims (10)

1. a kind of decoration project work progress management method based on technology of Internet of things, it is characterised in that including:
Decorations product data standardization in DPM management systems;Set up job site harvester and set up and DPM management The connection of system;Field data is gathered and monitor in real time;
Wherein, the field data collection includes with monitor in real time:Construction material enter outbound and service condition monitoring;Construct into Degree is followed the trail of;Construction quality control and analysis;Field worker construction task performance is monitored and analysis;Project Dynamic Construction cost Tracking.
2. management method according to claim 1, it is characterised in that the decorations standardization of products includes:
By norm, the Discourse of Enterprise's ration is classified according to construction technology for S101, foundation and perfect enterprise, sets unit construction work In, people, machine, the quantity and Price Range of material, and historical information is collected automatically;
S102, based on Discourse of Enterprise's ration, carry out the data normalization of decorations product, i.e., according to customer requirement, with reference to enterprise The unit constructor of associated construction setting, machine, the quantity and price of material, material standard is unified with purchasing department in industry quota, is built The vertical list of decorations product and construction drawing, divide construction area, form corresponding management unit.
3. management method according to claim 1, it is characterised in that the construction material enters outbound and service condition prison Control includes:
S201, by the scanning that is identified to bar code, Quick Response Code or RFID is written and read when outbound is entered, remembered That records material enters outbound state;
S202, internet long-distance Log server to DPM data servers is used by the interface that is connected with DPM management systems;
S203, information data is processed by DPM management systems, shown by graph mode.
4. management method according to claim 1, it is characterised in that the construction speed is followed the trail of to be included:
S301, unit division is carried out to project construction region, and carry out corresponding encoded, the bar that project site administrator will generate Shape code, Quick Response Code mark or RFID electronic marks, paste or are embedded into corresponding construction area, are easy to workmen to pass through to sweep Imaging apparatus are scanned;
S302, when workmen completes a certain construction task of certain unit construction area according to construction plan, workmen is led to The scanning of overscan imaging apparatus pastes or is embedded into the electronic mark in the region, confirms that construction task is completed, remotely by internet Reach DPM data servers;
S303, information data is processed by DPM management systems, statistics and tabulating unit region are constructed performance and totality Construction performance, and the either simplex kind efficiency of construction bond quality situation of each unit area is contrasted, and by chart side Formula shows.
5. management method according to claim 1, it is characterised in that the construction quality control includes with analysis:
S401, pasted by bar code, Quick Response Code or RFID electronic marks or be embedded into job site, site operation personnel complete After a certain construction task of certain unit construction area, workmen scans paste or is embedded in the region by scanning means Electronic mark, remotely by DPM management system interfaces, will confirm that information uploads to DPM data servers using internet.DPM Management system collects the information that job site uploads, and after being processed, system utilizes Work-flow control function, from trend field pipes Reason personnel push quality inspection application;
S402, by DPM management system interfaces, site administrator receives a certain construction task matter from unit construction area Inspection application information, within the time of regulation, site administrator is arranged into designated area and carries out quality inspection;
S403, quality inspection personnel at the scene, scan paste or are embedded into the electronic mark in the region using scanning means, remotely pass through DPM management system interfaces find corresponding quality inspection application using internet, confirm quality information, including quality inspection people name, quality inspection There is problem in time, quality inspection result, quality information is uploaded into DPM data servers;
S404, DPM management system are processed the data collected, every underproof region of quality inspection, and system passes through workflow Control function, rectification application is pushed from the site operation personnel in the trend region, and the corresponding workmen in the region remotely passes through DPM management system interfaces can receive the rectification application of a certain construction task from unit construction area, site operation personnel's root According to the rectification requirement in rectification application, the rectification construction in the unqualified region of quality inspection is arranged, and starting to rectify and improve and complete rectification When, the electronic mark for pasting or being embedded into the region is all scanned using scanning means, remotely by DPM management system interfaces, make Corresponding rectification application is found with internet, information is uploaded to DPM data servers;
S405, DPM management system are processed the data collected, and system passes through Work-flow control function, from trend field pipes Reason personnel are pushed and recheck application, and remotely by DPM management system interfaces, site administrator is received from unit construction area The reinspection application information of item rectification task.Regulation time in, site administrator be arranged into designated area carry out quality answer Inspection;
S406, quality inspection personnel at the scene, scan paste or are embedded into the electronic mark in the region using scanning means, remotely pass through DPM management system interfaces find corresponding reinspection using internet to be applied, reinspection information is uploaded into DPM data servers;
S407, DPM management system repeat rectification application, recheck application process by Work-flow control function, until inspection is closed Lattice;
S408, complete construction task in subregion or Zone Full, and after quality inspection is all qualified, DPM management systems pass through work Make flow control function, sampling observation application, remotely by DPM management system interfaces, QA Supervisor are pushed from trend QA Supervisor department Department can receive the sampling observation application information that construction task region has been completed from project management department, within the time of regulation, QA Supervisor Department is arranged into completion construction area and carries out sampling check for quality;
S409, sampling observation personnel scan the electronics mark for pasting or being embedded into the region using scanning means in the region inspected by random samples Know, remotely by DPM management system interfaces, corresponding sampling observation application is found using internet, sampling observation information is uploaded to DPM numbers According to server.
S410, DPM management system are processed the data collected, and every underproof region of sampling observation, system passes through workflow Control function, the project manager for being responsible for the region from trend pushes rectification application, remotely by DPM management system interfaces, Site administrator is received from the rectification application information for inspecting unqualified region by random samples, after confirming through site administrator, from trend The workmen for being responsible for the region pushes rectification application, and remotely by DPM management system interfaces, the workmen in the region receives From the construction rectification for after the rectification application information for inspecting unqualified region by random samples, arranging unqualified region;When start rectification and it is complete Cheng Shi, workmen scans the electronic mark for pasting or being embedded into the region using scanning means, remotely passes through DPM management systems Interface, corresponding rectification application is found using internet, and rectification information is uploaded into DPM data servers;
S411, DPM management system are returned by Work-flow control function according to flow original route, and system can automatic push The reinspection application of sampling observation to project manager, after confirming to scene through project manager, by onsite application scanning means Scanning pastes or is embedded into the electronic mark in the region, is remotely completed by DPM management system interfaces, confirmation rectification task, far Journey is uploaded to DPM data servers by internet.QA Supervisor department is returned to, sampling observation personnel can enter according to flow ibid Row confirmation, is uploaded to DPM data servers, until all rectification is qualified;
After S412, DPM management system are processed the information for collecting upload, statistics and tabulating unit region construction quality are qualified Rate and overall construction quality qualification rate, Analysis of Quality Problem etc., graphically represent.
6. management method according to claim 1, it is characterised in that the field worker construction task performance monitoring Include with analysis:
S501, by carrying out unit division to project construction region, and carry out corresponding encoded, project site administrator will generate Bar code, Quick Response Code mark or RFID electronic marks, paste or be embedded into corresponding construction area;
S502, when workmen starts to carry out construction operation to unit construction area, use scanning means scan paste or it is embedding Enter the electronic mark to the region, remotely confirm to start construction information using internet by DPM management system interfaces, including open Begin time, workmen's name, the construction content constructed, and information is uploaded into DPM data servers;
S503, when workmen completes the construction operation on the same day of unit construction area according to schedule, swept using scanning means The electronic mark for pasting or being embedded into the region is retouched, remotely confirms to terminate construction using internet by DPM management system interfaces Information, including terminate time, workmen's name, the construction content of construction, it is uploaded to DPM data servers;
After S504, DPM management system are processed the information for collecting upload, when starting construction according to unit area workmen Between and terminate the engineering time, collect and count field worker construction task complete efficiency, completion rate, graphically open up It is existing.
7. management method according to claim 1, it is characterised in that the project Dynamic Construction cost tracing includes:
When S601, construction material enter outbound, the electronic mark to pasting in advance or be embedded in material is identified, and remotely passes through DPM management system interfaces, recording materials title, enter the information such as outbound state, are uploaded to DPM data servers;
When S602, site operation workman start construction operation and terminate construction operation, construction area is pasted or embedded electronics Mark is identified, and records the information such as the start and end time of construction area construction operation, is remotely connect by DPM management systems Mouthful, it is uploaded to DPM data servers;
S603, DPM management system are processed collecting the information for uploading, in real time in dynamic calculating and tabulating unit region People, material, the consumption of machine, so as to count real-time project cost, realize the tracking of project Dynamic Construction cost.
8. a kind of decoration project work progress management system based on technology of Internet of things, it is characterised in that including:DPM data take Business device, and collection in worksite device, electronic tag;The electronic tag includes bar code, Quick Response Code and RFID electronic marks, institute Stating collection in worksite device includes reading bar code, the client device of Quick Response Code, and the RFID readings for reading RFID electronic marks Write device;
The client device passes through network connection DPM data servers;
The rfid interrogator is controlled by Zigbee terminal management servers by Zigbee network, the Zigbee terminals Management server is provided with DPM management system interfaces, by network connection DPM data servers.
9. management system according to claim 8, it is characterised in that the Zigbee network include Zigbee telegons and Zigbee routers, the Zigbee terminal management servers pass through software, via Zigbee telegons and Zigbee routers, Send read write command to rfid interrogator, rfid interrogator sends radiofrequency signal, triggering electronic mark work, electronic mark according to Data information transfer rfid interrogator, the data that rfid interrogator will be received are passed through Zigbee wireless networks and interconnection by instruction Reach DPM data servers on the net.
10. management system according to claim 8, it is characterised in that the client device is that PC equipment or movement set It is standby, for participating in project manager's login system, electronic mark is acquired, in the range of corresponding authority, task is entered Row is checked and managed;By manually using, bar code or Quick Response Code in scanning electron label, and by software, through on internet Reach DPM data servers.
CN201710114439.0A 2017-02-28 2017-02-28 Method and system of decoration project construction management based on technology of internet of things Pending CN106709703A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710114439.0A CN106709703A (en) 2017-02-28 2017-02-28 Method and system of decoration project construction management based on technology of internet of things

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710114439.0A CN106709703A (en) 2017-02-28 2017-02-28 Method and system of decoration project construction management based on technology of internet of things

Publications (1)

Publication Number Publication Date
CN106709703A true CN106709703A (en) 2017-05-24

Family

ID=58917666

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710114439.0A Pending CN106709703A (en) 2017-02-28 2017-02-28 Method and system of decoration project construction management based on technology of internet of things

Country Status (1)

Country Link
CN (1) CN106709703A (en)

Cited By (26)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107480912A (en) * 2017-08-31 2017-12-15 福建四创软件有限公司 Hydraulic engineering construction comprehensive management system based on big data analysis and Internet of Things
CN107480113A (en) * 2017-07-04 2017-12-15 宁夏东睿建筑科技有限公司 A kind of information-based cloud service platform product coding method
CN107831750A (en) * 2017-12-04 2018-03-23 青岛鹏海软件有限公司 IMES Intelligent Manufacturing Execution Systems
CN107977781A (en) * 2017-11-21 2018-05-01 上海筑想信息科技股份有限公司 Residence development project decoration construction quality inspection man-machine interactive system based on mobile terminal
CN108225814A (en) * 2017-11-25 2018-06-29 佛山职业技术学院 A kind of soil sample method based on technology of Internet of things
CN108469739A (en) * 2018-03-01 2018-08-31 深圳市百创网络科技有限公司 Remote home packing quality control system based on Internet of Things, video and artificial intelligence
CN108564343A (en) * 2018-04-11 2018-09-21 中国冶集团有限公司 A kind of pipe prefabrication construction method using BIM technology
CN108876190A (en) * 2018-07-09 2018-11-23 杭州溯影信息技术有限公司 A kind of engineering witness management method, system, device and medium
CN109118174A (en) * 2018-08-08 2019-01-01 厦门辰航工贸有限公司 Interconnect intelligence system
CN109165869A (en) * 2018-09-14 2019-01-08 广东电网有限责任公司 A kind of construction managing and control system and management-control method
CN109360123A (en) * 2018-10-22 2019-02-19 上海建工四建集团有限公司 A kind of multi-specialized execution management method therefor and system based on room
CN110428026A (en) * 2019-07-18 2019-11-08 国网河北省电力有限公司 The system and method that identification power grid infrastructure project is broken rules and regulations safely
CN111210209A (en) * 2020-04-20 2020-05-29 成都一智科技有限公司 Building engineering acceptance and wage approval management system with identity recognition function
CN111598402A (en) * 2020-04-20 2020-08-28 深圳市特辰科技股份有限公司 Method, system, server, terminal and storage medium for managing shelf-climbing product
CN112163649A (en) * 2020-09-24 2021-01-01 中铁七局集团电务工程有限公司 Automatic acquisition method for installation progress of electromechanical equipment of subway station
CN112258022A (en) * 2020-10-20 2021-01-22 中国石油集团渤海钻探工程有限公司 Well control device management system and method based on Internet of things and Internet
CN112351255A (en) * 2020-11-03 2021-02-09 浙江正和监理有限公司 Whole-process intelligent building engineering supervision system and method
CN112434906A (en) * 2020-10-28 2021-03-02 中建科技武汉有限公司 Generation method and device of complex process interpenetration slash analysis chart
CN112668679A (en) * 2020-12-21 2021-04-16 中铁十八局集团第三工程有限公司 Tunnel engineering construction quota measuring system and method
CN113095797A (en) * 2021-05-18 2021-07-09 河南佳润新材料有限公司 System for recording and tracing construction process in ceramic tile embedding project
CN113392941A (en) * 2021-05-08 2021-09-14 成都亲生命科技有限公司 Application of intelligent assembled material based on Radio Frequency Identification (RFID) technology
CN113487184A (en) * 2021-07-06 2021-10-08 江苏高速公路信息工程有限公司 Highway electromechanical engineering informatization control platform and method thereof
CN113743765A (en) * 2021-08-27 2021-12-03 深圳市炎唐装饰有限公司 Decoration project construction process management method and system based on Internet of things technology
CN114219429A (en) * 2021-12-08 2022-03-22 金华送变电工程有限公司 Engineering quality and progress management method and system based on RFID
CN115860429A (en) * 2023-01-06 2023-03-28 三峡高科信息技术有限责任公司 Pipe network construction management method and system based on label two-dimensional code
CN116011778A (en) * 2023-02-03 2023-04-25 杭州良渚古城文旅集团有限公司 Water conservancy river construction management system based on data analysis

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103810576A (en) * 2014-03-07 2014-05-21 西安工业大学 Workshop production management method and system based on Internet of Things
CN104156812A (en) * 2014-08-04 2014-11-19 江苏鼎思科技发展有限公司 Construction project construction site original data acquisition system and acquisition method
CN105225040A (en) * 2015-09-25 2016-01-06 中铁建电气化局集团南方工程有限公司 Based on the preparation of construction material overall process method for tracing of Internet of Things
CN106056268A (en) * 2016-05-17 2016-10-26 北京诺士诚国际工程项目管理有限公司 Engineering project management cloud platform system based on material tracking
CN206541333U (en) * 2017-02-28 2017-10-03 天津华惠安信装饰工程有限公司 A kind of decoration project work progress management system based on technology of Internet of things

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103810576A (en) * 2014-03-07 2014-05-21 西安工业大学 Workshop production management method and system based on Internet of Things
CN104156812A (en) * 2014-08-04 2014-11-19 江苏鼎思科技发展有限公司 Construction project construction site original data acquisition system and acquisition method
CN105225040A (en) * 2015-09-25 2016-01-06 中铁建电气化局集团南方工程有限公司 Based on the preparation of construction material overall process method for tracing of Internet of Things
CN106056268A (en) * 2016-05-17 2016-10-26 北京诺士诚国际工程项目管理有限公司 Engineering project management cloud platform system based on material tracking
CN206541333U (en) * 2017-02-28 2017-10-03 天津华惠安信装饰工程有限公司 A kind of decoration project work progress management system based on technology of Internet of things

Cited By (30)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107480113A (en) * 2017-07-04 2017-12-15 宁夏东睿建筑科技有限公司 A kind of information-based cloud service platform product coding method
CN107480912A (en) * 2017-08-31 2017-12-15 福建四创软件有限公司 Hydraulic engineering construction comprehensive management system based on big data analysis and Internet of Things
CN107977781A (en) * 2017-11-21 2018-05-01 上海筑想信息科技股份有限公司 Residence development project decoration construction quality inspection man-machine interactive system based on mobile terminal
CN108225814A (en) * 2017-11-25 2018-06-29 佛山职业技术学院 A kind of soil sample method based on technology of Internet of things
CN107831750A (en) * 2017-12-04 2018-03-23 青岛鹏海软件有限公司 IMES Intelligent Manufacturing Execution Systems
CN107831750B (en) * 2017-12-04 2024-03-22 青岛鹏海软件有限公司 IMES intelligent manufacturing execution system
CN108469739A (en) * 2018-03-01 2018-08-31 深圳市百创网络科技有限公司 Remote home packing quality control system based on Internet of Things, video and artificial intelligence
CN108564343A (en) * 2018-04-11 2018-09-21 中国冶集团有限公司 A kind of pipe prefabrication construction method using BIM technology
CN108876190A (en) * 2018-07-09 2018-11-23 杭州溯影信息技术有限公司 A kind of engineering witness management method, system, device and medium
CN109118174A (en) * 2018-08-08 2019-01-01 厦门辰航工贸有限公司 Interconnect intelligence system
CN109165869A (en) * 2018-09-14 2019-01-08 广东电网有限责任公司 A kind of construction managing and control system and management-control method
CN109360123A (en) * 2018-10-22 2019-02-19 上海建工四建集团有限公司 A kind of multi-specialized execution management method therefor and system based on room
CN110428026A (en) * 2019-07-18 2019-11-08 国网河北省电力有限公司 The system and method that identification power grid infrastructure project is broken rules and regulations safely
CN110428026B (en) * 2019-07-18 2023-02-10 国网河北省电力有限公司 System and method for identifying power grid infrastructure construction safety violation
CN111210209A (en) * 2020-04-20 2020-05-29 成都一智科技有限公司 Building engineering acceptance and wage approval management system with identity recognition function
CN111598402A (en) * 2020-04-20 2020-08-28 深圳市特辰科技股份有限公司 Method, system, server, terminal and storage medium for managing shelf-climbing product
CN112163649A (en) * 2020-09-24 2021-01-01 中铁七局集团电务工程有限公司 Automatic acquisition method for installation progress of electromechanical equipment of subway station
CN112258022A (en) * 2020-10-20 2021-01-22 中国石油集团渤海钻探工程有限公司 Well control device management system and method based on Internet of things and Internet
CN112434906A (en) * 2020-10-28 2021-03-02 中建科技武汉有限公司 Generation method and device of complex process interpenetration slash analysis chart
CN112351255A (en) * 2020-11-03 2021-02-09 浙江正和监理有限公司 Whole-process intelligent building engineering supervision system and method
CN112668679A (en) * 2020-12-21 2021-04-16 中铁十八局集团第三工程有限公司 Tunnel engineering construction quota measuring system and method
CN112668679B (en) * 2020-12-21 2023-04-25 中铁十八局集团有限公司 Tunnel engineering construction quota measurement system and method
CN113392941A (en) * 2021-05-08 2021-09-14 成都亲生命科技有限公司 Application of intelligent assembled material based on Radio Frequency Identification (RFID) technology
CN113095797A (en) * 2021-05-18 2021-07-09 河南佳润新材料有限公司 System for recording and tracing construction process in ceramic tile embedding project
CN113487184A (en) * 2021-07-06 2021-10-08 江苏高速公路信息工程有限公司 Highway electromechanical engineering informatization control platform and method thereof
CN113743765A (en) * 2021-08-27 2021-12-03 深圳市炎唐装饰有限公司 Decoration project construction process management method and system based on Internet of things technology
CN114219429A (en) * 2021-12-08 2022-03-22 金华送变电工程有限公司 Engineering quality and progress management method and system based on RFID
CN115860429A (en) * 2023-01-06 2023-03-28 三峡高科信息技术有限责任公司 Pipe network construction management method and system based on label two-dimensional code
CN116011778A (en) * 2023-02-03 2023-04-25 杭州良渚古城文旅集团有限公司 Water conservancy river construction management system based on data analysis
CN116011778B (en) * 2023-02-03 2023-08-15 杭州良渚古城文旅集团有限公司 Water conservancy river construction management system based on data analysis

Similar Documents

Publication Publication Date Title
CN106709703A (en) Method and system of decoration project construction management based on technology of internet of things
De Vass et al. The effect of “Internet of Things” on supply chain integration and performance: An organisational capability perspective
CN103810576A (en) Workshop production management method and system based on Internet of Things
CN105023201B (en) Assembled architecture Deepen Design and construction method based on BIM and big data
CN101556475B (en) Real-time tracking system for processing materials and production process based on radio frequency technique
CN203773582U (en) Real-time monitoring system of warehouse
CN106408173A (en) Quality random inspection execution process supervision system
Ikonen et al. Use of embedded RFID tags in concrete element supply chains.
CN110119801A (en) The method and system of the automatic check and accepting storing of equipment arrival
CN103810563A (en) RFID based electric power asset entire life-cycle management system
CN109087048A (en) Assembled architecture component method for tracing based on two dimensional code
CN107516136A (en) Power Line Inspection System
CN102185745A (en) IOT (internet of things) service system
CN105574698A (en) Intelligent storage management system based on big data
CN209785041U (en) system for equipment is arrived goods and is automatically inspected and accepted warehouse entry
Bendavid et al. Bridging the gap between RFID/EPC concepts, technological requirements and supply chain e-business processes
CN105654219A (en) Two-dimensional-code-based intelligent instrument life-cycle management system
CN206541333U (en) A kind of decoration project work progress management system based on technology of Internet of things
CN104463297A (en) Asset two-dimensional code identification application method and device structure
Liu et al. Applications of RFID technology for improving production efficiency in an integrated-circuit packaging house
CN103149855A (en) Remote monitoring system for offshore piling
CN109460804A (en) Intelligent aeronautical maintenance management system based on handheld terminal
Ustundag et al. Digital traceability through production value chain
CN106682547B (en) A kind of portable integrated intelligence is received terminal and its application
Sarkar et al. Development of an integrated BIM-ERP-IoT module for construction projects in Ahmedabad

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination