CN110428026A - The system and method that identification power grid infrastructure project is broken rules and regulations safely - Google Patents
The system and method that identification power grid infrastructure project is broken rules and regulations safely Download PDFInfo
- Publication number
- CN110428026A CN110428026A CN201910649683.6A CN201910649683A CN110428026A CN 110428026 A CN110428026 A CN 110428026A CN 201910649683 A CN201910649683 A CN 201910649683A CN 110428026 A CN110428026 A CN 110428026A
- Authority
- CN
- China
- Prior art keywords
- dimensional code
- regulations
- server
- power grid
- safety
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 21
- 238000012544 monitoring process Methods 0.000 claims abstract description 44
- 238000004891 communication Methods 0.000 claims abstract description 24
- 239000004575 stone Substances 0.000 claims abstract description 18
- 238000012360 testing method Methods 0.000 claims abstract description 18
- 238000010276 construction Methods 0.000 claims description 45
- 238000013507 mapping Methods 0.000 claims description 9
- 238000012806 monitoring device Methods 0.000 claims description 7
- 230000003760 hair shine Effects 0.000 claims description 3
- 230000005611 electricity Effects 0.000 abstract description 6
- 238000005516 engineering process Methods 0.000 description 7
- 238000010586 diagram Methods 0.000 description 5
- 238000013135 deep learning Methods 0.000 description 3
- 238000013473 artificial intelligence Methods 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000009172 bursting Effects 0.000 description 1
- 238000013461 design Methods 0.000 description 1
- 238000011161 development Methods 0.000 description 1
- 235000013399 edible fruits Nutrition 0.000 description 1
- 230000008030 elimination Effects 0.000 description 1
- 238000003379 elimination reaction Methods 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06K—GRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
- G06K17/00—Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations
- G06K17/0022—Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations arrangements or provisious for transferring data to distant stations, e.g. from a sensing device
- G06K17/0025—Methods or arrangements for effecting co-operative working between equipments covered by two or more of main groups G06K1/00 - G06K15/00, e.g. automatic card files incorporating conveying and reading operations arrangements or provisious for transferring data to distant stations, e.g. from a sensing device the arrangement consisting of a wireless interrogation device in combination with a device for optically marking the record carrier
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/10—Services
- G06Q50/26—Government or public services
- G06Q50/265—Personal security, identity or safety
-
- H—ELECTRICITY
- H04—ELECTRIC COMMUNICATION TECHNIQUE
- H04N—PICTORIAL COMMUNICATION, e.g. TELEVISION
- H04N7/00—Television systems
- H04N7/18—Closed-circuit television [CCTV] systems, i.e. systems in which the video signal is not broadcast
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y04—INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
- Y04S—SYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
- Y04S10/00—Systems supporting electrical power generation, transmission or distribution
- Y04S10/50—Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Tourism & Hospitality (AREA)
- Physics & Mathematics (AREA)
- General Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Development Economics (AREA)
- Educational Administration (AREA)
- Computer Networks & Wireless Communication (AREA)
- Computer Security & Cryptography (AREA)
- Economics (AREA)
- General Engineering & Computer Science (AREA)
- Human Resources & Organizations (AREA)
- Marketing (AREA)
- Primary Health Care (AREA)
- Strategic Management (AREA)
- General Business, Economics & Management (AREA)
- Multimedia (AREA)
- Signal Processing (AREA)
- Alarm Systems (AREA)
Abstract
The invention discloses the system and methods that identification power grid infrastructure project is broken rules and regulations safely, are related to power management techniques field;System includes the safety belt of server, video monitoring equipment, the safety cap for being provided with safety cap two dimensional code, the work clothes of work clothes two dimensional code and safety belt two dimensional code, and the video monitoring equipment is connect with server and one-way communication;Method includes S1 Work tool coding, S2 establishes java standard library, S3 determines test stone and S4 is according to test stone checking procedure, and the two dimensional code comparison in the two dimensional code of test stone and real-time live photo is judged whether there is violations of rules and regulations;It realizes project of transmitting and converting electricity identification violating the regulations safely by server, video monitoring equipment, the safety cap for being provided with safety cap two dimensional code, the work clothes of work clothes two dimensional code and safety belt of safety belt two dimensional code etc., time saving and energy saving, high-efficient.
Description
Technical field
The present invention relates to power management techniques field more particularly to a kind of systems that identification power grid infrastructure project is broken rules and regulations safely
And method.
Background technique
Currently, analysis violating the regulations is identified mainly by manual identified, labor intensive, working efficiency traditional project of transmitting and converting electricity safely
Low, the requirement for identification timeliness of breaking rules and regulations safely is increasingly unable to satisfy.
Summary of the invention
Technical problem to be solved by the invention is to provide a kind of system that identification power grid infrastructure project is broken rules and regulations safely and sides
Method passes through the work clothes of server, video monitoring equipment, the safety cap for being provided with safety cap two dimensional code, work clothes two dimensional code
With the safety belt of safety belt two dimensional code etc., project of transmitting and converting electricity identification violating the regulations safely is realized, it is time saving and energy saving, it is high-efficient.
In order to solve the above technical problems, the technical solution used in the present invention is: a kind of identification power grid infrastructure project is safe
System violating the regulations includes the work of server, video monitoring equipment, the safety cap for being provided with safety cap two dimensional code, work clothes two dimensional code
Make the safety belt of clothes and safety belt two dimensional code, the video monitoring equipment is connect with server and one-way communication, and video monitoring is set
Back-up not Shi Bie safety cap two dimensional code, work clothes two dimensional code and safety belt two dimensional code identity information and be sent to server.
A further technical solution lies in: module is wireless by wireless communication between the server and video monitoring equipment
Connection.
A further technical solution lies in: 5G is communicated to connect between the server and video monitoring equipment.
A further technical solution lies in: wired connection between the server and video monitoring equipment.
A further technical solution lies in: further include mobile terminal, the mobile terminal by wireless communication module and clothes
Business device connection.
A further technical solution lies in: 5G is communicated to connect between the mobile terminal and server.
A further technical solution lies in: it further include display, the display and server wired connection.
A further technical solution lies in: it further include printer, the printer and server wired connection.
A kind of method broken rules and regulations safely of identification power grid infrastructure project includes S1 Work tool coding, that S2 establishes java standard library, S3 is true
Test stone and S4 are determined according to test stone checking procedure, and the S3 determines that test stone step is existing by server and construction
The video monitoring equipment of field determines that the two dimensional code of safety construction, the S4 are by S3 step according to test stone checking procedure
Obtained in two dimensional code in two dimensional code and real-time live photo compare, according to whether identical to determine whether existing existing in violation of rules and regulations
As.
A further technical solution lies in: it further include S5 conclusion feedback, and S1~S5 step is specific as follows,
S1 Work tool coding
Two dimensional code number is carried out to safety cap, work clothes and safety belt respectively, obtains the safety cap, the work that have safety cap two dimensional code
Take the work clothes of two dimensional code and the safety belt of safety belt two dimensional code;
S2 establishes java standard library
Typical power grid infrastructure project operative scenario is inputted into server as standard capital construction work photo and establishes power grid capital construction work
Journey safety construction java standard library, while one is established between typical power grid infrastructure project operative scenario and its required Work tool of constructing
To more mappings;
S3 determines test stone
The video monitoring equipment of construction site take to realtime construction situation shines and is sent to server, and server will receive
Real-time live photo is compared with the histogram of the exemplary operation scene in power grid infrastructure project safety construction java standard library,
It is maximum as a result, determining the category of the power grid infrastructure project safety construction scene at scene in turn to choose wherein correlation factors
Property, by the one-to-many mapping of construct scene and its required Work tool of constructing, obtain the two dimensional code of safety construction;
S4 is examined according to test stone
Two dimensional code in two dimensional code obtained in S3 step and real-time live photo is compared, according to whether it is identical to determine whether
There are violations of rules and regulations;It is deposited if number of the number of the two dimensional code in real-time live photo less than two dimensional code obtained in S3 step
In violations of rules and regulations, if the obtained figure of two dimensional code of figure and S3 step of the two dimensional code in real-time live photo mismatch
Then there are violations of rules and regulations;
S5 conclusion feedback
The violations of rules and regulations occurred in S4 step are fed back immediately.
The beneficial effects of adopting the technical scheme are that
Its work clothes for passing through server, video monitoring equipment, the safety cap for being provided with safety cap two dimensional code, work clothes two dimensional code
With the safety belt of safety belt two dimensional code etc., project of transmitting and converting electricity identification violating the regulations safely is realized, it is time saving and energy saving, it is high-efficient.
It is detailed in specific embodiment part description.
Detailed description of the invention
Fig. 1 is the functional block diagram of the embodiment of the present invention 1;
Fig. 2 is the functional block diagram of the embodiment of the present invention 2;
Fig. 3 is the functional block diagram of the embodiment of the present invention 4;
Fig. 4 is the functional block diagram of the embodiment of the present invention 6;
Fig. 5 is the functional block diagram of the embodiment of the present invention 7;
Fig. 6 is the flow chart of the embodiment of the present invention 8;
Fig. 7 is the relational graph of safety cap and safety cap two dimensional code in the present invention;
Fig. 8 is the relational graph of safety belt and safety belt two dimensional code in the present invention;
Fig. 9 is exemplary operation scene and the one-to-many mapping relations figure of required Work tool of constructing in the present invention.
Specific embodiment
Below in conjunction with the attached drawing in the embodiment of the present application, technical solutions in the embodiments of the present application carries out clear, complete
Site preparation description, it is clear that described embodiments are only a part of embodiments of the present application, instead of all the embodiments.Below
Description only actually at least one exemplary embodiment be it is illustrative, never as to the application and its application or making
Any restrictions.Based on the embodiment in the application, those of ordinary skill in the art are not making creative work premise
Under every other embodiment obtained, shall fall in the protection scope of this application.
Many details are explained in the following description in order to fully understand the application, but the application can be with
Implemented using other than the one described here other way, those skilled in the art can be without prejudice to the application intension
In the case of do similar popularization, therefore the application is not limited by the specific embodiments disclosed below.
It should be noted that term used herein above is merely to describe specific embodiment, and be not intended to restricted root
According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singular
Also it is intended to include plural form, additionally, it should be understood that, when in the present specification using term "comprising" and/or " packet
Include " when, indicate existing characteristics, step, operation, device, component and/or their combination.
Unless specifically stated otherwise, positioned opposite, the digital table of the component and step that otherwise illustrate in these embodiments
Up to the unlimited scope of the present application processed of formula and numerical value.Simultaneously, it should be appreciated that for ease of description, each portion shown in attached drawing
The size divided not is to draw according to actual proportionate relationship.For technology, side known to person of ordinary skill in the relevant
Method and equipment may be not discussed in detail, but in the appropriate case, and the technology, method and apparatus should be considered as authorizing explanation
A part of book.In shown here and discussion all examples, any occurrence should be construed as merely illustratively, and
Not by way of limitation.Therefore, the other examples of exemplary embodiment can have different values.It should also be noted that similar label
Similar terms are indicated in following attached drawing with letter, therefore, once it is defined in a certain Xiang Yi attached drawing, then subsequent attached
It does not need that it is further discussed in figure.
In the description of the present application, it is to be understood that the noun of locality such as " front, rear, top, and bottom, left and right ", " laterally, vertical,
Vertically, orientation or positional relationship indicated by level " and " top, bottom " etc. is normally based on orientation or position shown in the drawings and closes
System is merely for convenience of description the application and simplifies description, and in the absence of explanation to the contrary, these nouns of locality do not indicate that
It must have a particular orientation or be constructed and operated in a specific orientation with the device or element for implying signified, therefore cannot manage
Solution is the limitation to the application protection scope;The noun of locality " inside and outside " refers to inside and outside the profile relative to each component itself.
For ease of description, spatially relative term can be used herein, as " ... on ", " ... top ",
" ... upper surface ", " above " etc., for describing such as a device shown in the figure or feature and other devices or spy
The spatial relation of sign.It should be understood that spatially relative term is intended to comprising the orientation in addition to device described in figure
Except different direction in use or operation.For example, being described as if the device in attached drawing is squeezed " in other devices
It will be positioned as " under other devices or construction after part or construction top " or the device of " on other devices or construction "
Side " or " under other devices or construction ".Thus, exemplary term " ... top " may include " ... top " and
" in ... lower section " two kinds of orientation.The device can also be positioned with other different modes and (is rotated by 90 ° or in other orientation), and
And respective explanations are made to the opposite description in space used herein above.
In addition, it should be noted that, limiting components using the words such as " first ", " second ", it is only for be convenient for
Corresponding components are distinguished, do not have Stated otherwise such as, there is no particular meanings for above-mentioned word, therefore should not be understood as to this
Apply for the limitation of protection scope.
Embodiment 1:
As shown in Figure 1, the invention discloses a kind of system that identification power grid infrastructure project is broken rules and regulations safely, including server, video
Monitoring device, the safety cap for being pasted with safety cap two dimensional code, the work clothes for being pasted with work clothes two dimensional code and it is pasted with safety belt
The safety belt of two dimensional code, the video monitoring equipment is connect with server using cable and one-way communication, video monitoring equipment point
Not Shi Bie safety cap two dimensional code, work clothes two dimensional code and safety belt two dimensional code identity information and be sent to server.
Embodiment 2:
As shown in Fig. 2, the invention discloses a kind of system that identification power grid infrastructure project is broken rules and regulations safely, including server, video
Monitoring device, the safety cap for being pasted with safety cap two dimensional code, the work clothes for being pasted with work clothes two dimensional code and it is pasted with safety belt
The safety belt of two dimensional code, module is wirelessly connected and unidirectionally leads to by wireless communication between the video monitoring equipment and server
Letter, video monitoring equipment identify that the identity information of safety cap two dimensional code, work clothes two dimensional code and safety belt two dimensional code is concurrent respectively
It send to server.
Embodiment 3:
The invention discloses a kind of system for breaking rules and regulations safely of identification power grid infrastructure project, including it is server, video monitoring equipment, viscous
The safety for posting the safety cap of safety cap two dimensional code, being pasted with the work clothes of work clothes two dimensional code and being pasted with safety belt two dimensional code
Band, module is wirelessly connected by wireless communication between the video monitoring equipment and server and one-way communication, video monitoring are set
Back-up not Shi Bie safety cap two dimensional code, work clothes two dimensional code and safety belt two dimensional code identity information and be sent to server.
5G is communicated to connect between the server and video monitoring equipment.
Embodiment 4:
As shown in figure 3, the invention discloses a kind of system that identification power grid infrastructure project is broken rules and regulations safely, including server, video
Monitoring device, the work clothes for being pasted with work clothes two dimensional code, is pasted with safety belt two at the safety cap for being pasted with safety cap two dimensional code
The safety belt and mobile terminal for tieing up code, module is wirelessly connected simultaneously by wireless communication between the video monitoring equipment and server
One-way communication, module is connect the mobile terminal with server by wireless communication, and the video monitoring equipment identifies peace respectively
Full cap two dimensional code, work clothes two dimensional code and safety belt two dimensional code identity information and be sent to server, server is by above-mentioned body
Part information is sent to mobile terminal.
5G is communicated to connect between the server and video monitoring equipment.
Embodiment 5:
As shown in figure 3, the invention discloses a kind of system that identification power grid infrastructure project is broken rules and regulations safely, including server, video
Monitoring device, the work clothes for being pasted with work clothes two dimensional code, is pasted with safety belt two at the safety cap for being pasted with safety cap two dimensional code
The safety belt and mobile terminal for tieing up code, module is wirelessly connected simultaneously by wireless communication between the video monitoring equipment and server
One-way communication, module is connect the mobile terminal with server by wireless communication, and the video monitoring equipment identifies peace respectively
Full cap two dimensional code, work clothes two dimensional code and safety belt two dimensional code identity information and be sent to server, server is by above-mentioned body
Part information is sent to mobile terminal.
5G is communicated to connect between the server and video monitoring equipment.
5G is communicated to connect between the mobile terminal and server.
Embodiment 6:
As shown in figure 4, the invention discloses a kind of system that identification power grid infrastructure project is broken rules and regulations safely, including server, video
Monitoring device, the work clothes for being pasted with work clothes two dimensional code, is pasted with safety belt two at the safety cap for being pasted with safety cap two dimensional code
Tie up code safety belt, mobile terminal and display, between the video monitoring equipment and server by wireless communication module without
Line connection and one-way communication, module is connect the mobile terminal with server by wireless communication, the video monitoring equipment point
Not Shi Bie safety cap two dimensional code, work clothes two dimensional code and safety belt two dimensional code identity information and be sent to server, server
Above-mentioned identity information is sent to mobile terminal.
5G is communicated to connect between the server and video monitoring equipment.
5G is communicated to connect between the mobile terminal and server.
The display and server wired connection.
Embodiment 7:
As shown in figure 5, the invention discloses a kind of system that identification power grid infrastructure project is broken rules and regulations safely, including server, video
Monitoring device, the work clothes for being pasted with work clothes two dimensional code, is pasted with safety belt two at the safety cap for being pasted with safety cap two dimensional code
Safety belt, mobile terminal, display and the printer of code are tieed up, between the video monitoring equipment and server by wireless communication
Module is wirelessly connected and one-way communication, and module is connect the mobile terminal with server by wireless communication, the video monitoring
Equipment identify respectively safety cap two dimensional code, work clothes two dimensional code and safety belt two dimensional code identity information and be sent to server,
Above-mentioned identity information is sent to mobile terminal by server.
5G is communicated to connect between the server and video monitoring equipment.
5G is communicated to connect between the mobile terminal and server.
The display and server wired connection.
The printer and server wired connection.
Embodiment 8:
As shown in fig. 6, the invention discloses a kind of methods that identification power grid infrastructure project is broken rules and regulations safely, it is characterised in that: including
Following steps,
S1 Work tool coding
Two dimensional code number is carried out to safety cap, work clothes and safety belt respectively, obtains the safety cap, the work that have safety cap two dimensional code
Take the work clothes of two dimensional code and the safety belt of safety belt two dimensional code.
S2 establishes java standard library
Typical power grid infrastructure project operative scenario is inputted into server as standard capital construction work photo and establishes power grid capital construction work
Journey safety construction java standard library, while one is established between typical power grid infrastructure project operative scenario and its required Work tool of constructing
To more mappings.
S3 determines test stone
The video monitoring equipment of construction site take to realtime construction situation shines and is sent to server, and server will receive
Real-time live photo is compared with the histogram of the exemplary operation scene in power grid infrastructure project safety construction java standard library,
It is maximum as a result, determining the category of the power grid infrastructure project safety construction scene at scene in turn to choose wherein correlation factors
Property, by the one-to-many mapping of construct scene and its required Work tool of constructing, obtain the two dimensional code of safety construction.
S4 is examined according to test stone
Two dimensional code in two dimensional code obtained in S3 step and real-time live photo is compared, according to whether it is identical to determine whether
There are violations of rules and regulations;It is deposited if number of the number of the two dimensional code in real-time live photo less than two dimensional code obtained in S3 step
In violations of rules and regulations, if the obtained figure of two dimensional code of figure and S3 step of the two dimensional code in real-time live photo mismatch
Then there are violations of rules and regulations.
S5 conclusion feedback
The violations of rules and regulations occurred in S4 step are fed back immediately.
Wherein, server, video monitoring equipment, two dimensional code, mobile terminal, display and printer itself and its mutually
Between communication linkage technology sheet as the prior art, details are not described herein.
Present invention design: it is by by server, video monitoring equipment, the safety for being provided with safety cap two dimensional code
The ingenious combination of the equipment such as the safety belt of cap, the work clothes of work clothes two dimensional code and safety belt two dimensional code, solves and how to identify
The technical issues of project of transmitting and converting electricity safety violating the regulations, time-consuming and laborious, low efficiency, realizes project of transmitting and converting electricity identification violating the regulations safely, province
Shi Shengli, it is high-efficient.
Illustrate:
Since in recent years, using deep learning as the artificial intelligence technology of new generation of representative each field achieve attract people's attention at
Fruit especially has reached or surmounts the mankind in computer vision field and deep learning algorithm etc..
With the progress and application of 4G, 5G technology, artificial intelligence deep learning and big data technology, infrastructure project bursting tube
For reason mode from personnel, apparatus management/control status to the trend that extends into of information technology, especially capital construction scene is widely applied letter
Breathization application, the change that foundation construction site safety control has had been provided with the way to manages such as informationization, intelligence, big data is a kind of
Trend and trend.
Method of the invention is explained further as follows:
Two dimensional code comparison in the two dimensional code of test stone and real-time live photo is judged whether there is into violations of rules and regulations.
1) required Work tool when as shown in Figure 7, Figure 8, to power grid infrastructure project safety construction, such as safety cap, safety
Band etc. carries out two dimensional code number.It is required that power grid infrastructure project staff wears there is the Work tool of unified two dimensional code number to carry out
Construction.
2) as shown in figure 9, according to different typical power grid infrastructure project operative scenarios, standard capital construction work photo is inputted,
Establish power grid infrastructure project safety construction java standard library.And it establishes needed for typical power grid infrastructure project operative scenario constructs with it
Work tool establishes one-to-many mapping.
3) realtime construction situation is carried out to take photograph by the video monitoring equipment of construction site, by real-time live photo with
The histogram of exemplary operation scene in power grid infrastructure project safety construction java standard library is compared, and chooses wherein correlation
The factor it is maximum as a result, determine scene which kind of power grid infrastructure project safety construction scene belonged to, pass through construction scene and its
The one-to-many mapping of Work tool needed for constructing, obtains the two dimensional code of safety construction.
4) by the number and figure and the two dimensional code in real-time live photo of two dimensional code obtained in comparison 3) whether phase
Together, violations of rules and regulations are judged whether there is.It is presence if two dimensional code number is less than or is mismatched with the two-dimension code pattern 3) obtained
Violations of rules and regulations.
5) 4) the middle violations of rules and regulations that occur are fed back immediately, notifying a line and person liable to stand, row is vertical to be changed, and is eliminated safe hidden trouble
With prevention act of violating regulations.
It is perspective:
1, solve the problems, such as the automatic processing of power grid construction image violating the regulations safely, meet instantly with the following power grid security management
Development trend.
2, the timeliness for improving site safety discovery violating the regulations, security risk and hidden danger reaches all standing, and dynamic is sent out in real time
Existing all kinds of security risk situations.
3, various safety, violating the regulations, risk and hidden danger timely feedback a line, and vertical change of vertical row mentions dangerous point and security risk
Preceding elimination avoids the generation of security incident.
4, further using the verifying executive condition for being used for security management and control, quality surveillance and all kinds of technical solutions.
The technical solution of the application can not only be applied in power grid infrastructure project, can be applied in other similar
In engineering, application field, the range of industry are very extensive, have very extensive versatility.
Claims (10)
1. a kind of system for breaking rules and regulations safely of identification power grid infrastructure project, it is characterised in that: including server, video monitoring equipment,
It is provided with the safety belt of the safety cap of safety cap two dimensional code, the work clothes of work clothes two dimensional code and safety belt two dimensional code, the view
Frequency monitoring device is connect with server and one-way communication, and video monitoring equipment identifies safety cap two dimensional code, work clothes two dimension respectively
The identity information of code and safety belt two dimensional code is simultaneously sent to server.
2. the system that identification power grid infrastructure project according to claim 1 is broken rules and regulations safely, it is characterised in that: the server
Module is wirelessly connected by wireless communication between video monitoring equipment.
3. the system that identification power grid infrastructure project according to claim 2 is broken rules and regulations safely, it is characterised in that: the server
5G is communicated to connect between video monitoring equipment.
4. the system that identification power grid infrastructure project according to claim 1 is broken rules and regulations safely, it is characterised in that: the server
The wired connection between video monitoring equipment.
5. the system that identification power grid infrastructure project according to claim 1 is broken rules and regulations safely, it is characterised in that: further include movement
Terminal, module is connect the mobile terminal with server by wireless communication.
6. the system that identification power grid infrastructure project according to claim 5 is broken rules and regulations safely, it is characterised in that: described mobile whole
5G is communicated to connect between end and server.
7. the system that identification power grid infrastructure project according to claim 1 is broken rules and regulations safely, it is characterised in that: further include display
Device, the display and server wired connection.
8. the system that identification power grid infrastructure project according to claim 1 is broken rules and regulations safely, it is characterised in that: further include printing
Machine, the printer and server wired connection.
9. the method that the identification power grid infrastructure project of system described according to claim 1~any one of 8 is broken rules and regulations safely, special
Sign is: including S1 Work tool coding, S2 establishes java standard library, S3 determines test stone and S4 foundation test stone checking procedure,
The S3 determines that test stone step is to determine safety construction by the video monitoring equipment of server and construction site
Two dimensional code, the S4 are by two in two dimensional code obtained in S3 step and real-time live photo according to test stone checking procedure
Code comparison is tieed up, according to whether identical to determine whether there are violations of rules and regulations.
10. the method that identification power grid infrastructure project according to claim 9 is broken rules and regulations safely, it is characterised in that: further include S5
Conclusion feedback, and S1~S5 step is specific as follows,
S1 Work tool coding
Two dimensional code number is carried out to safety cap, work clothes and safety belt respectively, obtains the safety cap, the work that have safety cap two dimensional code
Take the work clothes of two dimensional code and the safety belt of safety belt two dimensional code;
S2 establishes java standard library
Typical power grid infrastructure project operative scenario is inputted into server as standard capital construction work photo and establishes power grid capital construction work
Journey safety construction java standard library, while one is established between typical power grid infrastructure project operative scenario and its required Work tool of constructing
To more mappings;
S3 determines test stone
The video monitoring equipment of construction site take to realtime construction situation shines and is sent to server, and server will receive
Real-time live photo is compared with the histogram of the exemplary operation scene in power grid infrastructure project safety construction java standard library,
It is maximum as a result, determining the category of the power grid infrastructure project safety construction scene at scene in turn to choose wherein correlation factors
Property, by the one-to-many mapping of construct scene and its required Work tool of constructing, obtain the two dimensional code of safety construction;
S4 is examined according to test stone
Two dimensional code in two dimensional code obtained in S3 step and real-time live photo is compared, according to whether it is identical to determine whether
There are violations of rules and regulations;It is deposited if number of the number of the two dimensional code in real-time live photo less than two dimensional code obtained in S3 step
In violations of rules and regulations, if the obtained figure of two dimensional code of figure and S3 step of the two dimensional code in real-time live photo mismatch
Then there are violations of rules and regulations;
S5 conclusion feedback
The violations of rules and regulations occurred in S4 step are fed back immediately.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910649683.6A CN110428026B (en) | 2019-07-18 | 2019-07-18 | System and method for identifying power grid infrastructure construction safety violation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910649683.6A CN110428026B (en) | 2019-07-18 | 2019-07-18 | System and method for identifying power grid infrastructure construction safety violation |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110428026A true CN110428026A (en) | 2019-11-08 |
CN110428026B CN110428026B (en) | 2023-02-10 |
Family
ID=68410983
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910649683.6A Active CN110428026B (en) | 2019-07-18 | 2019-07-18 | System and method for identifying power grid infrastructure construction safety violation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110428026B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111091069A (en) * | 2019-11-27 | 2020-05-01 | 云南电网有限责任公司电力科学研究院 | Power grid target detection method and system guided by blind image quality evaluation |
Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102332101A (en) * | 2010-05-27 | 2012-01-25 | 美国能量变换公司 | Asset identification and management method and system |
CN102880882A (en) * | 2011-07-12 | 2013-01-16 | 江苏省电力公司南通供电公司 | Equipment patrolling and managing device based on two-dimensional code |
CN205080594U (en) * | 2015-09-28 | 2016-03-09 | 国家电网公司 | Multiplexer of ascending a height utensil management system based on two -dimensional code |
CN106022977A (en) * | 2016-08-09 | 2016-10-12 | 国网山西省电力公司电力科学研究院 | Transformer substation job site safety analysis method |
CN106709703A (en) * | 2017-02-28 | 2017-05-24 | 天津华惠安信装饰工程有限公司 | Method and system of decoration project construction management based on technology of internet of things |
CN106909687A (en) * | 2017-03-06 | 2017-06-30 | 江苏工程职业技术学院 | A kind of high-altitude working safety warning system |
CN107169546A (en) * | 2017-07-03 | 2017-09-15 | 国网冀北电力有限公司唐山供电公司 | A kind of power construction managing security tools and instruments management method and system based on Quick Response Code |
CN206757716U (en) * | 2017-05-04 | 2017-12-15 | 丁昕 | Anti- violation management system based on Quick Response Code |
CN108833831A (en) * | 2018-06-15 | 2018-11-16 | 陈在新 | A kind of power construction intelligent safety monitor system |
CN108961486A (en) * | 2018-05-17 | 2018-12-07 | 国网福建省电力有限公司漳州供电公司 | A kind of electric-power safe instruments intelligent management platform |
CN109002897A (en) * | 2018-08-29 | 2018-12-14 | 国网河南省电力公司检修公司 | Field operation in transformer substation security management and control system and method based on robot technology |
CN109472091A (en) * | 2018-11-13 | 2019-03-15 | 四川华芯项目管理有限公司 | A kind of assembled architecture construction and stage monitoring system and method for being on active service |
-
2019
- 2019-07-18 CN CN201910649683.6A patent/CN110428026B/en active Active
Patent Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102332101A (en) * | 2010-05-27 | 2012-01-25 | 美国能量变换公司 | Asset identification and management method and system |
CN102880882A (en) * | 2011-07-12 | 2013-01-16 | 江苏省电力公司南通供电公司 | Equipment patrolling and managing device based on two-dimensional code |
CN205080594U (en) * | 2015-09-28 | 2016-03-09 | 国家电网公司 | Multiplexer of ascending a height utensil management system based on two -dimensional code |
CN106022977A (en) * | 2016-08-09 | 2016-10-12 | 国网山西省电力公司电力科学研究院 | Transformer substation job site safety analysis method |
CN106709703A (en) * | 2017-02-28 | 2017-05-24 | 天津华惠安信装饰工程有限公司 | Method and system of decoration project construction management based on technology of internet of things |
CN106909687A (en) * | 2017-03-06 | 2017-06-30 | 江苏工程职业技术学院 | A kind of high-altitude working safety warning system |
CN206757716U (en) * | 2017-05-04 | 2017-12-15 | 丁昕 | Anti- violation management system based on Quick Response Code |
CN107169546A (en) * | 2017-07-03 | 2017-09-15 | 国网冀北电力有限公司唐山供电公司 | A kind of power construction managing security tools and instruments management method and system based on Quick Response Code |
CN108961486A (en) * | 2018-05-17 | 2018-12-07 | 国网福建省电力有限公司漳州供电公司 | A kind of electric-power safe instruments intelligent management platform |
CN108833831A (en) * | 2018-06-15 | 2018-11-16 | 陈在新 | A kind of power construction intelligent safety monitor system |
CN109002897A (en) * | 2018-08-29 | 2018-12-14 | 国网河南省电力公司检修公司 | Field operation in transformer substation security management and control system and method based on robot technology |
CN109472091A (en) * | 2018-11-13 | 2019-03-15 | 四川华芯项目管理有限公司 | A kind of assembled architecture construction and stage monitoring system and method for being on active service |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111091069A (en) * | 2019-11-27 | 2020-05-01 | 云南电网有限责任公司电力科学研究院 | Power grid target detection method and system guided by blind image quality evaluation |
Also Published As
Publication number | Publication date |
---|---|
CN110428026B (en) | 2023-02-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106650855B (en) | A kind of fire-fighting equipment total management system | |
CN110795989A (en) | Intelligent safety monitoring system for electric power operation and monitoring method thereof | |
CN108537463A (en) | Cast-in-situ bridge support system construction monitoring system and method based on BIM | |
CN109377585A (en) | Factory's public affairs match facility intelligent operation cruising inspection system and its method for inspecting | |
CN106790034A (en) | A kind of internet of things equipment certification and the method for secure accessing | |
CN107564126A (en) | Substation secondary device intelligent patrol detection mobile terminal, server and system | |
CN110428026A (en) | The system and method that identification power grid infrastructure project is broken rules and regulations safely | |
CN112365201A (en) | Neural network-based infrastructure construction monitoring and early warning system and method | |
CN207689859U (en) | A kind of grid switching operation whole process intelligence managing and control system | |
CN108427995A (en) | A kind of natural gas plant stand operation management system | |
CN111741089B (en) | Intelligent safety operation management and control system and method based on industrial Internet of things | |
CN115239071A (en) | Industrial production environment risk assessment system based on big data | |
CN209433522U (en) | Warning system | |
CN208044634U (en) | A kind of car plate intelligence production identifying system | |
CN208636980U (en) | Fire-fighting maintenance system based on Internet of Things | |
CN208903254U (en) | Face identification system | |
CN208506532U (en) | A kind of communication information equipment O&M intelligent alarm platform | |
CN206270750U (en) | Product oil mechanized production system | |
CN207558177U (en) | A kind of perimeter security intelligent monitoring device based on communication network | |
CN219658161U (en) | Access identification device for unattended station | |
CN208227086U (en) | One kind can wired and Lora wireless transmission line anti-slip device | |
CN216848816U (en) | Inspection system | |
CN206820779U (en) | A kind of IEC61968 message authentication apparatus | |
CN213342286U (en) | Wisdom campus network supervision device | |
CN213094355U (en) | Community security protection monitoring system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |