CN109087048A - Assembled architecture component method for tracing based on two dimensional code - Google Patents
Assembled architecture component method for tracing based on two dimensional code Download PDFInfo
- Publication number
- CN109087048A CN109087048A CN201810939426.1A CN201810939426A CN109087048A CN 109087048 A CN109087048 A CN 109087048A CN 201810939426 A CN201810939426 A CN 201810939426A CN 109087048 A CN109087048 A CN 109087048A
- Authority
- CN
- China
- Prior art keywords
- construction
- prefabricated components
- information
- production
- dimensional code
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 44
- 238000010276 construction Methods 0.000 claims abstract description 88
- 238000004519 manufacturing process Methods 0.000 claims abstract description 50
- 238000012544 monitoring process Methods 0.000 claims abstract description 34
- 238000012384 transportation and delivery Methods 0.000 claims abstract description 13
- 238000007726 management method Methods 0.000 claims abstract description 10
- 238000012545 processing Methods 0.000 claims description 15
- 238000005516 engineering process Methods 0.000 claims description 6
- 239000000463 material Substances 0.000 claims description 6
- 238000012806 monitoring device Methods 0.000 claims description 6
- 230000005540 biological transmission Effects 0.000 claims description 3
- 230000002950 deficient Effects 0.000 claims description 3
- 238000007689 inspection Methods 0.000 claims description 3
- 238000011900 installation process Methods 0.000 claims description 3
- 230000008447 perception Effects 0.000 claims description 3
- 239000002994 raw material Substances 0.000 claims description 3
- 238000012360 testing method Methods 0.000 claims description 3
- 238000012790 confirmation Methods 0.000 claims 1
- 230000002123 temporal effect Effects 0.000 claims 1
- 230000000007 visual effect Effects 0.000 claims 1
- 230000009286 beneficial effect Effects 0.000 description 2
- 238000012546 transfer Methods 0.000 description 2
- 238000012800 visualization Methods 0.000 description 2
- 206010054949 Metaplasia Diseases 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000005194 fractionation Methods 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 230000015689 metaplastic ossification Effects 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
- 238000013068 supply chain management Methods 0.000 description 1
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q10/00—Administration; Management
- G06Q10/08—Logistics, e.g. warehousing, loading or distribution; Inventory or stock management
- G06Q10/083—Shipping
- G06Q10/0833—Tracking
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06K—GRAPHICAL DATA READING; PRESENTATION OF DATA; RECORD CARRIERS; HANDLING RECORD CARRIERS
- G06K7/00—Methods or arrangements for sensing record carriers, e.g. for reading patterns
- G06K7/10—Methods or arrangements for sensing record carriers, e.g. for reading patterns by electromagnetic radiation, e.g. optical sensing; by corpuscular radiation
- G06K7/14—Methods or arrangements for sensing record carriers, e.g. for reading patterns by electromagnetic radiation, e.g. optical sensing; by corpuscular radiation using light without selection of wavelength, e.g. sensing reflected white light
- G06K7/1404—Methods for optical code recognition
- G06K7/1408—Methods for optical code recognition the method being specifically adapted for the type of code
- G06K7/1417—2D bar codes
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06Q—INFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
- G06Q50/00—Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
- G06Q50/08—Construction
Landscapes
- Engineering & Computer Science (AREA)
- Business, Economics & Management (AREA)
- Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Economics (AREA)
- General Physics & Mathematics (AREA)
- General Business, Economics & Management (AREA)
- Health & Medical Sciences (AREA)
- General Health & Medical Sciences (AREA)
- Strategic Management (AREA)
- Tourism & Hospitality (AREA)
- Marketing (AREA)
- Human Resources & Organizations (AREA)
- Entrepreneurship & Innovation (AREA)
- Development Economics (AREA)
- Operations Research (AREA)
- Electromagnetism (AREA)
- Quality & Reliability (AREA)
- Toxicology (AREA)
- Artificial Intelligence (AREA)
- Computer Vision & Pattern Recognition (AREA)
- Primary Health Care (AREA)
- General Factory Administration (AREA)
- Management, Administration, Business Operations System, And Electronic Commerce (AREA)
Abstract
The present invention relates to a kind of assembled architecture component method for tracing based on two dimensional code, belongs to assembled architecture technical field.Method which solve existing BIM platform still without carrying out unified tracking for assembled architecture component, the more low problem of efficiency.S1: tracing management system building, including two dimensional code system construction, roduction track system construction and construction tracking system construction, S2: tracing management system monitoring, including production task monitoring, delivery process monitoring and construction task monitoring.The present invention realizes the promotion of tracking efficiency the purpose is to organically combine the tracking of assembled architecture component and BIM platform.
Description
Technical field
The present invention relates to a kind of assembled architecture component method for tracing based on two dimensional code belongs to assembled architecture technology neck
Domain.
Background technique
Assembled architecture refers to prefabricated component building made of assemble in site, passes through that " standardized designs, factory are raw
Metaplasia production, fabricated construction, integration finishing, information system management ", General Promotion architecture quality and efficiency of construction, reaching can hold
The target of supervention exhibition.Assembled architecture component tracking after fractionation is key link.The U.S. is using planar bar code technology to prefabricated structure
Part is transported in way orientation management, and carries out real-time typing to the essential information of component;South Korea is carried out using planar bar code technology
Const ruction supply chain management realizes construction supply chain efficient operation, improves performance.Existing BIM platform is not built for assembled still
The method that component carries out unified tracking is built, efficiency is more low.
Summary of the invention
In view of the foregoing defects the prior art has, the invention proposes a kind of assembled architecture component based on two dimensional code
Method for tracing realizes mentioning for tracking efficiency the purpose is to organically combine the tracking of assembled architecture component and BIM platform
It rises.
Assembled architecture component method for tracing of the present invention based on two dimensional code, includes the following steps:
S1: tracing management system building, including two dimensional code system construction, roduction track system construction and construction tracking system
Building, specific as follows:
S11: two dimensional code system construction: two dimensional code system include prefabricated components, two-dimension code label and with two-dimension code label pair
The reader for two-dimension code answered, two-dimension code label are fixedly connected with prefabricated components, and reader for two-dimension code is fixed on roduction track system
On;
S12: roduction track system construction: roduction track system includes production Internet of Things platform, utilizes production Internet of Things platform pair
The production information of each component is tracked, and when tracking is first scanned the two-dimension code label of prefabricated components, then to each life
Prefabricated components in production are taken pictures, and roduction track data are obtained, and roduction track data are then stored in production Internet of Things platform
Terminal, production Internet of Things platform is a kind of based on manufacturing production Internet of things system;
S13: construction tracking system construction: construction tracking system includes construction Internet of Things platform, utilizes construction Internet of Things platform pair
The construction information of each component is tracked, and when tracking is first scanned the two-dimension code label of prefabricated components, then to respectively applying
Prefabricated components in work are taken pictures, and construction tracking data are obtained, and construction tracking data are then stored in construction Internet of Things platform
Terminal, construction Internet of Things platform is a kind of based on manufacturing construction Internet of things system;
S2: tracing management system monitoring, including production task monitoring, delivery process monitoring and construction task monitoring, specifically
It is as follows:
S21: production task monitoring: roduction track system is sent to terminal by BIM database production task, while handle is beaten
It prints off the two-dimensional bar code material board papery version come and task list is assigned to direct labor;
S22: delivery process monitoring: the monitoring of prefabricated components delivery process, after prefabricated components are offline from production line, by producing
Responsible person scans the two-dimension code label bundled on finished product, and checks according to prefabricated components, certainly to the roduction track system checked
Dynamic to pass through wireless network transmissions BIM database, it is errorless by confirming to have completed delivery prefabricated components to change the state of product
After transfer to construction Internet of Things platform carry out being distributed to construction site;
S23: construction task monitoring: the monitoring of prefabricated components installation process, construction site construction responsible person are read using two dimensional code
It reads device and checks and accepts prefabricated components, change the state of product to have completed to receive, and is online, real in each critical process to prefabricated components
Shi Jinhang is accurately tracked.
Preferably, in step S11, the spatial data and attribute number of the prefabricated components are stored on the two-dimension code label
According to the spatial data includes: object mounting position information and location information, and the attribute data includes: type information, time
Information and identification information.
Preferably, in step S12, roduction track system further includes monitoring device, material vehicle in indoor storage building
On monitoring device.
Preferably, in step S13, construction tracking system further includes the reader for two-dimension code for incuding two dimensional code system,
For the tester of prefabricated components all data, for receiving the R-T unit of tester data, and for receiving two dimensional code
Reader, R-T unit data and the processing platform for handling the data;Between the reader for two-dimension code and processing platform, transmitting-receiving
By wireless network connection between device and processing platform, and number can be mutually received and dispatched between the R-T unit and processing platform
According to.
Preferably, in step 21, production task monitoring further includes that information in typing production process and process check information,
Information in production process includes scene photograph, raw material test report;Process checks that information includes meeting component in process inspection
It is defective in quality, retract flow operations information in mobile phone terminal, and issue quality notice in time and carry out rectification information, it is ensured that
Each process completes the quality of rear part.
Preferably, it in step S22, is tracked on the whole fabricated prefabricated components lines of BIM database realizing, accurate perception
Each component current state realizes zero inventory for project, and every batch of component is transported from processing factory to after scene, without storage, directly
Capable lifting is tapped into, is provided a strong guarantee.
Preferably, in step S23, site operation personnel directly acquire component by being scanned to component built-in chip
Size and its location information under construction, can also as needed, in called data library the construction technology of the component and
Points for attention, after lifting component is completed, construction personnel lifts information by terminal scanning record, and lifting information will synchronize to
In BIM model, project implementation progress can be respectively checked in visualization of 3 d model.
The beneficial effects of the present invention are: using the assembled architecture component tracking side of the present invention based on two dimensional code
Method organically combines the tracking of assembled architecture component and BIM platform, realizes the promotion of tracking efficiency.
Detailed description of the invention
Fig. 1 is structural schematic diagram of the invention.
Specific embodiment
In order to which the object of the invention, technical solution is more clearly understood, below with reference to embodiment, the present invention is made further
It is described in detail.
As shown in Figure 1, the assembled architecture component method for tracing of the present invention based on two dimensional code, including walk as follows
It is rapid:
S1: tracing management system building, including two dimensional code system construction, roduction track system construction and construction tracking system
Building, specific as follows:
S11: two dimensional code system construction: two dimensional code system include prefabricated components, two-dimension code label and with two-dimension code label pair
The reader for two-dimension code answered, two-dimension code label are fixedly connected with prefabricated components, and reader for two-dimension code is fixed on roduction track system
On;
S12: roduction track system construction: roduction track system includes production Internet of Things platform, utilizes production Internet of Things platform pair
The production information of each component is tracked, and when tracking is first scanned the two-dimension code label of prefabricated components, then to each life
Prefabricated components in production are taken pictures, and roduction track data are obtained, and roduction track data are then stored in production Internet of Things platform
Terminal, production Internet of Things platform is a kind of based on manufacturing production Internet of things system;
S13: construction tracking system construction: construction tracking system includes construction Internet of Things platform, utilizes construction Internet of Things platform pair
The construction information of each component is tracked, and when tracking is first scanned the two-dimension code label of prefabricated components, then to respectively applying
Prefabricated components in work are taken pictures, and construction tracking data are obtained, and construction tracking data are then stored in construction Internet of Things platform
Terminal, construction Internet of Things platform is a kind of based on manufacturing construction Internet of things system;
S2: tracing management system monitoring, including production task monitoring, delivery process monitoring and construction task monitoring, specifically
It is as follows:
S21: production task monitoring: roduction track system is sent to terminal by BIM database production task, while handle is beaten
It prints off the two-dimensional bar code material board papery version come and task list is assigned to direct labor;
S22: delivery process monitoring: the monitoring of prefabricated components delivery process, after prefabricated components are offline from production line, by producing
Responsible person scans the two-dimension code label bundled on finished product, and checks according to prefabricated components, certainly to the roduction track system checked
Dynamic to pass through wireless network transmissions BIM database, it is errorless by confirming to have completed delivery prefabricated components to change the state of product
After transfer to construction Internet of Things platform carry out being distributed to construction site;
S23: construction task monitoring: the monitoring of prefabricated components installation process, construction site construction responsible person are read using two dimensional code
It reads device and checks and accepts prefabricated components, change the state of product to have completed to receive, and is online, real in each critical process to prefabricated components
Shi Jinhang is accurately tracked.
Preferably, in step S11, the spatial data and attribute number of the prefabricated components are stored on the two-dimension code label
According to the spatial data includes: object mounting position information and location information, and the attribute data includes: type information, time
Information and identification information.
Preferably, in step S12, roduction track system further includes monitoring device, material vehicle in indoor storage building
On monitoring device.
Preferably, in step S13, construction tracking system further includes the reader for two-dimension code for incuding two dimensional code system,
For the tester of prefabricated components all data, for receiving the R-T unit of tester data, and for receiving two dimensional code
Reader, R-T unit data and the processing platform for handling the data;Between the reader for two-dimension code and processing platform, transmitting-receiving
By wireless network connection between device and processing platform, and number can be mutually received and dispatched between the R-T unit and processing platform
According to.
Preferably, in step 21, production task monitoring further includes that information in typing production process and process check information,
Information in production process includes scene photograph, raw material test report;Process checks that information includes meeting component in process inspection
It is defective in quality, retract flow operations information in mobile phone terminal, and issue quality notice in time and carry out rectification information, it is ensured that
Each process completes the quality of rear part.
Preferably, it in step S22, is tracked on the whole fabricated prefabricated components lines of BIM database realizing, accurate perception
Each component current state realizes zero inventory for project, and every batch of component is transported from processing factory to after scene, without storage, directly
Capable lifting is tapped into, is provided a strong guarantee.
Preferably, in step S23, site operation personnel directly acquire component by being scanned to component built-in chip
Size and its location information under construction, can also as needed, in called data library the construction technology of the component and
Points for attention, after lifting component is completed, construction personnel lifts information by terminal scanning record, and lifting information will synchronize to
In BIM model, project implementation progress can be respectively checked in visualization of 3 d model.
The beneficial effects of the present invention are: using the assembled architecture component tracking side of the present invention based on two dimensional code
Method organically combines the tracking of assembled architecture component and BIM platform, realizes the promotion of tracking efficiency.
The present invention can be widely used in assembled architecture occasion.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not limitation with the present invention, all in essence of the invention
Made impartial modifications, equivalent substitutions and improvements etc., should be included in patent covering scope of the invention within mind and principle.
Claims (7)
1. a kind of assembled architecture component method for tracing based on two dimensional code, which comprises the steps of:
S1: tracing management system building, including two dimensional code system construction, roduction track system construction and construction tracking system structure
It builds, specific as follows:
S11: two dimensional code system construction: two dimensional code system includes prefabricated components, two-dimension code label and corresponding with two-dimension code label
Reader for two-dimension code, two-dimension code label are fixedly connected with prefabricated components, and reader for two-dimension code is fixed in roduction track system;
S12: roduction track system construction: roduction track system includes production Internet of Things platform, using production Internet of Things platform to each structure
The production information of part is tracked, and when tracking is first scanned the two-dimension code label of prefabricated components, then in each production
Prefabricated components take pictures, obtain roduction track data, then by roduction track data be stored in production Internet of Things platform end
End, production Internet of Things platform are a kind of based on manufacturing production Internet of things system;
S13: construction tracking system construction: construction tracking system includes construction Internet of Things platform, using construction Internet of Things platform to each structure
The construction information of part is tracked, and when tracking is first scanned the two-dimension code label of prefabricated components, then in each construction
Prefabricated components take pictures, obtain construction tracking data, then by construction tracking data be stored in construction Internet of Things platform end
End, construction Internet of Things platform are a kind of based on manufacturing construction Internet of things system;
S2: tracing management system monitoring, including production task monitoring, delivery process monitoring and construction task monitoring, specific as follows:
S21: production task monitoring: roduction track system is sent to terminal by BIM database production task, while handle prints
The two-dimensional bar code material board papery version and task list come are assigned to direct labor;
S22: delivery process monitoring: the monitoring of prefabricated components delivery process after prefabricated components are offline from production line, is responsible for by producing
People scans the two-dimension code label bundled on finished product, and checks according to prefabricated components, leads to automatically to the roduction track system checked
Wireless network transmissions BIM database is crossed, the state for changing product is to have completed delivery prefabricated components to hand over after confirmation is errorless
It carries out being distributed to construction site by construction Internet of Things platform;
S23: construction task monitoring: the monitoring of prefabricated components installation process, construction site construction responsible person use reader for two-dimension code
Check and accept prefabricated components, the state for changing product be completed to receive, and to prefabricated components each critical process it is online, in real time into
Row accurately tracking.
2. the assembled architecture component method for tracing according to claim 1 based on two dimensional code, which is characterized in that step
In S11, the spatial data and attribute data of the prefabricated components, the spatial data packet are stored on the two-dimension code label
Include: object mounting position information and location information, the attribute data include: type information, temporal information and identification information.
3. the assembled architecture component method for tracing according to claim 1 based on two dimensional code, which is characterized in that step
In S12, roduction track system further includes the monitoring device in indoor storage building, the monitoring device on material vehicle.
4. the assembled architecture component method for tracing according to claim 1 based on two dimensional code, which is characterized in that step
In S13, construction tracking system further includes the reader for two-dimension code for incuding two dimensional code system, is used for prefabricated components all data
Tester, for receiving the R-T unit of tester data, and for receiving reader for two-dimension code, R-T unit data simultaneously
Handle the processing platform of the data;Between the reader for two-dimension code and processing platform, lead between R-T unit and processing platform
Wireless network connection is crossed, and can mutual sending and receiving data between the R-T unit and processing platform.
5. the assembled architecture component method for tracing according to claim 1 based on two dimensional code, which is characterized in that step 21
In, production task monitoring further includes information and process inspection information in typing production process, and the information in production process includes
Scene photograph, raw material test report;Process check information include process check in meet component it is defective in quality, in mobile phone terminal
Flow operations information is retracted, and issues quality notice in time and carries out rectification information, it is ensured that each process completes rear part
Quality.
6. the assembled architecture component method for tracing according to claim 1 based on two dimensional code, which is characterized in that step
In S22, tracked on the whole fabricated prefabricated components lines of BIM database realizing, each component current state of accurate perception is
Project realizes zero inventory, and every batch of component is transported to after scene from processing factory, without storage, directly lifted, and provides strong
It ensures.
7. the assembled architecture component method for tracing according to claim 1 based on two dimensional code, which is characterized in that step
In S23, site operation personnel directly acquire the size and its under construction of component by being scanned to component built-in chip
Location information, can also as needed, and the construction technology and points for attention of the component in called data library, lifting component are completed
Later, construction personnel lifts information by terminal scanning record, and lifting information will synchronize in BIM model, respectively can be visual
Change in threedimensional model and checks project implementation progress.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810939426.1A CN109087048A (en) | 2018-08-17 | 2018-08-17 | Assembled architecture component method for tracing based on two dimensional code |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201810939426.1A CN109087048A (en) | 2018-08-17 | 2018-08-17 | Assembled architecture component method for tracing based on two dimensional code |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109087048A true CN109087048A (en) | 2018-12-25 |
Family
ID=64793752
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201810939426.1A Pending CN109087048A (en) | 2018-08-17 | 2018-08-17 | Assembled architecture component method for tracing based on two dimensional code |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109087048A (en) |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110457801A (en) * | 2019-07-30 | 2019-11-15 | 上海建工集团股份有限公司 | The monitoring method and system of assembled project component |
CN110866712A (en) * | 2019-07-31 | 2020-03-06 | 浙江精工钢结构集团有限公司 | Intelligent component logistics positioning method and system based on BIM (building information modeling) plug-in |
CN111444141A (en) * | 2020-03-26 | 2020-07-24 | 长沙中交京纬工程技术有限公司 | Data archive storage method based on BIM |
CN113128974A (en) * | 2021-04-28 | 2021-07-16 | 天津智中新窗业有限公司 | Intelligent progress control method and device for building matching product and electronic information platform |
CN113283874A (en) * | 2021-06-09 | 2021-08-20 | 青岛理工大学 | Intelligent building overall process simulation method for fabricated building based on BIM and two-dimensional code |
CN115187200A (en) * | 2022-07-11 | 2022-10-14 | 山西省安装集团股份有限公司 | Assembly type machine room construction management system based on BIM digital-analog separation |
CN115807412A (en) * | 2022-11-29 | 2023-03-17 | 中国电建集团成都勘测设计研究院有限公司 | Intelligent installation method for large-diameter pressure steel pipe in hole |
CN117094606A (en) * | 2023-10-18 | 2023-11-21 | 中亿丰数字科技集团有限公司 | Building element full life cycle quality tracking method and system based on BIM |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105023201A (en) * | 2015-07-24 | 2015-11-04 | 中建三局第一建设工程有限责任公司 | Assembled building detailed design and construction method based on BIM (Building Information Modeling) and large data |
CN105654318A (en) * | 2016-01-13 | 2016-06-08 | 上海振华重工(集团)股份有限公司 | Production internet of things management method |
CN105888248A (en) * | 2016-04-27 | 2016-08-24 | 河北建筑工程学院 | Construction method of guiding informationization prefabricated member based on BIM (Building Information Modeling)) technology |
CN106600239A (en) * | 2016-12-28 | 2017-04-26 | 中建科技有限公司 | Assembly type building construction full process data cooperation management system based on BIM |
US20170132567A1 (en) * | 2015-11-06 | 2017-05-11 | Benjamin F. GLUNZ | Method and system for native object collaboration, revision and analytics for bim and other design platforms |
CN107169539A (en) * | 2016-03-08 | 2017-09-15 | 上海宝冶集团有限公司 | Reinforcing bar automation processing delivery system and method based on two-dimensional bar code |
CN108154340A (en) * | 2017-12-08 | 2018-06-12 | 山东聊建集团有限公司 | Prefabricated component informationization management system based on BIM cloud platforms |
-
2018
- 2018-08-17 CN CN201810939426.1A patent/CN109087048A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105023201A (en) * | 2015-07-24 | 2015-11-04 | 中建三局第一建设工程有限责任公司 | Assembled building detailed design and construction method based on BIM (Building Information Modeling) and large data |
US20170132567A1 (en) * | 2015-11-06 | 2017-05-11 | Benjamin F. GLUNZ | Method and system for native object collaboration, revision and analytics for bim and other design platforms |
CN105654318A (en) * | 2016-01-13 | 2016-06-08 | 上海振华重工(集团)股份有限公司 | Production internet of things management method |
CN107169539A (en) * | 2016-03-08 | 2017-09-15 | 上海宝冶集团有限公司 | Reinforcing bar automation processing delivery system and method based on two-dimensional bar code |
CN105888248A (en) * | 2016-04-27 | 2016-08-24 | 河北建筑工程学院 | Construction method of guiding informationization prefabricated member based on BIM (Building Information Modeling)) technology |
CN106600239A (en) * | 2016-12-28 | 2017-04-26 | 中建科技有限公司 | Assembly type building construction full process data cooperation management system based on BIM |
CN108154340A (en) * | 2017-12-08 | 2018-06-12 | 山东聊建集团有限公司 | Prefabricated component informationization management system based on BIM cloud platforms |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110457801A (en) * | 2019-07-30 | 2019-11-15 | 上海建工集团股份有限公司 | The monitoring method and system of assembled project component |
CN110866712A (en) * | 2019-07-31 | 2020-03-06 | 浙江精工钢结构集团有限公司 | Intelligent component logistics positioning method and system based on BIM (building information modeling) plug-in |
CN110866712B (en) * | 2019-07-31 | 2024-02-23 | 比姆泰客信息科技(上海)有限公司 | Component intelligent logistics positioning method and system based on BIM model plug-in |
CN111444141A (en) * | 2020-03-26 | 2020-07-24 | 长沙中交京纬工程技术有限公司 | Data archive storage method based on BIM |
CN111444141B (en) * | 2020-03-26 | 2022-12-02 | 北京中交京纬公路造价技术有限公司 | Data archive storage method based on BIM |
CN113128974A (en) * | 2021-04-28 | 2021-07-16 | 天津智中新窗业有限公司 | Intelligent progress control method and device for building matching product and electronic information platform |
CN113283874A (en) * | 2021-06-09 | 2021-08-20 | 青岛理工大学 | Intelligent building overall process simulation method for fabricated building based on BIM and two-dimensional code |
WO2022257100A1 (en) * | 2021-06-09 | 2022-12-15 | 青岛理工大学 | Intelligent assembled building whole construction process simulation method based on bim and two-dimensional code |
CN115187200A (en) * | 2022-07-11 | 2022-10-14 | 山西省安装集团股份有限公司 | Assembly type machine room construction management system based on BIM digital-analog separation |
CN115807412A (en) * | 2022-11-29 | 2023-03-17 | 中国电建集团成都勘测设计研究院有限公司 | Intelligent installation method for large-diameter pressure steel pipe in hole |
CN117094606A (en) * | 2023-10-18 | 2023-11-21 | 中亿丰数字科技集团有限公司 | Building element full life cycle quality tracking method and system based on BIM |
CN117094606B (en) * | 2023-10-18 | 2024-04-05 | 中亿丰数字科技集团有限公司 | Building element full life cycle quality tracking method and system based on BIM |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109087048A (en) | Assembled architecture component method for tracing based on two dimensional code | |
CN106709703A (en) | Method and system of decoration project construction management based on technology of internet of things | |
CN103778472A (en) | Mobile built product resume system and management and control method of production line operation | |
CN103810576A (en) | Workshop production management method and system based on Internet of Things | |
CN103116821A (en) | Whole course tracking method and whole course tracking system of discrete manufacturing workshop production process quality | |
CN107516136A (en) | Power Line Inspection System | |
CN106228297A (en) | A kind of management system of fixed assets information | |
CN106789221A (en) | Automobile storage site management system and its management method based on UWB positioning | |
CN110648422A (en) | Standardized inspection method, system and platform | |
CN108375963A (en) | Collecting method based on Internet of Things | |
CN111399467A (en) | Intelligent manufacturing platform for customized plate-type furniture | |
CN107169539A (en) | Reinforcing bar automation processing delivery system and method based on two-dimensional bar code | |
CN203552288U (en) | Electric pole routing-inspection data-collecting label based tablet PC | |
CN206937352U (en) | A kind of material fetching mechanism of automatic identification pcb board | |
CN107609447A (en) | A kind of optical detection apparatus, system and method | |
CN206541333U (en) | A kind of decoration project work progress management system based on technology of Internet of things | |
CN202773089U (en) | Intelligent mobile terminal of IOT (Internet of Things) | |
CN204856612U (en) | Steel construction construction management system based on mobile internet | |
CN205563673U (en) | Process management system of smart business | |
CN106355335A (en) | Quick production work order operation progress acquiring method | |
CN106004716B (en) | A kind of intelligent logistic car networked system | |
CN107730142A (en) | Using Quick Response Code in BIM project management system | |
CN102446262A (en) | RFID (Radio Frequency Identification) automatic correlation system and method and portable equipment with system | |
CN209087002U (en) | Inspection device based on two dimensional code and wireless location | |
CN208400183U (en) | A kind of terminal device that electric inspection process personnel use |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181225 |
|
RJ01 | Rejection of invention patent application after publication |