CN104156812A - Construction project construction site original data acquisition system and acquisition method - Google Patents

Construction project construction site original data acquisition system and acquisition method Download PDF

Info

Publication number
CN104156812A
CN104156812A CN201410379567.4A CN201410379567A CN104156812A CN 104156812 A CN104156812 A CN 104156812A CN 201410379567 A CN201410379567 A CN 201410379567A CN 104156812 A CN104156812 A CN 104156812A
Authority
CN
China
Prior art keywords
construction
working
construction task
yard
electronic tag
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410379567.4A
Other languages
Chinese (zh)
Inventor
施威
郭云道
伍期志
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Suzhou No1 Construction Group Co Ltd
JIANGSU DINGSI TECHNOLOGY DEVELOPMENT Co Ltd
Original Assignee
Suzhou No1 Construction Group Co Ltd
JIANGSU DINGSI TECHNOLOGY DEVELOPMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Suzhou No1 Construction Group Co Ltd, JIANGSU DINGSI TECHNOLOGY DEVELOPMENT Co Ltd filed Critical Suzhou No1 Construction Group Co Ltd
Priority to CN201410379567.4A priority Critical patent/CN104156812A/en
Publication of CN104156812A publication Critical patent/CN104156812A/en
Pending legal-status Critical Current

Links

Landscapes

  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a construction project construction site original data acquisition system and an acquisition method of construction project construction site original data. The construction task information of the construction project is stored in a server of a construction site original data acquisition system; the construction tasks to be implemented on the current day are encoded by the server according to the construction progress plan and then made into corresponding electronic tags to be fixed in the construction site corresponding to the construction task; the construction task codes in the electronic tags placed in the corresponding construction site are read by a construction management personnel everyday through a mobile terminal, so that the input of the construction site original data can be completed and the routing inspection conditions of the construction management personnel can be automatically recorded through the same mobile terminal when the corresponding construction task information in the database is inquired through the construction task codes; finally, the original data and the routing inspection conditions are uploaded and stored in the server, and the construction site original data acquisition and the sign in of the construction management personnel for routing inspection corresponding to the construction task on the current day can be achieved.

Description

The on-the-spot initial data capture system of engineering construction and acquisition method
Technical field
The invention belongs to engineering construction field management technical field, be specifically related to the on-the-spot initial data capture system of engineering construction and raw data acquisition method thereof.
Background technology
At present, because engineering construction field management level is lower, and along with the progress of engineering, working-yard can produce the raw data of the aspects such as a large amount of relevant works progresses, construction quality, safe construction, resource consumption every day.In the past, to the collection of these working-yard raw data, all adopt paper record, the loss of capsule information, raw data, the situation such as damaged usually occur, the lighter, affect project progress, affect capital settlement, severe one, likely affects construction quality, or generation security incident, even cause engineering shut-down, suspend etc.Moreover, in actual management process, to the record of working-yard raw data, need to a great extent to rely on the consciousness of construction manager, thereby, often make an inspection tour, check not in place, cause the situations such as undetected, error of omission, incorrect posting.And, because working-yard operator is not very clearly familiar with the construction task on the same day, also can cause the delay of construction speed, also can cause the hidden danger of some quality, secure context simultaneously, therefore need a set of effective management system and method, carry out the collecting work of the on-the-spot raw data of standard construction, avoid artificial slacking off, working-yard task is told somebody what one's real intentions are clear, working-yard raw data acquisition, report in time, so that construction speed, the quality of the every construction task of management and control and even whole engineering, guarantee safe construction in time.
Summary of the invention
The object of this invention is to provide a kind of working-yard initial data capture system of practicality, convenient, realize the working-yard raw data such as progress to working-yard, quality, safety efficiently and gather, transmit, store, be convenient to progress to construction task, quality, safety etc. and monitor timely, and provide foundation for tracking, the tracing management in later stage.
Another object of the present invention, it is the working-yard raw data acquisition method of utilizing above-mentioned working-yard initial data capture system, for this numerous and diverse and necessary handwork process of raw data acquisition at engineering construction scene, provide a kind of information tool efficiently.
The present invention can make construction manager must, arrive construction task institute at the construction field (site) passively, complete scanning electron label, obtain construction task information, and input this job step of working-yard raw data, meet the collection of working-yard raw data and the job requirement to the necessary cyclic in-position measuring of construction manager.
For achieving the above object, the present invention has adopted following technical scheme:
A kind of working-yard initial data capture system, is characterized in that, comprises
Server, for storing each construction mission bit stream of construction project, and according to each construction task in construction schedule and commencement date of the construction thereof, generate corresponding construction task coding, then construction task code conversion is become to electronic tag, and have by the function of the corresponding construction task information of construction task coded query;
Electronic tag carrier, for carrying described electronic tag, this electronic tag carrier is fixed on the working-yard corresponding with construction task;
Electronic tag fetch equipment, for passing through the electronic tag on the described electronic tag carrier of scanning, obtain described construction task coding, then encode by this construction task, inquire construction task information corresponding in described server, and gather the working-yard raw data of working-yard, and automatically record construction manager cyclic in-position measuring situation simultaneously, then feedback transmission is to described server;
Described electronic tag fetch equipment, is connected in described server by mobile Internet.
Further, described server, comprise construction task information storage module, construction task coding generation module, electronic tag modular converter, construction task information inquiry module, construction manager register logging modle and working-yard raw data memory module and storer, wherein
Described construction task information storage module, carries out storage administration for the construction task information to construction project;
Described construction task coding generation module, for according to each construction task of construction schedule and commencement date of the construction thereof, generates corresponding construction task coding;
Described electronic tag modular converter, for becoming the construction task code conversion of above-mentioned generation the data layout of electronic tag and storing;
Described construction task information inquiry module for according to construction task coding, is searched corresponding construction task information in server;
Described working-yard raw data memory module, for working-yard source data collection that construction manager collection is uploaded and be stored into described storer;
The described construction manager logging modle of registering, for being stored into described storer by on-the-spot construction manager cyclic in-position measuring situation.
Further, described electronic tag is Quick Response Code or bar code.
Further, described electronic tag fetch equipment, for the mobile terminal of Quick Response Code or bar code recognition module is installed, comprise construction task information inquiry module, working-yard raw data load module, the construction manager transmission module in module and working-yard raw data of registering.
Further, described construction task information, the plan target information that project progress, resource consumption, quality, safety, the operating technique that comprises construction task told somebody what one's real intentions are etc.Described working-yard raw data, comprises the actual information completing of project progress, resource consumption, quality, safety of working-yard etc.
Further, described electronic tag is printed on papery or plastic medium and makes described electronic tag carrier, and described electronic tag carrier is pasted on the working-yard corresponding with construction task.
A kind of working-yard raw data acquisition method, adopts the above working-yard initial data capture system, it is characterized in that, comprises the steps:
(1) in server, store each of construction project construction mission bit stream;
(2), according to project progress plan, generate construction task corresponding to construction task information that started the same day to construct and encode and be stored in storer;
(3) the construction task code conversion of above-mentioned generation is become electronic tag by electronic tag modular converter, and this electronic tag is printed on papery or plastic medium, makes described electronic tag carrier; Then described electronic tag carrier is pasted on to the working-yard corresponding with construction task;
(4) construction manager is patrolled and examined in process at the scene, by electronic tag fetch equipment, read the electronic tag of corresponding working-yard, obtain described construction task coding, and according to this construction task coding, inquire construction task information corresponding in server, and carry out operation and management according to construction task information;
(5) construction manager is again by electronic tag fetch equipment, the working-yard raw data of the corresponding construction task performance on the same day of input reflection, and by the working-yard raw data of above-mentioned input, in uploading onto the server by mobile Internet, simultaneously by the construction manager module of registering, the scene of the uploading construction manager record of registering.
Further, construction task information in described step (1), schedule according to construction task and this construction task is stored, i.e. certain construction task that construction task information only starts construction corresponding a certain day, the corresponding construction task generating of this construction task information is encoded to unique coding.
Further, in described step (5), need reading of construction task coding described in the first completing steps of construction manager (4), and the working-yard raw data of the corresponding construction task performance on the same day of input reflection, could be by the construction manager module of registering, complete construction manager scene the uploading of record of registering.
Invention advantage:
Tool of the present invention has the following advantages:
1. be this numerous and diverse and necessary handwork process of raw data acquisition at engineering construction scene, a kind of efficient, practical raw data acquisition instrument is provided;
2. in time, the working-yard raw data acquisition mode that puts in place, the KXG of construction project is obtained in time, working-yard raw data becomes possibility accurately;
3. in time, working-yard raw data accurately, be tracking, the monitoring to construction speed, quality, safety, cost etc. in engineering construction process, and tracing management afterwards etc. provides foundation;
4. have and the construction manager of " patrol system " identity function of the practicality module of registering, make construction manager accomplish passively " must arrive on-the-spot implementation of construction task every day checks " this job requirement, be convenient to the cyclic in-position measuring work of construction manager to carry out management and control.
Brief description of the drawings
Fig. 1 is the module composition frame chart of working-yard of the present invention initial data capture system;
Fig. 2 is the process flow diagram of working-yard of the present invention raw data acquisition method;
Embodiment
Below in conjunction with accompanying drawing and preferred embodiment, technical scheme of the present invention is further described.
As shown in Figure 1:
A kind of working-yard initial data capture system, is characterized in that, comprises
Server, for storing each construction mission bit stream of construction project, and according to each construction task in construction schedule and commencement date of the construction thereof, generate corresponding construction task coding, then construction task code conversion is become to electronic tag, and have by the function of the corresponding construction task information of construction task coded query;
Electronic tag carrier, for carrying described electronic tag, this electronic tag carrier is fixed on the working-yard corresponding with construction task;
Electronic tag fetch equipment, for passing through the electronic tag on the described electronic tag carrier of scanning, obtain described construction task coding, then encode by this construction task, inquire construction task information corresponding in described server, and gather the working-yard raw data of working-yard, and automatically record construction manager cyclic in-position measuring situation simultaneously, then feedback transmission is to described server;
Described electronic tag fetch equipment, is connected in described server by mobile Internet.
Further, described server, comprise construction task information storage module, construction task coding generation module, electronic tag modular converter, construction task information inquiry module, construction manager register logging modle and working-yard raw data memory module and storer, wherein
Described construction task information storage module, carries out storage administration for the construction task information to construction project;
Described construction task coding generation module, for according to each construction task of construction schedule and commencement date of the construction thereof, generates corresponding construction task coding;
Described electronic tag modular converter, for becoming the construction task code conversion of above-mentioned generation the data layout of electronic tag and storing;
Described construction task information inquiry module for according to construction task coding, is searched corresponding construction task information in server;
Described working-yard raw data memory module, for working-yard source data collection that construction manager collection is uploaded and be stored into described storer;
The described construction manager logging modle of registering, for being stored into described storer by on-the-spot construction manager cyclic in-position measuring situation.
Further, described electronic tag is Quick Response Code or bar code.
Further, described electronic tag fetch equipment, for the mobile terminal of Quick Response Code or bar code recognition module is installed, comprise construction task information inquiry module, working-yard raw data load module, the construction manager transmission module in module and working-yard raw data of registering.
Further, described construction task information, the plan target information that project progress, resource consumption, quality, safety, the operating technique that comprises construction task told somebody what one's real intentions are etc.Described working-yard raw data, comprises the actual information completing of project progress, resource consumption, quality, safety of working-yard etc.
Further, described electronic tag is printed on papery or plastic medium and makes described electronic tag carrier, and described electronic tag carrier is pasted on the working-yard corresponding with construction task.
As shown in Figure 2
A kind of working-yard raw data acquisition method, adopts working-yard as above initial data capture system, comprises the steps:
(1) in server, store each of construction project construction mission bit stream;
(2), according to project progress plan, generate construction task corresponding to construction task information that started the same day to construct and encode and be stored in storer;
(3) by the electronic tag modular converter in server, above-mentioned construction task code conversion is become to electronic tag,
(4) and by this electronic tag be printed on and on papery or plastic medium, make described electronic tag carrier; Then described electronic tag carrier is pasted on to the working-yard corresponding with construction task;
(5) construction manager is patrolled and examined in process at the scene, by electronic tag fetch equipment, reads the electronic tag of corresponding working-yard, obtains described construction task coding;
(6) according to this construction task coding, inquire construction task information corresponding in server, and carry out operation and management according to construction task information;
(7) construction manager is again by electronic tag fetch equipment, and input reflects the working-yard raw data of corresponding construction task performance on the same day;
(8) in mobile terminal, complete the construction manager scene record of registering
(9) by transmission module in the raw data of mobile terminal working-yard, during the working-yard raw data of above-mentioned input and the record of registering are uploaded onto the server by mobile Internet;
(10), if this construction task does not complete, get back to step (5); If complete, to step (11)
(11) if if all construction task does not complete, get back to step (2), if complete power cut-off.
It is to be noted; as described above is only in order to explain the present invention's preferred embodiment; not attempt is done any formal restriction to the present invention according to this; be with; all any modification or changes that has the relevant the present invention that does under identical invention spirit, all must be included in the category that the invention is intended to protection.

Claims (9)

1. a working-yard initial data capture system, is characterized in that, comprises
Server, for storing each construction mission bit stream of construction project, again according to each construction task in construction schedule and commencement date of the construction thereof, generate corresponding construction task coding, then construction task code conversion is become to electronic tag, and have by the function of the corresponding construction task information of construction task coded query;
Electronic tag carrier, for carrying described electronic tag, this electronic tag carrier is fixed on the working-yard of corresponding construction task;
Electronic tag fetch equipment, for passing through the electronic tag on the described electronic tag carrier of scanning, obtain described construction task coding, then encode by this construction task, inquire construction task information corresponding in described server, and gather the working-yard raw data of working-yard, and automatically record construction manager cyclic in-position measuring situation simultaneously, then feedback transmission is to described server;
Described electronic tag fetch equipment, is connected in described server by mobile Internet.
2. working-yard according to claim 1 initial data capture system, it is characterized in that, described server, comprise construction task information storage module, construction task coding generation module, electronic tag modular converter, construction task information inquiry module, construction manager register logging modle and working-yard raw data memory module and storer, wherein
Described construction task information storage module, carries out storage administration for the construction task information to construction project;
Described construction task coding generation module, for according to each construction task of construction schedule and commencement date of the construction thereof, generates corresponding construction task coding;
Described electronic tag modular converter, for becoming the construction task code conversion of above-mentioned generation the data layout of electronic tag and storing;
Described construction task information inquiry module for according to construction task coding, is searched corresponding construction task information in server;
Described working-yard raw data memory module, for working-yard source data collection that construction manager collection is uploaded and be stored into described storer;
The described construction manager logging modle of registering, for being stored into described storer by on-the-spot construction manager cyclic in-position measuring situation.
3. working-yard according to claim 1 initial data capture system, is characterized in that, described electronic tag is Quick Response Code or bar code.
4. working-yard according to claim 3 initial data capture system, it is characterized in that, described electronic tag fetch equipment, for the mobile terminal of Quick Response Code or bar code recognition module is installed, comprise construction task information inquiry module, working-yard raw data load module, the construction manager transmission module in module and working-yard raw data of registering.
5. working-yard according to claim 1 initial data capture system, is characterized in that, described construction task information, the plan target information that project progress, resource consumption, quality, safety, the operating technique that comprises construction task told somebody what one's real intentions are etc.; Described working-yard raw data, comprises the actual information completing of project progress, resource consumption, quality, safety of working-yard etc.
6. working-yard according to claim 1 initial data capture system, is characterized in that, described electronic tag is printed on papery or plastic medium, makes described electronic tag carrier; Described electronic tag carrier, is pasted on the working-yard corresponding with construction task.
7. a working-yard raw data acquisition method, adopts the working-yard initial data capture system as described in claim 1~6 any one, it is characterized in that, comprises the steps:
(1) in server, store each of construction project construction mission bit stream;
(2), according to project progress plan, generate construction task corresponding to construction task information that started the same day to construct and encode and be stored in storer;
(3) the construction task code conversion of above-mentioned generation is become electronic tag by electronic tag modular converter, and this electronic tag is printed on papery or plastic medium, makes described electronic tag carrier; Then described electronic tag carrier is pasted on to the working-yard corresponding with construction task;
(4) construction manager is patrolled and examined in process at the scene, by electronic tag fetch equipment, read the electronic tag of corresponding working-yard, obtain described construction task coding, and according to this construction task coding, inquire construction task information corresponding in server, and carry out operation and management according to construction task information;
(5) construction manager is again by electronic tag fetch equipment, the working-yard raw data of the corresponding construction task performance on the same day of input reflection, and by the working-yard raw data of above-mentioned input, in uploading onto the server by mobile Internet, simultaneously by the construction manager module of registering, the scene of the uploading construction manager record of registering.
8. working-yard according to claim 7 raw data acquisition method, it is characterized in that, construction task information in described step (1), schedule according to construction task and this construction task is stored, i.e. certain construction task that construction task information only starts construction corresponding a certain day, the corresponding construction task generating of this construction task information is encoded to unique coding.
9. working-yard according to claim 7 raw data acquisition method, it is characterized in that, in described step (5), need reading of construction task coding described in the first completing steps of construction manager (4), and the working-yard raw data of the corresponding construction task performance on the same day of input reflection, could be by the construction manager module of registering, complete construction manager scene the uploading of record of registering.
CN201410379567.4A 2014-08-04 2014-08-04 Construction project construction site original data acquisition system and acquisition method Pending CN104156812A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410379567.4A CN104156812A (en) 2014-08-04 2014-08-04 Construction project construction site original data acquisition system and acquisition method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410379567.4A CN104156812A (en) 2014-08-04 2014-08-04 Construction project construction site original data acquisition system and acquisition method

Publications (1)

Publication Number Publication Date
CN104156812A true CN104156812A (en) 2014-11-19

Family

ID=51882307

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410379567.4A Pending CN104156812A (en) 2014-08-04 2014-08-04 Construction project construction site original data acquisition system and acquisition method

Country Status (1)

Country Link
CN (1) CN104156812A (en)

Cited By (20)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105117900A (en) * 2015-09-30 2015-12-02 北京恒华伟业科技股份有限公司 Progress information acquisition method and device, and terminal equipment
CN105160466A (en) * 2015-08-26 2015-12-16 中交第二航务工程局有限公司 Method for applying two-dimensional code to highway engineering
CN105260857A (en) * 2015-11-16 2016-01-20 苏州天地微易智能科技有限公司 Intelligent management system and method thereof for rural migrant workers
WO2016134535A1 (en) * 2015-02-28 2016-09-01 罗春晖 Construction process control method
CN106709703A (en) * 2017-02-28 2017-05-24 天津华惠安信装饰工程有限公司 Method and system of decoration project construction management based on technology of internet of things
CN106779386A (en) * 2016-12-07 2017-05-31 哈尔滨工程大学 Build management system and method in cruise cabin based on Quick Response Code
CN107067223A (en) * 2016-12-16 2017-08-18 上海建工集团股份有限公司 Construction information collection processing method
CN107219825A (en) * 2016-03-22 2017-09-29 赫克斯冈技术中心 Self-contr ol
CN107506929A (en) * 2017-08-28 2017-12-22 中国铁道科学研究院铁道建筑研究所 A kind of high-strength bolt construction information monitoring system and method
CN107734305A (en) * 2017-11-01 2018-02-23 广州供电局有限公司 It is a kind of to use remote speech commander and the electric power construction field informationization monitoring system of job site various dimensions solid show
CN108200173A (en) * 2018-01-03 2018-06-22 广州供电局有限公司 A kind of electric power construction field informationization monitoring system
CN108229807A (en) * 2017-12-28 2018-06-29 广州建软科技股份有限公司 A kind of marketing programs construction rotation managing and control system
CN109064139A (en) * 2018-08-08 2018-12-21 深圳市弘景装饰工程有限公司 A kind of building decoration engineering management system
CN110264168A (en) * 2019-07-26 2019-09-20 梧州市城建投资发展集团有限公司 A kind of Engineering Project Construction duration monitoring system and method
CN111309942A (en) * 2020-01-22 2020-06-19 清华大学 Data acquisition method, device and system for construction site
CN111506949A (en) * 2020-04-10 2020-08-07 中国电建集团昆明勘测设计研究院有限公司 BIM-based visualization method for road soft foundation treatment construction progress
CN112085346A (en) * 2020-08-18 2020-12-15 远光软件股份有限公司 Calendar-based safety inspection work display method and device and electronic equipment
CN113095797A (en) * 2021-05-18 2021-07-09 河南佳润新材料有限公司 System for recording and tracing construction process in ceramic tile embedding project
CN113393342A (en) * 2021-03-30 2021-09-14 浙江绿城房屋服务系统有限公司 Building decoration project overall process management method and system
CN113409168A (en) * 2021-03-24 2021-09-17 浙江绿城筑乐美城市发展有限公司 Building decoration project labor service and project quantity real-name management system and method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101127670A (en) * 2007-09-29 2008-02-20 济南东之林智能软件有限公司 A coal mine under-well secure integration management system
CN103329150A (en) * 2011-01-25 2013-09-25 蒂凡尼·何塞·布朗 Construction trade building information management system, software and method
CN103390258A (en) * 2013-06-28 2013-11-13 环境保护部华南环境科学研究所 Updating and inquiring method and management system of laboratory object information and based on information code
CN103793789A (en) * 2014-01-28 2014-05-14 上海市政建设有限公司 Pipe-jacking construction information management system and method based on two-dimensional bar codes
CN103886444A (en) * 2014-04-03 2014-06-25 江苏物联网研究发展中心 Provenance-oriented agricultural capital invoicing system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101127670A (en) * 2007-09-29 2008-02-20 济南东之林智能软件有限公司 A coal mine under-well secure integration management system
CN103329150A (en) * 2011-01-25 2013-09-25 蒂凡尼·何塞·布朗 Construction trade building information management system, software and method
CN103390258A (en) * 2013-06-28 2013-11-13 环境保护部华南环境科学研究所 Updating and inquiring method and management system of laboratory object information and based on information code
CN103793789A (en) * 2014-01-28 2014-05-14 上海市政建设有限公司 Pipe-jacking construction information management system and method based on two-dimensional bar codes
CN103886444A (en) * 2014-04-03 2014-06-25 江苏物联网研究发展中心 Provenance-oriented agricultural capital invoicing system

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016134535A1 (en) * 2015-02-28 2016-09-01 罗春晖 Construction process control method
CN105160466A (en) * 2015-08-26 2015-12-16 中交第二航务工程局有限公司 Method for applying two-dimensional code to highway engineering
CN105117900A (en) * 2015-09-30 2015-12-02 北京恒华伟业科技股份有限公司 Progress information acquisition method and device, and terminal equipment
CN105260857A (en) * 2015-11-16 2016-01-20 苏州天地微易智能科技有限公司 Intelligent management system and method thereof for rural migrant workers
US10789556B2 (en) 2016-03-22 2020-09-29 Hexagon Technology Center Gmbh Self control
CN107219825B (en) * 2016-03-22 2020-02-14 赫克斯冈技术中心 Method for providing inspection instruction, job site management system, and storage medium
CN107219825A (en) * 2016-03-22 2017-09-29 赫克斯冈技术中心 Self-contr ol
CN106779386A (en) * 2016-12-07 2017-05-31 哈尔滨工程大学 Build management system and method in cruise cabin based on Quick Response Code
CN107067223A (en) * 2016-12-16 2017-08-18 上海建工集团股份有限公司 Construction information collection processing method
CN106709703A (en) * 2017-02-28 2017-05-24 天津华惠安信装饰工程有限公司 Method and system of decoration project construction management based on technology of internet of things
CN107506929A (en) * 2017-08-28 2017-12-22 中国铁道科学研究院铁道建筑研究所 A kind of high-strength bolt construction information monitoring system and method
CN107734305A (en) * 2017-11-01 2018-02-23 广州供电局有限公司 It is a kind of to use remote speech commander and the electric power construction field informationization monitoring system of job site various dimensions solid show
CN108229807A (en) * 2017-12-28 2018-06-29 广州建软科技股份有限公司 A kind of marketing programs construction rotation managing and control system
CN108200173A (en) * 2018-01-03 2018-06-22 广州供电局有限公司 A kind of electric power construction field informationization monitoring system
CN109064139A (en) * 2018-08-08 2018-12-21 深圳市弘景装饰工程有限公司 A kind of building decoration engineering management system
CN110264168A (en) * 2019-07-26 2019-09-20 梧州市城建投资发展集团有限公司 A kind of Engineering Project Construction duration monitoring system and method
CN110264168B (en) * 2019-07-26 2023-05-02 梧州市城建投资发展集团有限公司 Engineering project construction period monitoring system and method
CN111309942A (en) * 2020-01-22 2020-06-19 清华大学 Data acquisition method, device and system for construction site
CN111309942B (en) * 2020-01-22 2020-11-24 清华大学 Data acquisition method, device and system for construction site
CN111506949A (en) * 2020-04-10 2020-08-07 中国电建集团昆明勘测设计研究院有限公司 BIM-based visualization method for road soft foundation treatment construction progress
CN112085346A (en) * 2020-08-18 2020-12-15 远光软件股份有限公司 Calendar-based safety inspection work display method and device and electronic equipment
CN113409168A (en) * 2021-03-24 2021-09-17 浙江绿城筑乐美城市发展有限公司 Building decoration project labor service and project quantity real-name management system and method
CN113393342A (en) * 2021-03-30 2021-09-14 浙江绿城房屋服务系统有限公司 Building decoration project overall process management method and system
CN113095797A (en) * 2021-05-18 2021-07-09 河南佳润新材料有限公司 System for recording and tracing construction process in ceramic tile embedding project

Similar Documents

Publication Publication Date Title
CN104156812A (en) Construction project construction site original data acquisition system and acquisition method
CN107146020B (en) Photovoltaic power plant engineering project informatization management system
CN202093536U (en) Intelligent routing inspection system for substation equipment
CN106815681B (en) Transformer substation secondary equipment closed-loop management platform based on two-dimensional code and management system thereof
CN103955754A (en) Mold workshop scheduling method based on real-time production data collection
Dold et al. The future of geospatial intelligence
CN102254142B (en) Storage battery production data acquiring device and controlling method thereof
CN103310300A (en) Mobile checking management method and system of power assets
CN202615415U (en) Full lifecycle management system of electric automobile power cell and based on Internet of Things
CN101419689A (en) Full lofe cycle management system of electric power tools
CN105224326A (en) A kind of incremental deploying method of system code and device
CN104992375A (en) Hand-held transformer-substation intelligent patrol system based on XML data conversion
CN102142108A (en) Information processing method of corresponding relationship among materials and equipment suitable for power system
CN111488999A (en) Be applied to wind-powered electricity generation field safety production information-based management system
CN116307570A (en) Subway vehicle electronic record system based on block chain technology
CN104766108A (en) Optimizing processing method for FID electronic tag in BIM model
CN104766107A (en) System utilizing RFID electronic product code to collect data in BIM
CN201242768Y (en) Information network assets management system based on wireless radio frequency RFID
CN112711399A (en) Audit application platform based on containerization design
CN112734059A (en) Water plant equipment point inspection information management system, method and storage medium
CN104281974A (en) Mobile operation unified identifying, recognizing and information obtaining method and system
CN107423035A (en) A kind of software development process product data management system
CN104240009A (en) Method for managing wiring relation by bar code combination
CN109978191A (en) The appraisal procedure and assessment device of the system mode of industrial equipment system
CN210955177U (en) Electronic resume management system for rail transit

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20141119