CN106640154A - Treatment method and structure for water seepage of tunnel lining circular construction joint crack - Google Patents

Treatment method and structure for water seepage of tunnel lining circular construction joint crack Download PDF

Info

Publication number
CN106640154A
CN106640154A CN201710026109.6A CN201710026109A CN106640154A CN 106640154 A CN106640154 A CN 106640154A CN 201710026109 A CN201710026109 A CN 201710026109A CN 106640154 A CN106640154 A CN 106640154A
Authority
CN
China
Prior art keywords
construction joint
tunnel
notch
circular construction
pvc
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710026109.6A
Other languages
Chinese (zh)
Inventor
秦江堂
薛江
王国俊
李细贵
吕鑫
霍俊晨
黄春明
丁飞
樊虎森
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
FOURTH ENGINEERING Co Ltd OF CCCC FOURTH HIGHWAY ENGINEERING Co Ltd
Original Assignee
FOURTH ENGINEERING Co Ltd OF CCCC FOURTH HIGHWAY ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by FOURTH ENGINEERING Co Ltd OF CCCC FOURTH HIGHWAY ENGINEERING Co Ltd filed Critical FOURTH ENGINEERING Co Ltd OF CCCC FOURTH HIGHWAY ENGINEERING Co Ltd
Priority to CN201710026109.6A priority Critical patent/CN106640154A/en
Publication of CN106640154A publication Critical patent/CN106640154A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/383Waterproofing; Heat insulating; Soundproofing; Electric insulating by applying waterproof flexible sheets; Means for fixing the sheets to the tunnel or cavity wall
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels

Abstract

The invention relates to a treatment method and structure for water seepage of a tunnel lining circular construction joint crack. The treatment method comprises the steps that a groove is cut along the crack of a circular construction joint of a secondary lining of a tunnel, a PVC drainage half-tube with the diameter being 50 cm is pre-buried, and seepage water is collected into an arch foot through the annular half-tube and then discharged into a gutter; after the drainage half-tube is fixed through a holding hoop, the groove wall is coated with an interface agent, and the groove opening is closed by means of polymer cement repair mortar; and after getting flat again, the surface of the lining is coated with a high-permeability cement-based crystal waterproof layer. In order to facilitate construction and control water seepage thoroughly, constructors need to consider chipping away the portions, 1 m away from the construction joint with the seepage water, of a cable duct side wall and the gutter during construction, and then restoring the portions after pre-burying the drainage tube, and the collected water in the circular PVC drainage half-tube is discharged into a cable duct and led out of the tunnel. By adoption of the treatment method and structure, the damage of seepage water of the crack of the circular construction joint of the secondary lining of the tunnel can be eradicated, operation is easy, and the safe use function and the service life of the tunnel are guaranteed.

Description

Seep water Treatment Methods and structure in tunnel-liner circular construction joint crack
Technical field
The present invention relates to building field, specifically a kind of tunnel-liner circular construction joint crack infiltration Treatment Methods and knot Structure.
Background technology
With the expanding day of highway in China transport development scale, China become in the world Tunnel Engineering quantity at most, Total kilometrage is most long, condition is most complicated, the country that technology is with fastest developing speed.China's First railway tunnel is built in 1888, so far Existing 128 years builds history.But while tunnel construction is scored achievements, the tunnel in some operations is due to service life Be continuously increased, the facility of the adverse effect of geologic(al) factor and environment, and guarded drainage in addition it is aging so that part tunnel goes out The annular crack and water leakage of now different degrees of infiltration and Lining cracks, wherein lining construction seam is the most serious, and disease occurs frequency Rate is higher, accounts for more than 60%, the consequence severe patient for bringing can cause road surface slippery situation, freeze and Lining cracks, come off, bearing capacity not The phenomenons such as foot.At present, most of lining construction seam crack pore gas flows are administered, and technology is immature, cures the symptoms, not the disease, effective sealing Time limit is short, it is impossible to fundamentally effect a radical cure seepage problem.
In view of above-mentioned defect, the positive in addition research and innovation of the design people is applied to founding a kind of tunnel-liner ring Work seam crack infiltration Treatment Methods and structure so as to more the value in industry.
The content of the invention
To solve above-mentioned technical problem, it is an object of the invention to provide a kind of definite effect, permanently effective, it is ensured that tunnel Liner structure safety and the tunnel-liner circular construction joint crack infiltration Treatment Methods for being open to traffic safe and structure.
Seep water Treatment Methods in tunnel-liner circular construction joint crack of the present invention, including:
Circumferential groove is dug in the concrete surface of lining construction seam, ring installs PVC draining semicanals in groove, using polymerization Thing cement mortar for reparation closes notch, and the notch of circumferential groove is floating;
High permeable strata base crystal waterproof layer is scratched in the notch surface of circumferential groove;
Wherein, the slot opening of the circumferential groove × a length of 6cm × 7.5cm, circumferential groove extends to arch springing position.
Further, also including cutting each 50cm scopes cable duct side wall and gutter before and after construction joint, and pour again Build, pre-buried PVC pipes when pouring, enable current in the PVC draining semicanals buried in circular construction joint to enter gutter, draw Outside hole.
Further, notch surface blade coating high permeable strata base crystal waterproof layer is specifically included:When first time waterproof layer is opened Begin after hardening, brushing second layer waterproof layer, each THICKNESS CONTROL brushes 3~4 layers in 2mm or so.
Further, the painting border of notch surface blade coating high permeable strata base crystal waterproof layer cuts border more than notch 50cm。
Further, the step of basic unit's lining cutting surface to brushing is rinsed also is included.
Further, the PVC drainings semicanal is the PVC draining semicanals of a diameter of 50mm.
Further, the PVC drainings semicanal, the anchor ear made of 2mm thickness galvanized sheets is fixed in notch, described Anchor ear makes of 2mm thickness galvanized sheets, circumferential distance 50cm.
Seep water treatment structures in tunnel-liner circular construction joint crack of the present invention, including:In the concrete table of lining construction seam Face is provided with circumferential groove, slot opening × a length of 6cm × 7.5cm of the circumferential groove, and circumferential groove extends to arch springing position, in groove inner ring To PVC draining semicanals are provided with, circumferential groove notch is provided with using Polymet-cement Mortar for Reparation closing notch sealing, notch surface High permeable strata base crystal waterproof layer, the waterproof layer includes 3~4 layers, and each thickness is 1.5 to 2.5mm.
Further, PVC pipes are embedded with before and after construction joint in the range of each 50cm, the PVC rows buried in circular construction joint Water semicanal is connected with PVC pipes.
Further, the PVC drainings semicanal, the anchor ear made of 2mm thickness galvanized sheets is fixed in notch, described Anchor ear makes of 2mm thickness galvanized sheets, circumferential distance 50cm.
By such scheme, the present invention at least has advantages below:
The present invention is combined by the way that water seepage of tunnel is punished mode " block up, draw, arranging ", by lining cutting annular construction joint fluting Device PVC semicanals are buried, and is fixed with anchor ear, lead-in cable ditch side wall and the pre-buried diameter 50mmPVC pipes of gutter, so Current in the diameter 50mmPVC draining semicanals buried in circular construction joint are enable smoothly to enter gutter afterwards, notch is using poly- Compound cement mortar for reparation is blocked, and surface is using the process of high permeable strata base crystal waterproof layer, it is ensured that lining cutting annular construction joint splits The permanently effective sealing of seam water seepage treatment, eradicates pore gas flow, and eliminating the consequence severe patient for bringing that seeps water can cause road surface slippery situation, knot Ice and Lining cracks, come off, the phenomenon such as Lack of support, it is ensured that the current safety of tunnel operation.
Described above is only the general introduction of technical solution of the present invention, in order to better understand the technological means of the present invention, And can be practiced according to the content of specification, below with presently preferred embodiments of the present invention and coordinate accompanying drawing describe in detail as after.
Description of the drawings
Fig. 1 is that tunnel-liner circular construction joint crack infiltration punishment draining semicanal arranges figure;
Fig. 2 is annular construction joint punishment lateral arrangement figure;
Fig. 3 is cable duct, gutter infiltration punishment drawing;
Fig. 4 is anchor ear A master drawings;
1st, external coating original text infiltration cement base crystal waterproof layer;2nd, interfacial agents;3rd, Polymet-cement Mortar for Reparation closing;4、 PVC draining semicanals;5th, lining construction seam;6th, spilled water hole;7th, raggle;8th, galvanized sheet;9th, construction joint pipe laying.
Specific embodiment
With reference to the accompanying drawings and examples, the specific embodiment of the present invention is described in further detail.Hereinafter implement Example is not limited to the scope of the present invention for illustrating the present invention.
As shown in figure 1, annular ring fluting is carried out to tunnel ring-shaped construction joint crack seepage part, notch size 6cm × To arch springing position, ring installs diameter 50mmPVC draining semicanals to 7.5cm in groove, with the anchor ear of 2mm thickness galvanized sheet making in notch Interior to install fixed draining semicanal, anchor ear circumferential distance 50cm, and crater wall brushing interfacial agents, notch repairs sand using polymer cement Slurry is floating.3~4 layers of blade coating high permeable strata base crystal waterproof layer in notch surface and both sides 50cm width ranges.Such as Fig. 2 institutes Show, the tunnel ring-shaped construction joint diameter 50mmPVC drainings semicanal layout drawings of Fig. 2.As shown in figure 3, arch springing raggle buried depth diameter 50mmPVC pipes, semicanal is connected with pipe, and infiltration Jing cable duct bottom of trench notches (wide 6cm, deep 5cm) is let out by diameter 50mm Water pipe, flows into gutter.As shown in figure 4, anchor ear makes of 2mm thickness galvanized sheets, circumferential distance 50cm, anchor ear is embraced using semicircle Hoop diameter 51mm, two ends are anchored among lining concrete using diameter 5mm expansion bolts.
Embodiment 1
Seep water Treatment Methods in the present embodiment tunnel-liner circular construction joint crack, including:
Circumferential groove is dug in the concrete surface of lining construction seam, ring installs PVC draining semicanals in groove, using polymerization Thing cement mortar for reparation closes notch, and the notch of circumferential groove is floating;
High permeable strata base crystal waterproof layer is scratched in the notch surface of circumferential groove;
Wherein, the slot opening of the circumferential groove × a length of 6cm × 7.5cm, circumferential groove extends to arch springing position.
In the present embodiment, circumferential groove is dug in the concrete surface of lining construction seam, notch size 6cm × 7.5cm is to arch Placement of foot, ring installs diameter 50mmPVC draining semicanals in groove, and the anchor ear made of 2mm thickness galvanized sheets is installed in notch Fixed draining semicanal, anchor ear circumferential distance 50cm, and it is floating with Polymet-cement Mortar for Reparation.Interface is smeared in cell wall both sides Agent, using Polymet-cement Mortar for Reparation notch is closed, and should ensure that draining semicanal is smooth during closing.Notch surface scratches Thief zone Cement base crystal waterproof layer, after first time waterproof layer starts hardening, brushing second layer waterproof layer, every layer of THICKNESS CONTROL is in 2mm Left and right, brushes 3~4 layers;Applying border should cut border 50cm more than notch.Basic unit's lining cutting surface washing of brushing is clean, it is ensured that High permeable strata base crystal waterproof layer is to whole annular printed regions infiltration stagnant water effect.
Embodiment 2
Seep water Treatment Methods in the present embodiment tunnel-liner circular construction joint crack, on the basis of embodiment 1, applies for convenience Work is harnessed the river thoroughly, considers will there is cable duct side wall and gutter cutting in the range of common lm before and after the construction joint of percolating water in construction Cut, again cast recovers after pre-buried drainpipe, the water that collects in ring PVC draining semicanals is entered into cable duct, draw outside hole.
In the present embodiment, each 50cm scopes cable duct side wall and gutter before and after construction joint are cut, and poured again, poured Pre-buried diameter 50mmPVC pipes when building, enable current in the diameter 50mmPVC draining semicanals buried in circular construction joint smoothly to arrange Enter gutter.
In the present embodiment, arch springing raggle buried depth diameter 50mmPVC pipes, need semicanal and Conduit Joint quality of connection compared with It is good, it is to avoid misconnection and plugging phenomenon occur, and infiltration Jing cable duct bottom of trench notches (wide 6cm, deep 5cm) is sluiced by diameter 50mm Pipe, flows into gutter.
Embodiment 3
Seep water treatment structures in the present embodiment tunnel-liner circular construction joint crack, including:In the concrete of lining construction seam Surface is provided with circumferential groove, slot opening × a length of 6cm × 7.5cm of the circumferential groove, and circumferential groove extends to arch springing position, in groove Ring is provided with PVC draining semicanals, and circumferential groove notch is set using Polymet-cement Mortar for Reparation closing notch sealing, notch surface There is high permeable strata base crystal waterproof layer.The waterproof layer includes 3~4 layers, and each thickness is 1.5 to 2.5mm.The PVC rows Water semicanal, the anchor ear made of 2mm thickness galvanized sheets is fixed in notch, and the anchor ear makes of 2mm thickness galvanized sheets, ring Spacing 50cm.
PVC pipes are embedded with before and after construction joint in the range of each 50cm, in circular construction joint bury PVC drainings semicanal with PVC pipes are connected.
Structure concrete construction method described in the present embodiment:
Annular ring fluting is carried out to tunnel ring-shaped construction joint crack seepage part, notch size 6cm × 7.5cm is to arch springing Position.
Ring installs diameter 50mmPVC draining semicanals in groove, and the anchor ear made of 2mm thickness galvanized sheets installs solid in notch Determine draining semicanal, anchor ear circumferential distance 50cm, and crater wall brushing interfacial agents, notch is floating using Polymet-cement Mortar for Reparation.
Each 50cm scopes cable duct side wall and gutter before and after construction joint are cut, and is poured again, it is pre-buried straight when pouring Footpath 50mmPVC pipes, enable current in the diameter 50mmPVC draining semicanals buried in circular construction joint smoothly to enter draining side Ditch.
It is mixed in cell wall both sides and smears interfacial agents, using Polymet-cement Mortar for Reparation notch, the row of should ensure that during closing is closed Water semicanal is smooth.
Former tunnel-liner in the 50cm width ranges of notch both sides is cleaned, is dried.
Blade coating high permeable strata base crystal waterproof layer in notch surface and both sides 50cm width ranges, when first time waterproof layer After starting hardening, brushing second layer waterproof layer brushes 3~4 layers.
Structure described in the present embodiment can also adopt the embodiment construction of any of the above-described method to obtain.
In the various embodiments described above, the diameter 50mmPVC draining semicanals that ring is installed in groove, anchor ear 2mm thickness galvanized sheet systems Make, circumferential distance 50cm.Anchor ear adopts semicircle anchor ear diameter 51mm, two ends to be anchored at lining cutting using diameter 5mm expansion bolts and mix Among solidifying soil.
The waterproof material handle measure of notch is by smearing interfacial agents in cell wall both sides, being repaired using polymer cement Mortar closes notch, 3~4 layers of notch surface blade coating high permeable strata base crystal waterproof layer, it is ensured that pre-buried draining semicanal coagulation Soil box mouth plugging effect is good.
Notch surface blade coating high permeable strata base crystal waterproof layer totally just can be carried out in basic unit's lining cutting surface washing, per layer After waterproof layer hardening, next layer is just brushed.
Notch surface scratches every layer of THICKNESS CONTROL of high permeable strata base crystal waterproof layer in 2mm or so, brushes 3~4 layers;Apply Border should cut border 50cm more than notch.
The above is only the preferred embodiment of the present invention, is not limited to the present invention, it is noted that for this skill For the those of ordinary skill in art field, on the premise of without departing from the technology of the present invention principle, can also make it is some improvement and Modification, these are improved and modification also should be regarded as protection scope of the present invention.

Claims (10)

1. seep water Treatment Methods a kind of tunnel-liner circular construction joint crack, it is characterised in that includes:
Circumferential groove is dug in the concrete surface of lining construction seam, ring installs PVC draining semicanals in groove, using polymer water Mud mending mortar closes notch, and the notch of circumferential groove is floating;
High permeable strata base crystal waterproof layer is scratched in the notch surface of circumferential groove;
Wherein, the slot opening of the circumferential groove × a length of 6cm × 7.5cm, circumferential groove extends to arch springing position.
2. seep water Treatment Methods tunnel-liner circular construction joint crack according to claim 1, it is characterised in that also includes Each 50cm scopes cable duct side wall and gutter before and after construction joint are cut, and is poured again, pre-buried PVC pipes, make when pouring Current can enter gutter in the PVC draining semicanals buried in circular construction joint, draw outside hole.
3. seep water Treatment Methods tunnel-liner circular construction joint crack according to claim 1, it is characterised in that notch table Face blade coating high permeable strata base crystal waterproof layer is specifically included:After first time waterproof layer starts hardening, brushing second layer waterproof Layer, each thickness is 1.5 to 2.5mm, brushes 3~4 layers.
4. seep water Treatment Methods tunnel-liner circular construction joint crack according to claim 3, it is characterised in that notch table The painting border of face blade coating high permeable strata base crystal waterproof layer cuts border 50cm more than notch.
5. seep water Treatment Methods tunnel-liner circular construction joint crack according to claim 3, it is characterised in that also includes The step of basic unit's lining cutting surface to brushing is rinsed.
6. seep water Treatment Methods tunnel-liner circular construction joint crack according to claim 1, it is characterised in that described PVC draining semicanals are the PVC draining semicanals of a diameter of 50mm.
7. seep water Treatment Methods tunnel-liner circular construction joint crack according to claim 1, it is characterised in that described PVC draining semicanals, the anchor ear made of 2mm thickness galvanized sheets is fixed in notch, anchor ear 2mm thickness galvanized sheet systems Make, circumferential distance 50cm.
8. seep water treatment structures a kind of tunnel-liner circular construction joint crack, it is characterised in that includes:In the mixed of lining construction seam Solidifying soil surface is provided with circumferential groove, and slot opening × a length of 6cm × 7.5cm of the circumferential groove, circumferential groove extends to arch springing position, Ring is provided with PVC draining semicanals in groove, and circumferential groove notch is using Polymet-cement Mortar for Reparation closing notch sealing, notch table Face is provided with high permeable strata base crystal waterproof layer,
The waterproof layer includes 3~4 layers, is 1.5 to 2.5mm per thickness degree.
9. seep water treatment structures tunnel-liner circular construction joint crack according to claim 8, it is characterised in that construction joint In front and back PVC pipes are embedded with the range of each 50cm, the PVC drainings semicanal buried in circular construction joint is connected with PVC pipes.
10. seep water treatment structures tunnel-liner circular construction joint crack according to claim 8, it is characterised in that described PVC draining semicanals, the anchor ear made of 2mm thickness galvanized sheets is fixed in notch, anchor ear 2mm thickness galvanized sheet systems Make, circumferential distance 50cm.
CN201710026109.6A 2017-01-13 2017-01-13 Treatment method and structure for water seepage of tunnel lining circular construction joint crack Pending CN106640154A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710026109.6A CN106640154A (en) 2017-01-13 2017-01-13 Treatment method and structure for water seepage of tunnel lining circular construction joint crack

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710026109.6A CN106640154A (en) 2017-01-13 2017-01-13 Treatment method and structure for water seepage of tunnel lining circular construction joint crack

Publications (1)

Publication Number Publication Date
CN106640154A true CN106640154A (en) 2017-05-10

Family

ID=58844254

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710026109.6A Pending CN106640154A (en) 2017-01-13 2017-01-13 Treatment method and structure for water seepage of tunnel lining circular construction joint crack

Country Status (1)

Country Link
CN (1) CN106640154A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107587434A (en) * 2017-10-16 2018-01-16 中交路桥建设有限公司 Culvert of reinforced concrete percolating water prevention and disposition method
CN107605513A (en) * 2017-09-13 2018-01-19 中交公局桥隧工程有限公司 A kind of application process of tunnel longitudinal direction construction joint cement base crystalline waterproof material
CN108104846A (en) * 2018-01-31 2018-06-01 湖南省交通科学研究院有限公司 The supercharging reverse osmosis mechanism of cavern and supercharging reverse osmosis method are reserved for square tunnel
CN108590752A (en) * 2018-01-09 2018-09-28 中交路桥建设有限公司 Draining repair system and its construction method after a kind of underdrain formula tunnel-liner
CN108825272A (en) * 2018-09-07 2018-11-16 西南交通大学 Lining construction seam infiltration drain structure and its implementation method
CN110184956A (en) * 2019-05-09 2019-08-30 中国铁道科学研究院集团有限公司铁道建筑研究所 A kind of construction method for reinforcing culvert
CN110567759A (en) * 2019-09-30 2019-12-13 安徽金联地矿科技有限公司 Soil layered water sample collecting device and method thereof
CN110808564A (en) * 2019-11-08 2020-02-18 南京聚联输变电安装有限责任公司 Concrete cable trench construction process
CN112317283A (en) * 2020-10-13 2021-02-05 杨恩德 Preparation method of ice-setting type self-plugging waterproof coating
CN112901222A (en) * 2021-02-23 2021-06-04 中铁五局集团有限公司 Treatment process for concrete water seepage cracks of inverted arch of tunnel

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201763359U (en) * 2010-09-07 2011-03-16 长安大学 Leakage water treatment node structure of tunnel construction joints
CN203783601U (en) * 2014-04-18 2014-08-20 山西省交通科学研究院 Treatment system suitable for tunnel construction seam water leakage in cold regions
CN104061017A (en) * 2014-07-08 2014-09-24 中交第二公路勘察设计研究院有限公司 Tunnel maintainable type pressure reducing and water draining method and device for water rich stratum
CN203925527U (en) * 2014-07-02 2014-11-05 山西省交通科学研究院 A kind of construction joint of tunnel percolating water punishment system
CN204419202U (en) * 2015-01-26 2015-06-24 上海路港建设工程有限公司 A kind of tunnel slot repair structure
CN204476470U (en) * 2015-01-20 2015-07-15 山西省交通科学研究院 A kind of waterproof and water drainage system of applicable tunnel project seam
CN206429253U (en) * 2017-01-13 2017-08-22 中交四公局第一工程有限公司 Seep water treatment structures in tunnel-liner circular construction joint crack

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201763359U (en) * 2010-09-07 2011-03-16 长安大学 Leakage water treatment node structure of tunnel construction joints
CN203783601U (en) * 2014-04-18 2014-08-20 山西省交通科学研究院 Treatment system suitable for tunnel construction seam water leakage in cold regions
CN203925527U (en) * 2014-07-02 2014-11-05 山西省交通科学研究院 A kind of construction joint of tunnel percolating water punishment system
CN104061017A (en) * 2014-07-08 2014-09-24 中交第二公路勘察设计研究院有限公司 Tunnel maintainable type pressure reducing and water draining method and device for water rich stratum
CN204476470U (en) * 2015-01-20 2015-07-15 山西省交通科学研究院 A kind of waterproof and water drainage system of applicable tunnel project seam
CN204419202U (en) * 2015-01-26 2015-06-24 上海路港建设工程有限公司 A kind of tunnel slot repair structure
CN206429253U (en) * 2017-01-13 2017-08-22 中交四公局第一工程有限公司 Seep water treatment structures in tunnel-liner circular construction joint crack

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
筑龙网: "《隧道与地下工程施工技术案例精选》", 30 April 2009, 中国电力出版社 *

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107605513A (en) * 2017-09-13 2018-01-19 中交公局桥隧工程有限公司 A kind of application process of tunnel longitudinal direction construction joint cement base crystalline waterproof material
CN107587434A (en) * 2017-10-16 2018-01-16 中交路桥建设有限公司 Culvert of reinforced concrete percolating water prevention and disposition method
CN108590752A (en) * 2018-01-09 2018-09-28 中交路桥建设有限公司 Draining repair system and its construction method after a kind of underdrain formula tunnel-liner
CN108104846A (en) * 2018-01-31 2018-06-01 湖南省交通科学研究院有限公司 The supercharging reverse osmosis mechanism of cavern and supercharging reverse osmosis method are reserved for square tunnel
CN108825272A (en) * 2018-09-07 2018-11-16 西南交通大学 Lining construction seam infiltration drain structure and its implementation method
CN110184956A (en) * 2019-05-09 2019-08-30 中国铁道科学研究院集团有限公司铁道建筑研究所 A kind of construction method for reinforcing culvert
CN110567759A (en) * 2019-09-30 2019-12-13 安徽金联地矿科技有限公司 Soil layered water sample collecting device and method thereof
CN110808564A (en) * 2019-11-08 2020-02-18 南京聚联输变电安装有限责任公司 Concrete cable trench construction process
CN112317283A (en) * 2020-10-13 2021-02-05 杨恩德 Preparation method of ice-setting type self-plugging waterproof coating
CN112901222A (en) * 2021-02-23 2021-06-04 中铁五局集团有限公司 Treatment process for concrete water seepage cracks of inverted arch of tunnel

Similar Documents

Publication Publication Date Title
CN106640154A (en) Treatment method and structure for water seepage of tunnel lining circular construction joint crack
CN110306616B (en) Construction method of sewage pipeline
CN110617083A (en) Real-time intelligent monitoring and alarming construction method for tunnel lining concrete compactness
CN107859064B (en) Waterproof structure for connection of prefabricated pipe gallery and cast-in-situ pipe gallery and construction method
CN107489167A (en) A kind of underground pipe gallery socket joint deformation joint structure and its construction method
CN206319910U (en) Infiltration disposal system is reinforced in a kind of tunnel-liner
CN110565779B (en) Method for trenchless replacement and repair of sewage pipeline
CN206429253U (en) Seep water treatment structures in tunnel-liner circular construction joint crack
CN105239729B (en) It has constructed the construction method of poling reparation of punching after roofing
CN109610606A (en) Underground piping, which moves, changes cutover construction and method
CN113513048A (en) Station house underground passage leakage-proof structure and construction process
CN104652495B (en) Internal support of foundation pit column and base plate node waterproof construction technology
CN104264700A (en) Seepage prevention construction method for light-weight precipitation well point post-cast strip of underground construction
CN109457571B (en) Construction method for repairing ground deformation joint
CN102425228A (en) Multifunctional environment-friendly movable water tank
CN202401561U (en) Multifunctional environment-friendly movable water channel
CN103741651B (en) A kind of concrete teeth groove stiling basin and construction method thereof
CN110808564B (en) Concrete cable trench construction process
CN207727733U (en) The spliced gutter that can be had enough to meet the need
CN105926665A (en) Large block assembled type prefabricated concrete drainage pipeline base and construction method thereof
CN111335445B (en) Construction method of concrete catch basin by using steel pipe as inner mold
CN110056071A (en) A kind of municipal administration storm sewer assembling module and construction method
CN109296011A (en) Underground structrue engineering concrete structure seam waterproof construction technology
CN107023061B (en) Assembled plastic municipal drainage inspection well and construction method
CN115012451A (en) Underground structure induced joint

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20170510

RJ01 Rejection of invention patent application after publication