CN109610606A - Underground piping, which moves, changes cutover construction and method - Google Patents

Underground piping, which moves, changes cutover construction and method Download PDF

Info

Publication number
CN109610606A
CN109610606A CN201811601411.0A CN201811601411A CN109610606A CN 109610606 A CN109610606 A CN 109610606A CN 201811601411 A CN201811601411 A CN 201811601411A CN 109610606 A CN109610606 A CN 109610606A
Authority
CN
China
Prior art keywords
pipeline
moves
built
wall
underground piping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811601411.0A
Other languages
Chinese (zh)
Inventor
王延辉
李逢魁
李云涛
汪朋
龚岳
李文玉
王世强
谢勇军
周天顺
张�林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Tunnel Group Co Ltd CRTG
China Railway Tunnel Stock Co Ltd
Original Assignee
China Railway Tunnel Group Co Ltd CRTG
China Railway Tunnel Stock Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tunnel Group Co Ltd CRTG, China Railway Tunnel Stock Co Ltd filed Critical China Railway Tunnel Group Co Ltd CRTG
Priority to CN201811601411.0A priority Critical patent/CN109610606A/en
Publication of CN109610606A publication Critical patent/CN109610606A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/06Methods of, or installations for, laying sewer pipes
    • EFIXED CONSTRUCTIONS
    • E03WATER SUPPLY; SEWERAGE
    • E03FSEWERS; CESSPOOLS
    • E03F3/00Sewer pipe-line systems
    • E03F3/06Methods of, or installations for, laying sewer pipes
    • E03F2003/065Refurbishing of sewer pipes, e.g. by coating, lining

Landscapes

  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Engineering & Computer Science (AREA)
  • Hydrology & Water Resources (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • Sewage (AREA)

Abstract

It is moved the invention discloses a kind of underground piping and changes cutover construction and method, which moves that change cutover construction include wait move the former pipeline changed, the pre- newly-built pipeline for being laid with completion, the operation well that former pipeline position to be cut is arranged in;Method includes the following steps: 1) determine wait move the former duct route changed and be laid with the completion of newly-built pipeline, construction operation well is being excavated wait move the former pipeline corresponding position to be cut changed;2) precast concrete chute;3) it cuts pipeline and lifts while carrying out, with the plugged and abandoned pipe end of fixed plate;4) it will be connect to reconfiguration pipe end with the newly-built pipe end laid with concrete chute, be sealed processing;5) it after the completion of reconfiguration, is excavated above the discarded pipe on the ground far from the operation borehole wall, excavation abolishes discarded pipe top, then builds and blocks brick wall, and blocking brick wall, bar planting enters exhaust piping wall up and down, pours waterproof and sealing material;The construction method is simple, easy to operate, securely and reliably.

Description

Underground piping, which moves, changes cutover construction and method
Technical field
The present invention relates to underground engineering technical fields, and in particular to a kind of underground piping, which moves, changes cutover construction and method.
Background technique
The municipal works such as subway frequently encounter underground utilities obstacle, sewage conduct and tap water in the construction of city busy section of town Pipeline is the municipal pipeline frequently encountered.Move change cutover municipal pipeline when, needing problems faced is the water having in pipeline Or sewage needs to handle, and can not be pumped to outside again in bustling place, cannot influence resident's normal life.This is seriously affected newly Build the construction speed and construction cost of pipeline connection.It is also faced with how the closure of processing discarded pipe rapidly and efficiently is asked simultaneously Topic.
Have at present and not only cut off the water but also the underground piping of pump drainage water moves and changes there are many kinds of method for cutting over, such as directly pipeline can be broken It removes, lays bricks, or new pipeline is directly connected by bend pipe, discarded pipe is directly the methods of deactivated.About without taking out The underground piping of draining, which moves, to be changed method for cutting over and there is no.
It currently needs one kind and does not have to pump drainage water, easy for construction, investment reduction, and safe and reliable buried pipe road moves and changes cutover structure The construction technology made.
Summary of the invention
The present invention is intended to provide a kind of underground piping, which moves, changes cutover construction and method, moves to change to reaching underground piping and do not have to Pump drainage water, the purpose that construction is rapid, the time is short, at low cost and safe and reliable.
To achieve the above object, the present invention adopts the following technical scheme:
It designs a kind of underground piping and moves and change cutover construction, including wait move the former pipeline changed, the pre- newly-built pipeline for being laid with completion, setting Operation well at former pipeline position to be cut: including to reconfiguration pipeline and discarded pipe wait move the former pipeline changed;To reconfiguration pipeline Port is connect by concrete chute with the pre- newly-built pipe end for being laid with completion;Support is provided in discarded pipe end to block Unit and fills unit.
Preferred: it includes closure brick wall and fixed plate with bar planting that support, which blocks unit,;Closure brick wall with bar planting It is sequentially arranged in discarded pipe from the inside to the outside with fixed plate;Or the closure brick wall with bar planting sets full discarded pipe from the inside to the outside Interior, fixed plate is located at discarded pipe port.
Preferred: fills unit includes waterproof material sealant;Waterproof material sealant is filled in support and blocks in unit.
Preferred: concrete chute is made of the concrete block with circular arc or concrete chute is interior recessed with circular arc The tetragonal body in face.
A kind of underground piping, which moves, changes method for cutting over, comprising the following steps:
(1) it determines wait move the former duct route changed and be laid with the completion of newly-built pipeline, wait move the former pipeline correspondence to be cut changed Position, which is excavated, builds operation well;
(2) precast concrete chute;
(3) it cuts pipeline and lifts while carrying out, with the plugged and abandoned pipe end of fixed plate;
(4) it will be connect to reconfiguration pipe end with the newly-built pipe end laid with concrete chute, be sealed processing;
(5) it after the completion of reconfiguration, is excavated above the discarded pipe on the ground far from the operation borehole wall, excavation is abolished on discarded pipe Then portion builds and blocks brick wall, blocking brick wall, bar planting enters exhaust piping wall up and down, pours waterproof and sealing material;
Or completely closure brick wall is built in discarded pipe of the place of abolishing to fixed plate excavating, blocking brick wall, bar planting enters exhaust piping up and down Wall.
It is preferred: in step (1), to operate 50~70cm of borehole wall thickness.
Preferred: in step (3), fixed plate is cement plate, armoured concrete slab or iron plate;Fixed 2~5 cm of plate thickness.
Preferred: in step (4), it is quick hardening cement that jointing, which handles material,.
Preferred: in step (5), waterproof and sealing material is cement concrete, asphalt waterproof material, rubber plastic class One of waterproof material.
Compared with prior art, the beneficial technical effect of the present invention lies in:
1. underground piping of the invention moves, to change cutover simple structure reliable, effectively quickly can move changing, low cost, while not Influence construction speed.
2. underground piping of the present invention moves and changes that method for cutting over is simple, and the construction time is short, easy to operate, at low cost, securely and reliably.
3. underground piping of the present invention, which moves, changes method for cutting over using rope saw and lifting device collective effect, it is ensured that smooth, peace Full cutting pipeline;Fixed plate is first blocked in advance, avoids the water in a large amount of pipelines or other sundries are flow in operation well, just In the connection to reconfiguration pipeline and newly-built pipeline;The closure brick wall with bar planting such as tube wall is built in pipeline not only effectively stops pipe The water and sundries having in road may also function as the effect for solidifying and stopping waterproof and sealing material, provide for filling waterproof and sealing material Good, safe insulating space;Construction safety is reliable, rapidly and efficiently;Upstream termination of pumping simultaneously, not pump drainage have water in pipeline Or sewage, do not influence construction speed.
4. underground piping of the present invention move change method for cutting over using concrete chute will be to reconfiguration pipe end and newly-built pipeline Port connection, fixes new old pipeline well and is connected the certain angle for being in, and concrete chute is played connection and smoothly made With, and concrete chute prepares in advance, quick and convenient, saving of work and time.
Detailed description of the invention
Fig. 1 moves for inventive pipeline changes control top view cross section structural schematic diagram;
Fig. 2 is present invention rope saw cut pipeline main view the schematic diagram of the section structure;
Fig. 3 is present invention cutting lifting pipeline main view the schematic diagram of the section structure;
Fig. 4 is the pre- plugged and abandoned pipeline main view the schematic diagram of the section structure of the present invention;
Fig. 5-1 is the top view cross section structural schematic diagram that the present invention is connect to reconfiguration pipeline with newly-built pipeline;
Fig. 5-2 is the top view cross section structural schematic diagram that the present invention is connect to reconfiguration pipeline with newly-built pipeline;
Fig. 6 is that discarded pipe of the present invention excavation abolishes place's main view the schematic diagram of the section structure;
Fig. 7 is that discarded pipe of the present invention excavates the place's of abolishing construction main view the schematic diagram of the section structure;
Fig. 8-1 is that discarded pipe of the present invention excavates main view the schematic diagram of the section structure after the place of abolishing blocks;
Fig. 8-2 is that discarded pipe of the present invention excavates main view the schematic diagram of the section structure after the place of abolishing blocks;
Fig. 9 is that well room of the present invention modifies main view the schematic diagram of the section structure;
Figure 10 is the structural schematic diagram of concrete chute of the present invention (a figure is top view, and b figure is left view);
In figure, 1 is former pipeline, and 101 is, to reconfiguration pipeline, 102 are discarded pipe, and 2 be newly-built pipeline, and 3 be operation well, and 301 are The borehole wall, 4 be inspection shaft, and 5 be rope sawing cutpoint, and 6 be lifting device, and 7 be fixed plate, and 8 be concrete chute, and 9 abolish to excavate Place, 10 is block brick wall, and 11 be waterproof and sealing material, and 12 be armoured concrete slab, and 13 be well head, and 14 be concrete filling block, 15 be hollow block.
Specific embodiment
Illustrate a specific embodiment of the invention with reference to the accompanying drawings and examples, but following embodiment is used only in detail It describes the bright present invention in detail, does not limit the scope of the invention in any way.
Components and structure involved in following embodiment or unit module are then unless otherwise instructed conventional city Sell product.
Embodiment 1:
A kind of underground piping, which moves, changes cutover construction, referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7, Fig. 8 and Fig. 9, including to It moves the former pipeline 1 changed, the pre- newly-built pipeline 2 for being laid with completion, the operation well 3 that former pipeline position to be cut is set: changing wait move Former pipeline 1 includes to reconfiguration pipeline 101 and discarded pipe 102;Pass through concrete chute 8 to 101 port of reconfiguration pipeline and overlay If 2 port of the newly-built pipeline connection of completion;It is provided with support in 102 end of discarded pipe and blocks unit and fills unit.It is discarded The end of pipeline 102 flushes or protrudes from operation 3 inner wall of well, prominent operation 3 inner wall of well in the end to reconfiguration pipeline 101.
Embodiment 2:
A kind of underground piping, which moves, changes cutover construction, referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7, Fig. 8 and Fig. 9, including to The former pipeline changed, the pre- newly-built pipeline for being laid with completion, the operation well that former pipeline position to be cut is set are moved, not with embodiment 1 Be with place: it includes closure brick wall 10 and fixed plate 7 with bar planting that support, which blocks unit,;Closure brick wall 10 with bar planting In discarded pipe 102, fixed plate 7 is located at 102 port of discarded pipe;Or the closure brick wall 10 with bar planting is set completely from the inside to the outside In discarded pipe 102, fixed plate 7 is located at discarded pipe port.
Fixed plate is cement plate, armoured concrete slab or iron plate.
Embodiment 3:
A kind of underground piping, which moves, changes cutover construction, referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7, Fig. 8, Fig. 9 and Figure 10, packet It includes wait move the former pipeline 1 changed, the pre- newly-built pipeline 2 for being laid with completion, the operation well 3 that former pipeline position to be cut is arranged in, with reality Apply example 2 the difference is that: fills unit includes waterproof material sealant;Waterproof material sealant is filled in support and blocks unit It is interior;Concrete chute 8 is made of the concrete block with circular arc or concrete chute 8 is the interior tetragonal body for having circular arc concave surface (chute circular arc both ends communicate, and do not bind) (such as Figure 10).
Waterproof material sealant is made of waterproof and sealing material 11.Waterproof and sealing material 11 can use cement concrete or drip Green waterproof material or rubber plastic class waterproof material.
Embodiment 4
A kind of underground piping, which moves, changes method for cutting over, referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7, Fig. 8, Fig. 9 and Figure 10, packet Include following steps:
(1) it determines wait move 1 route of former pipeline changed and be laid with the completion of newly-built pipeline 2, is waited for wait move 1 upstream and downstream of former pipeline changed It cuts corresponding position and excavates the construction operation operation well 3 of the upstream well 3(one, one, downstream operation well 3, totally two operation wells 3, are grasped Make 3 surrounding of well to lay bricks wall, 3 top of operation well does not carry out any renovation), operation 3 wall of well, 301 thickness is 50~70cm;
(2) basis moves the parameters precast concrete such as the diameter for changing new old pipeline, well room size, absolute altitude, angle chute 10: can use band There is the mold piecemeal of arc surface that concrete block is made, concrete block combines arc surface will be smoothly;Or it can be with shown in Fig. 10 Concrete chute 10;
(3) the operation well 3 dug in upstream and downstream, while pipeline is cut and being lifted, the plugged and abandoned pipe of fixed plate 7 is used later 102 port of road;Fixed plate 7 is cement plate, armoured concrete slab or iron plate, 7 thickness of fixed plate, 2~5 cm;
(4) by the concrete chute 10 made lift in supreme, downstream process well 3 respectively will to reconfiguration pipe end 101 with 2 port of the newly-built pipeline connection laid, carries out jointing encapsulation process with quick hardening cement;End to reconfiguration pipeline 101 is prominent Operate 3 inner wall of well;
(5) it after the completion of reconfiguration, is excavated above the discarded pipe 102 on the ground far from operation 3 wall 301 of well, excavation is abolished discarded Then 102 top of pipeline builds and blocks brick wall 10, block about 10 bar planting of brick wall and enter 102 wall of discarded pipe, pour waterproof sealing material Material 11, is permanently blocked;
Or excavate built in the place of abolishing to the discarded pipe 102 between fixed plate 7 completely block brick wall 10(block brick wall 10 can width 1m), It blocks about 10 bar planting of brick wall and enters 102 wall of discarded pipe.
(6) finishing operation well 3, well room top are equipped with well head, and discarded pipe 102 excavates the place of abolishing 9 up to ground and filled out Embedding is stifled.
Operation well 3 can be described as well of riding again herein, and the structure for well of riding is as the structure of inspection shaft 4, only title Difference, well of riding is vivider for cutting lifting pipeline.
It is laid with newly-built pipeline 2 in advance, but due to there is angle between pipeline connection, similarly uses concrete chute 8 Be attached, but concrete chute 8 at this time do not have to it is prefabricated, the mold with circular arc can be directly built in inspection shaft 4 and poured Build concrete completion (or can directly using it is brick at), this does not need the limitation of time.But newly-built pipeline 2 and former pipeline 1 When reconfiguration pipeline 101 connect when, due to the limitation of municipal construction time, the shorter the time the better, brings life with exempt from customs examination citizen Puzzlement just in advance prepares concrete chute 8.
It is had the gap between concrete chute 8 and fixed plate 7, but gap very little, in control range, concrete chute 8 is placed It, will be between concrete chute 8 and fixed plate 7 on gap sealing with concrete after getting well and carrying out jointing processing.
Waterproof and sealing material 11 is one of cement concrete, asphalt waterproof material, rubber plastic class waterproof material.
Figure 10 is the structural schematic diagram of concrete chute 8, and a figure is top view, and b figure is left view.Concrete chute is available Iron plate is fabricated to tetragonal body, interior hollow with arc-shaped, and hollow arc-shaped is assembled by two arc-shaped iron plates fixations, It is assembled secured.Outside arc-shaped iron plate camber line and structure one end of tetragonal body formation seals, and passes through other end casting concrete, is formed One concrete filling block 14;It is made of with this concrete chute 8 concrete filling block 14 and hollow block 15.
Embodiment 5
A kind of underground piping, which moves, changes method for cutting over, referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7, Fig. 8, Fig. 9 and Figure 10, packet Include following steps: first wait move 1 route of former pipeline changed and be laid with the completion of newly-built pipeline 2, wait move about the 1 former pipeline changed It swims corresponding position to be cut and excavates and build the operation operation well 3 of the upstream well 3(one, one, downstream operation well 3, totally two operation wells 3, operation well surrounding is laid bricks wall, and 3 top of operation well does not carry out any renovation), all are docked with the company of draining after the arrangements are complete, really The date and time point for determining cutover contact the upstream drainage pumping plant being related to, and upstream pumping unit is needed to cooperate termination of pumping during carrying out cutover Pump drainage, Emergency Preparedness when dragging down the preparation and emergency of water level, carry out cutover preparation;According to new and old pipe The parameter designings concrete chutes 8 such as diameter, well room size, absolute altitude, the angle in road, on the ground on precast concrete chute 8(, Concrete chute 8 used in downstream makes simultaneously, totally two concrete chutes 8), the mold made using iron plate or plank, then Production concrete chute 8 is poured with armored concrete;Cutover point has been dug, it manually will rope 5 duct bottom basis of sawing contact chisel It removes, is passed through in advance by duct bottom around in place with lifting device 6, rope sawing cutpoint 5 flushes or dashes forward with operation 3 inner wall end of well Out, to prominent operation 3 inner wall of well in the end of reconfiguration pipeline 101, after saw cut of restricting, directly the pipeline section that cutover goes out is hung out;With admittedly After fixed board 7 blocks 102 port of discarded pipe in advance, then produced concrete chute 8 is lifted in supreme downstream process well 3 and is divided It is not mounted on to 101 port of reconfiguration pipeline, and by corresponding newly-built 2 port of pipeline insertion concrete chute, reaches wait change The purpose that adapter tube road 101 is connected with newly-built pipeline 2, and jointing encapsulation process is carried out with quick hardening cement;On the ground far from behaviour Make to excavate broken hole above the discarded pipe 102 of 3 wall 301 of well, dig to discarded pipe 102, will be abolished at the top of discarded pipe 102, Artificial build blocks brick wall 10, blocks about 10 bar planting of brick wall and enters 102 wall of discarded pipe, prevents water in discarded pipe 102 well Or sundries carries out strong impact to brick wall 10 is blocked, and blocks 10 top of brick wall and does not build to staying a gap side at the top of discarded pipe 102 Just waterproof and sealing material 11 is poured, waterproof and sealing material 11 is poured, is permanently blocked, puzzles block brick wall 10 later, finishing Operate well 3;Sealing is built with armoured concrete slab 12,12 surrounding of armoured concrete slab is fixed on the borehole wall 301, and centre is equipped with well Mouth 13, well head 13 covers well lid;Discarded pipe 102 excavates the place of abolishing 9 up to ground and carries out landfill closure.
Or in order to catch up with construction speed, it can excavate in the discarded pipe 102 after broken hole, 1 meter wide of closure brick wall can be built 10, it blocks about 10 bar planting of brick wall and enters on 102 wall of discarded pipe, it is simple and quick, save working hour.
Operation well 3 can be described as well of riding again herein, and the structure for well of riding is as the structure of inspection shaft 4, only title Difference, well of riding is vivider for cutting lifting pipeline.
It is laid with newly-built pipeline 2 in advance, but due to there is angle between pipeline connection, similarly uses concrete chute 8 Be attached, but concrete chute 8 at this time do not have to it is prefabricated, the mold with circular arc can be directly built in inspection shaft 4 and poured Concrete completion is built, this does not need the limitation of time.But pipeline 2 and former when connecting when reconfiguration pipeline 101 of pipeline 1 are created, Due to the limitation of municipal construction time, the shorter the time the better, brings life to perplex with exempt from customs examination citizen, just in advance concrete chute 8 prepare.
It is had the gap between concrete chute 8 and fixed plate 7, but gap very little, in control range, concrete chute 8 is placed It, will be between concrete chute 8 and fixed plate 7 on gap sealing with concrete after getting well and carrying out jointing encapsulation process.
Figure 10 is the structural schematic diagram of concrete chute 8, and a figure is top view, and b figure is left view.Concrete chute is available Iron plate is fabricated to tetragonal body (concrete chute circular arc both ends communicate, and do not bind), and interior hollow with arc-shaped, arc-shaped is hollow It is to be assembled by two arc-shaped iron plate fixations, it is assembled secured.The outer structure one with tetragonal body formation of arc-shaped iron plate camber line End sealing forms a concrete filling block 14 by other end casting concrete;It is filled out with this concrete chute 8 by a concrete It fills block 14 and hollow block 15 forms.
Embodiment 6
A kind of underground piping, which moves, changes method for cutting over, referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7, Fig. 8, Fig. 9 and Figure 10, with Embodiment 5 the difference is that: operation 3 wall of well, 301 50~70cm of thickness;Rope sawing cutpoint 5 cut pipeline can end flush or dash forward For operation 3 inner wall of well;7 thickness of fixed plate, 2~5 cm, fixed plate 7 are cement plate, armoured concrete slab or iron plate;Waterproof sealing Material 11 is one of cement concrete, asphalt waterproof material, rubber plastic class waterproof material.
Embodiment 7
A kind of underground piping, which moves, changes method for cutting over, referring to Fig. 1, Fig. 2, Fig. 3, Fig. 4, Fig. 5, Fig. 6, Fig. 7, Fig. 8, Fig. 9 and Figure 10.
Construction method Detailed operating procedures are as follows:
The first step is available, and Fig. 1 shows determine at transformation duct route and constructing operation, and complete the laying of newly-built pipeline 2;
Second step can indicate with Figure 10, the preparation of concrete chute 8, according to moving the diameter for changing new old pipeline, well room size, mark The parameters precast concrete such as height, angle chute 8;
Third step can indicate with Fig. 2 and Fig. 3, treat to move and change pipeline and cut and lifted;
4th step can be indicated with Fig. 4, with pre- plugged and abandoned 102 port of pipeline of fixed plate 7;Fixed plate 7 is cement plate, reinforcing bar is mixed Concrete board or iron plate, 7 thickness of fixed plate, 2~5 cm;
5th step can indicate that lifting the concrete chute 8 made respectively will be to reconfiguration in supreme, downstream process well 3 with Fig. 5 101 port of pipeline is connect with 2 port of newly-built pipeline laid, carries out jointing encapsulation process with quick hardening cement;
6th step can be indicated with Fig. 6, be excavated above the discarded pipe 102 on the ground far from operation 3 wall 301 of well, excavation is abolished 102 top of discarded pipe;
7th step can be indicated with Fig. 7, built and blocked brick wall 10, blocked about 10 bar planting of brick wall and entered 102 wall of discarded pipe, block brick There are gaps between wall 10 and discarded pipe 102;
8th step is available, and Fig. 8 shows pour waterproof and sealing material 11, block brick wall and puzzle, block and complete.
9th step can be indicated with Fig. 9, at the top of finishing operation well 3.
Above-mentioned underground piping moves the specific implementation method for changing cutover construction:
Construction personnel is first wait move 1 route of former pipeline changed and be laid with the completion of newly-built pipeline 2, wait move on the former pipeline 1 changed Downstream corresponding position to be cut, which excavates, builds the operation operation well 3 of the upstream well 3(one, one, downstream operation well 3, totally two operations Well 3, operation 3 surrounding of well are laid bricks wall, and 3 top of operation well does not carry out any renovation), all after the arrangements are complete with draining company pair It connects, contacts the upstream drainage pumping plant being related to, the preparation that upstream pumping unit cooperation termination of pumping pump drainage is needed during carrying out cutover, drags down water level Emergency Preparedness when work and emergency, determines the date and time point of cutover, carries out cutover preparation;According to new The parameter designings concrete chutes 8 such as diameter, well room size, absolute altitude, the angle of old pipeline, on the ground precast concrete chute 8 (concrete chute 8 used in upstream and downstream makes simultaneously, totally two concrete chutes 8), the mould made using iron plate or plank Tool, then production concrete chute 8 is poured with armored concrete;Cutover point, brick walling, manually by cutover point pipeline bottom are dug Portion basis is cut, and is passed through in advance by duct bottom around in place, rope sawing cutpoint 5 and operation 3 inner wall end of well with lifting device 6 It flushes or protrudes, after saw cut of restricting, directly hang out the pipeline section that cutover goes out;102 port of discarded pipe is blocked in advance with fixed plate 7 Afterwards, then produced concrete chute 8 is lifted in supreme downstream process well 3 and is separately mounted to 101 port of reconfiguration pipeline, and It in corresponding newly-built 2 port of pipeline insertion concrete chute 8, will reach and be connected to reconfiguration pipeline 101 with newly-built pipeline 2 Purpose, and jointing processing is carried out with quick hardening cement;It is excavated above discarded pipe 102 on the ground far from operation 3 wall 301 of well broken Hole is dug to discarded pipe 102, will be abolished at the top of discarded pipe 102, and artificial build blocks brick wall 10, blocks about 10 brick wall and plants Muscle enters on 102 wall of discarded pipe, prevents water or sundries in discarded pipe 102 from carrying out strong impact to brick wall 10 is blocked well, It blocks the top of brick wall 10 not building to staying a gap conveniently to pour waterproof and sealing material 11 at the top of discarded pipe 102, it is close to pour building waterproofing It after closure material 11, is permanently blocked, puzzles block brick wall 10, finishing operation well 3 later;Envelope is built with armoured concrete slab 12 Mouthful, 12 surrounding of armoured concrete slab is fixed on the borehole wall 301, and centre is equipped with well head 13, and well head 13 covers well lid;Discarded pipe 102, which excavate 9 place of the place of abolishing up to ground, carries out landfill closure.
Or in order to catch up with construction speed, it can excavate in the discarded pipe 102 after broken hole, 1 meter wide of closure brick wall can be built 10, it blocks about 10 bar planting of brick wall and enters on 102 wall of discarded pipe, it is simple and quick, save working hour.
If constructing in low laying areas, water deposits stream in operation well 3, does not influence being normally carried out for construction.
The present invention is described in detail above in conjunction with drawings and examples, still, those of skill in the art Member is it is understood that without departing from the purpose of the present invention, can also carry out each design parameter in above-described embodiment Change, forms multiple specific embodiments, is common variation range of the invention, is no longer described in detail one by one herein.

Claims (9)

1. a kind of underground piping, which moves, changes cutover construction, including existing wait move the former pipeline changed, the pre- newly-built pipeline for being laid with completion, be arranged The operation well at former pipeline position to be cut, it is characterised in that: described wait move the former pipeline changed includes to reconfiguration pipeline and discarded pipe Road;It is described to be connect by concrete chute with the pre- newly-built pipe end for being laid with completion to reconfiguration pipe end;Described It is provided with support in discarded pipe end and blocks unit and fills unit.
2. underground piping according to claim 1, which moves, changes cutover construction, it is characterised in that: the support blocks unit and includes Closure brick wall and fixed plate with bar planting;The closure brick wall and fixed plate with bar planting is sequentially arranged at described from the inside to the outside In discarded pipe;Or the closure brick wall with bar planting is set from the inside to the outside in the completely described discarded pipe, the fixed plate is located at The discarded pipe port.
3. underground piping according to claim 1, which moves, changes cutover construction, it is characterised in that: the fills unit includes waterproof Material sealant;The waterproof material sealant is filled in support and blocks in unit.
4. underground piping according to claim 1, which moves, changes cutover construction, it is characterised in that: the concrete chute is by having The concrete block of circular arc is constituted or the concrete chute is the interior tetragonal body for having circular arc concave surface.
5. a kind of underground piping, which moves, changes method for cutting over, it is characterised in that: the following steps are included:
(1) it determines wait move the former duct route changed and be laid with the completion of newly-built pipeline, wait move the former pipeline correspondence to be cut changed Position, which is excavated, builds operation well;
(2) precast concrete chute;
(3) it cuts pipeline and lifts while carrying out, with the plugged and abandoned pipe end of fixed plate;
(4) it will be connect to reconfiguration pipe end with the newly-built pipe end laid with concrete chute, be sealed processing;
(5) it after the completion of reconfiguration, is excavated above the discarded pipe on the ground far from the operation borehole wall, excavation is abolished on discarded pipe Then portion builds and blocks brick wall, blocking brick wall, bar planting enters exhaust piping wall up and down, pours waterproof and sealing material;
Or completely closure brick wall is built in discarded pipe of the place of abolishing to fixed plate excavating, blocking brick wall, bar planting enters exhaust piping up and down Wall.
6. underground piping, which moves, according to claim 5 changes method for cutting over, it is characterised in that: in the step (1), the behaviour Make 50~70cm of borehole wall thickness.
7. underground piping, which moves, according to claim 5 changes method for cutting over, it is characterised in that: described solid in the step (3) Fixed board is cement plate, armoured concrete slab or iron plate;2~5 cm of fixed plate thickness.
8. underground piping, which moves, according to claim 5 changes method for cutting over, it is characterised in that: described close in the step (4) Envelope processing material is quick hardening cement.
9. underground piping, which moves, according to claim 5 changes method for cutting over, it is characterised in that: described anti-in the step (5) Watertight closure material is one of cement concrete, asphalt waterproof material, rubber plastic class waterproof material.
CN201811601411.0A 2018-12-26 2018-12-26 Underground piping, which moves, changes cutover construction and method Pending CN109610606A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811601411.0A CN109610606A (en) 2018-12-26 2018-12-26 Underground piping, which moves, changes cutover construction and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811601411.0A CN109610606A (en) 2018-12-26 2018-12-26 Underground piping, which moves, changes cutover construction and method

Publications (1)

Publication Number Publication Date
CN109610606A true CN109610606A (en) 2019-04-12

Family

ID=66012421

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811601411.0A Pending CN109610606A (en) 2018-12-26 2018-12-26 Underground piping, which moves, changes cutover construction and method

Country Status (1)

Country Link
CN (1) CN109610606A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185933A (en) * 2019-06-24 2019-08-30 华元创展(香港)有限公司 Pipeline oil product, which changes, moves system and method
CN113073722A (en) * 2021-02-20 2021-07-06 中国港湾工程有限责任公司 Demolishing and backfilling integrated device suitable for underground flexible pipeline and working method thereof
CN113700115A (en) * 2021-09-06 2021-11-26 中铁四局集团路桥工程有限公司 Suspension protection construction method for municipal drainage closed conduit steel pipe transformation
CN113932063A (en) * 2021-09-26 2022-01-14 上海电信工程有限公司 Underground pipeline construction process and moving and modifying method
CN116219916A (en) * 2023-03-23 2023-06-06 上海市政工程设计研究总院(集团)有限公司 Pressure box culvert pressure-changing system and construction method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2635736Y (en) * 2003-08-12 2004-08-25 张东川 Shaping mould for manhole
JP3860754B2 (en) * 2002-01-09 2006-12-20 株式会社ハネックス manhole
CN103352512A (en) * 2013-07-03 2013-10-16 张希文 Prefabricated inspection well sluice
CN103362204A (en) * 2012-04-09 2013-10-23 苏州园林营造工程有限公司 Method for blocking rain sewage pipeline
CN205742482U (en) * 2016-06-21 2016-11-30 宣城市政建设集团有限公司 A kind of novel prefabricated assembled rain sewage inspection well chute
CN106368241A (en) * 2016-01-27 2017-02-01 郑州市市政工程总公司 Inspection well for fast-connected newly-built pipeline and construction method thereof

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3860754B2 (en) * 2002-01-09 2006-12-20 株式会社ハネックス manhole
CN2635736Y (en) * 2003-08-12 2004-08-25 张东川 Shaping mould for manhole
CN103362204A (en) * 2012-04-09 2013-10-23 苏州园林营造工程有限公司 Method for blocking rain sewage pipeline
CN103352512A (en) * 2013-07-03 2013-10-16 张希文 Prefabricated inspection well sluice
CN106368241A (en) * 2016-01-27 2017-02-01 郑州市市政工程总公司 Inspection well for fast-connected newly-built pipeline and construction method thereof
CN205742482U (en) * 2016-06-21 2016-11-30 宣城市政建设集团有限公司 A kind of novel prefabricated assembled rain sewage inspection well chute

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
同济大学: "《排水工程 上》", 31 July 1978, 上海科学技术出版社 *
毛峰: "大型污水新老管道改接设计方案分析", 《中国市政工程》 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110185933A (en) * 2019-06-24 2019-08-30 华元创展(香港)有限公司 Pipeline oil product, which changes, moves system and method
CN113073722A (en) * 2021-02-20 2021-07-06 中国港湾工程有限责任公司 Demolishing and backfilling integrated device suitable for underground flexible pipeline and working method thereof
CN113700115A (en) * 2021-09-06 2021-11-26 中铁四局集团路桥工程有限公司 Suspension protection construction method for municipal drainage closed conduit steel pipe transformation
CN113932063A (en) * 2021-09-26 2022-01-14 上海电信工程有限公司 Underground pipeline construction process and moving and modifying method
CN113932063B (en) * 2021-09-26 2023-08-15 上海电信工程有限公司 Underground pipeline construction process and migration and modification method
CN116219916A (en) * 2023-03-23 2023-06-06 上海市政工程设计研究总院(集团)有限公司 Pressure box culvert pressure-changing system and construction method thereof

Similar Documents

Publication Publication Date Title
CN109610606A (en) Underground piping, which moves, changes cutover construction and method
CN109723065A (en) Deep basal pit freezing partly reinforced construction method in bracing means and rich water sandy pear variety
CN106640154A (en) Treatment method and structure for water seepage of tunnel lining circular construction joint crack
CN108547639B (en) Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN206636602U (en) Vault song wall tunnel structure
CN109403444A (en) The underground reinforced concrete supplying drainage of major diameter is not cut off the water connecting device and method
CN107461200A (en) A kind of construction technology for handling shield machine and passing through anchor cable barrier zone anchor cable
CN106120801A (en) In water-rich sand layer, pipeline crosses the construction method at foundation ditch
CN109778836A (en) A kind of prefabricated ground-connecting-wall structure and structure-based construction method
CN107938702A (en) A kind of cast-in-place concrete cable conduit construction method
CN106223976B (en) Shield well end steel tube shed reinforcement system based on agent structure and its construction method
CN108756955A (en) Shield tunnel gravity type sealing plugging structure and method
CN111455977A (en) Underground continuous wall construction method
CN110306449A (en) A kind of connection method of new box culvert and existing road box culvert
CN205714215U (en) Tunnel-liner decompression section of jurisdiction and pipe-plate lining structure
CN108166532A (en) A kind of groutable underground continuous wall connector and its construction method
CN208280969U (en) Shield tunnel gravity type sealing plugging structure
CN107740427A (en) A kind of construction method of interpolation concrete prefabricated square stake foundation pit enclosure structure
CN110258512A (en) It constructs in a kind of basement rock the method for diaphram wall
CN110318388A (en) Diaphram wall milling slot method
CN105040707B (en) Combine the construction method of close pile deep foundation pit support building enclosure
CN206429253U (en) Seep water treatment structures in tunnel-liner circular construction joint crack
CN203768925U (en) Seal device for dewatering well in foundation pit
CN108775009A (en) A kind of measure method preventing grooving spillage and leak

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20190412

RJ01 Rejection of invention patent application after publication