CN106320569A - 装配式剪力墙植筋法连接工艺 - Google Patents
装配式剪力墙植筋法连接工艺 Download PDFInfo
- Publication number
- CN106320569A CN106320569A CN201610719579.6A CN201610719579A CN106320569A CN 106320569 A CN106320569 A CN 106320569A CN 201610719579 A CN201610719579 A CN 201610719579A CN 106320569 A CN106320569 A CN 106320569A
- Authority
- CN
- China
- Prior art keywords
- sleeve
- wall
- construction
- component
- shear wall
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/56—Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/16—Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
- E04C5/162—Connectors or means for connecting parts for reinforcements
- E04C5/163—Connectors or means for connecting parts for reinforcements the reinforcements running in one single direction
- E04C5/165—Coaxial connection by means of sleeves
Abstract
本发明公开了一种装配式剪力墙“植筋法”连接工艺,包括下列步骤:(1)构件加工预制;(2)套筒注浆;(3)剪力墙构件吊装;(4)施工缝支模、浇筑。本发明的有益效果:采用套筒“植筋法”连接技术连接构件时,不需要留注浆孔和排气孔,可以采用不留侧孔的套筒,降低了套筒成本;由于套筒“植筋法”连接构造特点,构件生产和施工安装工艺简化,施工操作更加简单,从而有效节省了材料,缩短了工期,减少了劳动力,降低了施工成本。
Description
技术领域
本发明涉及一种装配式剪力墙植筋法连接工艺,属于建筑施工技术领域。
背景技术
随着我国经济和科技的快速发展,为转变经济发展方式和建设资源节约型、环境友好型社会,政府与建筑行业大力推进现代建筑产业化,装配整体式剪力墙结构以其高度机械化、工厂化施工模式逐渐赢得了建筑行业的认同。然而,传统的剪力墙钢筋朝上插入套筒注浆连接在构件生产、现场安装操作方面还存在一些缺点。在保证剪力墙连接质量满足相关规范的前提下,优化生产及安装工艺显得尤为重要。
发明内容
本发明所要解决的技术问题是:提供一种装配式剪力墙植筋法连接工艺
为解决上述技术问题,本发明采用的技术方案是:
本发明提供的装配式剪力墙“植筋法”连接工艺,包括下列步骤:
施工准备:施工准备包括施工图纸审查,材料与设备准备、施工人员安排、方案编制、培训与交底。
(1)构件加工预制
依据设计加工预制剪力墙构件,预制构件时把套筒预埋在构件的上部,插筋预留在构件的下部。预制剪力墙不需要留注浆孔和排气孔,因此可以采用不留侧孔的套筒,降低了套筒成本。由于构件表面不需要留孔,可以采用正打或反打工艺(即可以选择任一面朝下)生产,表面平整容易收光,降低了构件生产难度、节约成本,特别是采用正打工艺使构件的外立面装饰有了更多的选择性。
(2)套筒注浆
浇筑楼面混凝土后,套筒会高出楼地面10~20mm(在套筒上做标高标志,也有利于楼面混凝土厚度的控制),依据设计放线。
测标高、放置好调整墙体标高的垫块,并安装好墙体的定位靠板。取开临时封堵套筒的塑料盖,向套筒内注入足量的调配好的浆料。
(3)剪力墙构件吊装
墙体吊装到位后顺着定位靠板缓慢放下,下部钢筋插入套筒,用钢筋自身将少量浆料排挤出,此时墙体重量由标高垫块承受,用斜支撑加固墙体并及时调整墙体垂直度,固定牢靠后吊车脱钩。拍照留档证明浆料注满的情况,此时墙下与楼面之间有一条垫块高度的缝隙,但墙体已经是临时稳定的静定结构,先不要急于向墙体下缝注入灌浆料。
(4)施工缝支模、浇筑
施工边缘构件的钢筋和模板,安装楼面叠合板临时支撑,吊装上层楼面叠合板,浇筑边缘构件和叠合楼面的混凝土,每层只需浇筑一次混凝土。之后,再在剪力墙下缝处对夹模板,压力注入灌浆料,本层施工完成。
本发明的有益效果:
一、经济效益
1采用套筒“植筋法”连接技术连接构件时,不需要留注浆孔和排气孔,可以采用不留侧孔的套筒,降低了套筒成本。
2由于套筒“植筋法”连接构造特点,构件生产和施工安装工艺简化,施工操作更加简单,从而有效节省了材料,缩短了工期,减少了劳动力,降低了施工成本。同时灌浆一次成活,施工质量更容易得到保障避免了灌浆检测及重复施工浪费。
二、社会效益
通过本工艺的应用,有效控制了预制剪力墙构件连接的施工质量,且生产和安装施工过程更加安全、简易、快捷,现场无垃圾、无污染、安装噪音小、功效高,符合绿色可持续发展理念,获得了业主及主管部门的认同,树立了良好的企业形象。
附图说明
图1是预制剪力墙构件的结构。
图2是楼面浇筑混凝土前后的结构图,左边是混凝土浇筑前,右边是浇筑后。
图3是放置垫块调整标高、向套筒注浆的附图。
图4是构件吊装的附图。
图5是施工缝支模、浇筑附图。
具体实施方式
实施例1
本实施例提供的装配式剪力墙“植筋法”连接工艺,包括下列步骤:
施工准备:施工准备包括施工图纸审查,材料与设备准备、施工人员安排、方案编制、培训与交底。
(1)构件加工预制
依据设计加工预制剪力墙构件,预制构件时把套筒预埋在构件的上部,插筋预留在构件的下部。预制剪力墙不需要留注浆孔和排气孔,因此可以采用不留侧孔的套筒,降低了套筒成本。由于构件表面不需要留孔,可以采用正打或反打工艺(即可以选择任一面朝下)生产,表面平整容易收光,降低了构件生产难度、节约成本,特别是采用正打工艺使构件的外立面装饰有了更多的选择性。预制剪力墙构件的结构如图1所示。
(2)套筒注浆
浇筑楼面混凝土后,套筒会高出楼地面10~20mm(在套筒上做标高标志,也有利于楼面混凝土厚度的控制),依据设计放线。图2是楼面浇筑混凝土前后的结构图,左边是混凝土浇筑前,右边是浇筑后。
测标高、放置好调整墙体标高的垫块,并安装好墙体的定位靠板。取开临时封堵套筒的塑料盖,向套筒内注入足量的调配好的浆料。图3是放置垫块调整标高、向套筒注浆的附图。
(3)剪力墙构件吊装
墙体吊装到位后顺着定位靠板缓慢放下,下部钢筋插入套筒,用钢筋自身将少量浆料排挤出,此时墙体重量由标高垫块承受,用斜支撑加固墙体并及时调整墙体垂直度,固定牢靠后吊车脱钩。拍照留档证明浆料注满的情况,此时墙下与楼面之间有一条垫块高度的缝隙,但墙体已经是临时稳定的静定结构,先不要急于向墙体下缝注入灌浆料。图4是构件吊装的附图。
(4)施工缝支模、浇筑
施工边缘构件的钢筋和模板,安装楼面叠合板临时支撑,吊装上层楼面叠合板,浇筑边缘构件和叠合楼面的混凝土,每层只需浇筑一次混凝土。之后,再在剪力墙下缝处对夹模板,压力注入灌浆料,本层施工完成。图5是施工缝支模、浇筑附图。
Claims (1)
1.装配式剪力墙“植筋法”连接工艺,其特征在于,包括下列步骤:
(1)构件加工预制
依据设计加工预制剪力墙构件,预制构件时把套筒预埋在构件的上部,插筋预留在构件的下部;预制剪力墙不需要留注浆孔和排气孔,采用不留侧孔的套筒,降低了套筒成本;采用正打或反打工艺(即可以选择任一面朝下)生产,表面平整容易收光,降低了构件生产难度、节约成本;
(2)套筒注浆
浇筑楼面混凝土后,套筒会高出楼地面10~20mm(在套筒上做标高标志,也有利于楼面混凝土厚度的控制),依据设计放线;
测标高、放置好调整墙体标高的垫块,并安装好墙体的定位靠板;取开临时封堵套筒的塑料盖,向套筒内注入足量的调配好的浆料;
(3)剪力墙构件吊装
墙体吊装到位后顺着定位靠板缓慢放下,下部钢筋插入套筒,用钢筋自身将少量浆料排挤出,此时墙体重量由标高垫块承受,用斜支撑加固墙体并及时调整墙体垂直度,固定牢靠后吊车脱钩;拍照留档证明浆料注满的情况,此时墙下与楼面之间有一条垫块高度的缝隙,但墙体已经是临时稳定的静定结构,先不要急于向墙体下缝注入灌浆料;
(4)施工缝支模、浇筑
施工边缘构件的钢筋和模板,安装楼面叠合板临时支撑,吊装上层楼面叠合板,浇筑边缘构件和叠合楼面的混凝土,每层只需浇筑一次混凝土;之后,再在剪力墙下缝处对夹模板,压力注入灌浆料,本层施工完成。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610719579.6A CN106320569A (zh) | 2016-08-25 | 2016-08-25 | 装配式剪力墙植筋法连接工艺 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610719579.6A CN106320569A (zh) | 2016-08-25 | 2016-08-25 | 装配式剪力墙植筋法连接工艺 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN106320569A true CN106320569A (zh) | 2017-01-11 |
Family
ID=57790722
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610719579.6A Pending CN106320569A (zh) | 2016-08-25 | 2016-08-25 | 装配式剪力墙植筋法连接工艺 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106320569A (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106948493A (zh) * | 2017-04-05 | 2017-07-14 | 桂林理工大学 | 一种预座浆装配式结构构件连接方法 |
CN111636625A (zh) * | 2020-05-13 | 2020-09-08 | 天津中建建筑技术发展有限公司 | 一种适用于装配式建筑的钢筋套筒灌浆连接工艺 |
CN111705950A (zh) * | 2020-05-11 | 2020-09-25 | 广城建设集团有限公司 | 高强度装配式剪力墙构造 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101831985A (zh) * | 2010-06-04 | 2010-09-15 | 北京万科企业有限公司 | 一种预制混凝土墙板及其制作方法 |
CN105155734A (zh) * | 2015-08-19 | 2015-12-16 | 太原理工大学 | 卯榫连接装配式自保温隔热空心剪力墙体系及其吊装方法 |
CN205242837U (zh) * | 2015-12-04 | 2016-05-18 | 文登蓝岛建筑工程有限公司 | 一种组合式预制墙板 |
CN105821978A (zh) * | 2016-03-24 | 2016-08-03 | 天津住宅集团建设工程总承包有限公司 | 一种预制墙板半坐浆半注浆竖向连接施工方法 |
-
2016
- 2016-08-25 CN CN201610719579.6A patent/CN106320569A/zh active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101831985A (zh) * | 2010-06-04 | 2010-09-15 | 北京万科企业有限公司 | 一种预制混凝土墙板及其制作方法 |
CN105155734A (zh) * | 2015-08-19 | 2015-12-16 | 太原理工大学 | 卯榫连接装配式自保温隔热空心剪力墙体系及其吊装方法 |
CN205242837U (zh) * | 2015-12-04 | 2016-05-18 | 文登蓝岛建筑工程有限公司 | 一种组合式预制墙板 |
CN105821978A (zh) * | 2016-03-24 | 2016-08-03 | 天津住宅集团建设工程总承包有限公司 | 一种预制墙板半坐浆半注浆竖向连接施工方法 |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106948493A (zh) * | 2017-04-05 | 2017-07-14 | 桂林理工大学 | 一种预座浆装配式结构构件连接方法 |
CN111705950A (zh) * | 2020-05-11 | 2020-09-25 | 广城建设集团有限公司 | 高强度装配式剪力墙构造 |
CN111636625A (zh) * | 2020-05-13 | 2020-09-08 | 天津中建建筑技术发展有限公司 | 一种适用于装配式建筑的钢筋套筒灌浆连接工艺 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104652830B (zh) | 一种预制楼面板和预制墙板搭建的施工方法 | |
CN106638940B (zh) | 一种装配式高层住宅混凝土预制构件施工工法 | |
CN101644079B (zh) | 钢筋混凝土剪力墙墙体接茬施工方法 | |
CN106013172A (zh) | 双排桩与斜撑组合软土深基坑支护结构及施工方法 | |
CN201588207U (zh) | 施工缝处混凝土浇筑装置 | |
CN103195087A (zh) | 基坑地下室加腋剪力墙的支模方法 | |
CN106320569A (zh) | 装配式剪力墙植筋法连接工艺 | |
CN205822221U (zh) | 基础筏板超前止水后浇带钢筋混凝土基础底板结构 | |
CN111636625A (zh) | 一种适用于装配式建筑的钢筋套筒灌浆连接工艺 | |
CN106149877B (zh) | 混凝土框架结构预制柱与梁板节点处的对接结构及方法 | |
CN110005200B (zh) | 水平暗梁混凝土浇筑密实的施工工艺 | |
CN113250494A (zh) | 一种装配式集成卫生间以及施工方法 | |
CN106149878B (zh) | 混凝土框架结构预制柱与梁板节点处的连接结构及方法 | |
CN105971201A (zh) | 一种装配式坡屋面及其施工方法 | |
CN207032468U (zh) | 装配式建筑 | |
CN109811787A (zh) | 一种采用拼装式预制基础构件外加电梯结构及其施工方法 | |
CN112112295A (zh) | 一种后封闭外墙后浇带加固施工方法 | |
CN204475714U (zh) | 一种快装式预制楼梯 | |
CN106193120A (zh) | 地下室悬挑底板逆作结构及施工方法 | |
CN106013094A (zh) | 一种适用于人工挖孔桩桩身混凝土浇筑的方法 | |
CN203603462U (zh) | 后浇带梁板模板支设结构 | |
CN207891904U (zh) | 一种既有建筑外加电梯装配式预制基础构件 | |
CN207348280U (zh) | 一种新型预制楼板 | |
CN109853803A (zh) | 装配整体式楼板及制作安装方法 | |
CN109267578A (zh) | 一种斜面素混凝土结构及其施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170111 |
|
RJ01 | Rejection of invention patent application after publication |