CN106089214A - Service channel manual pipe jacking reinforced construction method - Google Patents

Service channel manual pipe jacking reinforced construction method Download PDF

Info

Publication number
CN106089214A
CN106089214A CN201610452159.6A CN201610452159A CN106089214A CN 106089214 A CN106089214 A CN 106089214A CN 201610452159 A CN201610452159 A CN 201610452159A CN 106089214 A CN106089214 A CN 106089214A
Authority
CN
China
Prior art keywords
construction
freezing
service channel
hole
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610452159.6A
Other languages
Chinese (zh)
Inventor
李涛
胡田玉
钱亮亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Original Assignee
Third Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd filed Critical Third Engineering Co Ltd of China Railway No 10 Engineering Group Co Ltd
Priority to CN201610452159.6A priority Critical patent/CN106089214A/en
Publication of CN106089214A publication Critical patent/CN106089214A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Soil Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The present invention provides a kind of service channel manual pipe jacking reinforced construction method, including preparation of construction, freeze front construction, curtain freezes, excavation construction and supporting and five stages of last lining cutting slip casting, specifically include as follows: first carry out preparation of construction work, then in the case of guaranteeing Frozen Soil Cylinder thickness, offer freezing hole, set up short distance orifice tube, freezing pipe creeps into and uses with tube method is crept into, freezing system enters after running well and actively freezes again, after Frozen Soil Cylinder reaches design requirement, freezing system enters maintenance to be freezed;After completing above operation, enter excavation construction and supporting and last lining cutting slip casting.This construction method reduces Freezing Method for Cross-passage Construction difficulty, adds the safety of engineering, reliability, shortens construction period and cost simultaneously, ensures construction quality while improving efficiency of construction.

Description

Service channel manual pipe jacking reinforced construction method
Technical field
The present invention relates to subway work Technology field, specifically refer to service channel manual pipe jacking reinforced construction method.
Background technology
Service channel is normally at lowest part in the middle of subway tunnel, is to there is unexpected peace in operation at subway train Full accident be need timely passenger is transferred to safety area.Although Metro Connection Passage builds the most about one-hundred-year history, But because of service channel, but because service channel buried depth is relatively big, geological and hydrological conditions are more complicated and by constructing tunnel place and construction week The objective circumstances such as surrounding environment is limited, its construction technology content is high, difficulty is big, so its arrangement and method for construction is the most difficult of great satisfaction. The frozen construction method used in service channel engineering construction at present is mostly the most conservative, i.e. strengthens Frozen wall thickness or reduction is frozen Junction temperature.Although truly having the safety that ensure that engineering and surrounding enviroment of power, but also consuming huge electric energy and fund, also will Difficulty is brought to the excavation in later stage.This makes the engineer applied of freezing process be extremely restricted.
Summary of the invention
In order to solve above technical problem, the present invention provides a kind of service channel manual pipe jacking reinforced construction method, including Following steps:
(1) preparation of construction: lay power cable, two water pipes in tunnel to construction working face;It is the wood of 5cm with thickness Plate is laying construction place at service channel;
(2) freeze front construction: before using total powerstation and level gauge monitoring perforate and during perforate, face upward Fu Jiao and azimuth up and down, bore The deflection in hole should control within 1%, and in the case of guaranteeing Frozen Soil Cylinder thickness, whole pitch of holes is not more than 1.0m.Go out in aperture Set up design orifice tube.By chipping at aperture during installation, good and sound four setscrews, then at the fish scale button of orifice tube On twined the sealer such as flax silk or staple, orifice tube is pounded into, tightens with setscrew, remove nut after tightening again, load onto DN125 ball valve, then ball valve is opened, with hole making drill from ball valve open interior, opening diameter is 91mm.Freezing pipe creeps into employing with pipe Method is crept into;
(3) curtain freezes: include installing freeze refrigeration plant be connected with Freezing Station, pipeline, pipe insulation and pipeline detector Table is installed;Dissolve calcium chloride and unit fills fluorine and refuels, equipment debugging and test running, enter actively after freezing system runs well Freezing, in one week, brine temp is down to less than-20 DEG C, and within 15 days, brine temp is down to less than-24 DEG C, and reaches to set at Frozen Soil Cylinder After meter requires, freezing system enters maintenance to be freezed;
(4) excavation construction and supporting: include passage driving and gib, is carrying out preparation of construction and is confirming permissible through exploration drilling After formally excavating, open steel pipe sheet, from the line direction tunneling to the right of left line opening.Operation uses pneumatic pick, shovel and pickaxe to tie mutually Close.Excavation uses upper and lower benching tunnelling method excavation, and excavation step pitch is 0.5m;
Grid steel frame sets up after excavation in time, spacing 0.5m, and the tolerance of bow member spacing and lateral attitude thereof and elevation is ± 5cm, perpendicularity is ± 2 °, gunite concrete use segmentation, piecemeal, order from bottom to top carry out and first spray reinforcing bar grid with Concrete support between wall, sprays concrete support between two reinforcing bar grids the most again;
(5) last lining cutting slip casting: including pump house base plate, channel base plate and side wall construction, filling and injecting slurry, wherein grouting pressure exists Between 0.5Mpa.
Further, described freezing hole has 69 a diameter of 89mm, and forms 22 and freeze loop;Described freezes Hole by facing upward, nearly level, three kinds of angles of nutation be arranged in the surrounding of passage, freezing hole is designed to pitch of holes service channel periphery hole For 900mm;Described temperature observation hole sets 8 a diameter of 89mm altogether, and described relief hole is provided with 4, a diameter of 45mm;Described Freezing hole and horizontal line angulation be-20 ° 20 °.
Further, use screw thread to be welded with between described freezing pipe and connect method of attachment in succession, after joint screw thread fastening again Electric arc welding by hand.
Further, described pipeline link uses Flange joint;Described saline and clear water pipeline are pressure respectively 0.7MPa and 0.3Mpa.
Further, in described freezing system, brine circulation system goes the loop temperature difference less than 2 DEG C.
This construction method reduces Freezing Method for Cross-passage Construction difficulty, adds the safety of engineering, reliability, shortens simultaneously and execute Work cycle and cost, ensure construction quality while improving efficiency of construction.
Accompanying drawing explanation
Fig. 1 is that freezing hole of the present invention arranges elevation.
Fig. 2 is the present invention left line freezing hole plane of arrangement figure.
Fig. 3 is the present invention right line freezing hole plane of arrangement figure.
Detailed description of the invention
Embodiment 1.
Wuhan Rail Transit No. six long 13.828m of line service channel, wide 3.8m, maximum height 6.96m, channel roof is buried Deep 19.97m, uses brine circulation system engineering with artificial freezing method soil mass consolidation, mine shallow mining method, it is contemplated that consolidation by freezing length 13.828m, reinforces width 9.8m, degree of depth 13.850m.In anticipated freezing range, the soil body is followed successively by silty clay from top to bottom, sticks Soil, Muddy Bottoms clay, silty clay folder flour sand, average natural moisture content is between 33% ~ 49%, and wherein silty clay, clay are The soft shape soil layer of moulding of high-compressibility, silty clay folder flour sand is the soft shape soil layer of moulding of middle compressibility, and Muddy Bottoms clay is in liquid-plastic state. Its unconfined compressive strength is between 34.32 ~ 42.78KPa, and bearing capacity is poor.The subsoil water master in location residing for service channel If the soil water in weak soil, the water yield is less, and wherein the subsoil water in silty clay folder silty sand ground is by lower angle gravel bed artesian water Impact, the water yield is less.Passage is arranged above present situation road, requires higher to surface subsidence control.Use preliminary bracing+secondary lining Structure.
A kind of service channel manual pipe jacking reinforced construction method, it is characterised in that: described consolidation by freezing construction method bag Include following steps.
(1) preparation of construction
1) according to power supply for construction and construction water requirement, in tunnel, power cable, two water pipes are laid to construction working Face;With plank laying construction place at service channel of thick 5cm, set up for construction scaffolding, materials processing and equipment are laid Site condition is provided.
(2) front construction is freezed
1) locating holes and orifice tube are installed: according to design requirement, utilize total powerstation that freezing hole position is carried out line setting. Selecting J-200 type diamond drill perforate, join φ 133mm diamond core bit, hole depth about 300mm, not drill section of jurisdiction Control.With gad wedge break rock core, take out after, squeeze into the orifice tube processed, and set 4 fixing points and be fixed;
2) opening arrangement is installed: by chipping at aperture, good and sound four setscrews, then the fish scale at orifice tube is buckled and twined fiber crops The sealers such as silk or staple, pound into orifice tube, tighten with setscrew, remove nut after tightening again, load onto DN125 ball Valve, then ball valve is opened, with hole making drill from ball valve open interior, opening diameter is 91mm.Run through concrete section of jurisdiction, if the mud in stratum Discharge shuts valve the most in time.With screw, opening arrangement is contained on ball valve, work progress notes added gasket seal;
3) freezing hole creeps into and freezing pipe is installed: using MD-80 drill hole of drilling machine, adapted BW250 type slush pump, drilling tool utilizes φ 89 × 8 freezing pipes make drilling rod, and freezing pipe creeps into and uses with tube method is crept into;Use screw thread to be welded with between freezing pipe to connect the most in succession Method, electric arc welding the most by hand after joint screw thread fastening, under normal circumstances, simple drill bit is installed when creeping into, if crept into Difficulty runs into layer of sand, for preventing from creeping into middle sand return, installs a special one-way cock at drill bit position.It is deep that freezing pipe arrives design Degree afterflush check valve, and seal freezing pipe end.In drilling process, strict monitoring deflection situation, finds that deflection to be entangled in time Partially, after lower good freezing pipe, carry out the repetition measurement of freezing pipe length, then carry out deviational survey and draw hole scattering figure.Freezing pipe length After qualified with deflection, then freezing pipe being suppressed leak test, after freezing pipe installs, cement injection seals freezing pipe and section of jurisdiction Between gap.Thorough investigation design requirement drills through freezing hole and has 69, and numbering is by D1 to D69;Temperature observation hole sets 8 altogether, number by C1 to C8;Relief hole is provided with 4, and numbering is by X1 to X4, shown in table specific as follows:
(3) curtain freezes
1) Freezing Station Housing, Furniture, Furnishing And Equipment is installed: equipment is installed and carried out by the requirement of equipment operating manual.For ensureing refrigeration system Reliably continuously running, Freezing Station selects JYSLGF-300 III 2 sets of type screw freezing unit, and two sets operate, a set of standby;Choosing With IS150-400A brine pump and IS150-250A type cooling water circulating pump each 1, it is a preparation and a use;;If brine tank 2, Each volume 6m;Salt water conduit tube and collection liquid distribution pipe all select φ 159 × 5mm seamless steel pipe, collection liquid distribution pipe to be connected selection with Cornu Caprae seu Ovis φ 51mm high-pressure rubber pipe;Cooling water pipe φ 127 × 5mm seamless steel pipe;Freezing plate φ 48 × 4mm steel pipe is processed;In freezing Mounting temperature sensor on machine water inlet pipe and water outlet pipe, installs pressure, temperature sensor and control valve going, in the saline line of loop, At brine tank, liquid level sensor is installed;Two, valve is installed between brine distributing ring and frigo, in order to control freezing device salt current Amount;Eminence in saline line installs vent valve;Outlet salt water conduit tube is installed check valve;Saline and pressure point of clear water pipeline Wei 0.7MPa and 0.3Mpa;
2) pipeline connects, is incubated and test instrumentation installation: pipeline Flange joint, the Brine Pipe pipe support in tunnel is laid in On tunnel duct piece, and it is current to avoid affecting tunnel.Expansion joint to be arranged, valve in saline line and cooling water circulation pipeline Door and the testing element such as temperature measurer, Pressure gauge.Saline line is incubated with polystyrene foam plastics after leak test, cleaning, insulation Thickness is 30mm, and the outside plastic sheeting of heat-insulation layer is wrapped up.Collection brine distributing ring and the connection high-pressure rubber pipe of freezing pipe, every freezes One, import and export each dress valve of knot pipe, to control flow.Service channel surrounding main freezing hole each two one is connected, and other freezes Knot every three one series connection in hole.The vaporizer of freezing unit and cryogenic pipe polystyrene foam plastics 30mmPEF warming plate, salt Water tank and salt water conduit tube are incubated with polystyrol plastic foam plate thick for 30mm;
3) dissolve calcium chloride and unit fills fluorine and refuels: saline (calcium chloride solution) proportion is 1.26~1.27, first in brine tank It is full of clear water, dissolves calcium chloride, be re-fed in salt water conduit tube, till brine system is full of, to remove when dissolving calcium chloride Impurity.Unit fills fluorine and fridge refuels and must carry out according to the requirement of equipment operating manual.First refrigeration system is carried out Leak detection and nitrogen rinse, and after guaranteeing system ne-leakage, then fill fluorine oiling;
4) actively freeze: equipment carries out debugging and test running after installing.When test running, pressure, temperature to be regulated at any time Etc. each state parameter, unit is made to run under the conditions of the technical parameter about technological procedure and equipment requirements.In freezing process, Timing detection brine temp, brine flow and Frozen Soil Cylinder spread scenarios, freezing system enters after working well and actively freezes.Want Ask freezing hole single hole flow not less than 5m/h;Actively freeze 7 days brine temps and be down to less than-20 DEG C;Actively freeze 15 days Brine temp is down to less than-24 DEG C, goes loop salt water temperature difference to be not more than 2 DEG C;During excavation, brine temp is down to less than-28 DEG C. As brine temp and brine flow do not reach design requirement, positive freeze-off time should be extended.
(4) excavation construction and supporting
1) excavation condition analysis is freezed with maintenance
In positive freezing process, to judge whether Frozen Soil Cylinder is handed over circle and reach design thickness according to observed temperature data, with Time Frozen Soil Cylinder to be monitored and tunnel cementing situation, thermometric judges that Frozen Soil Cylinder is handed over and encloses and reach design thickness and complete with tunnel Carrying out inspecting hole examination after the most cementing again to dig, in confirming Frozen Soil Cylinder, the basic no pressure of soil layer formally excavates;
1. thermometer hole analysis
According to thermometer hole measured data, calculate frozen soil development speed and develop radius at this frozen soil, drawing further according to becoming ice formula Freezing curtain mean temperature, if each layer of position, the thickness of position freezing curtain and mean temperature reach after design requires, through excavation Section of jurisdiction can be opened after front nodal point acceptance(check) excavate;
2. pressure relief vent is freezing the typically no pressure of initial stage pressure relief vent, and along with the gradually extension of frozen soil, moisture constantly migrates, and hands over circle Rear frozen soil forms the soil body closed, and frost-heaving force can not get release and is gradually increased, and pressure relief vent pressure increases after release, Pressure recovers the most rapidly, and after repeatedly release, pressure gradually declines then, and final pressure is zero, basic no pressure in freezing curtain, Substantially flow out without muddy water in pressure relief vent, possess examination and dig condition;
3. inspecting hole is before excavation, sets inspecting hole at left and right line hole making drill at freezing curtain weak place, to judge to freeze curtain Tent thickness and freezing efficiency;
4. water go, the loop temperature difference
Brine circulation system goes the loop temperature difference less than 2 DEG C.Determine open section of jurisdiction carry out excavating also need to combine thermometer hole data, The aspects such as pressure relief vent pressure, inspecting hole situation consider.Actively freeze brine temp and be adjusted to-28 DEG C~-30 DEG C, after excavation, For guaranteeing the stability of Frozen Soil Cylinder, brine temp still controls between-28 DEG C~-30 DEG C;
2) safety door is installed: installs emergent protective door on excavation tunnel, side reserved opening, and is equipped with air quantity not less than 6m/min Air compressor machine to protective door supply.Protective door switch should be easy to manual operation, and does not affect construction.Fastening bolt, airduct and company The accessory such as fitting, spanner and operation instrument should prepare to put in place.Dig through dismountable protective door after horizontal channel completes preliminary bracing;
3) examination is dug and open pipe sheet: soil mass consolidation intensity reach design require and preparation ready after first to carry out examination and dig, i.e. exist Opening an examination in the middle part of the excavation area do not freezed and dig window, window size is not preferably greater than 400 × 400mm, windows and progressively to expand.With Spade, pneumatic pick etc. dig window from examination and dig deep 400~600mm, check that the soil body is aqueous and stable case.If the soil body is dried, is able to support oneself, or Person digs and is deep to 800~1000mm without muddy water delivery time lasting more than 24h.Then can determine that possess formal excavation condition.Otherwise should Window is dug in backfill, closing examination, continues actively to freeze, till examination next time is dug and met above-mentioned requirements;
During open pipe sheet, prepare 2 32t jack, each one of 5t and 2t chain block.Two jack stands are by open pipe sheet two Side, centre is joined directly together with steel pipe sheet with a crossbeam, and by pushing tow crossbeam outside push-and-pull steel pipe sheet, 5t calabash is as main drawing Section of jurisdiction use, one end hooks section of jurisdiction to be torn open, and one end is hitched over there on tunnel duct piece, the afterburning drawing pipe in tunnel of horizontal direction Sheet.2t calabash is suspended in above section of jurisdiction to be torn open on section of jurisdiction, and section of jurisdiction to be torn open is hooked in one end, in case pounding suddenly in work during the pull-out of section of jurisdiction Make on platform.During with jack and 5t calabash drawing it is noted that observing tube off-chip is shifted one's love condition, and note at any time adjusting 2t calabash Reed degrees of tensions and direction.During because of section of jurisdiction corrosion pull-out difficulty, application sledgehammer hammer vibration tube sheet, reduce and extract pulling force.Because of secondary orifices side For reinforced concrete segment, section of jurisdiction uses pneumatic pick to abolish, has a shave by hand herein, constructs in strict accordance with design size;
4) excavation construction: section of jurisdiction enters formal excavation after removing, service channel excavation construction takies near service channel left The tunnel excavation of side, sets up work platforms at service channel opening part, utilizes tunnel as deslagging and transport of materials passage.Doing Good preparation of construction and through exploration drilling confirm can formally excavate after, open steel pipe sheet, from the line direction tunneling to the right of left line opening. Operation uses pneumatic pick, shovel and pickaxe to combine, and work surface casting handbarrow is shifted onto in the special casting case near well head, uses Elevator winches to ground and discharges.Excavation uses upper and lower benching tunnelling method excavation, and excavation step pitch is 0.5m.Should be timely in digging process Carry out convergent deformation monitoring, in order to adjustment support pattern and structure in time, and note the position of freezing pipe, in case pneumatic tools Break freezing pipe.If breaking freezing pipe, Freezing Station personnel should be notified in time, closing valve, repair welding freezing pipe;
5) preliminary bracing grid processing, installation: grid steel frame sets up after excavation in time, spacing 0.5m, remove footing before installing Under empty quarrel and foreign material, bottom connecting plate should on the soil body solid, firm if desired at connecting plate under the pad lumps of wood.Grillage Tolerance is installed: the tolerance of bow member spacing and lateral attitude thereof and elevation is ± 5cm, and perpendicularity is ± 2 °.Grille arch Frame is assembled in the scope of operation to be carried out, and tightens also with connecting plate bolt, it is ensured that connecting plate is closely connected between each joint bow member.By concrete after installation bow member Protective layer is reserved, and forbids out break, steel grating hoop to set HRB400E22mm dowel spacing 1m in construction;
6) preliminary bracing gunite concrete: gunite concrete operation should closely follow excavated surface, uses segmentation, piecemeal, from lower On order carry out and first spray reinforcing bar grid and wall between concrete, spray concrete between two reinforcing bar grids the most again;Injection is made During industry, spiralling the most slowly is done in injection, and screw diameter about 20-30cm, to ensure that concrete ejection is closely knit.Slap simultaneously Hold blast, hydraulic pressure and jet length, reduce the springback capacity of concrete;Rebound of shotcrete amount, abutment wall is not preferably greater than 25%;
7) construction of waterproof layer: service channel is held concurrently, and all to use 1.5mmPVC drainage systems entirely to wrap waterproof for waste water pump house, geotechnique Cloth cushion uses the short fine geotextiles of 400g/.First geotextiles is fixed on concrete surface, then will with hot bonding method Splash guard is pasted onto on fixing ring washer, i.e. uses without nail laying way, has no mechanical damage splash guard.
(5) last lining cutting slip casting
1) service channel and pump house secondary lining complete in just lining construction, carry out, first construction service channel and pump after waterproof layer Room baseplate reinforcing bar, reserves passage and pump house side wall reinforcing bar, first construction pump house base plate, channel base plate and both sides 30cm height side wall, Formwork erection pours concrete.Channel base plate is the most elongated to be poured, and centre does not set circular construction joint;
2) thaw collapse treatment measures: the same day, fall was heavy more than 0.5mm, or when service channel adds up sedimentation more than 1mm, should carry out thaw collapse Compensation and grouting;Grouting serous fluid is single liquid cement mortar.Grouting pressure is not more than 0.5Mpa.Grouting sequence is first floor rear wall.Note Slurry is front by fully open, during slip casting, when the continuous pulp of adjacent holes to the Grouting Pipe and its adjacent Grouting Pipe valve for the treatment of slip casting Time close adjacent ports valve door, quantitatively can stop this hole slip casting after press-in, close valve then to adjacent hole slip casting.The knot of thaw settlement grouting Bundle is with surface subsidence stabilization as foundation.If frost wall the most all melts, and in the case of not slip casting, survey stratum settlement Within two weeks ground day settling amount is maintained at 0.5mm continuously, accumulative settling amount, less than 1mm, can stop thaw collapse and compensate note Slurry.
Embodiment 2:
Wuhan one line service channel uses brine circulation system engineering with artificial freezing method soil mass consolidation, mine shallow mining method, it is contemplated that Consolidation by freezing length 14.028m, reinforces width 10.8m, degree of depth 14.850m.In anticipated freezing range, the soil body is the most successively For silty clay, clay, Muddy Bottoms clay, silty clay folder flour sand, average natural moisture content between 36% ~ 45%, wherein powder Matter clay, clay are the soft shape soil layer of moulding of high-compressibility, and silty clay folder flour sand is the soft shape soil layer of moulding of middle compressibility, Muddy Bottoms clay It is in liquid-plastic state.
A kind of service channel manual pipe jacking reinforced construction method, its consolidation by freezing construction method comprises the following steps:
(1) preparation of construction: lay power cable, two water pipes in tunnel to construction working face;It is the wood of 5cm with thickness Plate is laying construction place at service channel;
(2) freeze front construction: before using total powerstation and level gauge monitoring perforate and during perforate, face upward Fu Jiao and azimuth up and down, bore The deflection in hole should control within 1%, and in the case of guaranteeing Frozen Soil Cylinder thickness, whole pitch of holes is not more than 1.0m;Go out in aperture Set up design orifice tube, by chipping at aperture during installation, good and sound four setscrews, then at the fish scale button of orifice tube On twined the sealer such as flax silk or staple, orifice tube is pounded into, tightens with setscrew, remove nut after tightening again, load onto DN125 ball valve, then ball valve is opened, with hole making drill from ball valve open interior, opening diameter is 91mm, and freezing pipe creeps into employing with pipe Method is crept into;
(3) curtain freezes: include installing freeze refrigeration plant be connected with Freezing Station, pipeline, pipe insulation and pipeline detector Table is installed;Dissolve calcium chloride and unit fills fluorine and refuels, equipment debugging and test running, enter actively after freezing system runs well Freezing, in one week, brine temp is down to less than-20 DEG C, and within 15 days, brine temp is down to less than-24 DEG C, and reaches to set at Frozen Soil Cylinder After meter requires, freezing system enters maintenance to be freezed;
(4) excavation construction and supporting: include passage driving and gib, is carrying out preparation of construction and is confirming permissible through exploration drilling After formally excavating, open steel pipe sheet, from the line direction tunneling to the right of left line opening;Operation uses pneumatic pick, shovel and pickaxe to tie mutually Closing, excavation uses upper and lower benching tunnelling method excavation, and excavation step pitch is 0.5m;
Grid steel frame sets up after excavation in time, spacing 0.5m, and the tolerance of bow member spacing and lateral attitude thereof and elevation is ± 5cm, perpendicularity is ± 2 °;Gunite concrete use segmentation, piecemeal, order from bottom to top carry out and first spray reinforcing bar grid with Concrete support between wall, sprays concrete support between two reinforcing bar grids the most again;
(5) last lining cutting slip casting: including pump house base plate, channel base plate and side wall construction, filling and injecting slurry, wherein grouting pressure exists Between 0.5Mpa.
After interval No. 1 service channel of No. 6 line the 4th bid section civil engineerings of Wuhan Rail Transit applies this engineering method, through 51 Actively freezing of it, consolidation by freezing is respond well, meets excavation condition.Actively freeze-off time is fewer 4 days than design 55 ~ 60 days, Power cost saving 40,000 yuan, equipment leasing expense 100,000 yuan.Further, in positive freezing process, every technical parameter meets design to be wanted Asking, frozen construction quality is good.

Claims (5)

1. a service channel manual pipe jacking reinforced construction method, it is characterised in that: described consolidation by freezing construction method includes Following steps:
(1) preparation of construction: lay power cable, two water pipes in tunnel to construction working face;It is 5cm's with thickness Plank is laying construction place at service channel;
(2) freeze front construction: before using total powerstation and level gauge monitoring perforate and during perforate, face upward Fu Jiao and azimuth up and down, bore The deflection in hole should control within 1%, and in the case of guaranteeing Frozen Soil Cylinder thickness, whole pitch of holes is not more than 1.0m;Go out in aperture Set up design orifice tube, by chipping at aperture during installation, good and sound four setscrews, then at the fish scale button of orifice tube On twined the sealer such as flax silk or staple, orifice tube is pounded into, tightens with setscrew, remove nut after tightening again, load onto DN125 ball valve, then ball valve is opened, with hole making drill from ball valve open interior, opening diameter is 91mm, and freezing pipe creeps into employing with pipe Method is crept into;
(3) curtain freezes: include installing freeze refrigeration plant be connected with Freezing Station, pipeline, pipe insulation and pipeline detector Table is installed;Dissolve calcium chloride and unit fills fluorine and refuels, equipment debugging and test running, enter actively after freezing system runs well Freezing, in one week, brine temp is down to less than-20 DEG C, and within 15 days, brine temp is down to less than-24 DEG C, and reaches to set at Frozen Soil Cylinder After meter requires, freezing system enters maintenance to be freezed;
(4) excavation construction and supporting: include passage driving and gib, carry out preparation of construction and through exploration drilling confirm can After formally excavating, open steel pipe sheet, from the line direction tunneling to the right of left line opening;Operation uses pneumatic pick, shovel and pickaxe phase In conjunction with, excavation uses upper and lower benching tunnelling method excavation, and excavation step pitch is 0.5m;Grid steel frame sets up after excavation in time, spacing 0.5m, the tolerance of bow member spacing and lateral attitude thereof and elevation is ± 5cm, and perpendicularity is ± 2 °;Gunite concrete uses Segmentation, piecemeal, order from bottom to top carries out and first sprays concrete support between reinforcing bar grid and wall, spraying two reinforcing bar lattice the most again Concrete support between grid;
(5) last lining cutting slip casting: including pump house base plate, channel base plate and side wall construction, filling and injecting slurry, wherein grouting pressure exists Between 0.5Mpa.
A kind of service channel manual pipe jacking reinforced construction method the most according to claim 1, it is characterised in that described freezes Knot hole has 69 a diameter of 89mm, and forms 22 and freeze loop;Described freezing hole by facing upward, nearly level, nutation three kinds Angle is arranged in the surrounding of passage, and it is 900mm that freezing hole is designed to pitch of holes service channel periphery hole;Described temperature observation hole Setting 8 a diameter of 89mm altogether, described relief hole is provided with 4, a diameter of 45mm;Described freezing hole and horizontal line angulation For-20 ° 20 °.
A kind of service channel manual pipe jacking reinforced construction method the most according to claim 1, it is characterised in that described freezes Screw thread is used to be welded with and connect method of attachment in succession between knot pipe, electric arc welding the most by hand after joint screw thread fastening.
A kind of service channel manual pipe jacking reinforced construction method the most according to claim 1, it is characterised in that described pipe Road link uses Flange joint;Described saline and pressure respectively 0.7MPa and 0.3Mpa of clear water pipeline.
A kind of service channel manual pipe jacking reinforced construction method the most according to claim 1, it is characterised in that described freezes In clone system, brine circulation system goes the loop temperature difference less than 2 DEG C.
CN201610452159.6A 2016-06-21 2016-06-21 Service channel manual pipe jacking reinforced construction method Pending CN106089214A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610452159.6A CN106089214A (en) 2016-06-21 2016-06-21 Service channel manual pipe jacking reinforced construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610452159.6A CN106089214A (en) 2016-06-21 2016-06-21 Service channel manual pipe jacking reinforced construction method

Publications (1)

Publication Number Publication Date
CN106089214A true CN106089214A (en) 2016-11-09

Family

ID=57238148

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610452159.6A Pending CN106089214A (en) 2016-06-21 2016-06-21 Service channel manual pipe jacking reinforced construction method

Country Status (1)

Country Link
CN (1) CN106089214A (en)

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106837388A (en) * 2017-02-03 2017-06-13 天津大学 Suitable for the detachable steel pipeline section of construction freezing method at tunnel connection channel
CN108397202A (en) * 2018-03-06 2018-08-14 中交第二公路勘察设计研究院有限公司 Freeze the leading excavation method of base tunnel in multi-step under advance support
CN108843334A (en) * 2018-06-19 2018-11-20 中交公局厦门工程有限公司 A kind of method of reinforcing building lower section rich water soft soil layer service channel
CN109083645A (en) * 2018-08-01 2018-12-25 南宁轨道交通集团有限责任公司 Shield tunnel and service channel method for synchronously constructing under the conditions of rich water round gravel stratum
CN110130316A (en) * 2019-05-13 2019-08-16 南京林业大学 The method of thaw collapse after service channel bottom pre-pouring grout system and control freezing construction
CN110454170A (en) * 2019-08-19 2019-11-15 中铁十二局集团有限公司 Tunnel connection channel construction method based on freezing process
CN110593918A (en) * 2019-10-15 2019-12-20 中铁十二局集团有限公司 Freezing method based tunnel connection channel pump house construction method
CN110905561A (en) * 2019-12-16 2020-03-24 兰州理工大学 Weak surrounding rock tunnel freezing initial support structure and construction method
CN111173536A (en) * 2019-12-26 2020-05-19 中交一航局安装工程有限公司 Freezing construction method for tunnel connection channel
CN111271095A (en) * 2020-01-20 2020-06-12 中煤科工集团西安研究院有限公司 Method for improving grouting effect of mine curtain
WO2020244677A1 (en) * 2019-09-28 2020-12-10 中铁九局集团有限公司 Freezing construction method for connecting passage, and freezing system
CN112112244A (en) * 2020-08-13 2020-12-22 中国一冶集团有限公司 Construction method of drainage channel in limited space
CN113494313A (en) * 2021-06-25 2021-10-12 中铁一局集团有限公司 Contact passage portal breaking construction method for main tunnel segment
CN115977650A (en) * 2022-11-22 2023-04-18 安徽理工大学 Communication freezing system based on plane skew connection channel and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3621019A1 (en) * 1986-06-16 1987-12-17 Kunz Alfred & Co Method for producing a tunnel structure
CN2613590Y (en) * 2003-04-28 2004-04-28 上海市隧道工程轨道交通设计研究院 Structure setting for escape way of tunnel
CN1614152A (en) * 2004-10-14 2005-05-11 上海隧道工程股份有限公司 Constructing method for in tunnel weak soil layer by freezing method horizontally
CN1916362A (en) * 2006-09-04 2007-02-21 上海隧道工程股份有限公司 Construction method for tunnel contact passage in shield section of underground railway
CN101463724A (en) * 2008-12-30 2009-06-24 上海隧道工程股份有限公司 Construction method for connection passage by double-row hole horizontal freezing method
CN102619522A (en) * 2012-03-20 2012-08-01 天津城建隧道股份有限公司 Construction method for subway contact passage
CN104695964A (en) * 2013-12-04 2015-06-10 宏润建设集团股份有限公司 Subway shield tunnel freeze entering method

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3621019A1 (en) * 1986-06-16 1987-12-17 Kunz Alfred & Co Method for producing a tunnel structure
CN2613590Y (en) * 2003-04-28 2004-04-28 上海市隧道工程轨道交通设计研究院 Structure setting for escape way of tunnel
CN1614152A (en) * 2004-10-14 2005-05-11 上海隧道工程股份有限公司 Constructing method for in tunnel weak soil layer by freezing method horizontally
CN1916362A (en) * 2006-09-04 2007-02-21 上海隧道工程股份有限公司 Construction method for tunnel contact passage in shield section of underground railway
CN101463724A (en) * 2008-12-30 2009-06-24 上海隧道工程股份有限公司 Construction method for connection passage by double-row hole horizontal freezing method
CN102619522A (en) * 2012-03-20 2012-08-01 天津城建隧道股份有限公司 Construction method for subway contact passage
CN104695964A (en) * 2013-12-04 2015-06-10 宏润建设集团股份有限公司 Subway shield tunnel freeze entering method

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106837388A (en) * 2017-02-03 2017-06-13 天津大学 Suitable for the detachable steel pipeline section of construction freezing method at tunnel connection channel
CN108397202A (en) * 2018-03-06 2018-08-14 中交第二公路勘察设计研究院有限公司 Freeze the leading excavation method of base tunnel in multi-step under advance support
CN108843334A (en) * 2018-06-19 2018-11-20 中交公局厦门工程有限公司 A kind of method of reinforcing building lower section rich water soft soil layer service channel
CN109083645A (en) * 2018-08-01 2018-12-25 南宁轨道交通集团有限责任公司 Shield tunnel and service channel method for synchronously constructing under the conditions of rich water round gravel stratum
CN110130316A (en) * 2019-05-13 2019-08-16 南京林业大学 The method of thaw collapse after service channel bottom pre-pouring grout system and control freezing construction
CN110454170A (en) * 2019-08-19 2019-11-15 中铁十二局集团有限公司 Tunnel connection channel construction method based on freezing process
JP2021534337A (en) * 2019-09-28 2021-12-09 中▲鉄▼九局集▲団▼有限公司China Railway No.9 Group Co., Ltd Freezing method and freezing system for connecting passages
JP7141650B2 (en) 2019-09-28 2022-09-26 中▲鉄▼九局集▲団▼有限公司 Freezing method and freezing system for connecting passages
WO2020244677A1 (en) * 2019-09-28 2020-12-10 中铁九局集团有限公司 Freezing construction method for connecting passage, and freezing system
CN110593918A (en) * 2019-10-15 2019-12-20 中铁十二局集团有限公司 Freezing method based tunnel connection channel pump house construction method
CN110905561A (en) * 2019-12-16 2020-03-24 兰州理工大学 Weak surrounding rock tunnel freezing initial support structure and construction method
CN111173536A (en) * 2019-12-26 2020-05-19 中交一航局安装工程有限公司 Freezing construction method for tunnel connection channel
CN111271095B (en) * 2020-01-20 2021-05-14 中煤科工集团西安研究院有限公司 Method for improving grouting effect of mine curtain
CN111271095A (en) * 2020-01-20 2020-06-12 中煤科工集团西安研究院有限公司 Method for improving grouting effect of mine curtain
CN112112244A (en) * 2020-08-13 2020-12-22 中国一冶集团有限公司 Construction method of drainage channel in limited space
CN112112244B (en) * 2020-08-13 2022-05-10 中国一冶集团有限公司 Construction method of drainage channel in limited space
CN113494313A (en) * 2021-06-25 2021-10-12 中铁一局集团有限公司 Contact passage portal breaking construction method for main tunnel segment
CN115977650A (en) * 2022-11-22 2023-04-18 安徽理工大学 Communication freezing system based on plane skew connection channel and construction method thereof

Similar Documents

Publication Publication Date Title
CN106089214A (en) Service channel manual pipe jacking reinforced construction method
CN105909260B (en) Subway station water stop structure for protecting groundwater environment and construction method thereof
CN106761790B (en) A kind of open type TBM crosses tunneling boring carbonaceous slate driving and method for protecting support
CN105908765B (en) For protecting the open trench tunnel water sealing structure and construction method of groundwater environment
CN106837352A (en) Fault belt surrounding rock tunnel construction method
CN104074525B (en) Full-face pouring, rectangular horizontal are freezed and pipe canopy joint reinforcement structure and method
CN106049505B (en) A kind of construction method of deep pit support supporting system
CN109208637A (en) Increase the construction method of open-cut station newly on the basis of existing tunnel
CN102619522A (en) Construction method for subway contact passage
CN113833480A (en) Shield initial tunneling and arrival construction method
CN106050266A (en) Construction method for undermining connected channel between shield sections in water-rich sand cobble stratum tunnel
JP7257086B2 (en) Comprehensive Construction Method for Low Overburden Sections of Tunnels
CN106121686B (en) Underground excavation tunnel water stop structure for protecting groundwater environment and construction method thereof
CN104806253B (en) A kind of construction method punched between rectangular top pipe passage
CN108412519A (en) The slight large deformation single-track tunnel suspension device of highlands soft rock and construction method
WO2020259059A1 (en) Tbm parallel heading tunnel trunk construction method
CN112081595B (en) Shield construction method, and waterproof and monitoring method for shield construction
CN104831734A (en) Construction method of jet-grouting pile and composite soil-nailed wall support for deep foundation pit construction
CN108457658A (en) A kind of texture stratum tunnel list hole bidirectional construction crosses section constructing method
CN108071400A (en) Horizontal freezing consolidation combines shield driving construction method with steel jacket box
CN111119900A (en) Earth pressure balance shield liquid nitrogen vertical freezing and underwater receiving comprehensive construction method
CN106759375B (en) A kind of high water level soft soil foundation pit freezes soil nail wall supporting structure system and construction method
CN212272200U (en) Vertical shaft freezing system
CN205669398U (en) A undercut tunnel stagnant water structure for protecting groundwater environment
CN111075455A (en) Freezing method channel construction process

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20161109

WD01 Invention patent application deemed withdrawn after publication