CN104806253B - A kind of construction method punched between rectangular top pipe passage - Google Patents

A kind of construction method punched between rectangular top pipe passage Download PDF

Info

Publication number
CN104806253B
CN104806253B CN201510246989.9A CN201510246989A CN104806253B CN 104806253 B CN104806253 B CN 104806253B CN 201510246989 A CN201510246989 A CN 201510246989A CN 104806253 B CN104806253 B CN 104806253B
Authority
CN
China
Prior art keywords
freezing
pipe
construction
hole
passage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510246989.9A
Other languages
Chinese (zh)
Other versions
CN104806253A (en
Inventor
刘杰
陈卓
陈强
夏炜洋
王启成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway No 2 Engineering Group Co Ltd
Original Assignee
China Railway No 2 Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway No 2 Engineering Group Co Ltd filed Critical China Railway No 2 Engineering Group Co Ltd
Priority to CN201510246989.9A priority Critical patent/CN104806253B/en
Publication of CN104806253A publication Critical patent/CN104806253A/en
Application granted granted Critical
Publication of CN104806253B publication Critical patent/CN104806253B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Soil Sciences (AREA)
  • Civil Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention discloses a kind of rectangular top pipe construction technology.The construction method punched between the rectangular top pipe passage of the present invention, including step: preparation of construction;Freezing hole construction;Freezing Station is installed;Actively freeze to freeze with maintenance;Excavation and construction;Freezing hole blocks;Thaw settlement grouting.By the layout of freezing hole and freezing hole construction process are set preventive measure, it is ensured that construction safety and construction effect;For excavation and the construction of service channel, use the mode earth excavation that layering, piecemeal cut, it is ensured that the structural stability after Freezing Method for Cross-passage Construction, little to surrounding structure damaging;Freezing Method for Cross-passage Construction utilizes the push pipe passage reserved injected hole of both sides and roof and floor that punches to carry out thaw settlement grouting after completing, control surface subsidence and malformation;This construction method solves the construction problem punched between rectangular top pipe passage, its work progress safely, the channel design outputed reliable and stable, and efficiency of construction is high.

Description

A kind of construction method punched between rectangular top pipe passage
Technical field
The present invention relates to a kind of push pipe passage construction technology, particularly to the construction punched between a kind of rectangular top pipe passage Method.
Background technology
Jacking construction is a kind of non-excavating construction method, and it refers to a kind of excavation or the piping laying construction of few excavation Technology.Construction by pipeline jacking method is the top power produced by means of jacking device in working pit, overcomes the friction of pipeline and surrounding soil Power, is headed into pipeline in soil by the gradient of design, and the earthwork is transported.After one length of tubing completes to head into soil layer, more lower second Length of tubing continues jacking.Its principle is by mean of main top oil cylinder and the thrust such as pipeline enclosure, relay well, tool pipe or development machine from Sling in being advanced to receive hole through soil layer in working pit always.After pipeline follows tool pipe or development machine closely, be embedded in two holes it Between.
Push pipe passage is not enough for urban land resource, traffic heavy congestion, and road passage capability can not meet city and send out During exhibition demand, can use as a kind of Urban Underground Passage.And stratum residing for city underground engineering is mainly silty sand ground, ground The layer water yield is enriched, good water permeability, and belongs to the arenaceous stratum of serious liquefaction so that the interconnective construction of push pipe interchannel becomes Extremely difficult, many push pipe passages all can only be individually present, and push pipe interchannel is not connected with each other, and is intended only as single " tunnel Road " exist, it is impossible to play preferably driving, the function of pedestrian.
Summary of the invention
It is an object of the invention to overcome stratum, Urban Underground push pipe passage place to be mainly silty sand ground, the stratum water yield is rich Rich, good water permeability, and belong to the arenaceous stratum of serious liquefaction so that the interconnective construction of push pipe interchannel becomes extremely to be stranded Difficult, it is impossible to the problem playing the preferably function of driving, pedestrian, it is provided that the construction party punched between a kind of rectangular top pipe passage Method, for solving the construction that punches between the aqueous abundant and silty sand ground stratum rectangular top pipe passage of good water permeability, the method is executed Work process safety, the channel design outputed are reliable and stable, and efficiency of construction is high.
In order to realize foregoing invention purpose, the invention provides techniques below scheme:
The construction method punched between a kind of rectangular top pipe passage, comprises the following steps:
(1) preparation of construction: to the Rock Conditions, hydrogeologic condition and the periphery pipeline that prepare near the rectangular top pipe of construction Situation does corresponding understanding, carries out the position planning opening service channel between rectangular top pipe passage;
(2) freezing hole construction: open freezing hole with diamond core drill on rectangular top pipe inwall, freeze by pipe-following drilling FAXIA Knot pipe, according to the position, hole of Freezing Method for Cross-passage Construction, uses order from bottom to top to construct;It is designed with at each drilling orifice Orifice tube, and boring sealing device is installed;When generation emits mud retention of excessive fluid phenomenon during construction freezing hole, strength level is used to bore Machine, realizes without mud drilling as far as possible;If occurring that muddy water runs off during boring, carry out in time mending slurry filling;
(3) Freezing Station is installed: Freezing Station is arranged on termination, ground well location and puts, and Freezing Station equipment includes freezing unit, salt Water tank, brine pump, clarified water pump, cooling tower and control cabinet for power distribution, connect each equipment with pipeline, uses freezing unit by freezing Liquid is squeezed into and is carried out freezing soil construction in freezing pipe;Actively freezing period chilled liquid temperature is-28 DEG C~-30 DEG C, safeguards freezing period Temperature is-25 DEG C~-28 DEG C;Chilling requirement calculates and fridge type selecting: freezes chilling requirement and calculates: Q=1.3 π d H K, its Middle H freezing hole total length, d freezing pipe diameter, K freezing pipe coefficient of heat transfer, according to chilling requirement to fridge type selecting;
(5) excavation and construction: after possessing excavation condition, reserved service channel is carried out accurate setting-out, carry out line position Labelling, uses the mode earth excavation that unilateral manual zoning, piecemeal cut;First excavate the half region on upper strata, excavated Falsework and gunite concrete are installed after one-tenth in time;Excavation upper strata remaining area and lower region the most successively, and install in time Falsework and gunite concrete;Last property integrated poured secondary lining permanent structure;
(6) freezing hole closure: freezing hole closure is carried out after secondary permanent structure form removal, and freezing pipe is not extracted, and uses Cutting off process, and close the mouth of pipe with Plate Welding, each freezing pipe blocks freezing hole after cutting off at once;
(7) thaw settlement grouting: utilize the push pipe passage reserved injected hole of both sides and roof and floor that punches to carry out thaw settlement grouting, thaw collapse Slip casting is based on the cement grout of single liquid, and dual slurry is auxiliary mode, carries out the thaw settlement grouting on stratum.
As preferably, in step (2) work progress, strict monitoring slanting of freezing hole situation, finds that deflection to be rectified a deviation in time, Under after good freezing pipe, carry out the repetition measurement of freezing pipe length, carry out deviational survey with Inclination Measurement by Light instrument the most again and draw hole scattering figure.
As preferably, freezing pipe selects φ 89*5mm and φ 45*3.5mm low-carbon (LC) seamless steel pipe, and freezing pipe is pressure to be not less than 0.8Mpa, and be not less than and freeze 1.5 times of work surface brine pressure, freezing pipe joint tensile strength is not less than the 75% of female pipe.
As preferably, according to the position, hole of Freezing Method for Cross-passage Construction, order from bottom to top is used to construct, freezing hole perforate Site error is not more than 100mm, should avoid joints of segment, dark beam and sleeper.So can prevent because the construction of lower floor's freezing hole is drawn Play upper formation disturbance, reduce accident rate during drilling construction.
As preferably, in drill process, soil body loss volume cannot be greater than freezing hole volume, and each freezing hole has been holed After, in time by injected hole, stratum compensated slip casting (carrying out pressure injection by 2 ~ 3 times of volumes), it is ensured that surface subsidence is controlled;Freeze Knot length of tube and deflection qualified after carry out suppressing leak test again, Stress control is at 0.8MPa, it is desirable to little the first 15 minutes pressure losses In 0.05MPa, in 30 minutes afterwards, pressure stability is that pressure testing is qualified time unchanged.If pressure testing is defective, freezing pipe can be extracted and enter Row redrilling, or setting of casing processes.
As preferably, step (3) arranges valve, temperature measurer, Pressure gauge in saline line and cooling water circulation pipeline Deng test suite;Saline line is incubated with warming plate or cotton-wool after leak test, cleaning, and insulation thickness is 20mm, outside heat-insulation layer Face plastic sheeting is wrapped up.Collection brine distributing ring and the connection high-pressure rubber pipe of freezing pipe, often organize import and export each dress valve of freezing pipe One, in order to control flow.PEF plate heat-insulation and heat-preservation is used, to reduce loss of refrigeration capacity outside tube coupling.
As preferably, in step (4), equipment carries out debugging and test running after installing.When test running, adjust at any time Joint each state parameter such as pressure, temperature, makes unit run under the conditions of the technical parameter of congealing process code and equipment requirements.Freeze Clone system enters after working well and actively freezes.
In positive freezing process, to judge whether freezing curtain is handed over circle and reach design thickness according to observed temperature data Degree, the cementing situation of freezing curtain to be monitored and passage, thermometric judge freezing curtain hand over enclose and reach design thickness and with After passage is the most cementing, can enter maintenance and freeze the stage, safeguard that freezing period temperature is-25 DEG C~-28 DEG C, freeze-off time runs through other Ground settlement and tunnel and main structure construction are all the time.
As preferably, in step (5), service channel longitudinal direction degree of depth 0.5m is taked disposably to have excavated, and excavated section is backbreak It is not more than 30mm, it is desirable to after each excavation in zones has excavated, freezing curtain open-assembly time is not more than 12 hours.
As preferably, in step (5), soil body both sides carry out artificial pneumatic pick excavation, and the middle soil body not freezed uses pickaxe Excavate with spade;In digging process, bottom will have part freezing pipe to be exposed, and first need to close the going of this group freezing pipe, return valve Door, cuts off internal saline emptying again.In order to improve drivage efficiency, accelerating construction progress, shorten frozen soil open-assembly time, Pneumatic pick point need to do Quenching Treatment.And tunneling ambient temperature below 0 DEG C, the condensed water in wind conveying pipe road and pneumatic pick is easily tied Ice, need to carry out dehumidification treatments, on the one hand airduct suspention is got up, and additionally injected ethanol in airduct every 1~2 hour, prevents The appearance of ice bits.And require well matched standby 5~6 pneumatic picks of each driving, to avoid irregular working to affect construction speed.In pick Enter the consolidation effect according to the exposure soil body in construction, and purpose monitoring information, adjust excavation step pitch and supporting intensity in time, really Ensure safety construction.In digging process, also want in time the freezing curtain exposed to be incubated.Ensure that the safety of work progress With the construction effect of service channel, improve efficiency of construction.
As preferably, step (6) is cut off a freezing pipe one freezing hole of closure the most in time, forbids several freezing pipes Cut off together, block together.
As preferably, in step (7), cement grout is cement list slurry, and water ash mass ratio is water: cement=1:1.Slip casting Pressure is not more than 0.3MPa, when internal channel sedimentation in a day is more than 0.5mm, or when the accumulative sedimentation of passage is more than 1.0mm, should melt Heavy compensation and grouting;Slip casting should be suspended as passage protuberance 2.0mm;Solum settlement relative with surrounding soil layer stable after, can terminate Thaw settlement grouting.
As preferably, in step (7), slip casting is with on a small quantity repeatedly as principle, and single hole once grouting amount is not more than 0.5 m3, note Slurry pressure is not more than 0.3Mpa.To treat that the Grouting Pipe of slip casting and its adjacent Grouting Pipe valve are fully open before slip casting;Slip casting Cheng Zhong, closes adjacent ports valve door, quantitatively can stop this hole slip casting after the single slurry of press-in, close valve closing when the continuous pulp of adjacent holes Door, is then followed by adjacent hole slip casting.When altering slurry consolidation in running into Grouting Pipe and cause plugging, need to be with lengthening drill hammer siphunculus.
According to surface subsidence and structural deformation monitoring situation, the Reasonable adjustment organization of labour, carry out repeatedly slip-casting in good time, until Sinking deformation monitoring is basicly stable, and reach structure without substantially infiltration till.
Control surface subsidence and malformation are the purposes of slip casting.Therefore, in course of defrosting, supervise by facial disfigurement intentinonally Water And Earth Pressures monitoring after survey, frozen soils temperature monitoring, frost wall.It addition, during mortar depositing construction, the pressure of serosity can pass through Adjacent injected hole is installed Pressure gauge and is reflected.Above comprehensive monitoring data, are the foundations of grouting parameter adjustment.The knot of thaw settlement grouting Bundle is to stabilize to foundation with ground deformation.Frost wall the most all melts, and the lasting month every first quarter moon of actual measurement stratum settlement is little In 0.5mm, thaw collapse compensation and grouting can be stopped.
Compared with prior art, beneficial effects of the present invention:
1, the construction method punched between this rectangular top pipe passage, by the layout of freezing hole and freezing hole construction process All do corresponding preventive measure, it is ensured that construction safety and construction effect;For excavation and the construction of service channel, adopt The mode earth excavation cut with layering, piecemeal, a part is timely after having excavated installs falsework and gunite concrete, Rear disposable integrated poured secondary lining permanent structure, it is ensured that the stability after Freezing Method for Cross-passage Construction, damages surrounding formation structure Bad little;Freezing Method for Cross-passage Construction utilizes the push pipe passage reserved injected hole of both sides and roof and floor that punches to carry out thaw settlement grouting after completing, Control surface subsidence and malformation;This construction method solves the construction problem punched between rectangular top pipe passage, and it was constructed Cheng Anquan, the channel design outputed are reliable and stable, and efficiency of construction is high;
2, during freezing hole construction, at each drilling orifice, it is designed with orifice tube, and boring sealing device is installed, can prevent When creeping into, a large amount of water, blowout go out;Produce during for construction freezing hole and emit mud retention of excessive fluid phenomenon, use strength horizontal drill, the most real Now without mud drilling;Occur during boring that muddy water runs off, carry out in time mending slurry filling;So water during the construction of construction energy control freezing hole Soil runs off, and reduces the impact on surrounding enviroment to greatest extent;
3, service channel earth excavation follows the principle of " from top to bottom, hierarchical block ", " early spray anchor, close soon " when removing, First excavate the half region on upper strata, falsework and gunite concrete are installed in time, it is ensured that construction safety after having excavated;Depend on again Secondary excavation upper strata remaining area and lower region, and falsework and gunite concrete are installed in time;Last property entirety is watered Note secondary lining permanent structure;Work progress is orderly, improves efficiency of construction.
Accompanying drawing illustrates:
Fig. 1 is the construction process figure of the construction method punched between the rectangular top pipe passage of the present invention.
Fig. 2 is the construction location relation schematic diagram punched between the rectangular top pipe passage of the present invention.
Fig. 3 is the A-A view in Fig. 2.
Fig. 4 is the schematic diagram opening freezing hole in rectangular top pipe.
Fig. 5 is Freezing Method for Cross-passage Construction schematic diagram between rectangular top pipe.
Fig. 6 is service channel excavation and construction flow chart.
Labelling in figure: 1-starting well, 2-rectangular top pipe, 3-service channel, 4-received well, 5-rectangular top pipe passage, 6-freezes Knot hole, 7-pressure relief vent, 8-thermometer hole.
Detailed description of the invention
Below in conjunction with test example and detailed description of the invention, the present invention is described in further detail.But this should not understood Scope for the above-mentioned theme of the present invention is only limitted to below example, and all technology realized based on present invention belong to this The scope of invention.
Embodiment 1
The present embodiment, as a example by the construction of somewhere Subway Tunnel service channel, is opened between the rectangular top pipe passage of the present invention The construction method in hole illustrates.
As in figure 2 it is shown, be provided with the separate rectangular push pipe that three rectangular top pipes 2 are formed between starting well 1 and received well 4 Passage 5, is now intended to get through three rectangular top pipe passages 5, as it is shown on figure 3, the rectangular top pipe interchannel after getting through establishes contact Passage 3, the construction method punched between the rectangular top pipe passage of the present embodiment, comprise the following steps:
(1) preparation of construction: to the Rock Conditions, hydrogeologic condition and the periphery pipeline that prepare near the rectangular top pipe of construction Situation does corresponding understanding, carries out and opens the position of service channel and the planning of other parameters between rectangular top pipe passage;Analyze Prepare rock stratum attribute and the stratum water content situation of construction surrounding formation, carry out corresponding preparation of construction, it is to avoid affect Zhou Bianhuan Border safety;
(2) freezing hole construction: open freezing hole with diamond core drill on rectangular top pipe inwall, freeze by pipe-following drilling FAXIA Knot pipe, according to the position, hole of Freezing Method for Cross-passage Construction, uses order from bottom to top to construct;As shown in Figure 4, the freezing of the present embodiment Knot hole 6 is arranged in the four sides of rectangular top pipe conduit wall, is divided into the horizontal frozen hole being arranged on rectangular top tube wall, is arranged on rectangle Vertical freezing hole, rectangular top tube wall and top board, the inclination freezing hole of back plate connections on push pipe top board and base plate;
At each drilling orifice, it is designed with orifice tube, and boring sealing device is installed, a large amount of water, blowout when preventing from creeping into Go out;Produce during for construction freezing hole and emit mud retention of excessive fluid phenomenon, use strength horizontal drill, it is achieved without mud drilling;If during boring Occur that muddy water runs off, carry out in time mending slurry filling;
(3) Freezing Station is installed: Freezing Station is arranged on termination, ground well location and puts, and Freezing Station equipment includes freezing unit, salt Water tank, brine pump, clarified water pump, cooling tower and control cabinet for power distribution, connect each equipment with pipeline, uses freezing unit by freezing Liquid is squeezed into and is carried out freezing soil construction in freezing pipe;
(4) actively freeze to freeze with maintenance: actively freezing period chilled liquid temperature is-28 DEG C~-30 DEG C, safeguards freezing period temperature Degree is for-25 DEG C~-28 DEG C;Chilling requirement calculates and fridge type selecting: freezes chilling requirement and calculates: Q=1.3 π d H K, wherein H freezes total length, d freezing pipe diameter, and K freezing pipe coefficient of heat transfer, according to chilling requirement to fridge type selecting;
(5) excavation and construction: after possessing excavation condition, reserved service channel is carried out accurate setting-out, carry out line position Labelling, uses the mode earth excavation that unilateral manual zoning, piecemeal cut;First excavate the half region on upper strata, excavated Falsework and gunite concrete are installed after one-tenth in time;Excavation upper strata remaining area and lower region the most successively, and install in time Falsework and gunite concrete;Last property integrated poured secondary lining permanent structure;As it is shown in figure 5, service channel 3 is executed Work point is that 4th district cut, and follows the principle of " from top to bottom, hierarchical block ", " early spray anchor, close soon ", first when cutting Excavate I subregion, falsework and gunite concrete are installed after having excavated in time;Excavate II, III, IV subregion the most successively, and and Time falsework and gunite concrete are installed;Last property integrated poured secondary lining permanent structure;
Being the situation of reinforced concrete structure for service channel to be excavated, service channel structure needs first to reinforcing bar before constructing Concrete tube coupling cuts.Therefore how to control vibration effect when armored concrete cuts, and the deformation of tube coupling after punching Impact, as it is shown in figure 5, the present embodiment is before service channel punches construction, offers 4 horizontal thermometer holes 8 in the range of punching, and sees Survey the frozen soils temperature of the soil body, it is desirable to reach less than-10 DEG C of design code;
When the tube coupling that punches cuts, it then follows " from top to bottom, hierarchical block " and the principle of " early spray anchor, soon closing ", the most first general After piecemeal position, the tube coupling top layering that punches cuts, carry out spraying anchor immediately or Plate Welding is closed, carry out again after having closed Next piecemeal cut operation, thus reduce the disturbing influence to tube coupling;
In whole work progress, strengthen, to frozen construction parameter and the monitoring frequency of malformation, adjusting according to Monitoring Data Homogeneous tube joint cuts time and order;If malformation is excessive, with gunite concrete, face should be carried out sealing treatment immediately, After carrying out pre-pouring grout reinforcing if desired, then carry out punching that tube coupling is remaining cuts operation;
(6) freezing hole closure: freezing hole closure is carried out after secondary permanent structure form removal, and freezing pipe is not extracted, and uses Cut off process, and close the mouth of pipe with Plate Welding, cut off a freezing pipe one freezing hole of closure the most at once, forbid to freeze several Knot hole is cut off together, blocks together;
(7) thaw settlement grouting: utilize the push pipe passage reserved injected hole of both sides and roof and floor that punches to carry out thaw settlement grouting, thaw collapse Slip casting is based on the cement grout of single liquid, and dual slurry is auxiliary mode, carries out the thaw settlement grouting on stratum;
When and top buried depth less for adjacent rectangle push pipe interchannel clear distance is deep, need to consider above rectangular top pipe Pipeline arrange, it is necessary to when reducing frozen construction, the frozen swell and melt settlement of shaping channel structure and upper pipeline thereof is affected, for These situations can use quick freezing to reduce frost heave, if desired freezing range is carried out front pre-grouting;Because shallow soil layer freezes Body volume is the least, and under conditions of quick freezing, the frost heave of generation is the least.
For ensureing engineering safety and quality thereof, set up inclination thermometer hole on rectangular top pipe top, by temperature measurement data analysis, Judge to freeze to hand over circle and the development of freezing curtain thereof, thus adjust and freeze the body speed of development, and then play restriction frozen soil body of wall The long-pending effect upwards developed;
As it is shown in figure 5, service channel punch both sides lay two pressure relief vents 7, according to pressure relief vent 7 upward pressure meter reading become Change, discharge frost-heaving force in advance, reduce the frost heave impact on jacking pipe joints;
Pre-buried madjack pipe in service channel lining cutting, uses tracking grouting mode to compensate soil layer thaw collapse, but grouting amount and pressure Power must be adjusted according to monitoring measurement feedback data.
In the present embodiment, in step (2) work progress, strict monitoring slanting of freezing hole situation, finds that deflection to be entangled in time Partially, after lower good freezing pipe, carry out the repetition measurement of freezing pipe length, carry out deviational survey with Inclination Measurement by Light instrument the most again and draw hole scattering Figure.
In the present embodiment, freezing pipe selects φ 89*5mm and φ 45*3.5mm low-carbon (LC) seamless steel pipe, and it is the lowest that freezing pipe is pressure In 0.8Mpa, and being not less than and freeze 1.5 times of work surface brine pressure, freezing pipe joint tensile strength is not less than female pipe 75%.So, freeze chilling requirement calculate: Q=1.3 π d H K, wherein H freezing hole total length: Φ 89mm=102.5m and Φ 45mm=448m, d freezing pipe diameter: Φ 89mm and Φ 45mm, K freezing pipe coefficient of heat transfer 250~280 Kcal/m2h:
So calculating chilling requirement is 3.17 × 104 Kcal/h, according to chilling requirement, service channel selects JYSLGF-300II Type Screw chiller one set, single unit design conditions refrigerating capacity is 8.75 × 104 Kcal/h, power of motor 110KW, completely Meet refrigeration demand.Selecting J-200 type diamond drill, join φ 130mm diamond core bit and hole, the degree of depth is about 320mm, control must not drill tube coupling;
In the present embodiment, according to the position, hole of Freezing Method for Cross-passage Construction, using order from bottom to top to construct, freezing hole is opened Hole site error is not more than 100mm, should avoid joints of segment, dark beam and sleeper.So can prevent because of the construction of lower floor's freezing hole Cause upper formation disturbance, reduce accident rate during drilling construction.
In the present embodiment, in drill process, soil body loss volume cannot be greater than freezing hole volume, and each freezing hole has been holed Cheng Hou, in time compensates slip casting (carrying out pressure injection by 2 ~ 3 times of volumes) by injected hole, it is ensured that surface subsidence is controlled to stratum; Freezing pipe length and deflection qualified after carry out suppressing leak test again, Stress control was at 0.8MPa, it is desirable to the first 15 minutes pressure losses Less than 0.05MPa, in 30 minutes afterwards, pressure stability is that pressure testing is qualified time unchanged.If pressure testing is defective, freezing pipe can be extracted Carry out redrilling, or setting of casing processes.
In the present embodiment, step (3) arranges valve, temperature measurer, pressure in saline line and cooling water circulation pipeline The test suites such as table;Saline line is incubated with warming plate or cotton-wool after leak test, cleaning, and insulation thickness is 20mm, heat-insulation layer Outside plastic sheeting is wrapped up, collection brine distributing ring and the connection high-pressure rubber pipe of freezing pipe, often organizes import and export each dress valve of freezing pipe One, door, in order to control flow.PEF plate heat-insulation and heat-preservation is used, to reduce loss of refrigeration capacity outside tube coupling.
In the present embodiment, in step (4), equipment carries out debugging and test running after installing.When test running, be at any time Regulation each state parameter such as pressure, temperature, makes unit run under the conditions of the technical parameter of congealing process code and equipment requirements. Freezing system enters after working well and actively freezes.
In positive freezing process, to judge whether freezing curtain is handed over circle and reach design thickness according to observed temperature data Degree, the cementing situation of freezing curtain to be monitored and passage, thermometric judge freezing curtain hand over enclose and reach design thickness and with After passage is the most cementing, can enter maintenance and freeze the stage, safeguard that freezing period temperature is-25 DEG C~-28 DEG C, freeze-off time runs through other Ground settlement and tunnel and main structure construction are all the time.
Such as figure, shown in 6, excavation and construction flow chart, the service channel longitudinal direction degree of depth in step (5) in the present embodiment 0.5m takes disposably to have excavated, and excavated section is backbreak no more than 30mm, it is desirable to after each excavation in zones has excavated, freeze Curtain open-assembly time is not more than 12 hours.
In the present embodiment, in step (5), soil body both sides carry out artificial pneumatic pick excavation, and the middle soil body not freezed uses hands Pick and spade excavation;In digging process, bottom will have part freezing pipe to be exposed, and first need to close the going of this group freezing pipe, loop Valve, cuts off internal saline emptying again.In order to improve drivage efficiency, accelerating construction progress, when shortening frozen soil exposure Between, pneumatic pick point need to do Quenching Treatment.And tunneling ambient temperature below 0 DEG C, the condensed water in wind conveying pipe road and pneumatic pick is easy Freeze, dehumidification treatments need to be carried out, on the one hand airduct suspention is got up, additionally in airduct, injected ethanol every 1~2 hour, anti- The appearance of stagnant ice bits.And require well matched standby 5~6 pneumatic picks of each driving, to avoid irregular working to affect construction speed.? According to disclosing the consolidation effect of the soil body in tunneling construction, and purpose monitoring information, adjust excavation step pitch and supporting intensity in time, Guarantee safe construction.In digging process, also want in time the freezing curtain exposed to be incubated.
In the present embodiment, step (6) is cut off a freezing pipe one freezing hole of closure the most in time, forbids to freeze several Pipe cuts off together, blocks together.
In the present embodiment, in step (7), cement grout is single slurry, and the ratio of mud is water: cement=1:1.Grouting pressure is not More than 0.3MPa, when internal channel sedimentation in a day is more than 0.5mm, or when the accumulative sedimentation of passage is more than 1.0mm, thaw collapse compensation should be carried out Slip casting;Slip casting should be suspended as passage protuberance 2.0mm;Solum settlement relative with surrounding soil layer stable after, thaw collapse note can be terminated Slurry.
In the present embodiment, in step (7), slip casting is with on a small quantity repeatedly as principle, and single hole once grouting amount is not more than 0.5 m3, Grouting pressure is not more than 0.3Mpa.To treat that the Grouting Pipe of slip casting and its adjacent Grouting Pipe valve are fully open before slip casting;Slip casting During, close adjacent ports valve door when the continuous pulp of adjacent holes, quantitatively can stop this hole slip casting after the single slurry of press-in, close valve closing Door, is then followed by adjacent hole slip casting.When altering slurry consolidation in running into Grouting Pipe and cause plugging, need to be with lengthening drill hammer siphunculus.
According to surface subsidence and structural deformation monitoring situation, the Reasonable adjustment organization of labour, carry out repeatedly slip-casting in good time, until Sinking deformation monitoring is basicly stable, and reach structure without substantially infiltration till.
Control surface subsidence and malformation are the purposes of slip casting.Therefore, in course of defrosting, supervise by facial disfigurement intentinonally Water And Earth Pressures monitoring after survey, frozen soils temperature monitoring, frost wall.It addition, during mortar depositing construction, the pressure of serosity can pass through Adjacent injected hole is installed Pressure gauge and is reflected.Above comprehensive monitoring data, are the foundations of grouting parameter adjustment.The knot of thaw settlement grouting Bundle, stabilizes to foundation with ground deformation, and frost wall the most all melts, and actual measurement stratum settlement continues month every first quarter moon and is not more than 0.5mm, can stop thaw collapse compensation and grouting.
All features disclosed in this specification, or disclosed all methods or during step, except mutually exclusive Feature and/or step beyond, all can combine by any way.
Any feature disclosed in this specification (including any accessory claim, summary and accompanying drawing), unless chatted especially State, all can be by other equivalences or there is the alternative features of similar purpose replaced.I.e., unless specifically stated otherwise, each feature is only It it is an example in a series of equivalence or similar characteristics.

Claims (11)

1. the construction method punched between a rectangular top pipe passage, it is characterised in that comprise the following steps:
(1) preparation of construction: to the Rock Conditions, hydrogeologic condition and the periphery line conditions that prepare near the rectangular top pipe of construction Do corresponding understanding, carry out the position planning punched;
(2) freezing hole construction: open freezing hole with diamond core drill on rectangular top pipe inwall, freeze by pipe-following drilling FAXIA Pipe, according to the position, hole of Freezing Method for Cross-passage Construction, uses order from bottom to top to construct;It is designed with hole at each drilling orifice Mouth pipe, and boring sealing device is installed;When generation emits mud retention of excessive fluid phenomenon during construction freezing hole, use strength horizontal drill, Realize without mud drilling;If occurring that muddy water runs off during boring, carry out in time mending slurry filling;Cloth at each tube coupling that punches of freezing pipe Putting 3 ~ 4 thermometer holes, 1 ~ 2 thermometer hole is respectively arranged in the both sides that punch, and thermometer hole sum is not less than 3;
(3) Freezing Station is installed: Freezing Station is arranged on termination, ground well location and puts, Freezing Station equipment include freezing unit, brine tank, Brine pump, clarified water pump, cooling tower and control cabinet for power distribution, connect each equipment with pipeline, uses freezing unit to be beaten by freezing liquid Enter and freezing pipe carries out frozen construction;
(4) actively freeze to freeze with maintenance: actively freezing period brine temp be-28 DEG C~-30 DEG C, safeguard freezing period temperature be- 25 DEG C~-28 DEG C;Chilling requirement calculates and fridge type selecting: freezes chilling requirement and calculates: Q=1.3 π d H K, wherein H freezes Knot hole total length, d freezing pipe diameter, K freezing pipe coefficient of heat transfer;
(5) excavation and construction: after possessing excavation condition, reserved service channel is carried out accurate setting-out, carry out line position labelling, Use the mode earth excavation that unilateral manual zoning, piecemeal cut;First excavate the half region on upper strata, excavated after and Time falsework and gunite concrete are installed;Excavation upper strata remaining area and lower region the most successively, and install interim in time Frame and gunite concrete;Last property integrated poured secondary lining permanent structure;
(6) freezing hole closure: freezing hole closure is carried out after secondary permanent structure form removal, and freezing pipe is not extracted, and employing is cut off Processing, and close the mouth of pipe with Plate Welding, single freezing pipe blocks freezing hole after cutting off at once;
(7) thaw settlement grouting: utilize the push pipe passage reserved injected hole of both sides and roof and floor that punches to carry out thaw settlement grouting, thaw settlement grouting Based on the cement grout of single liquid, dual slurry is auxiliary mode, carries out the thaw settlement grouting on stratum.
The construction method punched between rectangular top pipe passage the most according to claim 1, it is characterised in that step (2) is executed During work, strict monitoring slanting of freezing hole situation, finds that deflection to be rectified a deviation in time, after lower good freezing pipe, carries out freezing pipe length Repetition measurement, carry out deviational survey with Inclination Measurement by Light instrument the most again and draw hole scattering figure.
The construction method punched between rectangular top pipe passage the most according to claim 1 and 2, it is characterised in that rectangular top Both sides freezing pipe φ 89 × 5mm mild steel seamless steel pipe in pipe;Top, bottom freezing pipe with φ 45 × 3.5mm mild steel without Seam steel pipe;Freezing pipe is pressure is not less than 0.8Mpa, and is not less than and freezes 1.5 times of work surface brine pressure.
The construction method punched between rectangular top pipe passage the most according to claim 3, it is characterised in that described freezing hole Position, hole according to Freezing Method for Cross-passage Construction, uses order from bottom to top to construct, and freezing hole position of opening error is not more than 100mm, should avoid joints of segment, dark beam and sleeper.
The construction method punched between rectangular top pipe passage the most according to claim 4, it is characterised in that in drill process Soil body loss volume cannot be greater than freezing hole volume, after each freezing hole has been holed, is carried out stratum by injected hole in time Compensation and grouting;Freezing pipe length and deflection qualified after carry out suppressing leak test again, Stress control was at 0.8MPa, it is desirable at first 15 minutes The pressure loss is less than 0.05MPa, and in 30 minutes afterwards, pressure stability is that pressure testing is qualified time unchanged.
The construction method punched between rectangular top pipe passage the most according to claim 1, it is characterised in that in step (3) Saline line and cooling water circulation pipeline arrange valve, temperature measurer, Pressure gauge;Saline line is used after leak test, cleaning and is protected Temperature plate or cotton-wool insulation, insulation thickness is 20mm, and the outside plastic sheeting of heat-insulation layer is wrapped up;Collection brine distributing ring and the company of freezing pipe Connect with high-pressure rubber pipe, often organize one, import and export each dress valve of freezing pipe, outside tube coupling, use PEF plate heat-insulation and heat-preservation, to reduce Loss of refrigeration capacity.
The construction method punched between rectangular top pipe passage the most according to claim 1, it is characterised in that in step (4) Equipment carries out debugging and test running after installing;When test running, pressure, temperature to be regulated at any time, make unit freeze work Running under the conditions of the technical parameter of skill code and equipment requirements, freezing system enters after working well and actively freezes.
The construction method punched between rectangular top pipe passage the most according to claim 7, it is characterised in that actively freezing During, to judge whether freezing curtain is handed over circle and reach design thickness according to observed temperature data, to monitor simultaneously and freeze curtain Curtain and the cementing situation of passage, thermometric judge freezing curtain friendship enclose and reach design thickness and the most cementing with passage after, can enter Entering maintenance and freeze the stage, safeguard that freezing period temperature is-25 DEG C~-28 DEG C, freeze-off time runs through by-pass excavation and agent structure Construction is all the time.
The construction method punched between rectangular top pipe passage the most according to claim 1, it is characterised in that in step (5) Service channel longitudinal direction degree of depth 0.5m is taked disposably to have excavated, and excavated section is backbreak no more than 30mm, it is desirable to each excavation divides After district has excavated, freezing curtain open-assembly time is not more than 12 hours.
The construction method punched between rectangular top pipe passage the most according to claim 9, it is characterised in that described contact Passage soil at both sides carries out artificial pneumatic pick excavation, and the middle soil body not freezed uses pickaxe and spade excavation;In digging process Bottom will have part freezing pipe to be exposed, and first need to close the outlet of this group freezing pipe and loop valve, and internal is freezed liquid Emptying is cut off again.
The construction method punched between 11. rectangular top pipe passages according to claim 1, it is characterised in that in step (7) The water ash mass ratio of cement grout is water: cement=1:1;Grouting pressure is not more than 0.3MPa, when internal channel sedimentation in a day is more than 0.5mm, or when the accumulative sedimentation of passage is more than 1.0mm, thaw collapse compensation and grouting should be carried out;Note should be suspended as passage protuberance 2.0mm Slurry;Solum settlement relative with surrounding soil layer stable after, thaw settlement grouting can be terminated.
CN201510246989.9A 2015-05-15 2015-05-15 A kind of construction method punched between rectangular top pipe passage Active CN104806253B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510246989.9A CN104806253B (en) 2015-05-15 2015-05-15 A kind of construction method punched between rectangular top pipe passage

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510246989.9A CN104806253B (en) 2015-05-15 2015-05-15 A kind of construction method punched between rectangular top pipe passage

Publications (2)

Publication Number Publication Date
CN104806253A CN104806253A (en) 2015-07-29
CN104806253B true CN104806253B (en) 2016-11-09

Family

ID=53691405

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510246989.9A Active CN104806253B (en) 2015-05-15 2015-05-15 A kind of construction method punched between rectangular top pipe passage

Country Status (1)

Country Link
CN (1) CN104806253B (en)

Families Citing this family (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105862932B (en) * 2016-04-30 2018-08-17 叶香竹 Protect the structure of municipal pipeline
CN106014460A (en) * 2016-06-14 2016-10-12 中铁隧道勘测设计院有限公司 Incremental launching type underground space group construction method and application
CN108222949A (en) * 2018-01-03 2018-06-29 上海市机械施工集团有限公司 Passage construction structures and methods
CN109000963A (en) * 2018-08-30 2018-12-14 广东水利电力职业技术学院(广东省水利电力技工学校) A kind of plastic concrete cut-off wall sampling method
CN109409777A (en) * 2018-11-16 2019-03-01 安徽国祯环境修复股份有限公司 A kind of Groundwater Contamination Risk management-control method based on construction freezing method
CN110132347A (en) * 2019-04-25 2019-08-16 中铁十二局集团有限公司 The construction monitoring method in the tunnel based on frozen construction
CN110847151B (en) * 2019-10-23 2021-07-06 河南城建学院 Method for repairing tunnel underpass cavity by freezing method
CN111173536A (en) * 2019-12-26 2020-05-19 中交一航局安装工程有限公司 Freezing construction method for tunnel connection channel
CN112459799A (en) * 2020-11-23 2021-03-09 张同勇 Construction method of underground water supply pipeline
CN113404430A (en) * 2021-05-27 2021-09-17 中国一冶集团有限公司 Safe embedding method of freezing pipe

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102619522A (en) * 2012-03-20 2012-08-01 天津城建隧道股份有限公司 Construction method for subway contact passage

Also Published As

Publication number Publication date
CN104806253A (en) 2015-07-29

Similar Documents

Publication Publication Date Title
CN104806253B (en) A kind of construction method punched between rectangular top pipe passage
CN104074525B (en) Full-face pouring, rectangular horizontal are freezed and pipe canopy joint reinforcement structure and method
CN104963334B (en) Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement
CN104695964B (en) Subway shield tunnel freeze entering method
CN108035335B (en) Method for constructing shaft type underground parking garage by freezing method
CN105908765B (en) For protecting the open trench tunnel water sealing structure and construction method of groundwater environment
CN105909260B (en) Subway station water stop structure for protecting groundwater environment and construction method thereof
CN102619522A (en) Construction method for subway contact passage
CN207131404U (en) Railway tunnel ultra-deep shaft construction freezing method structural system
CN205975649U (en) Freezing pipe curtain steel pipe supporting construction
CN101463724A (en) Construction method for connection passage by double-row hole horizontal freezing method
CN106121686B (en) Underground excavation tunnel water stop structure for protecting groundwater environment and construction method thereof
CN104832196B (en) Pipe curtain freezing process supporting construction and its construction method
CN107119669A (en) For shield, the pre-pouring grout consolidated subsoil method in house is worn in side in water-rich sand layer
CN101418567A (en) Protective cutting construction method for tunnel segment
CN108843328A (en) A kind of Metro Connection Passage excavation construction support construction method
CN111593726A (en) Joint reinforcement method for underground tunnel penetrating sensitive pipeline of water-rich stratum and butt joint of existing structure MJS + artificial freezing
CN108071400A (en) Horizontal freezing consolidation combines shield driving construction method with steel jacket box
CN109209396A (en) A kind of shield tunnel end joint reinforcement structure and construction method
CN109296371A (en) MJS method and horizontal freezing joint reinforcement pressure-bearing rich water arenaceous stratum overlap the system and its construction method that section is worn under station
CN108825247B (en) External inclination side wall horizontal bottom-making basin-shaped freezing water stop construction method for 8 pilot tunnel PBA construction method
CN111236947A (en) Construction method of vertical freezing subway shaft
CN106759375B (en) A kind of high water level soft soil foundation pit freezes soil nail wall supporting structure system and construction method
CN212272200U (en) Vertical shaft freezing system
CN205669398U (en) A undercut tunnel stagnant water structure for protecting groundwater environment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
EXSB Decision made by sipo to initiate substantive examination
SE01 Entry into force of request for substantive examination
C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20160301

Address after: Jinniu District Kam Tong Road Chengdu city Sichuan province 610031 No. 16

Applicant after: CHINA RAILWAY NO.2 BUREAU ENGINEERING CO., LTD.

Address before: 610041, No. nine, No. 156, building B, high building, Xing Xing Road, Chengdu hi tech Zone, Sichuan

Applicant before: China Railway Erju Co., Ltd.

Applicant before: City reduction of fractions to a common denominator company of China Railway Erju Co., Ltd

C14 Grant of patent or utility model
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: No. 16, Jinniu District Road, Jinniu District Road, Chengdu, Sichuan

Patentee after: China Railway No. 2 Engineering Group Co., Ltd.