CN104963334B - Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement - Google Patents

Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement Download PDF

Info

Publication number
CN104963334B
CN104963334B CN201510407722.3A CN201510407722A CN104963334B CN 104963334 B CN104963334 B CN 104963334B CN 201510407722 A CN201510407722 A CN 201510407722A CN 104963334 B CN104963334 B CN 104963334B
Authority
CN
China
Prior art keywords
pipe
slip casting
freezing
hole
grouting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201510407722.3A
Other languages
Chinese (zh)
Other versions
CN104963334A (en
Inventor
杨平
张婷
何冬
何文龙
陈斌
丁顺良
王升福
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Forestry University
Original Assignee
Nanjing Forestry University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Forestry University filed Critical Nanjing Forestry University
Priority to CN201510407722.3A priority Critical patent/CN104963334B/en
Publication of CN104963334A publication Critical patent/CN104963334A/en
Application granted granted Critical
Publication of CN104963334B publication Critical patent/CN104963334B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

Freeze the construction method that service channel suppresses frozen swell and melt settlement the present invention relates to a kind of reinforced with slip casting freezing pipe, by the way that freezing pipe is also served as into Grouting Pipe, it is characterized in that the slip casting freezing pipe is made up of Grouting Pipe I and feed pipe II, wherein Grouting Pipe I is made up of 3 ~ 6 sections, Section 1 pipe end is equipped with drill bit III, and a check valve IV is respectively arranged in pipe shaft both sides;Feed pipe II is made up of two steel pipe cross welds, and a certain amount of cement mortar is mixed in the soil body improves the physico-mechanical properties of the soil body, and frozen swell and melt settlement is to surrounding formation when can suppress service channel consolidation by freezing and builds(Structure)Build the influence of thing.Construction procedure is that preparation of construction → locating holes → slip casting → installation feed pipe → installation refrigeration system → maintenance completion start is freezed.This engineering method advantage is that soil cement is reinforced and further enhances the intensity of the soil body, and the enhancing soil body is impervious and self-stability ability, service channel stratum sealing, effectively controls seepage action of ground water, improves the later stage and excavate the security constructed.

Description

Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement
Technical field
Freeze the construction method that service channel suppresses frozen swell and melt settlement the present invention relates to a kind of reinforced with slip casting freezing pipe.This work Method mixes a certain amount of cement mortar to improve the physical mechanics property of the soil body by the way that freezing pipe is also served as into Grouting Pipe in the soil body Matter, can suppress influence of the frozen swell and melt settlement to surrounding formation and buildings or structures during service channel consolidation by freezing.
Background technology
There is a wide range of soft layer in the nearly river such as Ningbo, Shanghai and Nanjing, Haiti area, soil strength is relatively low, water content compared with It is high.During underground engineering construction, it is necessary to take into account collapse, the reinforcing work of many problems, wherein service channel such as water burst Work is crucial.Engineering with artificial freezing method and soil cement method for strengthening are all in daily use in engineering, cut both ways.
Freezing process utilizes manual pipe jacking Refrigeration Technique, the water in stratum is build-up ice, natural ground is become frozen soil, increases Its strength and stability, isolation underground water and underground engineering are contacted, under the protection of frost wall, to carry out underground engineering pick Build construction.It has can form frozen soil wall under extremely complex engineering geology and hydrogeologic condition, not by supporting scope and The limitation of supporting depth, there is strict water proofing property and nonstaining property.
But after engineering with artificial freezing method construction, surrounding formation is produced frost heave, thaw collapse phenomenon, for surrounding environment so that soil Engineering properties and adjacent buildings be adversely affected, such as cause foundation instability, make close to buildings produce inclination, crack, The accidents such as building collapse can be caused when serious, or underground utilities is occurred the adverse consequences such as destruction.
After service channel frozen construction terminates, typically stratum is controlled by the way of the frost free period tracking grouting filling soil body Sedimentation, selected most dependence engineering experience at slip casting position, grouting amount only only in accordance with daily Ground Subsidence Monitoring, engineering it is controllable Property it is poor, it is difficult to completely control soft soil layer work after thaw collapse;Due to thaw collapse influence the cycle it is longer, early stage slip casting it is not in place past During metro operation is caused, line produces differential settlement up and down, causes serious potential safety hazard.
The mode for forming soil cement induration in soil at present uses slip casting method, deep-mixed pile and high-pressure rotary spraying method. This engineering method uses slip casting method therein.
Slip casting method be by cementing material be configured to slurries and inject it is loose containing sand or aquifer water-bearing stratum, it is the rock stratum containing crack, molten Hole, crushed zone make the construction method that it solidifies.Slurries are condensed after hardening, are played cementing, ponding, stratum is consolidated and is separated Water source, to ensure smooth construction.
In actual underground engineering, to improve the validity of foundation stabilization, engineering with artificial freezing method is integrated sometimes and soil cement is reinforced Method is carried out simultaneously.As during metro tunnel excavation, shield end is originated and received, the construction of service channel is often because of soil cement Reinforce failure to go wrong, freezing process at this moment can be taken to carry out once supplement again and reinforced;Or risk is larger, strata condition running into When complicated or surrounding buildings or structures require sedimentation very little, basement process first is carried out with soil cement method for strengthening, is being formed afterwards Soil cement on the basis of carry out engineering with artificial freezing method construction again.
The content of the invention
Had the advantages that simultaneously using engineering with artificial freezing method and the progress ground reinforcement of soil cement method for strengthening very important:Soil cement is carried The high physico-mechanical properties of ground, when carrying out engineering with artificial freezing method construction on this basis, the freeze-thaw damage of generation is suppressed etc.. The later stage is avoided because condition does not allow to cause slip casting not in place, not in time, causes soft soil layer UNICOM road with tunnel structure in fortune Differential settlement, problems of crack are produced during battalion.
Freeze applying for service channel suppression frozen swell and melt settlement it is an object of the invention to provide a kind of reinforced with slip casting freezing pipe Work method., can be by the control of stratum settlement amount in 5mm by using this engineering method, thaw collapse coverage is controlled in 24m or so.
The purpose of the present invention is achieved through the following technical solutions:
A kind of slip casting freezing pipe, it is characterised in that the slip casting freezing pipe is made up of Grouting Pipe I and feed pipe II, wherein slip casting Pipe I is made up of 3~6 sections, and Section 1 pipe end is equipped with drill bit III, and a check valve IV is respectively arranged in pipe shaft both sides;Feed pipe II is by two Steel pipe cross weld is made.
Described a kind of slip casting freezing pipe, it is characterised in that described Grouting Pipe I is the seamless steel of Φ 89 × 8mm, 20# low-carbons Pipe, Section 1 length is 1m, and follow-up each section length is 1.5m.
Described a kind of slip casting freezing pipe, it is characterised in that described feed pipe II is that Φ 45 × 3mm, 20# low-carbons are seamless On steel pipe, one of 2~8m of length of steel pipe, another length of steel pipe 0.5m, the one side for being welded on 2~8m steel pipes front end.
Reinforced using described slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement, it is characterised in that Construction procedure is as follows:
Barrier in a, preparation of construction, cleaning tunnel, builds construction operation platform;Supply line is connected, to meet drilling Freezing system and excavation construct power supply in construction, tunnel;Lay pipeline to Freezing Method for Cross-passage Construction working face, drilled for hole position and Freeze operating to supply water and blowdown;Check cement quality, rig service behaviour and the intact degree of measuring equipment;
B, locating holes, take secondary hole opening technology, according to hole position position, deflection, depth;Rig is in place, from MD-60 Rig, control mode 2KN/m, thrust 17KN carries out hole position and is drilled with;
After c, perforate are finished, Grouting Pipe is pierced to pre-pouring grout hole position and carries out slip casting, Grouting Pipe is low from Φ 89 × 8mm, 20# Carbon seamless steel pipe, Section 1 slip casting length of tube is 1m, and follow-up Grouting Pipe is using 1.5m as a section, head section Grouting Pipe pipe ends and pipe shaft peace Check valve slip casting is filled, check valve opens pressure between 0.3~0.5MPa, according to projected depth slip casting section by section;
D, grouting parameter, for soft soil layer, cement grout proportioning selects 10%, for the service channel of normal buried depth (buried depth≤20m), controls 0.4~0.5MPa of grouting pressure during slip casting, if service channel buried depth it is relatively deep (20m < buried depths≤ When 40m), grouting pressure is increased to 0.8~1.0Mpa, it is ensured that slurries diffusion is uniform, control slip casting radius is in 1.8m~2.0m;Note The control of slurry amount is according to undisturbed soil space when boring procedure soil erosion amount, and slurries finally fill the space of undisturbed soil 50%~60% Conveniently;
E, rotation Grouting Pipe, it is ensured that cement mortar is sufficiently mixed uniformly with soil, and slip casting is suppressed after finishing to Grouting Pipe, row Except unnecessary slurries, then feed pipe is disposed to be used as follow-up freezing pipe in Grouting Pipe, and with sponge or foamed plastic plugging hole Mouthful, leaked outside to prevent slurries;
F, mobile drill are to next hole position, and hole position is drilled with is drilled method, and repeat step b-e using interval, until all notes Slurry hole slip casting is finished;
G, drilling sequences, are preferentially drilled with to contact channel bottom hole position, then to hole position at the top of service channel, finally For service channel both sides hole position, service channel both sides hole position is drilled with can be while carry out;
H, do not make grouting hole and directly arrange freezing pipe, sequence of construction is:Locating holes and orifice tube installation → aperture are close Seal apparatus installation → drilling → measurement → blind hole bottom → bulge test.
Refrigeration system is freezed in i, installation, arrangement thermometer hole, relief hole, connecting line, installs heat-preserving equipment, test instrumentation, Dissolve calcium chloride and fluorine oiling is filled to unit;
J, treat to conserve 14 days after the completion of last hole slip casting, start frozen construction, keep minimum brine temp -28~- 30 DEG C, until design frozen region reinforces and completed.
Beneficial effect
This reinforced with slip casting freezing pipe freezes the construction method that service channel suppresses frozen swell and melt settlement, compared to existing work Method, has the advantages that:
1st, it is workable all with current existing engineering machinery;
2nd, engineering with artificial freezing method further enhances the intensity of the soil body on the basis of soil cement method for strengthening, is added the soil body Gu, the enhancing of impervious and self-stability ability;
3rd, service channel stratum sealing strengthens, and can effectively control seepage action of ground water, reduces high water head pressure influence, increase Later stage excavates the security constructed;
4th, soil cement stratum consolidation can effectively suppress the thaw collapse of surrounding frozen ground and its to surrounding building, structures Influence;
5th, cement soil improvement is carried out in advance, it is to avoid the later stage does not allow to cause slip casting not in place, not in time because of condition, causes Soft soil layer UNICOM road produces differential settlement, problems of crack with tunnel structure during runing, and strengthens later stage supplement Slip casting controllability and reduction slip casting cycle in later stage, cement usage amount can be saved, reduce engineering time and manpower, machine cost.
Brief description of the drawings
Fig. 1 is slip casting freezing pipe schematic diagram,
Fig. 2 be the reinforcing of service channel soil cement order and stabilization zone schematic diagram,
Reference:I-Grouting Pipe, II-feed pipe, III-drill bit, IV-check valve, V-service channel external boundary VI-freeze hole position (43~54) VII-slip casting and freeze hole position (1~42) VIII-drilling sequences number (1~54).
Embodiment
Embodiment 1:A kind of slip casting freezing pipe
Ningbo Metro Connection Passage, it is plain fill, silty sand ground, silty clay from top to down that geology where it rises on ground Layer, the stratum of shield crossing is mainly silty clay layer.Service channel buried depth 27.6m, reinforcing engineering uses soil cement reinforcing+water Flat freezing process joint reinforcement.According to design requirement, service channel reinforcement depth is 8.5m.
1st, a kind of slip casting freezing pipe, length is 8.5m, it is characterised in that the slip casting freezing pipe is by Grouting Pipe I and feed pipe II Composition, wherein Grouting Pipe I is made up of 6 sections, and Section 1 pipe end is equipped with drill bit III, and a check valve IV is respectively arranged in pipe shaft both sides;Feed flow Pipe II is made up of two steel pipe cross welds.
2nd, described a kind of slip casting freezing pipe, it is characterised in that described Grouting Pipe I is that Φ 89 × 8mm, 20# low-carbons are seamless Steel pipe, Section 1 length is 1m, and follow-up each section length is 1.5m.
3rd, described a kind of slip casting freezing pipe, it is characterised in that described feed pipe II be Φ 45 × 3mm, 20# low-carbons without Stitch on steel pipe, one of length of steel pipe 8.0m, another length of steel pipe 0.5m, the one side for being welded on 8m steel pipes front end.
Embodiment 2:A kind of slip casting freezing pipe
No. 3 line service channels of Suzhou subway, it is plain fill, silty clay from top to down that geology where it rises on ground Layer, flour sand alternation of bed, Extra-fine sand.The stratum of shield crossing is mainly fine sand layer.Service channel buried depth 15.2m, reinforcing engineering + horizontal freezing joint reinforcement is reinforced using soil cement.According to design requirement, service channel reinforcement depth is 4m.
A kind of slip casting freezing pipe, length is respectively 4m, it is characterised in that the slip casting freezing pipe is by Grouting Pipe I and feed pipe II Composition, wherein Grouting Pipe I is made up of 3 sections, and Section 1 pipe end is equipped with drill bit III, and a check valve IV is respectively arranged in pipe shaft both sides;Feed flow Pipe II is made up of two steel pipe cross welds.
2nd, described a kind of slip casting freezing pipe, it is characterised in that described Grouting Pipe I is that Φ 89 × 8mm, 20# low-carbons are seamless Steel pipe, Section 1 length is 1m, and follow-up each length is 1.5m.
3rd, described a kind of slip casting freezing pipe, it is characterised in that described feed pipe II be Φ 45 × 3mm, 20# low-carbons without Stitch on steel pipe, one of length of steel pipe 3.5m, another length of steel pipe 0.5m, the one side for being welded on 3.5m steel pipes front end.
Embodiment 3:A kind of slip casting freezing pipe
Ningbo subway service channel, it is plain fill from top to down that geology where it rises on ground, and silty clay layer, powder is thin Layer of sand.The stratum of shield crossing is mainly fine sand layer.Service channel buried depth 21.8m, reinforcing engineering uses soil cement reinforcing+water Flat freezing process joint reinforcement.According to design requirement, service channel reinforcement depth is 7m.
A kind of slip casting freezing pipe, length is respectively 7m, it is characterised in that the slip casting freezing pipe is by Grouting Pipe I and feed pipe II Composition, wherein Grouting Pipe I is made up of 5 sections, and Section 1 pipe end is equipped with drill bit III, and a check valve IV is respectively arranged in pipe shaft both sides;Feed flow Pipe II is made up of two steel pipe cross welds.
2nd, described a kind of slip casting freezing pipe, it is characterised in that described Grouting Pipe I is that Φ 89 × 8mm, 20# low-carbons are seamless Steel pipe, Section 1 length is 1m, and follow-up each section length is 1.5m.
3rd, described a kind of slip casting freezing pipe, it is characterised in that described feed pipe II be Φ 45 × 3mm, 20# low-carbons without Stitch on steel pipe, one of length of steel pipe 6.5m, another length of steel pipe 0.5m, the one side for being welded on 6.5m steel pipes front end.
Embodiment 4:A kind of reinforced with slip casting freezing pipe freezes the construction method that service channel suppresses frozen swell and melt settlement
Ningbo Metro Connection Passage, it is plain fill, silty sand ground, silty clay from top to down that geology where it rises on ground Layer, the stratum of shield crossing is mainly silty clay layer.Service channel buried depth 27.6m, reinforcing engineering uses soil cement reinforcing+water Flat freezing process joint reinforcement.According to design requirement, service channel reinforcement depth is 8.5m.
A kind of reinforced with slip casting freezing pipe freezes the construction method that service channel suppresses frozen swell and melt settlement, and its construction procedure is such as Under:
1st, barrier in preparation of construction, cleaning tunnel, builds construction operation platform;Supply line is connected, to meet drilling Freezing system and excavation construct power supply in construction, tunnel;Lay pipeline to Freezing Method for Cross-passage Construction working face, drilled for hole position and Freeze operating to supply water and blowdown;Check cement quality, rig service behaviour and the intact degree of measuring equipment;
2nd, locating holes, perforate inclination angle and azimuth are determined with theodolite and compass, accurately make perforate hole position, direction, And help to layout in tunnel two, using secondary hole opening technology, and verified with stringing method, control hole position direction;Rig is in place, selects MD-60 rigs, adjustment rig position, control mode 2KN/m, thrust 17KN carries out No. 1 hole position and is drilled with;
3rd, Grouting Pipe is pierced to No. 1 hole position and carries out slip casting, Grouting Pipe selects Φ 89 × 8mm, 20# low-carbon seamless steel pipes, the One section slip casting length of tube is 1m, and pipe end installs check valve slip casting, and check valve opens pressure between 0.3~0.5MPa, according to design Depth 8.5m, follow-up each section slip casting pipe range 1.5m, section by section slip casting;
4th, cement grout proportioning selects 10%, and 0.8~1.0MPa of grouting pressure is controlled during slip casting, controls slip casting radius In 2.0m, grouting amount control is according to undisturbed soil space when boring procedure soil erosion amount, and slurries finally fill undisturbed soil 50% ~60% space;
5th, Grouting Pipe is rotated, it is ensured that cement mortar is sufficiently mixed uniformly with soil, and slip casting is finished disposes feed pipe in Grouting Pipe Used as follow-up freezing pipe, feed pipe uses Φ 45 × 3mm, 20# low-carbon seamless steel pipes, with sponge or foamed plastic plugging hole Mouthful, leaked outside to prevent slurries;
6th, mobile drill is to No. 2 hole positions, and hole position, which is drilled with, drills that (detailed bored grouting order is shown in Fig. 2 institutes to method using interval Show), repeat step 2-6 is completed until soil cement reinforcing area is constructed;
7th, drilling sequences, are preferentially drilled with to contact channel bottom hole position (hole number 1~hole number 17), then logical to getting in touch with Hole position (hole number 18~hole number 34), is finally service channel both sides hole position (hole number 35~hole number 42), service channel two at the top of road Side opening position is drilled with can be while carry out;
8th, freezing pipe is arranged, is designed, freezed between hole count 54, each hole position in service channel top and bottom according to freezing curtain Away from 0.7m, each side hole position spacing 0.6m;Injected hole use is not done in hole number 43~hole number 54, is mounted directly freezing pipe;Construction Sequentially it is:Examination is suppressed in locating holes and orifice tube installation → port seal installation → drilling → measurement → blind hole bottom → Test.
9th, install and freeze refrigeration system, refrigeration system can be synchronously installed during bored grouting, save the time;Freezing Station Interior equipment mainly includes II type Screw chillers of YSLGF300 2 (standby one), and its maximum cooling capacity is about 87500kcal/h, Freeze unit motor general power 110kw;IS150-125-250 salt water circulating pumps 2 (1 standby), flow 200m3/h, lift 30m, motor general power 30kw;IS150-125-250 cooling water circulating pumps 1, flow 200m3/h, lift 30m, motor total work Rate 30kw;Cooling tower 2, motor general power 6kw;Brine tank one, volume 6m3;Afterwards connecting line, install heat-preserving equipment with Test instrumentation, salt water conduit tube and collection liquid distribution pipe use Φ 159 × 5mm seamless steel pipes, and Φ is selected in collection, liquid distribution pipe and goat's horn connection 1.5 " high-pressure rubber pipes;The cooling water pipe welded tubes of Φ 5 ";Freezing plate is processed with the pipes of Φ 1.5 ";Temperature is installed on refrigerator water inlet pipe and water outlet pipe Sensor is spent, pressure, temperature sensor and control valve are installed going, on the Brine Pipe of loop, flow is installed in Brine Pipe outlet Meter, liquid level sensor is installed in brine tank;Two, valve is installed between brine distributing ring and frigo, so as to control freezing device salt solution Flow;Vent valve is installed in the eminence of saline line;Check valve is installed on the salt water conduit tube of outlet;Salt solution and clear water pipeline are pressure-resistant Respectively 0.7Mpa and 0.3MPA;Treat all to install, dissolve calcium chloride and fluorine oiling is filled to unit, salt solution proportion is 1.26 ~1.27;
10th, frozen construction is started after last injected hole is conserved 14 days, positive freeze-off time is 40 days, is kept minimum - 30 DEG C~-28 DEG C of brine temp, is completed until frozen region is reinforced;Then excavate and freeze the stage into maintenance, keep salt water temperature Degree is at -28 DEG C or so, until service channel main structure construction is finished.
Embodiment 5:A kind of reinforced with slip casting freezing pipe freezes the construction method that service channel suppresses frozen swell and melt settlement
No. 3 line service channels of Suzhou subway, it is plain fill, silty clay from top to down that geology where it rises on ground Layer, flour sand alternation of bed, Extra-fine sand.The stratum of shield crossing is mainly fine sand layer.Service channel buried depth 15.2m, reinforcing engineering + horizontal freezing joint reinforcement is reinforced using soil cement.According to design requirement, service channel reinforcement depth is 4.0m.
A kind of reinforced with slip casting freezing pipe freezes the construction method that service channel suppresses frozen swell and melt settlement, and its construction procedure is such as Under:
1st, barrier in preparation of construction, cleaning tunnel, builds construction operation platform;Supply line is connected, to meet drilling Freezing system and excavation construct power supply in construction, tunnel;Lay pipeline to Freezing Method for Cross-passage Construction working face, drilled for hole position and Freeze operating to supply water and blowdown;Check cement quality, rig service behaviour and the intact degree of measuring equipment;
2nd, locating holes, perforate inclination angle and azimuth are determined with theodolite and compass, accurately make perforate hole position, direction, And help to layout in tunnel two, using secondary hole opening technology, and verified with stringing method, control hole position direction;Rig is in place, selects MD-60 rigs, adjustment rig position, control mode 2KN/m, thrust 17KN carries out No. 1 hole position and is drilled with;
3rd, Grouting Pipe is pierced to No. 1 hole position and carries out slip casting, Grouting Pipe selects Φ 89 × 8mm, 20# low-carbon seamless steel pipes, the One section slip casting length of tube is 1m, and pipe end installs check valve slip casting, and check valve opens pressure between 0.3~0.5MPa, according to design Depth 4.0m, follow-up each section slip casting pipe range 1.5m, section by section slip casting;
4th, cement grout proportioning selects 10%, and 0.4~0.5MPa of grouting pressure is controlled during slip casting, controls slip casting radius For 1.8m, grouting amount control is according to undisturbed soil space when boring procedure soil erosion amount, and slurries finally fill undisturbed soil 50% ~60% space;
5th, Grouting Pipe is rotated, it is ensured that cement mortar is sufficiently mixed uniformly with soil, and slip casting is finished disposes feed pipe in Grouting Pipe Used as follow-up freezing pipe, feed pipe uses Φ 45 × 3mm, 20# low-carbon seamless steel pipes, with sponge or foamed plastic plugging hole Mouthful, leaked outside to prevent slurries;
6th, mobile drill is to No. 2 hole positions, and hole position, which is drilled with, drills that (detailed bored grouting order is shown in Fig. 2 institutes to method using interval Show), repeat step 2-6 is completed until soil cement reinforcing area is constructed;
7th, drilling sequences, are preferentially drilled with to contact channel bottom hole position (hole number 1~hole number 17), then logical to getting in touch with Hole position (hole number 18~hole number 34), is finally service channel both sides hole position (hole number 35~hole number 42), service channel two at the top of road Side opening position is drilled with can be while carry out;
8th, freezing pipe is arranged, is designed, freezed between hole count 54, each hole position in service channel top and bottom according to freezing curtain Away from 0.7m, each side hole position spacing 0.6m;Injected hole use is not done in hole number 43~hole number 54, is mounted directly freezing pipe;Construction Sequentially it is:Examination is suppressed in locating holes and orifice tube installation → port seal installation → drilling → measurement → blind hole bottom → Test.
9th, install and freeze refrigeration system, refrigeration system can be synchronously installed during bored grouting, save the time;Freezing Station Interior equipment mainly includes II type Screw chillers of YSLGF300 2 (standby one), and its maximum cooling capacity is about 84500kcal/h, Freeze unit motor general power 110kw;IS150-125-250 salt water circulating pumps 2 (1 standby), flow 200m3/h, lift 30m, motor general power 30kw;IS150-125-250 cooling water circulating pumps 1, flow 200m3/h, lift 30m, motor total work Rate 30kw;Cooling tower 2, motor general power 8kw;Brine tank one, volume 6m3;Afterwards connecting line, install heat-preserving equipment with Test instrumentation, salt water conduit tube and collection liquid distribution pipe use Φ 159 × 5mm seamless steel pipes, and Φ is selected in collection, liquid distribution pipe and goat's horn connection 1.5 " high-pressure rubber pipes;The cooling water pipe welded tubes of Φ 5 ";Freezing plate is processed with the pipes of Φ 1.5 ";Temperature is installed on refrigerator water inlet pipe and water outlet pipe Sensor is spent, pressure, temperature sensor and control valve are installed going, on the Brine Pipe of loop, flow is installed in Brine Pipe outlet Meter, liquid level sensor is installed in brine tank;Two, valve is installed between brine distributing ring and frigo, so as to control freezing device salt solution Flow;Vent valve is installed in the eminence of saline line;Check valve is installed on the salt water conduit tube of outlet;Salt solution and clear water pipeline are pressure-resistant Respectively 0.7Mpa and 0.3MPA;Treat all to install, dissolve calcium chloride and fluorine oiling is filled to unit, from N46 refrigerators Oil, R22 refrigerants, saline solution proportion is 1.27;
10th, frozen construction is started after last injected hole is conserved 14 days, positive freeze-off time is 40 days, is kept minimum - 30 DEG C~-28 DEG C of brine temp, is completed until frozen region is reinforced;Then excavate and freeze the stage into maintenance, keep salt water temperature Degree is at -28 DEG C or so, until service channel main structure construction is finished.
Embodiment 6:A kind of reinforced with slip casting freezing pipe freezes the construction method that service channel suppresses frozen swell and melt settlement
Ningbo subway service channel, it is plain fill from top to down that geology where it rises on ground, and silty clay layer, powder is thin Layer of sand.The stratum of shield crossing is mainly fine sand layer.Service channel buried depth 21.8m, reinforcing engineering using soil cement reinforce+ Horizontal freezing joint reinforcement.According to design requirement, service channel reinforcement depth is 7m.
A kind of reinforced with slip casting freezing pipe freezes the construction method that service channel suppresses frozen swell and melt settlement, and its construction procedure is such as Under:
1st, barrier in preparation of construction, cleaning tunnel, builds construction operation platform;Supply line is connected, to meet drilling Freezing system and excavation construct power supply in construction, tunnel;Lay pipeline to Freezing Method for Cross-passage Construction working face, drilled for hole position and Freeze operating to supply water and blowdown;Check cement quality, rig service behaviour and the intact degree of measuring equipment;
2nd, locating holes, perforate inclination angle and azimuth are determined with theodolite and compass, accurately make perforate hole position, direction, And help to layout in tunnel two, using secondary hole opening technology, and verified with stringing method, control hole position direction;Rig is in place, selects MD-60 rigs, adjustment rig position, control mode 2KN/m, thrust 17KN carries out No. 1 hole position and is drilled with;
3rd, Grouting Pipe is pierced to No. 1 hole position and carries out slip casting, Grouting Pipe selects Φ 89 × 8mm, 20# low-carbon seamless steel pipes, the One section slip casting length of tube is 1m, and pipe end installs check valve slip casting, and check valve opens pressure between 0.3~0.5MPa, according to design Depth 7.0m, follow-up each section slip casting length of tube is 1.5m, section by section slip casting;
4th, cement grout proportioning selects 10%, and 0.8~0.9MPa of grouting pressure is controlled during slip casting, controls slip casting radius For 1.9m, grouting amount control is according to undisturbed soil space when boring procedure soil erosion amount, and slurries finally fill undisturbed soil 50% ~60% space;
5th, Grouting Pipe is rotated, it is ensured that cement mortar is sufficiently mixed uniformly with soil, and slip casting is finished disposes feed pipe in Grouting Pipe Used as follow-up freezing pipe, feed pipe uses Φ 45 × 3mm, 20# low-carbon seamless steel pipes, with sponge or foamed plastic plugging hole Mouthful, leaked outside to prevent slurries;
6th, mobile drill is to No. 2 hole positions, and hole position, which is drilled with, drills that (detailed bored grouting order is shown in Fig. 2 institutes to method using interval Show), repeat step 2-6 is completed until soil cement reinforcing area is constructed;
7th, drilling sequences, are preferentially drilled with to contact channel bottom hole position (hole number 1~hole number 17), then logical to getting in touch with Hole position (hole number 18~hole number 34), is finally service channel both sides hole position (hole number 35~hole number 42), service channel two at the top of road Side opening position is drilled with can be while carry out;
8th, freezing pipe is arranged, is designed, freezed between hole count 54, each hole position in service channel top and bottom according to freezing curtain Away from 0.7m, each side hole position spacing 0.6m;Injected hole use is not done in hole number 43~hole number 54, is mounted directly freezing pipe;Construction Sequentially it is:Examination is suppressed in locating holes and orifice tube installation → port seal installation → drilling → measurement → blind hole bottom → Test.
9th, install and freeze refrigeration system, refrigeration system can be synchronously installed during bored grouting, save the time;Freezing Station Interior equipment mainly includes II type Screw chillers of YSLGF300 2 (standby one), and its maximum cooling capacity is about 84500kcal/h, Freeze unit motor general power 110kw;IS150-125-250 salt water circulating pumps 2 (1 standby), flow 200m3/h, lift 30m, motor general power 30kw;IS150-125-250 cooling water circulating pumps 1, flow 200m3/h, lift 30m, motor total work Rate 30kw;Cooling tower 2, motor general power 8kw;Brine tank one, volume 6m3;Afterwards connecting line, install heat-preserving equipment With test instrumentation, salt water conduit tube and collection liquid distribution pipe use Φ 159 × 5mm seamless steel pipes, and collection, liquid distribution pipe and goat's horn connection are selected The high-pressure rubber pipes of Φ 1.5 ";The cooling water pipe welded tubes of Φ 5 ";Freezing plate is processed with the pipes of Φ 1.5 ";Installed on refrigerator water inlet pipe and water outlet pipe Temperature sensor, installs pressure, temperature sensor and control valve going, on the Brine Pipe of loop, stream is installed in Brine Pipe outlet Gauge, liquid level sensor is installed in brine tank;Two, valve is installed between brine distributing ring and frigo, so as to control freezing device salt Water-carrying capacity;Vent valve is installed in the eminence of saline line;Check valve is installed on the salt water conduit tube of outlet;Salt solution and clear water pipeline are resistance to Pressure is respectively 0.7Mpa and 0.3MPA;Treat all to install, dissolve calcium chloride and fluorine oiling is filled to unit, freezed from N46 Machine oil, R22 refrigerants, saline solution proportion is 1.27;
10th, frozen construction is started after last injected hole is conserved 14 days, positive freeze-off time is 40 days, is kept minimum - 30 DEG C~-28 DEG C of brine temp, is completed until frozen region is reinforced;Then excavate and freeze the stage into maintenance, keep salt water temperature Degree is at -28 DEG C or so, until service channel main structure construction is finished.

Claims (1)

  1. Freeze the construction method that service channel suppresses frozen swell and melt settlement 1. being reinforced with slip casting freezing pipe, it is characterised in that described slip casting Freezing pipe is by Grouting Pipe(Ⅰ)And feed pipe(Ⅱ)Composition;Described Grouting Pipe(Ⅰ)It is made up of 3 ~ 6 sections, Section 1 pipe end is equipped with brill Head(Ⅲ), a check valve is respectively arranged in pipe shaft both sides(Ⅳ), Grouting Pipe(Ⅰ)For 89 × 8mm of Φ, 20# low-carbon seamless steel pipes, the 1st Section length is 1m, and the 2nd ~ 6 section length is 1.5m;Described feed pipe(Ⅱ)For 45 × 3mm of Φ, 20# low-carbon seamless steel pipes, by two Individual steel pipe cross weld is made, 2 ~ 8m of one of steel pipe length, and the long 0.5m of another steel pipe is welded on 2~8m steel pipes front end On one side;Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement, it is characterised in that construction step It is rapid as follows:
    A, preparation of construction:Barrier in tunnel is cleared up, construction operation platform is built;Connect supply line, with meet drilling construction, Freezing system and excavation construct the demand of power supply in tunnel;Pipeline is laid to Freezing Method for Cross-passage Construction working face, is drilled for hole position And freeze operating water supply and blowdown;Check cement quality, rig service behaviour and the intact degree of measuring equipment;
    B, locating holes are to take secondary hole opening technology, according to hole position position, deflection, depth that rig is in place, are bored from MD-60 Machine, control mode 2KN/m, thrust 17KN carries out hole position and is drilled with;
    After c, perforate are finished, pre-pouring grout hole position is pierced Grouting Pipe carry out slip casting, Grouting Pipe from Φ 89 × 8mm, 20# low-carbons without Steel pipe is stitched, Section 1 slip casting length of tube is 1m, and follow-up Grouting Pipe is using 1.5m as a section, and Section 1 Grouting Pipe pipe end and pipe shaft install single To valve slip casting, check valve opens pressure between 0.3 ~ 0.5MPa, according to projected depth slip casting section by section;
    D, grouting parameter:For soft soil layer, cement grout proportioning selects 10%, for the service channel of normal buried depth, i.e. buried depth ≤ 20m, during slip casting control 0.4 ~ 0.5MPa of grouting pressure, for the service channel that buried depth is deeper, i.e. 20m < buried depths≤ During 40m, grouting pressure is increased to 0.8 ~ 1.0MPa, it is ensured that slurries diffusion is uniform, control slip casting radius is in 1.8m-2.0m;Slip casting Amount control is according to undisturbed soil hole when boring procedure soil erosion amount, until slurries amount finally fills the 50% ~ 60% of undisturbed soil Hole;
    E, rotation Grouting Pipe, it is ensured that cement mortar is sufficiently mixed uniformly with soil, and slip casting is suppressed after finishing to Grouting Pipe, is excluded many Remaining slurry liquid, feed pipe formation slip casting freezing pipe is then disposed in Grouting Pipe and is subsequently being used as freezing pipe, is sealed using sponge Plug-hole mouthful, leaks outside to prevent slurries;
    F, mobile drill are to next hole position, and hole position is drilled with is drilled method, and repeat step b ~ e using interval, until all slip castings Hole slip casting is finished;
    G, drilling sequences:It is preferential that contact channel bottom hole position is drilled with, it is finally connection then to hole position at the top of service channel Network passage both sides hole position, service channel both sides hole position is drilled with to be carried out simultaneously;
    H, do not make grouting hole and directly arrange freezing pipe, sequence of construction is:Locating holes and orifice tube installation → orifice sealing dress Put installation → drilling → measurement → blind hole bottom → bulge test;
    I, installation freeze refrigeration system, and arrangement thermometer hole, relief hole, connecting line install heat-preserving equipment, test instrumentation, dissolving Calcium chloride and unit is filled fluorine oiling;
    J, treat to conserve 14 days after the completion of last hole slip casting, start frozen construction, keep brine temp -28~-30 DEG C, until Design frozen region and reinforce completion.
CN201510407722.3A 2015-07-13 2015-07-13 Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement Active CN104963334B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510407722.3A CN104963334B (en) 2015-07-13 2015-07-13 Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510407722.3A CN104963334B (en) 2015-07-13 2015-07-13 Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement

Publications (2)

Publication Number Publication Date
CN104963334A CN104963334A (en) 2015-10-07
CN104963334B true CN104963334B (en) 2017-10-13

Family

ID=54217407

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510407722.3A Active CN104963334B (en) 2015-07-13 2015-07-13 Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement

Country Status (1)

Country Link
CN (1) CN104963334B (en)

Families Citing this family (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107085085B (en) * 2017-03-06 2018-04-17 安徽理工大学 Hydro-thermal power THM coupling manual pipe jacking disturbed soil grouting test device and method
CN107034874B (en) * 2017-03-06 2019-01-25 安徽理工大学 Double-screw type slip casting type freezing plant and construction method
FR3066204B1 (en) 2017-05-11 2020-12-04 Vinci Construction METHOD AND DEVICE FOR FREEZING A SOLID SOIL
CN108179740B (en) * 2017-12-29 2019-12-10 湖北工业大学 Construction method for filling pile through karst cave
CN108412432A (en) * 2018-03-11 2018-08-17 吕琳 Drilling rod is freezed in a kind of novel well lane engineering
CN108798677A (en) * 2018-06-08 2018-11-13 中煤隧道工程有限公司 A kind of Metro Connection Passage method for rapidly thawing
CN109296371A (en) * 2018-11-29 2019-02-01 南京林业大学 MJS method and horizontal freezing joint reinforcement pressure-bearing rich water arenaceous stratum overlap the system and its construction method that section is worn under station
CN110130316A (en) * 2019-05-13 2019-08-16 南京林业大学 The method of thaw collapse after service channel bottom pre-pouring grout system and control freezing construction
CN110820786B (en) * 2019-11-19 2021-04-23 青海大学 Deep foundation structure for preventing freeze-thaw diseases in permafrost region
CN111022059A (en) * 2019-12-24 2020-04-17 中交路桥建设有限公司 Freezing hole construction process
CN110984239B (en) * 2020-01-06 2021-08-24 海南大学 Local reinforcement treatment method for preventing garbage factory seepage
CN112726684B (en) * 2020-12-25 2022-05-13 中国矿业大学 Method for inhibiting frost heaving deformation of fiber-modified stratum
CN113774892B (en) * 2021-09-16 2022-07-29 中国矿业大学 Control method for freezing, swelling and thawing-sinking of municipal engineering
CN114109399A (en) * 2021-12-01 2022-03-01 中国铁建大桥工程局集团有限公司 Freezing construction method for limestone stratum
CN114135302B (en) * 2021-12-09 2024-03-22 中交天和机械设备制造有限公司 Grouting control method and device for shield tunneling machine
CN114934776B (en) * 2022-05-28 2023-04-07 中铁一局集团(广州)建设工程有限公司 Construction method for inhibiting frost heaving and thawing sinking of water-rich geology
CN115095329B (en) * 2022-06-06 2023-04-18 浙江大学 Advanced freezing device and method for shield tunnel

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3514554B2 (en) * 1995-06-13 2004-03-31 株式会社精研 Freezing and expansion measures
JP3500464B2 (en) * 1999-10-27 2004-02-23 強化土エンジニヤリング株式会社 Ground injection method
CN102979083A (en) * 2012-11-08 2013-03-20 沈阳信达信息科技有限公司 Liquid nitrogen freezing device
CN103015402B (en) * 2012-12-27 2014-08-13 南京林业大学 Construction method for inhibiting frost heaving and thaw collapse of horizontally frozen end through cement-soil reinforcement method
CN203145846U (en) * 2013-01-06 2013-08-21 李立国 Grouting freezing tube with traction valve control
CN203022003U (en) * 2013-01-06 2013-06-26 杨聪 Grouting freezing pipe with rotary control hole
CN204780857U (en) * 2015-07-13 2015-11-18 南京林业大学 Pipe is freezed in slip casting

Also Published As

Publication number Publication date
CN104963334A (en) 2015-10-07

Similar Documents

Publication Publication Date Title
CN104963334B (en) Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement
CN103015402B (en) Construction method for inhibiting frost heaving and thaw collapse of horizontally frozen end through cement-soil reinforcement method
CN107676097B (en) A kind of high hydraulic pressure soft soil layer HFE composite shield originating method
CN105909260B (en) Subway station water stop structure for protecting groundwater environment and construction method thereof
CN105908765B (en) For protecting the open trench tunnel water sealing structure and construction method of groundwater environment
CN109208637A (en) Increase the construction method of open-cut station newly on the basis of existing tunnel
CN104806253B (en) A kind of construction method punched between rectangular top pipe passage
CN111119940B (en) Grouting construction treatment method
CN101463724A (en) Construction method for connection passage by double-row hole horizontal freezing method
CN106121686B (en) Underground excavation tunnel water stop structure for protecting groundwater environment and construction method thereof
CN102619522A (en) Construction method for subway contact passage
CN104074525A (en) Full-sectional grouting, rectangular horizontal freezing and pipe roof combined reinforcing structure and method
CN205172598U (en) Pipe curtain spouts a supporting construction soon
CN105804761A (en) Construction method suitable for making shield penetrate through building in close range on liquefied sandy soil stratum
CN111593726A (en) Joint reinforcement method for underground tunnel penetrating sensitive pipeline of water-rich stratum and butt joint of existing structure MJS + artificial freezing
CN205975649U (en) Freezing pipe curtain steel pipe supporting construction
CN107119669A (en) For shield, the pre-pouring grout consolidated subsoil method in house is worn in side in water-rich sand layer
CN101418567A (en) Protective cutting construction method for tunnel segment
CN110030007B (en) Shield horizontal freezing receiving construction method
CN107034874B (en) Double-screw type slip casting type freezing plant and construction method
CN108071400A (en) Horizontal freezing consolidation combines shield driving construction method with steel jacket box
CN108843328A (en) A kind of Metro Connection Passage excavation construction support construction method
CN109296371A (en) MJS method and horizontal freezing joint reinforcement pressure-bearing rich water arenaceous stratum overlap the system and its construction method that section is worn under station
CN105064335A (en) Ultrahigh pressure rotary jet grouting method suitable for sandy cobble stratum shield end well reinforcement
CN108005662B (en) A kind of processing method of underground water seal cave depot storage cavern area geology crushed zone

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20151007

Assignee: Jiangsu Construction Engineering Consulting Co., Ltd.

Assignor: Nanjing Forestry University

Contract record no.: X2019320000076

Denomination of invention: Construction method for utilizing grouting freezing pipe to reinforce and freeze contact passage to restrain frost heaving and thaw collapsing

Granted publication date: 20171013

License type: Common License

Record date: 20190923

Application publication date: 20151007

Assignee: Jiangsu Rong Rui Construction Technology Co., Ltd.

Assignor: Nanjing Forestry University

Contract record no.: X2019320000077

Denomination of invention: Construction method for utilizing grouting freezing pipe to reinforce and freeze contact passage to restrain frost heaving and thaw collapsing

Granted publication date: 20171013

License type: Common License

Record date: 20190923

Application publication date: 20151007

Assignee: Nanjing Soil Instrument Co., Ltd.

Assignor: Nanjing Forestry University

Contract record no.: X2019320000075

Denomination of invention: Construction method for utilizing grouting freezing pipe to reinforce and freeze contact passage to restrain frost heaving and thaw collapsing

Granted publication date: 20171013

License type: Common License

Record date: 20190923

EE01 Entry into force of recordation of patent licensing contract