CN108005662B - A kind of processing method of underground water seal cave depot storage cavern area geology crushed zone - Google Patents

A kind of processing method of underground water seal cave depot storage cavern area geology crushed zone Download PDF

Info

Publication number
CN108005662B
CN108005662B CN201711295807.2A CN201711295807A CN108005662B CN 108005662 B CN108005662 B CN 108005662B CN 201711295807 A CN201711295807 A CN 201711295807A CN 108005662 B CN108005662 B CN 108005662B
Authority
CN
China
Prior art keywords
crushed zone
geology
slip casting
grouting
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201711295807.2A
Other languages
Chinese (zh)
Other versions
CN108005662A (en
Inventor
曹洋兵
詹淦基
黄真萍
陈玉华
邱冬冬
陈俊熙
程志伟
林其隆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuzhou University
Original Assignee
Fuzhou University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuzhou University filed Critical Fuzhou University
Priority to CN201711295807.2A priority Critical patent/CN108005662B/en
Publication of CN108005662A publication Critical patent/CN108005662A/en
Application granted granted Critical
Publication of CN108005662B publication Critical patent/CN108005662B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/021Grouting with inorganic components, e.g. cement

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Inorganic Chemistry (AREA)
  • Chemical & Material Sciences (AREA)
  • Civil Engineering (AREA)
  • Soil Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The present invention relates to a kind of processing methods of underground water seal cave depot storage cavern area geology crushed zone, comprising the following steps: determines geology crushed zone feature in conjunction with geology and exploration hole data;It determines grouting serous fluid, technique and termination criteria, pre-pouring grout is carried out to geology crushed zone and its periphery Rock And Soil by injected hole, water-stop curtain is formed and reinforces crushed zone, carry out detection of grouting effects;After Blasting Excavation to geology crushed zone exposure, cavern periphery a certain range crushed zone Rock And Soil is excavated and changed and fills out concrete;Slip casting is carried out to the contact surface between concrete and rock mass, between concrete and concrete, slurries identical with pre-pouring grout, technique, termination criteria and effect detection standard can be used;The surrouding rock deformation of matter crushed zone surface layer setting in situ monitors after the completion of support construction, and judges whether to need to enhance bolt-spary supports.The present invention can solve the water blockoff of storage cavern area geology crushed zone and reinforce problem, and step is simple, easy construction, and investment cost saves, short processing time.

Description

A kind of processing method of underground water seal cave depot storage cavern area geology crushed zone
Technical field
The present invention relates to geology crushed zone processing technology fields in underground water seal cave depot technology, underground engineering, especially relate to And a kind of processing method of underground water seal cave depot storage cavern area geology crushed zone.
Background technique
Tomography and crushed zone are common bad geological phenomenons during cavern excavation.In most cases, fault disruption zone Band has on physico mechanical characteristic there are low-intensity, the features such as easily-deformable, water penetration is big, water-resistance is poor with its two sides rock mass Significant difference.For underground water seal cave depot storage cavern area, mainly there is water curtain system water in the technical issues of being caused by crushed zone Effect reduction, oil gas are sealed along crushed zone leakage, crushed zone Rock And Soil collapsing etc..It is then desired to which a kind of be directed to underground water seal cave depot The processing method of storage cavern area geology crushed zone.
The processing method common to geology crushed zone has freezing, high-pressure rotary jet grouting pile method, slip casting method both at home and abroad at present, later It is subject to supporting by applying anchor pole, gunite concrete or the prefabricated concrete lining of placement etc..1. freezing is to utilize artificial system Refrigeration technique makes the water in crushed zone build-up ice, and Jiang Yan and water become whole.To increase crushed zone strength and stability, isolation ground It is lauched, to carry out underground engineering digging operation.Freezing is a kind of temperature pier technology, generally requires a large amount of power equipments simultaneously It is restricted vulnerable to external condition.2. high-pressure rotary jet grouting pile method is to be mixed on cement slurry penetrating stratum with Rock And Soil with the nozzle of high-pressure rotary It closes, forms the cement stabilization body of lap connection.High-pressure rotary jet grouting pile method requires height to mechanical equipment and operative skill, and easily causes useless The unordered discharge of slurries.3. slip casting method, is injected hole or fabricated device by drilling through, will be certain in the way of hydraulic, air pressure etc. In curable slurries injection Rock And Soil, to keep ground and grout curing rear formation whole, improve the physical mechanics of Rock And Soil Property.Slip casting method operation can be carried out, be adjusted at any time at any time and water reinforcement effect is relatively preferable.
But for underground water seal cave depot storage cavern area, above-mentioned three kinds of water reinforcement processing techniques are all infeasible, Wu Fabao Demonstrate,prove stability, permeability and the sealing requirements of geology crushed zone.The present invention passes through pre-pouring grout, excavates crushed zone and change and fill out coagulation The technical steps such as soil, contact surface slip casting, deformation monitoring, can thoroughly solve the water blockoff and reinforcement criteria of storage cavern area geology crushed zone.
Summary of the invention
It is an object of the present invention to overcome the above-mentioned drawbacks of the prior art and provide a kind of underground water seal cave depots The processing method of storage cavern area geology crushed zone, can overcome existing geology be crushed tape processing method be difficult to ensure water blockoff sealing and Stable problem is reinforced, to meet the needs of underground water seal cave depot engineering construction.
The purpose of the present invention can be achieved through the following technical solutions:
A kind of processing method of underground water seal cave depot storage cavern area geology crushed zone, comprising the following steps:
S1: building cave depot area three-dimensional geological model, and obtain the position of geology crushed zone;
S2: multiple slip casting inclined holes are drilled through on the face before the geology crushed zone position that distance is estimated and are infused in advance Slurry, the multiple slip casting inclined hole is radial towards geology crushed zone tilt distribution in center, and geology is crossed in the end of slip casting inclined hole Crushed zone certain distance;
S3: after geology crushed zone is excavated and is exposed, geology crushed zone region is excavated, formwork with pour it is mixed Solidifying soil;
S4: the interface between concrete poured to the interface between cast-in-place concrete and country rock, segmentation carries out contact note Slurry;
S5: it constructs by the supporting construction that surrounding rock supporting construction design method determines, to geology crushed zone and peripheral region After the support construction of domain, country rock convergence and settlement monitoring measure is arranged in situ matter crushed zone surface layer, according to deflection Value and rate of deformation evaluation grouting consolidation effect simultaneously judge whether to enhance bolt-spary supports.
In the step S1, at the 15-30m face before the geology crushed zone position that distance is estimated, in advance Position, thickness, occurrence and the crushed zone Rock And Soil engineering properties of geology crushed zone are verified and determined to matter exploration hole.
The hole count and face area in the advance geology exploration hole are proportional, and the diameter in each advance geology exploration hole is not Less than 50mm.
If advance geology exploration hole coring, the information that evaluation obtains geology crushed zone is carried out to drilling core;If Not coring then records drilling rate, water yield, water outlet colouring information.
In the step S2, the end of slip casting inclined hole crosses geology crushed zone and is no less than 10m;The tilt distribution of slip casting inclined hole So that grouting serous fluid excavates 7-9m other than the wall of hole to pre- along cavern's radial diffusion;Grouting serous fluid dilation angle is calculated by 2-3m, and Ensure adjacent slip casting inclined hole reinforcing scope overlap joint and without slip casting blind area.
In the step S2, the method for drilling holes and late grouting includes: protrusive segmenting slip casting method, specified region reinforcing slip casting Method and the long once grouting method of full section.
The slurries of slip casting are selected according to Rock And Soil void characteristics, and the type of grouting serous fluid includes ordinary cement slurry, water Mud-bentonite slurry, superfine cement slurry and chemicals slurries.
The concentration of slurry of slip casting process converts and termination criteria are as follows:
1. during slip casting when grouting pressure remains unchanged and injection rate persistently reduces or injection rate is constant and pressure is held When of continuing rising high, do not change the ratio of mud;
2. when grouting serous fluid injection rate has reached 500L or more, and no changes have been made or change is not shown for grouting pressure and slip casting flow velocity When work, change the dense level-one ratio of mud or the thick slurry more sticky than current grouting serous fluid;
3. repeating the 2. to walk until grouting pressure reaches PsWhen+1.5MPa or when slip casting flow velocity is less than 2L/min, stablize one Stop slip casting after the section time, wherein PsIt is using hydrostatic pressure in the hole for using manometry after antipriming closing drilling.
Slip casting effect is detected after slip casting, specifically: inspection hole is additionally drilled through in slip casting region, according to inspection hole Middle water burst flow velocity judges slip casting effect:
①Q<Q1, slip casting effect is good, needs not continue to slip casting, and inspection hole is backfilled with cement slurry;
②Q1<Q<Q2, by encryption injected hole, expansion range of grouting, thick slurry is selected to re-start slip casting, slip casting is complete Cheng Hou is detected again;
③Q>Q2, drilling first seals, and after determining water burst concrete condition, detects using measures of preventing water and again;
Wherein, Q is water yield, Q1Take 0.01 L/min/m, Q2Take 0.1 L/min/m.
The step S3 specifically:
After geology crushed zone is excavated and is exposed, according to geology crushed zone steadiness, stop driving in due course;
Using construction machinery artificial or equipped with hydraulic shock destroyer, it is deep that geology crushed zone 3-5m is radially excavated along cavern Spend the Rock And Soil in range;
Using plank sheathing or steel form, along hole wall to installation template outside the geology crushed zone excavated;
Cast-in-place intensity is not less than the concrete of C25 at the geology crushed zone hollowed out, and is stirred evenly using vibrating head.
Compared with prior art, the invention has the following advantages that
(1) patent in terms of there is no underground water seal cave depot geology to be crushed tape processing method at present.The present invention by pre-pouring grout, Excavate crushed zone and change and fill out the technical steps such as concrete, contact surface slip casting, deformation monitoring, is able to satisfy storage cavern area geology crushed zone Water blockoff and reinforcement criteria solve the operation phase leakproofness and long-time stability problem of geology crushed zone.
(2) operation of the present invention step is simple, and required equipment is all underground engineering commonly used equipment, and site operation is easy, feasible Property it is high, the expense that can reduce investment outlay and shorten the processing time.
(3) by being drilled through on face in the radial slip casting inclined hole in center, to guarantee over the ground in the method for the present invention The a certain range of Rock And Soil of matter crushed zone and its periphery applies water blockoff, reinforces pre-pouring grout, forms water-stop curtain and reinforces geology and breaks Broken band.
Detailed description of the invention
Fig. 1 is the method for the present invention flow chart;
Fig. 2 is storage cavern area geology crushed zone feature schematic diagram in the embodiment of the present invention;
Fig. 3 is face pre-pouring grout borehole pattern in the embodiment of the present invention.
In figure, 1- has excavated cavern's abutment wall;2- face;3- slip casting inclined hole;4- geology crushed zone;5- does not excavate cavern side Wall;The cavern 6- central axes;Slip casting inclined hole end profile line at 7- geology crushed zone;Grouting serous fluid is spread at 8- geology crushed zone Outside boundary line;9- geology crushed zone excavates boundary line outside range.
Specific embodiment
The present invention is described in detail with specific embodiment below in conjunction with the accompanying drawings.The present embodiment is with technical solution of the present invention Premised on implemented, the detailed implementation method and specific operation process are given, but protection scope of the present invention is not limited to Following embodiments.
As shown in Figure 1, a kind of processing method of underground water seal cave depot storage cavern area geology crushed zone 4 the following steps are included:
S1: surveying data and cave depot construction time geological mapping data based on geology in detail, constructs cave depot area three-dimensional geological model, pushes away The output position of the disconnected geology crushed zone 4 of tomography, the intensive crushed zone in joint etc. out.In the geology crushed zone 4 estimated apart from storage cavern area At 15-30m face 2 before position, using advance geology exploration hole, verifies and determine the position of geology crushed zone 4, thickness Degree, occurrence and crushed zone Rock And Soil engineering properties.The hole count in advance geology exploration hole can flexibly increase and decrease according to 2 area of face, Generally 3, the diameter in each advance geology exploration hole is not less than 50mm.
If advance geology exploration hole coring, there should be special geological personnel to carry out evaluation acquisition geology to drilling core broken With 4 details;If not coring, the information such as drilling rate, water yield, water outlet color should be recorded in detail.
In the present embodiment, detection hole number takes 3, and aperture takes 50mm.4 position of geology crushed zone is obtained away from face 2 Axis 22m, thickness 2m, 339 ° of occurrence, 90 ° of ∠ (using cavern's axis as direct north), crushed zone Rock And Soil are fault breccia. Crushed zone schematic diagram is shown in Fig. 2.
S2: drilling through a certain number of slip casting inclined holes 3 on face 2, to guarantee to geology crushed zone 4 and its periphery one The Rock And Soil for determining range applies water blockoff, reinforces pre-pouring grout, forms water-stop curtain and reinforces geology crushed zone 4.Such as Fig. 2 and Fig. 3 institute Show, 3 length of slip casting inclined hole is to cross geology crushed zone 4 to be no less than 10m;It is radial centered on injected hole arrangement form, inclination Angle is so that grouting serous fluid excavates 8m other than the wall of hole to pre- along cavern's radial diffusion;Grout spreading range is calculated by 3m, and really Adjacent injected hole reinforcing scope overlap joint is protected without slip casting blind area, inlet well arrangement is shown in Fig. 3, and mark 8 is exactly grouting serous fluid in Fig. 3 By the outside boundary line that dilation angle 2m is obtained, mark 9 is exactly corresponding outside boundary line when excavating crushed zone 4m depth.Based on geology 4 geometry of crushed zone and mechanical characteristic reasonably select grouting serous fluid, grouting process, slip casting termination criteria and detection of grouting effects mark Standard should also detect slip casting effect after grout cures, specific as follows:
Grouting serous fluid should be selected according to Rock And Soil void characteristics, mainly select ordinary cement slurry, cement-bentonite Slurry, superfine cement slurry, chemicals slurries (such as nano silica etc.).Since rock cranny has millimetre-sized opening width, Therefore choose cement slurry.
Grouting method mainly includes following three kinds in step 2:
1. protrusive segmenting slip casting method: first section slip casting should use more sticky rapid hardening slurries and use lower slip casting pressure Power keeps its rapidly solidified, reduces running pulp, grout leaking;Next segment length is drilled through after the completion of first section, and uses normal grouting pressure and slurry Liquid is until completion full section is long.
2. grouting method is strengthened in specified region: using the Grouting Pipe for having mould bag at the 5m of end, reaching specified region When first pass through ductule slip casting carried out to mould bag and strut it to fit closely with country rock, then high slip casting pressure is used to specified region Power, big injection rate carry out reinforcing slip casting.
3. the long once grouting of full section: drilling preferable for quality of surrounding rock, that water amount of seepage is few can be used, and injected hole is primary It is drilled into unified slip casting after full section is grown.This uses protrusive segmenting slip casting method.
The concentration of slurry of slip casting process converts and termination criteria are as follows:
1. during slip casting when grouting pressure remains unchanged and injection rate persistently reduces or injection rate is constant and pressure is held When of continuing rising high, the ratio of mud should not be changed;
2. when certain grade of grouting serous fluid injection rate has reached 500L or more, and no changes have been made or changes for grouting pressure and slip casting flow velocity When not significant, the Ying Gainong level-one ratio of mud or other thick slurries more sticky than current grouting serous fluid;
3. repeating the 2. to walk until grouting pressure reaches PsWhen+1.5MPa or when slip casting flow velocity is less than 2L/min, stablize one Stop slip casting after the section time, wherein PsIt is using hydrostatic pressure, P in the hole for using manometry after antipriming closing drillingsIt takes 1MPa。
Slip casting effect is detected after slip casting, specifically: inspection hole is additionally drilled through in slip casting region, according to inspection hole Middle water burst flow velocity judges slip casting effect:
①Q<Q1, slip casting effect is good, needs not continue to slip casting, and inspection hole is backfilled with cement slurry;
②Q1<Q<Q2, by encryption injected hole, expansion range of grouting, thick slurry is selected to re-start slip casting, slip casting is complete Cheng Hou is detected again using the detection of grouting effects method;
③Q>Q2, drilling first seals, and after determining water burst concrete condition, the more strict measures of preventing water of use simultaneously uses the note Slurry effect detection method detects again;
Wherein, Q(L/min/m) it is every meter of drilling water yield per minute, general Q1Take 0.01 L/min/m, Q2Take 0.1 L/min/m。
S3: after geology crushed zone 4 is exposed by excavation, according to 4 steadiness of geology crushed zone, stop pick in due course Into;
Using construction machinery artificial or equipped with hydraulic shock destroyer, 4 depth of geology crushed zone is radially excavated along cavern Rock And Soil in range 3-5m;
Using plank sheathing or steel form, (branch should be segmented to the 4 outside installation template of geology crushed zone excavated along hole wall Mould);
Cast-in-place intensity is not less than the concrete (should be segmented and pour) of C25 at the geology crushed zone 4 hollowed out, and utilizes vibration Stick stirs evenly, and should conserve before concrete setting, reduces the crack that concrete shrinkage generates.
S4: the interface between concrete poured to the interface between cast-in-place concrete and country rock, segmentation carries out contact note Slurry, injected hole answer wide-angle to intersect with contact surface.Grouting serous fluid, grouting process, slip casting termination criteria and detection of grouting effects etc. It is identical as specified in step S2 pre-pouring grout.
In the present embodiment, grouting serous fluid selects cement slurry, grouting process that specified region is selected to strengthen slip casting, and slip casting terminates mark Quasi- and detection of grouting effects etc. is identical as specified in step S2 pre-pouring grout.Wherein when detection of grouting effects, since detection hole is straight It connects and is communicated with atmosphere, therefore PsTake zero.
S5: it constructs by the supporting construction that surrounding rock supporting construction design method determines, to geology crushed zone 4 and peripheral region After the support construction of domain, in situ 4 surface layer of matter crushed zone setting country rock is restrained and settlement monitoring measure, according to deflection Value and rate of deformation evaluation grouting consolidation effect simultaneously judge whether to enhance bolt-spary supports.
The present invention can solve the water blockoff of storage cavern area geology crushed zone 4 and reinforce problem, and step is simple, easy construction, investment Cost saving, short processing time.

Claims (6)

1. a kind of processing method of underground water seal cave depot storage cavern area geology crushed zone, which comprises the following steps:
S1: building cave depot area three-dimensional geological model, and obtain the position of geology crushed zone;
S2: drilling through multiple slip casting inclined holes on the face before the geology crushed zone position that distance is estimated and carry out pre-pouring grout, The multiple slip casting inclined hole is radial towards geology crushed zone tilt distribution in center, and it is broken that geology is crossed in the end of slip casting inclined hole Band certain distance;
S3: after geology crushed zone is excavated and is exposed, geology crushed zone region is excavated, formwork and pours coagulation Soil;
S4: the interface between concrete poured to the interface between cast-in-place concrete and country rock, segmentation carries out contact slip casting;
S5: it constructs by the supporting construction that surrounding rock supporting construction design method determines, to geology crushed zone and neighboring area branch After protection structure is constructed, in situ matter crushed zone surface layer is arranged country rock and restrains and settlement monitoring measure, according to deformation value and Rate of deformation evaluation grouting consolidation effect simultaneously judges whether to enhance bolt-spary supports;
The concentration of slurry of slip casting process converts and termination criteria are as follows:
1. during slip casting when grouting pressure remains unchanged and injection rate persistently reduces or injection rate is constant and pressure persistently rises Gao Shi does not change the ratio of mud;
2. when grouting serous fluid injection rate has reached 500L or more, and no changes have been made or changes not significant for grouting pressure and slip casting flow velocity When, change the dense level-one ratio of mud or the thick slurry more sticky than current grouting serous fluid;
3. repeating the 2. to walk until grouting pressure reaches PsWhen+1.5MPa or when slip casting flow velocity is less than 2L/min, when stablizing one section Between after stop slip casting, wherein PsIt is using hydrostatic pressure in the hole for using manometry after antipriming closing drilling;
Slip casting effect is detected after slip casting, specifically: inspection hole is additionally drilled through in slip casting region, is gushed according in inspection hole Water flow velocity judges slip casting effect:
①Q<Q1, slip casting effect is good, needs not continue to slip casting, and inspection hole is backfilled with cement slurry;
②Q1<Q<Q2, by encryption injected hole, expansion range of grouting, thick slurry is selected to re-start slip casting, after the completion of slip casting, Again it detects;
③Q>Q2, drilling first seals, and after determining water burst concrete condition, detects using measures of preventing water and again;
Wherein, Q is water yield, Q1Take 0.01 L/min/m, Q2Take 0.1 L/min/m;
In the step S2, the end of slip casting inclined hole crosses geology crushed zone and is no less than 10m;The tilt distribution of slip casting inclined hole makes Grouting serous fluid excavates 7-9m other than the wall of hole to pre- along cavern's radial diffusion;Grouting serous fluid dilation angle is calculated by 2-3m, and is ensured Adjacent slip casting inclined hole reinforcing scope overlap joint and without slip casting blind area;
The step S3 specifically:
After geology crushed zone is excavated and is exposed, according to geology crushed zone steadiness, stop driving in due course;
Using construction machinery artificial or equipped with hydraulic shock destroyer, geology crushed zone 3-5m depth model is radially excavated along cavern Enclose interior Rock And Soil;
Using plank sheathing or steel form, along hole wall to installation template outside the geology crushed zone excavated;
Cast-in-place intensity is not less than the concrete of C25 at the geology crushed zone hollowed out, and is stirred evenly using vibrating head.
2. a kind of processing method of underground water seal cave depot storage cavern area geology crushed zone according to claim 1, feature exist In at the 15-30m face before the geology crushed zone position that distance is estimated, using advance geology exploration in the step S1 Position, thickness, occurrence and the crushed zone Rock And Soil engineering properties of geology crushed zone are verified and determined in hole.
3. a kind of processing method of underground water seal cave depot storage cavern area geology crushed zone according to claim 2, feature exist In the hole count and face area in the advance geology exploration hole are proportional, and the diameter in each advance geology exploration hole is not less than 50mm。
4. a kind of processing method of underground water seal cave depot storage cavern area geology crushed zone according to claim 2, feature exist In, if advance geology exploration hole coring, to drilling core carry out evaluation obtain geology crushed zone information;If not taking Core then records drilling rate, water yield, water outlet colouring information.
5. a kind of processing method of underground water seal cave depot storage cavern area geology crushed zone according to claim 1, feature exist In in the step S2, the method for drilling holes and late grouting includes: protrusive segmenting slip casting method, specified region reinforcing grouting method With the long once grouting method of full section.
6. a kind of processing method of underground water seal cave depot storage cavern area geology crushed zone according to claim 1, feature exist In the slurries of slip casting are selected according to Rock And Soil void characteristics, and the type of grouting serous fluid includes that ordinary cement slurry, cement-are swollen Moisten soil paste, superfine cement slurry and chemicals slurries.
CN201711295807.2A 2017-12-08 2017-12-08 A kind of processing method of underground water seal cave depot storage cavern area geology crushed zone Active CN108005662B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711295807.2A CN108005662B (en) 2017-12-08 2017-12-08 A kind of processing method of underground water seal cave depot storage cavern area geology crushed zone

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711295807.2A CN108005662B (en) 2017-12-08 2017-12-08 A kind of processing method of underground water seal cave depot storage cavern area geology crushed zone

Publications (2)

Publication Number Publication Date
CN108005662A CN108005662A (en) 2018-05-08
CN108005662B true CN108005662B (en) 2019-08-09

Family

ID=62057490

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711295807.2A Active CN108005662B (en) 2017-12-08 2017-12-08 A kind of processing method of underground water seal cave depot storage cavern area geology crushed zone

Country Status (1)

Country Link
CN (1) CN108005662B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108868843A (en) * 2018-08-21 2018-11-23 华东建工集团有限公司 A kind of anchor rod support method in tunnel
CN111506943B (en) * 2020-03-23 2023-02-28 中建五局第三建设有限公司 Method for guiding reinforcing construction of fractured rock mass by three-dimensional geological model
CN112127909B (en) * 2020-09-08 2021-12-07 河海大学 Accurate grouting repairing and reinforcing method for broken surrounding rock of tunnel

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101638989B (en) * 2009-07-30 2012-01-18 中铁二局股份有限公司 Milling and supporting construction method of fault crushed zone of subbottom tunnel
JP5959040B2 (en) * 2011-03-22 2016-08-02 株式会社大林組 How to treat aerated soil
CN102787846B (en) * 2012-07-31 2015-07-08 中铁隧道集团有限公司 Upper-blocking and lower-draining construction method for undersea tunnel fault fracture zone
CN103147778A (en) * 2013-03-23 2013-06-12 孟志强 Method for lane development and support in extremely crushed rock stratum
CN106837352A (en) * 2017-01-22 2017-06-13 中南大学 Fault belt surrounding rock tunnel construction method

Also Published As

Publication number Publication date
CN108005662A (en) 2018-05-08

Similar Documents

Publication Publication Date Title
CN101638987B (en) Tunnel construction method for crossing high-pressure water-enriched fracture zone with curtain grouting and grout stopping wall
CN104963334B (en) Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement
CN106437726B (en) Shallow-depth-excavation tunnel crosses ground fissure crushed zone construction method
CN109208637A (en) Increase the construction method of open-cut station newly on the basis of existing tunnel
CN106837351A (en) Tunnel karst water detection and treatment method
CN205172598U (en) Pipe curtain spouts a supporting construction soon
CN111119940B (en) Grouting construction treatment method
CN108951612A (en) A kind of subway tunnel shield end reinforcement means
CN110067563A (en) Close on the station entrance-exit main structure construction method of urban architecture and road
CN106759297A (en) A kind of construction method of support pile and three pipe high-pressure rotary jet grouting pile deep basal pits
CN107605498A (en) Rich water sand-pebble layer shield tunnel termination horizontal grouting ruggedized construction construction method
CN108661650A (en) A kind of rich water magmatic body area depth pozo shaft construction method
CN105715296A (en) Blowing sand backfill and grouting construction method of tunnel crossing coal mine goaf
CN108005662B (en) A kind of processing method of underground water seal cave depot storage cavern area geology crushed zone
CN103835651A (en) Single-hole directional drilling local grouting raise boring technology
CN108252719A (en) Plastic flow modeling shape red clay layer construction method is worn under a kind of urban shallow tunnel
CN103410522A (en) Continuous close-range underpass railway bridge construction method employing shallow tunneling method
CN108952727B (en) A kind of grouting water blocking method of the vertical creviced formation of high inclination-angle
CN110130936A (en) It dashes forward in a kind of shield tunneling process and meets the construction method of untreated solution cavity or crack
CN103572764A (en) Ultra-deep manual hole digging pile dado water stop structure and construction method thereof
CN106013078A (en) Construction method of strong permeable stratum reinforcing curtain structure
CN207406345U (en) Rich water sand-pebble layer shield tunnel end horizontal grouting ruggedized construction
CN102979087B (en) Construction method for rotary excavation pile
CN110500119A (en) A kind of waterproof consolidation structure construction method for passing through Debris Flow Deposition body tunnel
CN205296194U (en) Rich irrigated land layer undercut tunnel interlock pipe curtain

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant