CN108868843A - A kind of anchor rod support method in tunnel - Google Patents

A kind of anchor rod support method in tunnel Download PDF

Info

Publication number
CN108868843A
CN108868843A CN201810953752.8A CN201810953752A CN108868843A CN 108868843 A CN108868843 A CN 108868843A CN 201810953752 A CN201810953752 A CN 201810953752A CN 108868843 A CN108868843 A CN 108868843A
Authority
CN
China
Prior art keywords
suspension roof
roof support
parts
scheme
drilling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810953752.8A
Other languages
Chinese (zh)
Inventor
张忠洋
张洋
王磊
李元江
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guo Cheng Group Co., Ltd
Original Assignee
East China Construction Engineering Group Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by East China Construction Engineering Group Ltd filed Critical East China Construction Engineering Group Ltd
Priority to CN201810953752.8A priority Critical patent/CN108868843A/en
Publication of CN108868843A publication Critical patent/CN108868843A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/021Grouting with inorganic components, e.g. cement

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Chemical & Material Sciences (AREA)
  • Inorganic Chemistry (AREA)
  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

The invention discloses the anchor rod support methods in a kind of tunnel, include the following steps:(1) advance geologic prediction is carried out using physical prospecting and probing, collects geologic data;(2) 3-dimensional digital Integrated Model is constructed according to the data that advance geologic prediction is collected;(3) it proposes preliminary suspension roof support scheme, and carries out analysis calculation with 3-dimensional digital Integrated Model, adjust preliminary suspension roof support scheme according to resulting in, determine final suspension roof support scheme;(4) suspension roof support construction is carried out according to suspension roof support scheme.The present invention is using advance geologic prediction and establishes 3-dimensional digital Integrated Model, can quickly determine supporting scheme and the required material of supporting, to save support cost, and uses the stronger mortar of stability, the stability after improving rockbolt installation.

Description

A kind of anchor rod support method in tunnel
Technical field
The invention belongs to technical field of tunnel construction, and in particular to the anchor rod support method in a kind of tunnel.
Background technique
Suspension roof support is a ring important in supporting and protecting system of tunnel, and whether design parameters of bolt rationally directly affects construction The structure safety problem in stage and operation stage.It is current to carry out Tunnel Rock Bolt design according to domestic vcehicular tunnel design specification When, only using Grades of Surrounding Rock as emphasis Consideration, simple foundation Grades of Surrounding Rock provides the support form and supporting parameter of recommendation, Tunneling boring takes homogenization parameter simultaneously, to be easy to ignore Rock Joints Surrounding feature when to different constructing tunnel supportings, is applied Work engineering method and blasting parameter influence, and easily cause to waste or there are security risks, while being influenced by mortar, stablize after suspension roof support Property is poor.
Summary of the invention
The technical problems to be solved by the invention are in view of the above shortcomings of the prior art, to provide the anchor in a kind of tunnel Bar method for protecting support, it is ensured that the safety of supporting, while the cost of supporting can be saved.
The technical scheme adopted by the invention is that:A kind of anchor rod support method in tunnel, includes the following steps:
(1) advance geologic prediction is carried out using physical prospecting and probing, collects geologic data;
(2) 3-dimensional digital Integrated Model is constructed according to the data that advance geologic prediction is collected;
(3) it proposes preliminary suspension roof support scheme, and carries out analysis calculation with 3-dimensional digital Integrated Model, tied according to calculation Fruit adjusts preliminary suspension roof support scheme, determines final suspension roof support scheme;
(4) suspension roof support construction is carried out according to suspension roof support scheme.
Preferably, the construction of suspension roof support described in step (4) is specially:
A, it first carries out putting survey using the full instrument that bores according to supporting scheme, and carries out mark for dowel hold;
B, it drills using using wet brill in mark;
C, preliminary flushing is carried out to drilling using drilling machine water flow after drilling, drilling rod is slowly extracted after cleaning, then utilize height Pressure fan carries out borehole cleaning to drilling;
D, in being drilled after borehole cleaning with water lubrication, Grouting Pipe is inserted into bottom hole, is then log out 50-100mm;
E, mortar is injected, Grouting Pipe is slowly at the uniform velocity extracted with the injection of mortar, is immediately inserted into anchor pole after extraction, anchor pole After insertion mortar will be filled up in drilling.
Preferably, grouting pressure control is in 2.5-5Mpa.
Preferably, the mortar includes following components by weight:100 parts of portland cement, 60 parts of flyash, 16 parts of concrete early strength agent, 38 parts of filler powder, 0.1 part of aluminium powder, 5 parts of swelling agent, 2 parts of defoaming agent and 70 parts of water.
It is bloodstone, kaolinite, big preferably, the filler powder includes bloodstone, kaolinite, marble and granite Fibrous gypsum and the proportion of granite are 3:2:0.5:0.5.
The present invention is using advance geologic prediction and establishes 3-dimensional digital Integrated Model, can quickly determine supporting scheme and branch Required material is protected, to save support cost, and uses the stronger mortar of stability, the stabilization after improving rockbolt installation Property.
Specific embodiment
Below in conjunction with specific embodiment, invention is further described in detail.
Embodiment
Anchor rod support method in tunnel provided in this embodiment includes the following steps:
(1) advance geologic prediction is carried out using physical prospecting and probing, advance geologic prediction includes survey for the purpose of locating hydrogeological resources, hole Nei Shui Literary geologic survey, record EXIT POINT position, water outlet dotted state and water yield, record tomography, joints development occurrence, record country rock, Joint plane key mechanics parameter;
(2) 3-dimensional digital Integrated Model is constructed according to the parameter that advance geologic prediction is collected;
(3) it proposes preliminary suspension roof support scheme, and carries out analysis calculation with 3-dimensional digital Integrated Model, and pass through scene Test, engineering investigation, quantitative analysis difference Bolting Parameters flowering structure stress deformation characteristic and adjoining rock stability safety coefficient, most Suitable suspension roof support scheme and parameter are determined eventually;
(4) suspension roof support construction is carried out according to suspension roof support scheme and parameter:A, instrument is first bored using complete according to supporting scheme It carries out putting survey, and carries out mark for dowel hold;B, it drills using using wet brill in mark;C, drilling machine water flow pair is utilized after drilling Drilling carries out preliminary flushing, and drilling rod is slowly extracted after cleaning, then carries out borehole cleaning to drilling using high pressure blower;D, it is used after borehole cleaning In water lubrication drilling, Grouting Pipe is inserted into bottom hole, is then log out 50-100mm;E, mortar is injected, silicon by weight is chosen 100 parts of acid salt cement, 60 parts of flyash and 38 parts of filler powder uniformly mix in mortar machine, and water 70 is added after mixing and carries out at the uniform velocity It stirs, 16 parts of concrete early strength agent of addition, 0.1 part of aluminium powder, 5 parts of swelling agent and 2 parts of defoaming agent, are sufficiently stirred mixed in whipping process It is sent into slip casting machine after even, slip casting machine, which controls pressure, starts slip casting in 2.5-5Mpa, and Grouting Pipe is with mortar during slip casting Injection is slowly at the uniform velocity extracted, and is immediately inserted into anchor pole after extraction, will be filled up mortar in drilling after anchor pole insertion, is completed the peace of anchor pole Dress.
In above-described embodiment, the filler powder includes bloodstone, kaolinite, marble and granite, bloodstone, kaolinite The proportion of stone, marble and granite is 3:2:0.5:0.5.
The above is only the preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto, any The transformation and replacement carried out based on technical solution provided by the present invention and inventive concept should all be covered in protection model of the invention In enclosing.

Claims (5)

1. the anchor rod support method in a kind of tunnel, it is characterised in that:Include the following steps:
(1) advance geologic prediction is carried out using physical prospecting and probing, collects geologic data;
(2) 3-dimensional digital Integrated Model is constructed according to the data that advance geologic prediction is collected;
(3) it proposes preliminary suspension roof support scheme, and carries out analysis calculation with 3-dimensional digital Integrated Model, adjusted according to resulting in Whole preliminary suspension roof support scheme, determines final suspension roof support scheme;
(4) suspension roof support construction is carried out according to suspension roof support scheme.
2. the anchor rod support method in a kind of tunnel according to claim 1, it is characterised in that:Anchor described in step (4) Bar supporting construction is specially:
A, it first carries out putting survey using the full instrument that bores according to supporting scheme, and carries out mark for dowel hold;
B, it drills using using wet brill in mark;
C, preliminary flushing is carried out to drilling using drilling machine water flow after drilling, drilling rod is slowly extracted after cleaning, then utilize high-pressure blast Machine carries out borehole cleaning to drilling;
D, in being drilled after borehole cleaning with water lubrication, Grouting Pipe is inserted into bottom hole, is then log out 50-100mm;
E, mortar is injected, Grouting Pipe is slowly at the uniform velocity extracted with the injection of mortar, is immediately inserted into anchor pole after extraction, anchor pole insertion Afterwards mortar will be filled up in drilling.
3. the anchor rod support method in a kind of tunnel according to claim 2, it is characterised in that:Inject the control of mortar pressure In 2.5-5Mpa.
4. the anchor rod support method in a kind of tunnel according to claim 2, it is characterised in that:The mortar includes by weight Measure the following components of part meter:100 parts of portland cement, 60 parts of flyash, 16 parts of concrete early strength agent, 38 parts of filler powder, aluminium powder 0.1 part, 5 parts of swelling agent, 2 parts of defoaming agent and 70 parts of water.
5. the anchor rod support method in a kind of tunnel according to claim 4, it is characterised in that:The filler powder includes red Iron ore, kaolinite, marble and granite, bloodstone, kaolinite, marble and granite proportion be 3:2:0.5:0.5.
CN201810953752.8A 2018-08-21 2018-08-21 A kind of anchor rod support method in tunnel Pending CN108868843A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810953752.8A CN108868843A (en) 2018-08-21 2018-08-21 A kind of anchor rod support method in tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810953752.8A CN108868843A (en) 2018-08-21 2018-08-21 A kind of anchor rod support method in tunnel

Publications (1)

Publication Number Publication Date
CN108868843A true CN108868843A (en) 2018-11-23

Family

ID=64320872

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810953752.8A Pending CN108868843A (en) 2018-08-21 2018-08-21 A kind of anchor rod support method in tunnel

Country Status (1)

Country Link
CN (1) CN108868843A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111484285A (en) * 2020-03-31 2020-08-04 中交隧道工程局有限公司 Paste mortar for tunnel vault mortar anchor rod construction and grouting method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102536250A (en) * 2010-12-31 2012-07-04 中铁二局股份有限公司 Construction method for tunnels with karst and gas simultaneously
CN106837352A (en) * 2017-01-22 2017-06-13 中南大学 Fault belt surrounding rock tunnel construction method
CN106837353A (en) * 2017-01-22 2017-06-13 中南大学 Filling karst tunnel construction treatment method
CN108005662A (en) * 2017-12-08 2018-05-08 福州大学 A kind of processing method of underground water seal cave depot bank area geology crushed zone
CN108166981A (en) * 2017-12-31 2018-06-15 中铁十九局集团第二工程有限公司 Tunnel soft rock large deformation section construction technology

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102536250A (en) * 2010-12-31 2012-07-04 中铁二局股份有限公司 Construction method for tunnels with karst and gas simultaneously
CN106837352A (en) * 2017-01-22 2017-06-13 中南大学 Fault belt surrounding rock tunnel construction method
CN106837353A (en) * 2017-01-22 2017-06-13 中南大学 Filling karst tunnel construction treatment method
CN108005662A (en) * 2017-12-08 2018-05-08 福州大学 A kind of processing method of underground water seal cave depot bank area geology crushed zone
CN108166981A (en) * 2017-12-31 2018-06-15 中铁十九局集团第二工程有限公司 Tunnel soft rock large deformation section construction technology

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111484285A (en) * 2020-03-31 2020-08-04 中交隧道工程局有限公司 Paste mortar for tunnel vault mortar anchor rod construction and grouting method thereof

Similar Documents

Publication Publication Date Title
CN107447765B (en) Side slope construction supported with framed anchor construction
CN109611102B (en) Construction method for cold excavation underpass overpass
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN106837352A (en) Fault belt surrounding rock tunnel construction method
CN104453946B (en) Advanced reinforcing construction method for building tunnel in soft surrounding rock
CN106837353A (en) Filling karst tunnel construction treatment method
CN109595004B (en) Tunnel two-expansion four-expansion excavation method
CN105155550B (en) Construction method for digging deep foundation pit in large-thickness highly weathered sandstone stratum in combined supporting mode
JP7257086B2 (en) Comprehensive Construction Method for Low Overburden Sections of Tunnels
CN108517877B (en) Supporting construction method combining consolidation grouting of hybrid filling ultra-deep foundation pit with double-row steel pipe piles
CN108915736A (en) The water damage control method of digging laneway under the strong weak cementing water-bearing layer of rich water
CN109209392A (en) Loopful excavation method suitable for IV-V grade of country rock of large cross-section tunnel
CN104831734A (en) Construction method of jet-grouting pile and composite soil-nailed wall support for deep foundation pit construction
CN114233385B (en) Treatment method for mud-bursting water of inclined shaft
CN109457694A (en) A kind of variable diameters steel reinforcement cage enlarged footing anti-floating or pressure bearing pile and construction in conjunction with mixing pile or rotary churning pile
CN108487286A (en) A kind of construction method of the continuous supporting course of beading karst region super long pile
CN101832137A (en) Pre-embedding method for coal seam roof strut
CN203530988U (en) One-time forming major-diameter anchor rod foundation pit supporting structure
CN110206550A (en) A kind of complicated geological excavates the construction of shield received well
CN110005456A (en) A kind of large-deformation tunnel in soft rock benching tunnelling method anchor pole rapid constructing method
CN108868843A (en) A kind of anchor rod support method in tunnel
CN112281933A (en) Construction method of high-pressure jet grouting pile test
CN209586373U (en) The support system of the lower rock compound cross-section stratum jacking construction inlet and outlet cave of upper soil
CN209669857U (en) A kind of variable diameters steel reinforcement cage enlarged footing anchor pole anti-floating or pressure bearing pile
CN116517573A (en) Tunnel excavation method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20190520

Address after: 610000 No. 58 Tengfei Avenue, Qingyang District, Chengdu City, Sichuan Province

Applicant after: Guo Cheng Group Co., Ltd

Address before: 266071 Yanji Road 237, Shinan District, Qingdao City, Shandong Province

Applicant before: East China Construction Engineering Group Limited

TA01 Transfer of patent application right
RJ01 Rejection of invention patent application after publication

Application publication date: 20181123

RJ01 Rejection of invention patent application after publication