CN109000963A - A kind of plastic concrete cut-off wall sampling method - Google Patents

A kind of plastic concrete cut-off wall sampling method Download PDF

Info

Publication number
CN109000963A
CN109000963A CN201811004458.9A CN201811004458A CN109000963A CN 109000963 A CN109000963 A CN 109000963A CN 201811004458 A CN201811004458 A CN 201811004458A CN 109000963 A CN109000963 A CN 109000963A
Authority
CN
China
Prior art keywords
wall
plastic concrete
concrete cut
cut
freezing pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811004458.9A
Other languages
Chinese (zh)
Inventor
袁以美
朱国武
彭守良
叶合欣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Polytechnic of Water Resources and Electric Engineering Guangdong Water Resources and Electric Power Technical School
Original Assignee
Guangdong Polytechnic of Water Resources and Electric Engineering Guangdong Water Resources and Electric Power Technical School
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Polytechnic of Water Resources and Electric Engineering Guangdong Water Resources and Electric Power Technical School filed Critical Guangdong Polytechnic of Water Resources and Electric Engineering Guangdong Water Resources and Electric Power Technical School
Priority to CN201811004458.9A priority Critical patent/CN109000963A/en
Publication of CN109000963A publication Critical patent/CN109000963A/en
Pending legal-status Critical Current

Links

Classifications

    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N1/00Sampling; Preparing specimens for investigation
    • G01N1/02Devices for withdrawing samples
    • G01N1/04Devices for withdrawing samples in the solid state, e.g. by cutting
    • G01N1/08Devices for withdrawing samples in the solid state, e.g. by cutting involving an extracting tool, e.g. core bit

Landscapes

  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Chemical & Material Sciences (AREA)
  • Analytical Chemistry (AREA)
  • Biochemistry (AREA)
  • General Health & Medical Sciences (AREA)
  • General Physics & Mathematics (AREA)
  • Immunology (AREA)
  • Pathology (AREA)
  • Sampling And Sample Adjustment (AREA)

Abstract

The invention discloses a kind of plastic concrete cut-off wall sampling methods, freeze to plastic concrete cut-off wall sample position;Drill hole sampling when being chilled to setting condition.The present invention freezes plastic concrete cut-off wall by implementing, and can completely get plastic concrete cut-off wall core sample, can intuitively, reliably evaluate plastic concrete cut-off wall pouring quality.

Description

A kind of plastic concrete cut-off wall sampling method
Technical field
The present invention relates to inspection of hydraulic structure field, in particular to a kind of plastic concrete cut-off wall sampling method.
Background technique
Plastic concrete refers to replace most of cement in normal concrete to be formed with clay and (or) bentonite one Kind flexible material, cement consumption is far below normal concrete, and adds the cementitious materials such as more bentonite, clay, It is suitble to the fluidity concrete of underwater casting, compression strength is not more than 5MPa, and has low bullet and the biggish spy of limiting strain Property.Plastic concrete cut-off wall refers to a kind of cut-pff wall form using plastic concrete.The total amount of plastic concrete cementitious material It is not preferably less than 240kg/m3, wherein cement consumption should not be less than 80kg/m3, bentonite consumption should not be less than 40kg/m3, cement with Bentonitic total dosage should not be less than 160kg/m3, sand coarse aggregate ratio not be preferably less than 45%.Under the premise of meeting mobility requirement, preferably Water consumption is reduced, and preferably uses a graded aggregate.
Due to the difference of ingredient, plastic concrete is more much smaller than the elasticity modulus of normal concrete or Clay-concrete, with The deformation modulus of surrounding soil is close, thus can be well adapted for the deformation of ground, considerably reduces the intracorporal stress of wall, keeps away Exempt from wall crazing, furthermore can also save cement material.Plastic concrete cut-off wall is mainly used in hydraulic and hydroelectric engineering Construction cofferdam, dykes and dams reinforcement etc..In the recent decade, in the engineerings such as Changjiang dyke and numerous Strengthening Projects of Dangerous Reservoirs In, the thin impervious wall construction technology of 200-400mm waits until to be widely applied.
It is the most for evaluation plastic concrete cut-off wall quality that core sample is taken at scene from plastic concrete cut-off wall body Intuitively, reliably.By taking core sample that can extract sample, it is a series of that resistance to compression, tension, impervious, shearing resistance, bulk density etc. are done indoors Test, can obtain the physical mechanical property index of plastic concrete cut-off wall, provide for evaluation plastic concrete cut-off wall quality The foundation of science.Since plastic concrete cut-off wall wall is thin, generally 200-1200cm is thick, and depth is big, and tens meters even super Hundred meters are crossed, elasticity modulus is small, and compression strength is low, and ingredient is hard soft alternate (containing aggregate, sand, cement, clay etc.), and boring and coring is difficult Degree is big, and lithology is easily broken in boring procedure, and often drilled flushing liquor destroys adhesive, and core is substantially in granular media shape, it is difficult to At sample, test core sample can not be made and carry out correlation test, especially for thin cut-pff wall, thickness only has 200-400cm, deposits In the significant technology issues such as through walls, core is imperfect.
Difficult due to sampling on plastic concrete cut-off wall body, current coring method is: taking in machine mouth or slot mouth Sample, i.e., take plastic concrete sample before pouring, then maintenance molding is tested accordingly.Obviously, the examination that this method obtains Sample is not that plastic concrete pours the core sample for building up leakage proof wall, and test result only represents the matter of the plastic concrete before pouring Amount, far from represent poured in mud adverse effect under the conditions of practical wall quality.
Summary of the invention
For the technical problems in the prior art, the object of the present invention is to provide a kind of plastic concrete cut-off walls Sampling method.
The purpose of the invention is achieved by the following technical solution: a kind of plastic concrete cut-off wall sampling method, to plasticity Concrete cut sample position is freezed;
Drill hole sampling when being chilled to setting condition.
Preferably, freezing pipe is arranged in plastic concrete cut-off wall lateral surface, when sample position temperature in corresponding sample position At -20 DEG C or less, boring and coring.
Preferably, freezing pipe is multiple, and multiple freezing pipes are enclosed in respectively on the outside of plastic concrete cut-off wall, solidification point Control, hereinafter, when freezing the soil body and having handed over to enclose and when reaching set temperature, shows that sample position temperature has reached setting and takes at -20 DEG C Sample temperature.
Preferably, freezing pipe is squeezed into plastic concrete cut-off wall bottom or set depth.
Preferably, the insertion tapered freezing pipe in head is into plastic concrete cut-off wall bottom or stratum, with pipe rammer handle Freezing pipe is squeezed among stratum, is rectified a deviation when generating deflection during squeezing into, is sealed freezing pipe nozzle, when driving depth and partially When gradient reaches sets requirement, suppress leaking hunting, pressure control in 0.8Mpa and no less than 15min, leak hunting pressure process without Show qualification when variation.
Preferably, sampling finishes after plastic concrete cut-off wall natural thaw, intermittent grouting is carried out to sampling hole, when taking When slurry is continuously returned in sample hole aperture three times, show to have blocked closely knit.
Preferably, sampling finishes after plastic concrete cut-off wall natural thaw, carries out intermittent grouting to each freezing pipe, when When freezing pipe nozzle continuously returns slurry three times, show to block freezing pipe closely knit.
Preferably, freezing pipe block it is closely knit after extract freezing pipe, after every extractions section freezing pipe, carry out primary supplement filling Slurry, until all extracting freezing pipe.
Preferably, it during drill hole sampling, is persistently freezed.
Preferably, adjacent two that plastic concrete cut-off wall same side is arranged in freeze tube spacing from 50-100cm.
The present invention has the following advantages and effects with respect to the prior art:
1, the present invention freezes plastic concrete cut-off wall by implementing, and can completely get plastic concrete cut-off wall core Sample can intuitively, reliably evaluate plastic concrete cut-off wall pouring quality.
2, the present invention can provide satisfactory core sample for laboratory test, so that test result preferably reflects that plasticity is mixed The actual state of solidifying soil cut-pff wall.
3, after the present invention takes core sample, to freezing pipe and the timely rockfill grouting of sampling hole, it is unfavorable that freeze thawing bring can be eliminated It influences.
Detailed description of the invention
Fig. 1 is the schematic diagram that freezing pipe of the invention freezes plastic concrete cut-off wall;
Fig. 2 is the schematic diagram that freezing pipe of the invention extends along plastic concrete cut-off wall.
Specific embodiment
Present invention will now be described in further detail with reference to the embodiments and the accompanying drawings, but embodiments of the present invention are unlimited In this.
A kind of plastic concrete cut-off wall sampling method, freezes plastic concrete cut-off wall sample position 1, to modeling Property concrete cut carry out freezing it can be made to freeze tightly, intensity greatly improves, and prevents from causing to crack because of sampling or collapsing, together When be also convenient for getting the core sample met the requirements.
Drill hole sampling when being chilled to setting condition.
Preferably, freezing pipe 2 is arranged in plastic concrete cut-off wall lateral surface, when sample position 1 in corresponding sample position 1 Temperature is at -20 DEG C or less, boring and coring.
Preferably, freezing pipe 2 is multiple, and multiple freezing pipes 2 are enclosed in respectively on the outside of plastic concrete cut-off wall, freezes temperature Degree control hereinafter, handed over circle 3 and when reaching set temperature when freezing the soil body, shows that 1 temperature of sample position has reached and sets at -20 DEG C Determine probe temperature.
It can substantially be estimated by daily 20mm the time required to freezing.
Preferably, freezing pipe 2 is squeezed into the set depth into plastic concrete cut-off wall bottom 4 or stratum.
Specifically, the insertion tapered freezing pipe 2 in head, squeezes into freezing pipe 2 among stratum, while also to protect with pipe rammer It demonstrate,proves 2 orifice sealing device of freezing pipe to seal, securely, blowout prevention, and strict control deflection can be played the role of, when more than sets requirement When, it should rectify a deviation in time.Orifice sealing device, which can be taken to change, fills out clay to be sealed.When driving depth and deflection reach setting It is required that when, it should carry out suppressing leak test, pressure is controlled in 0.8Mpa and no less than 15min, shows qualification when pressure is unchanged.
Preferably, sampling finishes after plastic concrete cut-off wall natural thaw, intermittent grouting is carried out to sampling hole, when taking When slurry is continuously returned in sample hole aperture three times, show to have blocked closely knit.
Preferably, sampling finishes after plastic concrete cut-off wall natural thaw, carries out intermittent grouting to each freezing pipe 2, When 2 nozzle of freezing pipe continuously returns slurry three times, show to block freezing pipe 2 closely knit.
Preferably, freezing pipe 2 block it is closely knit after extract freezing pipe 2, after one section freezing pipe 2 of every extraction, once supplemented Grouting, until all extracting freezing pipe 2.
Preferably, it during drill hole sampling, is persistently freezed.
Preferably, freezing pipe 2 is 2-8.It, can be in plastic concrete cut-off wall two if plastic concrete cut-off wall is thicker Freezing hole is arranged in side more.
Preferably, distance 50-100cm between adjacent two freezing pipe 2 of plastic concrete cut-off wall same side is set.
The above embodiment is a preferred embodiment of the present invention, but embodiments of the present invention are not by above-described embodiment Limitation, other any changes, modifications, substitutions, combinations, simplifications made without departing from the spirit and principles of the present invention, It should be equivalent substitute mode, be included within the scope of the present invention.

Claims (10)

1. a kind of plastic concrete cut-off wall sampling method, it is characterised in that: carried out to plastic concrete cut-off wall sample position Freezing;
Drill hole sampling when being chilled to setting condition.
2. plastic concrete cut-off wall sampling method according to claim 1, which is characterized in that corresponding sample position, Freezing pipe, when sample position temperature is at -20 DEG C or less, boring and coring is arranged in plastic concrete cut-off wall lateral surface.
3. plastic concrete cut-off wall sampling method according to claim 2, which is characterized in that freezing pipe be it is multiple, it is more A freezing pipe is enclosed in respectively on the outside of plastic concrete cut-off wall, and solidification point control is at -20 DEG C hereinafter, having handed over when freezing the soil body When enclosing and reaching set temperature, show that sample position temperature has reached setting probe temperature.
4. plastic concrete cut-off wall sampling method according to claim 2 or 3, which is characterized in that squeeze into freezing pipe To plastic concrete cut-off wall bottom or set depth.
5. plastic concrete cut-off wall sampling method according to claim 4, which is characterized in that the insertion tapered jelly in head Pipe is tied into plastic concrete cut-off wall bottom or stratum, freezing pipe is squeezed among stratum with pipe rammer, is produced during squeezing into It rectifies a deviation when raw deflection, seals freezing pipe nozzle, when driving depth reaches sets requirement with deflection, carry out suppressing survey Leakage, pressure are controlled in 0.8Mpa and no less than 15min, and the pressure process that leaks hunting shows qualification when unchanged.
6. plastic concrete cut-off wall sampling method according to claim 2, which is characterized in that sampling finishes mixed to plasticity After solidifying soil cut-pff wall natural thaw, intermittent grouting is carried out to sampling hole and shows to have sealed when slurry is continuously returned three times in sampling hole aperture It blocks up closely knit.
7. plastic concrete cut-off wall sampling method according to claim 4, which is characterized in that sampling finishes mixed to plasticity After solidifying soil cut-pff wall natural thaw, intermittent grouting is carried out to each freezing pipe and is shown when freezing pipe nozzle continuously returns slurry three times Freezing pipe is blocked closely knit.
8. plastic concrete cut-off wall sampling method according to claim 7, which is characterized in that after freezing pipe closure is closely knit Freezing pipe is extracted, after every extractions section freezing pipe, carries out a supplementary grouting, until all extraction freezing pipes.
9. plastic concrete cut-off wall sampling method according to claim 1, which is characterized in that during drill hole sampling, Persistently freezed.
10. plastic concrete cut-off wall sampling method according to claim 2, which is characterized in that be arranged in plasticity coagulation Adjacent the two of native cut-pff wall same side freeze tube spacing from 50-100cm.
CN201811004458.9A 2018-08-30 2018-08-30 A kind of plastic concrete cut-off wall sampling method Pending CN109000963A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811004458.9A CN109000963A (en) 2018-08-30 2018-08-30 A kind of plastic concrete cut-off wall sampling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811004458.9A CN109000963A (en) 2018-08-30 2018-08-30 A kind of plastic concrete cut-off wall sampling method

Publications (1)

Publication Number Publication Date
CN109000963A true CN109000963A (en) 2018-12-14

Family

ID=64594648

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811004458.9A Pending CN109000963A (en) 2018-08-30 2018-08-30 A kind of plastic concrete cut-off wall sampling method

Country Status (1)

Country Link
CN (1) CN109000963A (en)

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201250397Y (en) * 2008-09-03 2009-06-03 安徽省水利水电勘测设计院 Concrete anti-seepage wall with quality inspection coring pipes
CN102368051A (en) * 2011-09-15 2012-03-07 中国科学院东北地理与农业生态研究所 Method for sampling wetland soil
CN202330055U (en) * 2011-11-30 2012-07-11 安徽工业大学 Sampling device of outdoor water body sediment
CN104316391A (en) * 2014-10-10 2015-01-28 同济大学 Freezing and thawing test model device and method of simulating artificial ground freezing method
CN104806253A (en) * 2015-05-15 2015-07-29 中铁二局股份有限公司 Construction method for opening hole between rectangular pipe jacking channels
CN105758775A (en) * 2016-02-03 2016-07-13 华北水利水电大学 Device and method for detecting anti-penetrability performance of concrete impermeable wall
CN106124243A (en) * 2016-06-16 2016-11-16 重庆大学 Coal seam gas-bearing capacity measures advanced freezing sampling method
CN205691360U (en) * 2016-06-16 2016-11-16 重庆大学 Coal seam gas-bearing capacity measures advanced freezing sampler
CN206002338U (en) * 2016-08-31 2017-03-08 浙江中林勘察研究股份有限公司 A kind of original state sandy soil sampler
CN106525484A (en) * 2016-08-31 2017-03-22 浙江中林勘察研究股份有限公司 Sampling method and sampling device for original state sandy soil
CN106872210A (en) * 2017-03-28 2017-06-20 江西省水利科学研究院 A kind of method that drill core test cut-pff wall drills through complete opening original state core sample
CN106950077A (en) * 2017-05-16 2017-07-14 中国科学院武汉岩土力学研究所 A kind of prismatical joint rock mass sampling method
CN107119629A (en) * 2017-06-23 2017-09-01 广东水利电力职业技术学院(广东省水利电力技工学校) A kind of Ecological Retaining Wall and its method constructed on existing barricade
CN107237339A (en) * 2017-08-03 2017-10-10 杭州江润科技有限公司 A kind of concrete cut increases leakage preventing structure and its construction method
CN207623044U (en) * 2017-12-11 2018-07-17 河海大学 Vertical freezing sampling apparatus

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201250397Y (en) * 2008-09-03 2009-06-03 安徽省水利水电勘测设计院 Concrete anti-seepage wall with quality inspection coring pipes
CN102368051A (en) * 2011-09-15 2012-03-07 中国科学院东北地理与农业生态研究所 Method for sampling wetland soil
CN202330055U (en) * 2011-11-30 2012-07-11 安徽工业大学 Sampling device of outdoor water body sediment
CN104316391A (en) * 2014-10-10 2015-01-28 同济大学 Freezing and thawing test model device and method of simulating artificial ground freezing method
CN104806253A (en) * 2015-05-15 2015-07-29 中铁二局股份有限公司 Construction method for opening hole between rectangular pipe jacking channels
CN105758775A (en) * 2016-02-03 2016-07-13 华北水利水电大学 Device and method for detecting anti-penetrability performance of concrete impermeable wall
CN106124243A (en) * 2016-06-16 2016-11-16 重庆大学 Coal seam gas-bearing capacity measures advanced freezing sampling method
CN205691360U (en) * 2016-06-16 2016-11-16 重庆大学 Coal seam gas-bearing capacity measures advanced freezing sampler
CN206002338U (en) * 2016-08-31 2017-03-08 浙江中林勘察研究股份有限公司 A kind of original state sandy soil sampler
CN106525484A (en) * 2016-08-31 2017-03-22 浙江中林勘察研究股份有限公司 Sampling method and sampling device for original state sandy soil
CN106872210A (en) * 2017-03-28 2017-06-20 江西省水利科学研究院 A kind of method that drill core test cut-pff wall drills through complete opening original state core sample
CN106950077A (en) * 2017-05-16 2017-07-14 中国科学院武汉岩土力学研究所 A kind of prismatical joint rock mass sampling method
CN107119629A (en) * 2017-06-23 2017-09-01 广东水利电力职业技术学院(广东省水利电力技工学校) A kind of Ecological Retaining Wall and its method constructed on existing barricade
CN107237339A (en) * 2017-08-03 2017-10-10 杭州江润科技有限公司 A kind of concrete cut increases leakage preventing structure and its construction method
CN207623044U (en) * 2017-12-11 2018-07-17 河海大学 Vertical freezing sampling apparatus

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘小生 等: "饱和原状砂取样技术和质量控制", 《工程勘察》 *
周兴旺 等: "《矿山建设工程技术新进展》", 30 September 2008 *

Similar Documents

Publication Publication Date Title
CN105926636B (en) Deep Foundation Pit Frozen back cover construction method
CN106759297A (en) A kind of construction method of support pile and three pipe high-pressure rotary jet grouting pile deep basal pits
CN107085085B (en) Hydro-thermal power THM coupling manual pipe jacking disturbed soil grouting test device and method
CN105220687B (en) Prestressed concrete pipe pile grouting behind shaft or drift lining method fills core reinforcing construction method
CN108036985B (en) Device and method for manufacturing split grouting slurry vein and detecting permeability coefficient
CN106759250B (en) Unfavorable geologic body grouting method under the conditions of a kind of pressure-bearing seepage flow
CN109236367A (en) A kind of tunnel structure and its frozen construction method with antiseepage drain function
CN103410119A (en) Method for water interception curtain grouting in leakage concrete
CN106198890A (en) A kind of indoor grouting simulation test device and using method thereof
CN105155541A (en) Double-slurry closing construction method for sump
CN108166532A (en) A kind of groutable underground continuous wall connector and its construction method
CN105257309A (en) Tool changing construction method for in-chamber grouting of earth pressure balance shield machine in sand bed
CN208982109U (en) A kind of tunnel structure with antiseepage drain function
CN105604075B (en) It is easy to the interim dock entrance cofferdam construction method and cofferdam structure recovered
CN105178342B (en) Precipitation well casing and method for blocking reserved hole of foundation pit through precipitation well casing
CN104328781B (en) A kind of unfavorable geologic body controlling oozes profit chemical grouting method
CN109000963A (en) A kind of plastic concrete cut-off wall sampling method
WO2021013186A1 (en) Test device and test method for simulating earth-filling and grouting
CN108677959A (en) A kind of grouting tube and grouting construction method suitable for mortar depositing construction under the conditions of limited space
CN209603074U (en) A kind of ruggedized construction of geomembrane and concrete walls connecting portion
CN209011169U (en) A kind of experimental rig for simulating underground engineering impervious blocking material
CN204436370U (en) Determination of coal seam gas pressure structure in fractured rock
CN103114823B (en) A kind of device and method utilizing ice-bound embolism segmentation shutoff to hole
CN110055976A (en) A kind of reinforced concrete precast member
CN104278660B (en) The earth and rockfill dam of the direct fixed strengthening of the horizontal coiled pipe delamination pour slurry method of construction of building a dam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181214