CN111173536A - Freezing construction method for tunnel connection channel - Google Patents

Freezing construction method for tunnel connection channel Download PDF

Info

Publication number
CN111173536A
CN111173536A CN201911366379.7A CN201911366379A CN111173536A CN 111173536 A CN111173536 A CN 111173536A CN 201911366379 A CN201911366379 A CN 201911366379A CN 111173536 A CN111173536 A CN 111173536A
Authority
CN
China
Prior art keywords
freezing
holes
hole
tunnel
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911366379.7A
Other languages
Chinese (zh)
Inventor
张春雷
赵运乐
田福军
张昭
王龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC First Harbor Engineering Co Ltd
CCCC First Harbor Installation Engineering Co Ltd
Original Assignee
CCCC First Harbor Engineering Co Ltd
CCCC First Harbor Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC First Harbor Engineering Co Ltd, CCCC First Harbor Installation Engineering Co Ltd filed Critical CCCC First Harbor Engineering Co Ltd
Priority to CN201911366379.7A priority Critical patent/CN111173536A/en
Publication of CN111173536A publication Critical patent/CN111173536A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)
  • Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)

Abstract

The invention provides a freezing construction method for a tunnel connection channel, which comprises the following steps: construction preparation; the freezing curtain is designed to ensure that the strength of the frozen soil meets the requirement; designing a freezing hole; the temperature measuring hole and the pressure relief hole are designed. Compared with the traditional freezing construction method of the tunnel connection channel, the freezing construction method has the advantages that the reasonable positive freezing time is set, the heat dissipation amount of each meter of freezing pipe including the freezing calandria is not less than 100kcal/h, the lower salt water temperature and the larger salt water flow are adopted to accelerate the freezing speed, the pressure relief holes are arranged at the proper positions, the influence of frost heaving on the tunnel is reduced, the reasonable number, distribution and installation parameters of the freezing holes are set on the connection channel, the requirements of the freezing holes on the connection channel are met, a large amount of muddy water is prevented from gushing out during drilling, the construction is safe, and the requirement of connection channel excavation is met.

Description

Freezing construction method for tunnel connection channel
Technical Field
The invention relates to the technical field of tunnel engineering connection channel construction, in particular to a freezing construction method for a tunnel connection channel.
Background
The communication channel is an emergency channel arranged between the two tunnels, so that one tunnel can be conveniently and directly communicated with the other tunnel to play roles of communication, drainage, fire prevention and the like, if one tunnel has a problem, pedestrians can be transferred to the other tunnel through the communication channel, the safety factor is greatly increased, and the communication channel is called as an escape channel; meanwhile, when a problem occurs in one tunnel, the rescue workers can reach the connection channel from the other tunnel and then enter the position needing rescue through the connection channel, so that the purpose of quick rescue is achieved, and the rapid escape and rescue are facilitated.
The design of the connection channel usually adopts a freezing method to reinforce the stratum and mine method underground excavation construction, wherein the freezing construction is a key process of tunnel connection channel construction. However, in the prior art, the influence of frost heaving on the tunnel is large and the design of the freezing hole is unreasonable when the prior art is used for freezing the tunnel connection channel, so that certain potential safety hazards exist in the construction, and the requirement of connection channel excavation cannot be met.
Disclosure of Invention
The invention aims to solve the defects of the prior art and provides a freezing construction method for a tunnel communication channel.
In order to achieve the purpose, the invention adopts the following technical scheme:
a freezing construction method for a tunnel connection channel is characterized by comprising the following steps:
(1) preparation for construction
Before the operation, processing a workpiece, wherein the workpiece comprises a drill bit combination, a freezing pipe, an orifice pipe, an extension bar for an upper plug, a brine main pipe, a liquid collecting and distributing pipe, a freezing pipe head, a clean water tank, a brine tank, a tunnel prestressed support, an end well lifting frame and a communication channel waterproof door;
(2) freezing curtain
(2.1) when the active freezing is carried out, no precipitation measure can be taken within the range of 200m near the freezing area, and no concentrated water flow can be obtained in the soil layer in the freezing area;
(2.2) laying an insulating layer on the inner side of the tunnel near the freezing curtain within a range of 2m from the boundary of the designed freezing wall, wherein the insulating layer is made of flame-retardant flexible plastic foam insulating materials;
(2.3) the active freezing time can be adjusted according to the actual freezing effect, and the single-hole flow of the freezing hole is required to be not less than 5m3Positively freezing the brine for 7 days until the temperature is reduced to below 18 ℃ below zero, positively freezing the brine for 15 days until the temperature is reduced to below 24 ℃ below zero, ensuring that the temperature difference of the brine in the return circuit is not more than 2 ℃, and when excavating, reducing the temperature of the brine to below 28 ℃ below zero, if the temperature and the flow of the brine cannot meet the design requirements, prolonging the positive freezing time, wherein the designed heat dissipation amount of each meter of freezing pipes including freezing calandria is not less than 100 kcal/h;
(2.4) the temperature of the joint of the frozen wall and the tunnel segment on the arrangement ring of the freezing holes on the periphery of the excavated area is not higher than-5 ℃, and the average temperature of the frozen wall is designed to be-10 ℃ at other parts;
(2.5) when the stratum and the environmental condition in the construction have great changes with the original design basis data, correspondingly modifying the design of the freezing curtain in time to ensure that the frozen soil strength meets the requirements;
(3) freezing hole
(3.1) the number of the freezing holes of the communication channel is 63, wherein 40 freezing holes are arranged in the right tunnel, 23 freezing holes are arranged in the left tunnel, the hole opening position error of the freezing holes is not more than 100mm, and the segment joints, bolts, main ribs and steel tube rib plates are avoided;
(3.2) the maximum allowable deflection of the freezing holes is 150mm, the distance between the hole forming track of the freezing holes and the design track is 1300mm, and the maximum allowable distance of the final holes of the freezing holes of the communication channel is 1300 mm;
(3.3) 4 pairs of through holes are arranged in the communication channel and are used for circulating the brine in the freezing hole on the opposite side;
(3.4) the effective depth of the freezing hole is the length of the circulating brine section of the freezing pipe below the surface of the pipe piece and is not less than the design depth of the freezing hole, the head of the freezing pipe touches the freezing hole of the opposite side tunnel pipe piece of the freezing station, and the length of the head which can not circulate the brine is not more than 150 mm;
(3.5) the pressure resistance of the freezing pipe is not lower than 0.8Mpa and not lower than 1.5 times of the salt water pressure of the freezing working surface;
(3.6) the freezing pipes are connected by screw threads and then welded, and the compressive strength of the joints is not lower than 75% of that of the main pipes;
(3.7) when the freezing hole is constructed, the soil mass loss is not more than the freezing hole volume, otherwise, grouting is carried out in time to control the stratum settlement;
(3.8) the positions of the reserved openings of the two tunnels are rechecked through the through holes, and if the relative position error of the reserved openings of the two tunnels is more than 100mm, the arrangement of the freezing holes is adjusted according to the principle of ensuring the design thickness of the freezing wall;
(4) temperature measuring hole and pressure relief hole
The number of the temperature measuring holes 8 are arranged in the communication channel and are respectively arranged inside and outside the channel and in the tunnels at two sides, wherein 2 freezing stations are arranged on the side, 6 freezing stations are arranged on the side opposite to the side tunnels, the depth is 2-5.5m, 4 pressure relief holes are arranged in the middle of the freezing curtain, 2 left lines and 2 right lines are arranged respectively, and the depth is 3 m.
Preferably, in the step (2.2), the heat-insulating layer has a thickness of 50mm and a thermal conductivity of not more than 0.04W/MK.
Preferably, the active freezing time of the communication channel in step (2.3) is designed to be 40-45 days.
Preferably, the frozen soil strength in the step (2.5) is designed as follows: under the temperature of minus 10 ℃, the uniaxial compression resistance is 4.1Mpa, the bending resistance is 1.8Mpa and the shearing resistance is 1.5 Mpa.
Preferably, the freezing pipe in the step (3.5) is made of 20# Q235B steel
Figure BDA0002338532510000031
89X 8mm low-carbon seamless steel pipe.
The invention has the beneficial effects that: the invention has simple process, compared with the freezing construction method of the traditional tunnel connection channel, the reasonable positive freezing time is set, the heat dissipation capacity of each meter of freezing pipe including the freezing calandria is not less than 100kcal/h, the lower salt water temperature and the larger salt water flow are adopted to accelerate the freezing speed, the pressure relief holes are arranged at the proper positions to reduce the influence of frost heaving on the tunnel, the reasonable freezing hole number, distribution and installation parameters are set on the connection channel to meet the requirement of the freezing holes on the connection channel, prevent a large amount of muddy water from gushing out during drilling, ensure the construction safety and further meet the requirement of the excavation of the connection channel.
Detailed Description
The invention is further illustrated by the following examples:
a freezing construction method for a tunnel connection channel is characterized by comprising the following steps:
(1) preparation for construction
Before the operation, processing a workpiece, wherein the workpiece comprises a drill bit combination, a freezing pipe, an orifice pipe, an extension bar for an upper plug, a brine main pipe, a liquid collecting and distributing pipe, a freezing pipe head, a clean water tank, a brine tank, a tunnel prestressed support, an end well lifting frame and a communication channel waterproof door;
(2) freezing curtain
(2.1) when the active freezing is carried out, no precipitation measure can be taken within the range of 200m near the freezing area, and no concentrated water flow can be obtained in the soil layer in the freezing area;
(2.2) laying an insulating layer on the inner side of the tunnel near the freezing curtain within a range of 2m from the boundary of the designed freezing wall, wherein the insulating layer is made of flame-retardant flexible plastic foam insulating materials;
(2.3) the active freezing time can be adjusted according to the actual freezing effect, and the single-hole flow of the freezing hole is required to be not less than 5m3Positively freezing the brine for 7 days until the temperature is reduced to below 18 ℃ below zero, positively freezing the brine for 15 days until the temperature is reduced to below 24 ℃ below zero, ensuring that the temperature difference of the brine in the return circuit is not more than 2 ℃, and when excavating, reducing the temperature of the brine to below 28 ℃ below zero, if the temperature and the flow of the brine cannot meet the design requirements, prolonging the positive freezing time, wherein the designed heat dissipation amount of each meter of freezing pipes including freezing calandria is not less than 100 kcal/h;
(2.4) the temperature of the joint of the frozen wall and the tunnel segment on the arrangement ring of the freezing holes on the periphery of the excavated area is not higher than-5 ℃, and the average temperature of the frozen wall is designed to be-10 ℃ at other parts;
(2.5) when the stratum and the environmental condition in the construction have great changes with the original design basis data, correspondingly modifying the design of the freezing curtain in time to ensure that the frozen soil strength meets the requirements;
(3) freezing hole
(3.1) the number of the freezing holes of the communication channel is 63, wherein 40 freezing holes are arranged in the right tunnel, 23 freezing holes are arranged in the left tunnel, the hole opening position error of the freezing holes is not more than 100mm, and the segment joints, bolts, main ribs and steel tube rib plates are avoided;
(3.2) the maximum allowable deflection of the freezing holes is 150mm, the distance between the hole forming track of the freezing holes and the design track is 1300mm, and the maximum allowable distance of the final holes of the freezing holes of the communication channel is 1300 mm;
(3.3) 4 pairs of through holes are arranged in the communication channel and are used for circulating the brine in the freezing hole on the opposite side;
(3.4) the effective depth of the freezing hole is the length of the circulating brine section of the freezing pipe below the surface of the pipe piece and is not less than the design depth of the freezing hole, the head of the freezing pipe touches the freezing hole of the opposite side tunnel pipe piece of the freezing station, and the length of the head which can not circulate the brine is not more than 150 mm;
(3.5) the pressure resistance of the freezing pipe is not lower than 0.8Mpa and not lower than 1.5 times of the salt water pressure of the freezing working surface;
(3.6) the freezing pipes are connected by screw threads and then welded, and the compressive strength of the joints is not lower than 75% of that of the main pipes;
(3.7) when the freezing hole is constructed, the soil mass loss is not more than the freezing hole volume, otherwise, grouting is carried out in time to control the stratum settlement;
(3.8) the positions of the reserved openings of the two tunnels are rechecked through the through holes, and if the relative position error of the reserved openings of the two tunnels is more than 100mm, the arrangement of the freezing holes is adjusted according to the principle of ensuring the design thickness of the freezing wall;
(4) temperature measuring hole and pressure relief hole
The number of the temperature measuring holes 8 are arranged in the communication channel and are respectively arranged inside and outside the channel and in the tunnels at two sides, wherein 2 freezing stations are arranged on the side, 6 freezing stations are arranged on the side opposite to the side tunnels, the depth is 2-5.5m, 4 pressure relief holes are arranged in the middle of the freezing curtain, 2 left lines and 2 right lines are arranged respectively, and the depth is 3 m.
Preferably, in the step (2.2), the heat-insulating layer has a thickness of 50mm and a thermal conductivity of not more than 0.04W/MK.
Preferably, the active freezing time of the communication channel in step (2.3) is designed to be 40-45 days.
Preferably, the frozen soil strength in the step (2.5) is designed as follows: under the temperature of minus 10 ℃, the uniaxial compression resistance is 4.1Mpa, the bending resistance is 1.8Mpa and the shearing resistance is 1.5 Mpa.
Preferably, the freezing pipe in the step (3.5) is made of 20# Q235B steel
Figure BDA0002338532510000051
89X 8mm low-carbon seamless steel pipe.
Example 1
A freezing construction method for a tunnel connection channel comprises the following steps:
(1) preparation for construction
Before the operation, processing a workpiece, wherein the workpiece comprises a drill bit combination, a freezing pipe, an orifice pipe, an extension bar for an upper plug, a brine main pipe, a liquid collecting and distributing pipe, a freezing pipe head, a clean water tank, a brine tank, a tunnel prestressed support, an end well lifting frame and a communication channel waterproof door;
(2) freezing curtain
(2.1) when the active freezing is carried out, no precipitation measure can be taken within the range of 200m near the freezing area, and no concentrated water flow can be obtained in the soil layer in the freezing area;
(2.2) laying an insulating layer on the inner side of the tunnel near the freezing curtain within a range of 2m from the boundary of the designed freezing wall, wherein the insulating layer is made of flame-retardant flexible plastic foam insulating material, the thickness of the insulating layer is 50mm, and the heat conductivity coefficient of the insulating layer is 0.04W/MK;
(2.3) the active freezing time of the communication channel is designed to be 40 days, and the single-hole flow of the freezing hole is required to be 8m3Positively freezing the brine for 7 days until the temperature is reduced to below 18 ℃ below zero, positively freezing the brine for 15 days until the temperature is reduced to below 24 ℃ below zero, ensuring that the temperature difference of the brine in the return circuit is not more than 2 ℃, and when excavating, reducing the temperature of the brine to below 28 ℃ below zero, if the temperature and the flow of the brine cannot meet the design requirements, prolonging the positive freezing time, wherein the designed heat dissipation of each meter of freezing pipes including freezing calandria is 105 kcal/h;
(2.4) the temperature of the joint of the frozen wall and the tunnel segment on the arrangement ring of the freezing holes on the periphery of the excavated area is not higher than-5 ℃, and the average temperature of the frozen wall is designed to be-10 ℃ at other parts;
(2.5) when the stratum and the environmental condition in the construction have great changes with the original design basis data, correspondingly modifying the design of the freezing curtain in time to ensure that the frozen soil strength meets the requirements, wherein the design requirements of the frozen soil strength at the temperature of minus 10 ℃ are as follows: uniaxial compression resistance of 4.1Mpa, bending resistance of 1.8Mpa and shearing resistance of 1.5 Mpa;
(3) freezing hole
(3.1) the number of the freezing holes of the communication channel is 63, wherein 40 freezing holes are arranged in the right tunnel, 23 freezing holes are arranged in the left tunnel, the hole opening position error of the freezing holes is not more than 100mm, and the segment joints, bolts, main ribs and steel tube rib plates are avoided;
(3.2) the maximum allowable deflection of the freezing holes is 150mm, the distance between the hole forming track of the freezing holes and the design track is 1300mm, and the maximum allowable distance of the final holes of the freezing holes of the communication channel is 1300 mm;
(3.3) 4 pairs of through holes are arranged in the communication channel and are used for circulating the brine in the freezing hole on the opposite side;
(3.4) the effective depth of the freezing hole is the length of the circulating brine section of the freezing pipe below the surface of the pipe piece and is not less than the design depth of the freezing hole, the head of the freezing pipe touches the freezing hole of the opposite side tunnel pipe piece of the freezing station, and the length of the head which can not circulate the brine is not more than 150 mm;
(3.5) the freezing pipe is made of 20# Q235B steel
Figure BDA0002338532510000061
89 x 8mm low-carbon seamless steel pipe, the pressure resistance of the freezing pipe is not lower than 0.8Mpa, and is not lower than 1.5 times of the salt water pressure of the freezing working surface;
(3.6) the freezing pipes are connected by screw threads and then welded, and the compressive strength of the joints is not lower than 75% of that of the main pipes;
(3.7) when the freezing hole is constructed, the soil mass loss is not more than the freezing hole volume, otherwise, grouting is carried out in time to control the stratum settlement;
(3.8) the positions of the reserved openings of the two tunnels are rechecked through the through holes, and if the relative position error of the reserved openings of the two tunnels is more than 100mm, the arrangement of the freezing holes is adjusted according to the principle of ensuring the design thickness of the freezing wall;
(4) temperature measuring hole and pressure relief hole
8 temperature measurement holes are arranged in the communication channel, the temperature measurement holes are respectively arranged inside and outside the channel and in tunnels at two sides, 2 temperature measurement holes are arranged on the side of the freezing station, 6 temperature measurement holes are arranged on the side of the freezing station, the depth of each temperature measurement hole is 2m, 4 pressure relief holes are arranged in the middle of the freezing curtain, and the left line and the right line are 2 and 3m in depth.
Example 2
A freezing construction method for a tunnel connection channel comprises the following steps:
(1) preparation for construction
Before the operation, processing a workpiece, wherein the workpiece comprises a drill bit combination, a freezing pipe, an orifice pipe, an extension bar for an upper plug, a brine main pipe, a liquid collecting and distributing pipe, a freezing pipe head, a clean water tank, a brine tank, a tunnel prestressed support, an end well lifting frame and a communication channel waterproof door;
(2) freezing curtain
(2.1) when the active freezing is carried out, no precipitation measure can be taken within the range of 200m near the freezing area, and no concentrated water flow can be obtained in the soil layer in the freezing area;
(2.2) laying an insulating layer on the inner side of the tunnel near the freezing curtain within a range of 2m from the boundary of the designed freezing wall, wherein the insulating layer is made of flame-retardant flexible plastic foam insulating material, the thickness of the insulating layer is 50mm, and the heat conductivity coefficient of the insulating layer is 0.02W/MK;
(2.3) the active freezing time can be adjusted according to the actual freezing effect, the active freezing time of the communication channel is designed to be 43 days, and the single-hole flow of the freezing hole is required to be 10m3Positively freezing the brine for 7 days until the temperature is reduced to below 18 ℃ below zero, positively freezing the brine for 15 days until the temperature is reduced to below 24 ℃ below zero, ensuring that the temperature difference of the brine in the return circuit is not more than 2 ℃, and when excavating, reducing the temperature of the brine to below 28 ℃ below zero, if the temperature and the flow of the brine cannot meet the design requirements, prolonging the positive freezing time, wherein the designed heat dissipation of each meter of freezing pipes including freezing calandria is 150 kcal/h;
(2.4) the temperature of the joint of the frozen wall and the tunnel segment on the arrangement ring of the freezing holes on the periphery of the excavated area is not higher than-5 ℃, and the average temperature of the frozen wall is designed to be-10 ℃ at other parts;
(2.5) when the stratum and the environmental condition in the construction have great changes with the original design basis data, correspondingly modifying the design of the freezing curtain in time to ensure that the frozen soil strength meets the requirements, wherein the design requirements of the frozen soil strength at the temperature of minus 10 ℃ are as follows: uniaxial compression resistance of 4.1Mpa, bending resistance of 1.8Mpa and shearing resistance of 1.5 Mpa;
(3) freezing hole
(3.1) the number of the freezing holes of the communication channel is 63, wherein 40 freezing holes are arranged in the right tunnel, 23 freezing holes are arranged in the left tunnel, the hole opening position error of the freezing holes is not more than 100mm, and the segment joints, bolts, main ribs and steel tube rib plates are avoided;
(3.2) the maximum allowable deflection of the freezing holes is 150mm, the distance between the hole forming track of the freezing holes and the design track is 1300mm, and the maximum allowable distance of the final holes of the freezing holes of the communication channel is 1300 mm;
(3.3) 4 pairs of through holes are arranged in the communication channel and are used for circulating the brine in the freezing hole on the opposite side;
(3.4) the effective depth of the freezing hole is the length of the circulating brine section of the freezing pipe below the surface of the pipe piece and is not less than the design depth of the freezing hole, the head of the freezing pipe touches the freezing hole of the opposite side tunnel pipe piece of the freezing station, and the length of the head which can not circulate the brine is not more than 150 mm;
(3.5) the freezing pipe is made of 20# Q235B steel
Figure BDA0002338532510000071
89 x 8mm low-carbon seamless steel pipe, the pressure resistance of the freezing pipe is not lower than 0.8Mpa, and is not lower than 1.5 times of the salt water pressure of the freezing working surface;
(3.6) the freezing pipes are connected by screw threads and then welded, and the compressive strength of the joints is not lower than 75% of that of the main pipes;
(3.7) when the freezing hole is constructed, the soil mass loss is not more than the freezing hole volume, otherwise, grouting is carried out in time to control the stratum settlement;
(3.8) the positions of the reserved openings of the two tunnels are rechecked through the through holes, and if the relative position error of the reserved openings of the two tunnels is more than 100mm, the arrangement of the freezing holes is adjusted according to the principle of ensuring the design thickness of the freezing wall;
(4) temperature measuring hole and pressure relief hole
8 temperature measuring holes are arranged in the communication channel and are respectively arranged inside and outside the channel and in tunnels at two sides, wherein 2 freezing stations are arranged on the side, 6 freezing stations are arranged on the side opposite to the side tunnels, the depth is 4.5m, 4 pressure relief holes are arranged in the middle of the freezing curtain, 2 left and right lines are arranged, and the depth is 3 m.
Example 3
A freezing construction method for a tunnel connection channel comprises the following steps:
(1) preparation for construction
Before the operation, processing a workpiece, wherein the workpiece comprises a drill bit combination, a freezing pipe, an orifice pipe, an extension bar for an upper plug, a brine main pipe, a liquid collecting and distributing pipe, a freezing pipe head, a clean water tank, a brine tank, a tunnel prestressed support, an end well lifting frame and a communication channel waterproof door;
(2) freezing curtain
(2.1) when the active freezing is carried out, no precipitation measure can be taken within the range of 200m near the freezing area, and no concentrated water flow can be obtained in the soil layer in the freezing area;
(2.2) laying an insulating layer on the inner side of the tunnel near the freezing curtain within a range of 2m from the boundary of the designed freezing wall, wherein the insulating layer is made of flame-retardant flexible plastic foam insulating material, the thickness of the insulating layer is 50mm, and the heat conductivity coefficient of the insulating layer is 0.01W/MK;
(2.3) the active freezing time can be adjusted according to the actual freezing effect, the active freezing time of the communication channel is designed to be 45 days, and the single-hole flow of the freezing hole is required to be 18m3Positively freezing the brine for 7 days until the temperature is reduced to below 18 ℃ below zero, positively freezing the brine for 15 days until the temperature is reduced to below 24 ℃ below zero, ensuring that the temperature difference of the brine in the return circuit is not more than 2 ℃, and when excavating, reducing the temperature of the brine to below 28 ℃ below zero, if the temperature and the flow of the brine cannot meet the design requirements, prolonging the positive freezing time, wherein the designed heat dissipation amount of each meter of freezing pipes including freezing calandria is 220 kcal/h;
(2.4) the temperature of the joint of the frozen wall and the tunnel segment on the arrangement ring of the freezing holes on the periphery of the excavated area is not higher than-5 ℃, and the average temperature of the frozen wall is designed to be-10 ℃ at other parts;
(2.5) when the stratum and the environmental condition in the construction have great changes with the original design basis data, correspondingly modifying the design of the freezing curtain in time to ensure that the frozen soil strength meets the requirements, wherein the design requirements of the frozen soil strength at the temperature of minus 10 ℃ are as follows: uniaxial compression resistance of 4.1Mpa, bending resistance of 1.8Mpa and shearing resistance of 1.5 Mpa;
(3) freezing hole
(3.1) the number of the freezing holes of the communication channel is 63, wherein 40 freezing holes are arranged in the right tunnel, 23 freezing holes are arranged in the left tunnel, the hole opening position error of the freezing holes is not more than 100mm, and the segment joints, bolts, main ribs and steel tube rib plates are avoided;
(3.2) the maximum allowable deflection of the freezing holes is 150mm, the distance between the hole forming track of the freezing holes and the design track is 1300mm, and the maximum allowable distance of the final holes of the freezing holes of the communication channel is 1300 mm;
(3.3) 4 pairs of through holes are arranged in the communication channel and are used for circulating the brine in the freezing hole on the opposite side;
(3.4) the effective depth of the freezing hole is the length of the circulating brine section of the freezing pipe below the surface of the pipe piece and is not less than the design depth of the freezing hole, the head of the freezing pipe touches the freezing hole of the opposite side tunnel pipe piece of the freezing station, and the length of the head which can not circulate the brine is not more than 150 mm;
(3.5) the freezing pipe is made of 20# Q235B steel
Figure BDA0002338532510000091
89 x 8mm low-carbon seamless steel pipe, the pressure resistance of the freezing pipe is not lower than 0.8Mpa, and is not lower than 1.5 times of the salt water pressure of the freezing working surface;
(3.6) the freezing pipes are connected by screw threads and then welded, and the compressive strength of the joints is not lower than 75% of that of the main pipes;
(3.7) when the freezing hole is constructed, the soil mass loss is not more than the freezing hole volume, otherwise, grouting is carried out in time to control the stratum settlement;
(3.8) the positions of the reserved openings of the two tunnels are rechecked through the through holes, and if the relative position error of the reserved openings of the two tunnels is more than 100mm, the arrangement of the freezing holes is adjusted according to the principle of ensuring the design thickness of the freezing wall;
(4) temperature measuring hole and pressure relief hole
8 temperature measuring holes are arranged in the communication channel and are respectively arranged inside and outside the channel and in tunnels at two sides, wherein 2 freezing stations are arranged on the side, 6 freezing stations are arranged on the side opposite to the side tunnels, the depth is 5.5m, 4 pressure relief holes are arranged in the middle of the freezing curtain, 2 left and right lines are arranged, and the depth is 3 m.
The invention has been described in an illustrative manner, and it is to be understood that the invention is not limited to the specific embodiments described above, but is intended to cover various modifications, which may be made by the methods and technical solutions of the invention, or may be applied to other applications without modification.

Claims (5)

1. A freezing construction method for a tunnel connection channel is characterized by comprising the following steps:
(1) preparation for construction
Before the operation, processing a workpiece, wherein the workpiece comprises a drill bit combination, a freezing pipe, an orifice pipe, an extension bar for an upper plug, a brine main pipe, a liquid collecting and distributing pipe, a freezing pipe head, a clean water tank, a brine tank, a tunnel prestressed support, an end well lifting frame and a communication channel waterproof door;
(2) freezing curtain
(2.1) when the active freezing is carried out, no precipitation measure can be taken within the range of 200m near the freezing area, and no concentrated water flow can be obtained in the soil layer in the freezing area;
(2.2) laying an insulating layer on the inner side of the tunnel near the freezing curtain within a range of 2m from the boundary of the designed freezing wall, wherein the insulating layer is made of flame-retardant flexible plastic foam insulating materials;
(2.3) the active freezing time can be adjusted according to the actual freezing effect, and the single-hole flow of the freezing hole is required to be not less than 5m3Positively freezing the brine for 7 days until the temperature is reduced to below 18 ℃ below zero, positively freezing the brine for 15 days until the temperature is reduced to below 24 ℃ below zero, ensuring that the temperature difference of the brine in the return circuit is not more than 2 ℃, and when excavating, reducing the temperature of the brine to below 28 ℃ below zero, if the temperature and the flow of the brine cannot meet the design requirements, prolonging the positive freezing time, wherein the designed heat dissipation amount of each meter of freezing pipes including freezing calandria is not less than 100 kcal/h;
(2.4) the temperature of the joint of the frozen wall and the tunnel segment on the arrangement ring of the freezing holes on the periphery of the excavated area is not higher than-5 ℃, and the average temperature of the frozen wall is designed to be-10 ℃ at other parts;
(2.5) when the stratum and the environmental condition in the construction have great changes with the original design basis data, correspondingly modifying the design of the freezing curtain in time to ensure that the frozen soil strength meets the requirements;
(3) freezing hole
(3.1) the number of the freezing holes of the communication channel is 63, wherein 40 freezing holes are arranged in the right tunnel, 23 freezing holes are arranged in the left tunnel, the hole opening position error of the freezing holes is not more than 100mm, and the segment joints, bolts, main ribs and steel tube rib plates are avoided;
(3.2) the maximum allowable deflection of the freezing holes is 150mm, the distance between the hole forming track of the freezing holes and the design track is 1300mm, and the maximum allowable distance of the final holes of the freezing holes of the communication channel is 1300 mm;
(3.3) 4 pairs of through holes are arranged in the communication channel and are used for circulating the brine in the freezing hole on the opposite side;
(3.4) the effective depth of the freezing hole is the length of the circulating brine section of the freezing pipe below the surface of the pipe piece and is not less than the design depth of the freezing hole, the head of the freezing pipe touches the freezing hole of the opposite side tunnel pipe piece of the freezing station, and the length of the head which can not circulate the brine is not more than 150 mm;
(3.5) the pressure resistance of the freezing pipe is not lower than 0.8Mpa and not lower than 1.5 times of the salt water pressure of the freezing working surface;
(3.6) the freezing pipes are connected by screw threads and then welded, and the compressive strength of the joints is not lower than 75% of that of the main pipes;
(3.7) when the freezing hole is constructed, the soil mass loss is not more than the freezing hole volume, otherwise, grouting is carried out in time to control the stratum settlement;
(3.8) the positions of the reserved openings of the two tunnels are rechecked through the through holes, and if the relative position error of the reserved openings of the two tunnels is more than 100mm, the arrangement of the freezing holes is adjusted according to the principle of ensuring the design thickness of the freezing wall;
(4) temperature measuring hole and pressure relief hole
The number of the temperature measuring holes 8 are arranged in the communication channel and are respectively arranged inside and outside the channel and in the tunnels at two sides, wherein 2 freezing stations are arranged on the side, 6 freezing stations are arranged on the side opposite to the side tunnels, the depth is 2-5.5m, 4 pressure relief holes are arranged in the middle of the freezing curtain, 2 left lines and 2 right lines are arranged respectively, and the depth is 3 m.
2. The freezing construction method for the tunnel communication channel according to claim 1, wherein the thickness of the heat-insulating layer in the step (2.2) is 50mm, and the thermal conductivity is not more than 0.04W/MK.
3. The freezing construction method for the tunnel communication channel according to claim 1, wherein the active freezing time of the communication channel in the step (2.3) is designed to be 40-45 days.
4. The freezing construction method for the tunnel communication channel according to claim 1, wherein the design requirement of the frozen soil strength in the step (2.5) is as follows: under the temperature of minus 10 ℃, the uniaxial compression resistance is 4.1Mpa, the bending resistance is 1.8Mpa and the shearing resistance is 1.5 Mpa.
5. The freezing construction method for the tunnel communication channel according to claim 1, wherein the freezing pipe in the step (3.5) is made of 20# Q235B steel
Figure FDA0002338532500000021
The low-carbon seamless steel pipe.
CN201911366379.7A 2019-12-26 2019-12-26 Freezing construction method for tunnel connection channel Pending CN111173536A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911366379.7A CN111173536A (en) 2019-12-26 2019-12-26 Freezing construction method for tunnel connection channel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911366379.7A CN111173536A (en) 2019-12-26 2019-12-26 Freezing construction method for tunnel connection channel

Publications (1)

Publication Number Publication Date
CN111173536A true CN111173536A (en) 2020-05-19

Family

ID=70657499

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911366379.7A Pending CN111173536A (en) 2019-12-26 2019-12-26 Freezing construction method for tunnel connection channel

Country Status (1)

Country Link
CN (1) CN111173536A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113153312A (en) * 2021-03-30 2021-07-23 广东华隧建设集团股份有限公司 Construction and monitoring method for freezing soft and hard strata of subway communication channel
CN115977650A (en) * 2022-11-22 2023-04-18 安徽理工大学 Communication freezing system based on plane skew connection channel and construction method thereof

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08189290A (en) * 1995-01-12 1996-07-23 Komatsu Ltd Shield excavator for underground jointing and method for underground jointing of tunnel
EA011909B1 (en) * 2008-01-30 2009-06-30 Открытое Акционерное Общество "Белгорхимпром" (Оао "Белгорхимпром") Method of vertical shaft sinking
CN104806253A (en) * 2015-05-15 2015-07-29 中铁二局股份有限公司 Construction method for opening hole between rectangular pipe jacking channels
CN105569661A (en) * 2015-10-12 2016-05-11 上海勘测设计研究院有限公司 Arrangement structure and construction method of river-crossing underground square
CN106089214A (en) * 2016-06-21 2016-11-09 中铁十局集团第三建设有限公司 Service channel manual pipe jacking reinforced construction method
CN106593487A (en) * 2017-02-03 2017-04-26 天津大学 Detachable steel tube section construction method used for freezing method construction in tunnel contact channel
CN107740699A (en) * 2017-09-01 2018-02-27 北京中煤矿山工程有限公司 The method that ground pours construction freezing method Metro Connection Passage concrete structure
CN109083645A (en) * 2018-08-01 2018-12-25 南宁轨道交通集团有限责任公司 Shield tunnel and service channel method for synchronously constructing under the conditions of rich water round gravel stratum
CN110159275A (en) * 2019-06-26 2019-08-23 中交路桥建设有限公司 Water-rich sand layer geology Metro Thoroughfare freezing hole arragement construction and construction method

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08189290A (en) * 1995-01-12 1996-07-23 Komatsu Ltd Shield excavator for underground jointing and method for underground jointing of tunnel
EA011909B1 (en) * 2008-01-30 2009-06-30 Открытое Акционерное Общество "Белгорхимпром" (Оао "Белгорхимпром") Method of vertical shaft sinking
CN104806253A (en) * 2015-05-15 2015-07-29 中铁二局股份有限公司 Construction method for opening hole between rectangular pipe jacking channels
CN105569661A (en) * 2015-10-12 2016-05-11 上海勘测设计研究院有限公司 Arrangement structure and construction method of river-crossing underground square
CN106089214A (en) * 2016-06-21 2016-11-09 中铁十局集团第三建设有限公司 Service channel manual pipe jacking reinforced construction method
CN106593487A (en) * 2017-02-03 2017-04-26 天津大学 Detachable steel tube section construction method used for freezing method construction in tunnel contact channel
CN107740699A (en) * 2017-09-01 2018-02-27 北京中煤矿山工程有限公司 The method that ground pours construction freezing method Metro Connection Passage concrete structure
CN109083645A (en) * 2018-08-01 2018-12-25 南宁轨道交通集团有限责任公司 Shield tunnel and service channel method for synchronously constructing under the conditions of rich water round gravel stratum
CN110159275A (en) * 2019-06-26 2019-08-23 中交路桥建设有限公司 Water-rich sand layer geology Metro Thoroughfare freezing hole arragement construction and construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113153312A (en) * 2021-03-30 2021-07-23 广东华隧建设集团股份有限公司 Construction and monitoring method for freezing soft and hard strata of subway communication channel
CN113153312B (en) * 2021-03-30 2022-04-08 广东华隧建设集团股份有限公司 Construction and monitoring method for freezing soft and hard strata of subway communication channel
CN115977650A (en) * 2022-11-22 2023-04-18 安徽理工大学 Communication freezing system based on plane skew connection channel and construction method thereof

Similar Documents

Publication Publication Date Title
CN108060908B (en) Long-distance horizontal directional drilling and grouting reinforcement process for water-rich sand layer under building group
WO2020244677A1 (en) Freezing construction method for connecting passage, and freezing system
CN104074525B (en) Full-face pouring, rectangular horizontal are freezed and pipe canopy joint reinforcement structure and method
CN104963334B (en) Reinforced with slip casting freezing pipe and freeze the construction method that service channel suppresses frozen swell and melt settlement
CN105908765B (en) For protecting the open trench tunnel water sealing structure and construction method of groundwater environment
CN201460904U (en) Ultra-long horizontal freezing consolidation structure for shield entry
CN111173536A (en) Freezing construction method for tunnel connection channel
CN106121686B (en) Underground excavation tunnel water stop structure for protecting groundwater environment and construction method thereof
CN104088652B (en) A kind of pipe interlude horizontal dynamic controlling freezes water-stop method
CN106812540B (en) Shield initial plain wall sealing water-stopping reinforcing structure and construction process
CN207131404U (en) Railway tunnel ultra-deep shaft construction freezing method structural system
CN104806253A (en) Construction method for opening hole between rectangular pipe jacking channels
CN109296371A (en) MJS method and horizontal freezing joint reinforcement pressure-bearing rich water arenaceous stratum overlap the system and its construction method that section is worn under station
CN110878697A (en) Shield underwater receiving method next to urban main road in high-water-rich sandy gravel stratum
CN111608688A (en) Method for reinforcing ground of shield underpass building
CN111945704A (en) Method for reinforcing water-rich silt stratum by obliquely arranging multiple rows of freezing pipes
CN113323680B (en) Disposal method for long-time shutdown of shield machine in tunneling tunnel
CN210714701U (en) Freezing system for freezing construction of communication channel
CN104481571B (en) Mine flyash grouting fire extinguishing method
CN111550251A (en) Structure for realizing freezing of contact channel of shield tunnel of water-rich sand layer and construction process
CN103527205A (en) Shield underwater oblique crossing hole entering construction method
CN215169989U (en) Freezing system for reinforcing 60-meter-grade ultra-long distance communication channel by freezing method
CN112832821B (en) Fracture surface supporting method based on high pressure water fault fracture zone rheological research
CN212296407U (en) Reinforced structure of shield underpass building
CN112302669A (en) Subway shield arrival auxiliary construction method and structure under complex environment condition

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication