CN106065661A - Large span unsettled steel corridor construction engineering method - Google Patents
Large span unsettled steel corridor construction engineering method Download PDFInfo
- Publication number
- CN106065661A CN106065661A CN201610420915.7A CN201610420915A CN106065661A CN 106065661 A CN106065661 A CN 106065661A CN 201610420915 A CN201610420915 A CN 201610420915A CN 106065661 A CN106065661 A CN 106065661A
- Authority
- CN
- China
- Prior art keywords
- sliding
- lifting
- iii
- pull
- lifter
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/0046—Loggias
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04G—SCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
- E04G21/00—Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
- E04G21/14—Conveying or assembling building elements
- E04G21/16—Tools or apparatus
- E04G21/162—Handles to carry construction blocks
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Mechanical Engineering (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
本发明公开了一种大跨度悬空钢连廊施工工法,采用以下步骤:1)设置多个提升滑移装置;在裙楼上完成上部钢结构的成型;2)启动提升滑移装置的提升器,将上部钢结构提升至第一设定高度;3)在裙楼上完成第一下挂层钢结构的成型,将第一下挂层钢结构连接在上部钢结构的下方,启动提升滑移装置的提升器,将上部钢结构提升至第二设定高度;4)重复步骤3),直至完成所有下挂层钢结构的连接;5)启动所有提升滑移装置的提升器,将整个悬空钢连廊整体同步提升至安装设计高度;6)启动提升滑移装置的推拉器,将钢连廊整体滑移就位。本发明能够完成超限高、大跨度悬空、利用裙楼楼面作业且荷载力不足、采用整体提升无可靠提升点的钢连廊施工。
The invention discloses a construction method for a large-span suspended steel corridor, which adopts the following steps: 1) setting a plurality of lifting and sliding devices; completing the forming of the upper steel structure on the podium; 2) starting the lifter of the lifting and sliding devices , lift the upper steel structure to the first set height; 3) complete the forming of the first lower hanging layer steel structure on the podium, connect the first lower hanging layer steel structure below the upper steel structure, and start lifting and sliding The lifter of the device lifts the upper steel structure to the second set height; 4) Repeat step 3) until the connection of all lower hanging layer steel structures is completed; 5) Start the lifters of all lifting and sliding devices to lift the entire suspended The whole steel corridor is synchronously lifted to the installation design height; 6) The push-pull device of the lifting and sliding device is activated to slide the whole steel corridor into place. The invention can complete the construction of steel corridors with over-limit height, large-span suspended, using podium floors for operation and insufficient load capacity, and adopting overall lifting without reliable lifting points.
Description
技术领域technical field
本发明涉及一种钢连廊的施工方法,特别是涉及一种大跨度悬空钢连廊施工工法。The invention relates to a construction method for a steel corridor, in particular to a construction method for a large-span suspended steel corridor.
背景技术Background technique
随着社会经济的发展,人们对于建筑的需求和需要也在不断增加与提高,连体复杂高层建筑大量涌现。连体结构一般指两幢或几幢高层建筑之间由架空连接体相互连接,满足建筑造型及使用功能的要求。连体结构的设置一方面出于建筑功能的要求,可以方便两塔楼之间的联系。当前的连体结构具有良好的采光效果和广阔的视野,由于连体结构的设置,使建筑外观上更具特色。目前大跨度高空连体钢结构施工方法主要包括:高空散装法、分条(分块)吊装法、整体提升法、整体吊装法、悬臂安装法、高空滑移法、逆作安装法等。With the development of social economy, people's demands and needs for buildings are also increasing and improving, and a large number of conjoined complex high-rise buildings have emerged. Conjoined structures generally refer to two or several high-rise buildings connected to each other by overhead connectors to meet the requirements of building shape and use function. On the one hand, the setting of the conjoined structure is due to the requirements of architectural functions, which can facilitate the connection between the two towers. The current conjoined structure has good lighting effects and a wide field of vision. Due to the setting of the conjoined structure, the appearance of the building is more distinctive. At present, the construction methods of large-span high-altitude conjoined steel structures mainly include: high-altitude bulk method, strip (block) hoisting method, overall lifting method, overall hoisting method, cantilever installation method, high-altitude sliding method, reverse installation method, etc.
某综合体项目的钢结构连廊主要由桁架连接而成的上部钢结构和下挂层钢结构组成。连廊整体平面呈矩形,包括左右两部分,左边部分与A塔楼连接,由位于楼面板上的结构内部分和与其连接的悬挑部分组成,右边部分是将A塔楼和B塔楼连接在一起的悬空部分,悬空部分与结构内部分和悬挑部分同时对接,连廊的悬空部分和悬挑部分在同一平面内呈L形。上述钢结构连廊属于高挑异形超限结构,钢桁架的最大跨度为30m,高度4.4m。整体吊装高度为68.63米,其中悬挑部分的悬挑长度为11.050m,重量为165吨,提升无可靠支点。上部钢结构和下挂层钢结构所有构件重量达425吨。上述构件的作业面均在裙房的楼面板上进行,但是上述裙房的楼面板不具有承载425吨的能力。综上所述,将A塔楼和B塔楼连接在一起的右边悬空部分是大跨度悬空钢连廊,采用现有的大跨度高空连体钢结构施工方法不能完成上述钢结构连廊的施工。The steel structure corridor of a complex project is mainly composed of the upper steel structure and the lower hanging layer steel structure connected by trusses. The overall plan of the corridor is rectangular, including left and right parts. The left part is connected with Tower A, and is composed of the internal part of the structure on the floor plate and the cantilevered part connected with it. The right part connects Tower A and Tower B. The suspended part, the suspended part is connected with the internal part of the structure and the overhanging part at the same time, and the suspended part and the overhanging part of the corridor are L-shaped in the same plane. The above-mentioned steel structure corridor is a tall and special-shaped overrun structure. The maximum span of the steel truss is 30m and the height is 4.4m. The overall hoisting height is 68.63 meters, of which the cantilevered part has a cantilevered length of 11.050 meters and a weight of 165 tons. There is no reliable fulcrum for lifting. The weight of all components of the upper steel structure and the lower hanging layer steel structure reaches 425 tons. The working surfaces of the above-mentioned components are all carried out on the floor slab of the podium, but the floor slab of the above-mentioned podium does not have the capacity to carry 425 tons. To sum up, the right suspended part connecting Tower A and Tower B is a large-span suspended steel corridor, and the construction of the above-mentioned steel structure corridor cannot be completed by using the existing construction method of large-span high-altitude conjoined steel structure.
发明内容Contents of the invention
本发明为解决公知技术中存在的技术问题而提供一种大跨度悬空钢连廊施工工法,该工法能够完成超限高、大跨度悬空、缺少作业面、利用裙楼楼面作业、楼面荷载力不足、采用整体提升无可靠提升点的钢连廊施工。The present invention provides a construction method for large-span suspended steel corridors in order to solve the technical problems existing in the known technologies. Insufficient strength, and steel corridor construction with no reliable lifting points for overall lifting.
本发明为解决公知技术中存在的技术问题所采取的技术方案是:一种大跨度悬空钢连廊施工工法,所述悬空钢连廊连接在A塔楼和B塔楼之间,主要由桁架连接而成的上部钢结构和下挂层钢结构组成,所述悬空钢连廊整体平面呈矩形;该施工工法采用以下步骤:The technical solution adopted by the present invention to solve the technical problems existing in the known technology is: a construction method of a large-span suspended steel corridor, the suspended steel corridor is connected between the A tower and the B tower, and is mainly connected by trusses. Composed of the upper steel structure and the lower hanging layer steel structure, the overall plane of the suspended steel corridor is rectangular; the construction method adopts the following steps:
1)在A塔楼靠近B塔楼端的顶部从内至外依次设置提升滑移装置Ⅰ和提升滑移装置Ⅱ;在B塔楼的楼顶靠近A塔楼的边部设置与所述提升滑移装置Ⅰ和所述提升滑移装置Ⅱ一一对应的提升滑移装置Ⅲ和提升滑移装置Ⅳ;1) On the top of tower A near the end of tower B, install lifting and sliding device I and lifting and sliding device II sequentially from inside to outside; The lifting and sliding device II corresponds to the lifting and sliding device III and the lifting and sliding device IV;
所述提升滑移装置Ⅰ固定在A塔楼的结构柱上,在所述提升滑移装置Ⅰ上设有外伸的提升滑移梁Ⅰ,所述提升滑移梁Ⅰ与A塔楼的端立面垂直,在所述提升滑移梁Ⅰ上从外至内依次设有支座Ⅰ、推拉器Ⅰ和滑移推杆Ⅰ,所述支座Ⅰ与所述提升滑移梁Ⅰ滑动连接,所述推拉器Ⅰ的伸缩端与所述支座Ⅰ铰接,所述推拉器Ⅰ的内端与所述滑移推杆Ⅰ铰接,在所述滑移推杆Ⅰ上设有沿轴向布置的多个卡板Ⅰ,在所述提升滑移梁Ⅰ上固定有限位挡板Ⅰ,所述卡板Ⅰ顶压在所述限位挡板Ⅰ的外端面上;在所述支座Ⅰ上固装有提升器Ⅰ;The lifting and sliding device I is fixed on the structural column of the A tower, and the lifting and sliding device I is provided with an extended lifting and sliding beam I, and the lifting and sliding beam I is connected to the end elevation of the A tower. Vertically, a support I, a push-pull device I and a sliding push rod I are sequentially provided on the lifting glide beam I from the outside to the inside, the support I is slidingly connected with the lifting glide beam I, and the The telescopic end of the push-pull I is hinged to the support I, and the inner end of the push-pull I is hinged to the sliding push rod I. On the sliding push rod I, there are multiple axially arranged Clamp I, the limit baffle I is fixed on the lifting and sliding beam I, and the clamp I presses against the outer end surface of the limit baffle I; Lifter I;
在所述提升滑移装置Ⅱ上设有外伸的提升滑移梁Ⅱ,所述提升滑移梁Ⅱ与A塔楼的端立面垂直,在所述提升滑移梁Ⅱ上从外至内依次设有支座Ⅱ、推拉器Ⅱ和滑移推杆Ⅱ,所述支座Ⅱ与所述提升滑移梁Ⅱ滑动连接,所述推拉器Ⅱ的伸缩端与所述支座Ⅱ铰接,所述推拉器Ⅱ的内端与所述滑移推杆Ⅱ铰接,在所述滑移推杆Ⅱ上设有沿轴向布置的多个卡板Ⅱ,在所述提升滑移梁Ⅱ上固定有限位挡板Ⅱ,所述卡板Ⅱ顶压在所述限位挡板Ⅱ的外端面上;在所述支座Ⅱ上固装有提升器Ⅱ;The lifting and sliding device II is provided with an outwardly extending lifting and sliding beam II, and the lifting and sliding beam II is perpendicular to the end elevation of the A tower, and on the lifting and sliding beam II from outside to inside A support II, a push-pull device II and a sliding push rod II are provided, the support II is slidingly connected to the lifting sliding beam II, the telescopic end of the push-pull device II is hinged to the support II, and the The inner end of the push-pull II is hinged with the sliding push rod II, and a plurality of clamping plates II arranged in the axial direction are arranged on the sliding push rod II, and are fixed on the lifting sliding beam II The baffle II, the clamp II presses against the outer end surface of the limit baffle II; the lifter II is fixedly installed on the support II;
所述提升滑移装置Ⅲ位于B塔楼楼顶边部中间区域,在所述提升滑移装置Ⅲ上设有外伸的提升滑移梁Ⅲ,所述提升滑移梁Ⅲ与A塔楼的端立面垂直,在所述提升滑移梁Ⅲ上从外至内依次设有支座Ⅲ、推拉器Ⅲ和滑移拉杆Ⅲ,所述支座Ⅲ与所述提升滑移梁Ⅲ滑动连接,所述推拉器Ⅲ的伸缩端与所述支座Ⅲ铰接,所述推拉器Ⅲ的内端与所述滑移拉杆Ⅲ铰接,在所述滑移拉杆Ⅲ上设有沿轴向布置的多个卡板Ⅲ,在所述提升滑移梁Ⅲ上固定有限位挡板Ⅲ,所述卡板Ⅲ拉压在所述限位挡板Ⅲ的内端面上;在所述支座Ⅲ上固装有提升器Ⅲ;The lifting and sliding device III is located in the middle area of the top edge of the B tower, and the lifting and sliding device III is provided with an outstretched lifting and sliding beam III, and the lifting and sliding beam III is vertical to the end of the A tower. The surface is vertical, on the lifting and sliding beam III, there are successively a support III, a push-pull device III and a sliding pull rod III from the outside to the inside, the support III is slidingly connected with the lifting and sliding beam III, and the The telescopic end of the push-pull device III is hinged to the support III, the inner end of the push-pull device III is hinged to the sliding rod III, and a plurality of clamping plates arranged in the axial direction are arranged on the sliding rod III III, the limit baffle III is fixed on the lifting and sliding beam III, and the clamping plate III is pulled and pressed on the inner end surface of the limit baffle III; a lifter is fixed on the support III III;
所述提升滑移装置Ⅳ位于B塔楼楼顶的边角部区域,所述提升滑移装置Ⅳ包括与楼顶板固接的提升梁Ⅰ和提升梁Ⅱ,所述提升梁Ⅰ沿与B塔楼侧立面垂直的方向伸出,所述提升梁Ⅱ偏向B塔楼的侧立面伸出,在所述提升梁Ⅰ和所述提升梁Ⅱ的外伸端部上固装有滑移梁,所述滑移梁位于B塔楼的侧边之外,所述滑移梁与B塔楼的侧立面平行,在所述提升梁Ⅰ和所述提升梁Ⅱ的下方分别设有斜撑,所述斜撑的下端与B塔楼固接;The lifting and sliding device IV is located in the corner area of the roof of Tower B. The lifting and sliding device IV includes lifting beam I and lifting beam II fixed to the roof plate, and the lifting beam I is connected to the top of Tower B. The side facade protrudes in a vertical direction, and the lifting beam II protrudes toward the side facade of the B tower, and a sliding beam is fixed on the extended end of the lifting beam I and the lifting beam II, so that The sliding beam is located outside the side of Tower B, the sliding beam is parallel to the side facade of Tower B, and diagonal braces are respectively provided under the lifting beam I and the lifting beam II. The lower end of the brace is fixedly connected to Tower B;
在所述滑移梁上从外至内依次设有支座Ⅳ、推拉器Ⅳ和滑移拉杆Ⅳ,所述支座Ⅳ与所述滑移梁滑动连接,所述推拉器Ⅳ的伸缩端与所述支座Ⅳ铰接,所述推拉器Ⅳ的内端与所述滑移拉杆Ⅳ铰接,在所述滑移拉杆Ⅳ上设有沿轴向布置的多个卡板Ⅳ,在所述滑移梁上固定有一个限位挡板Ⅳ,所述卡板Ⅳ拉压在所述限位挡板Ⅳ的内端面上;在所述支座Ⅳ上固装有提升器Ⅳ;A support IV, a push-pull device IV and a sliding pull rod IV are sequentially provided on the sliding beam from outside to inside, the support IV is slidingly connected with the sliding beam, and the telescopic end of the push-pull device IV is connected to the The support IV is hinged, the inner end of the push-pull IV is hinged with the sliding rod IV, and a plurality of clamping plates IV arranged in the axial direction are arranged on the sliding rod IV. A limit baffle IV is fixed on the beam, and the clamp IV is pulled and pressed against the inner end surface of the limit baffle IV; a lifter IV is fixed on the support IV;
在裙楼的屋面板上完成所述悬空钢连廊的上部钢结构成型作业;Complete the upper steel structure forming operation of the suspended steel corridor on the roof panel of the podium;
2)启动所述提升器Ⅰ、所述提升器Ⅱ、所述提升器Ⅲ和所述提升器Ⅳ,将成型后的所述悬空钢连廊的上部钢结构提升至第一设定高度;2) Start the lifter I, the lifter II, the lifter III and the lifter IV, and lift the formed upper steel structure of the suspended steel corridor to a first set height;
3)在裙楼的屋面板上完成所述悬空钢连廊的第一下挂层钢结构的成型作业,然后将成型后的所述悬空钢连廊的第一下挂层钢结构连接在所述悬空钢连廊的上部钢结构的下方,启动所述提升器Ⅰ、所述提升器Ⅱ、所述提升器Ⅲ和所述提升器Ⅳ,将所述连廊悬空部分的上部钢结构提升至第二设定高度;3) Complete the forming operation of the first lower hanging layer steel structure of the suspended steel corridor on the roof panel of the podium, and then connect the first lower hanging layer steel structure of the formed suspended steel corridor to the Below the upper steel structure of the suspended steel corridor, start the lifter I, the lifter II, the lifter III and the lifter IV, and lift the upper steel structure of the suspended part of the corridor to second set height;
4)重复步骤3),直至完成所述悬空钢连廊的所有下挂层钢结构的连接;4) Repeat step 3) until the connection of all lower hanging layer steel structures of the suspended steel corridor is completed;
5)启动所述提升器Ⅰ、所述提升器Ⅱ、所述提升器Ⅲ和所述提升器Ⅳ,将整个所述悬空钢连廊整体同步提升至安装设计高度;5) Start the lifter I, the lifter II, the lifter III and the lifter IV, and synchronously lift the entire suspended steel corridor to the installation design height;
6)启动所述推拉器Ⅰ、所述推拉器Ⅱ、所述推拉器Ⅲ和所述推拉器Ⅳ,在空中将整个所述悬空钢连廊整体水平向右逐步滑移就位,使所述悬空钢连廊的右端支承在滑移支座上,所述滑移支座固定在牛腿上,所述牛腿设置在B塔楼的结构柱上;然后将所述悬空钢连廊的左端与A塔楼上的永久结构连接在一起。6) Start the push-pull device I, the push-pull device II, the push-pull device III and the push-pull device IV, and gradually slide the entire suspended steel corridor to the right in the air, so that the The right end of the suspended steel corridor is supported on the sliding support, and the sliding support is fixed on the corbel, and the corbel is arranged on the structural column of the B tower; then the left end of the suspended steel corridor is connected to the The permanent structures on Tower A are linked together.
本发明具有的优点和积极效果是:The advantages and positive effects that the present invention has are:
一)针对悬空钢连廊整体重量大,裙房楼面板荷载力不足的问题,采用倒挂法施工,分次提升到下挂层层高位置后再增加下挂层的方式,即解决了裙房楼面板承载力不足的问题,又增加了起吊重量。钢结构主要的拼装、焊接及油漆等工作在楼面的拼装胎架上进行,可用塔吊进行散件吊装,施工效率高,施工质量易于保证。悬空钢连廊整体提升后通过加长滑移拉杆实现了长距离滑移(滑移长度1700mm);悬空钢连廊整体与右侧B塔楼立柱牛腿上的滑移支座焊接,解决了钢结构应力变形问题。1) In view of the problem that the overall weight of the suspended steel corridor is large and the load capacity of the podium floor slab is insufficient, the upside-down method is adopted for construction, and the method of adding the lower hanging storey after lifting to the height of the lower hanging storey in stages solves the problem of the podium. The problem of insufficient bearing capacity of the floor slab increases the lifting weight. The main assembly, welding and painting work of the steel structure is carried out on the assembled tire frame on the floor, and the parts can be hoisted by a tower crane. The construction efficiency is high and the construction quality is easy to guarantee. After the overall lifting of the suspended steel corridor, the long-distance sliding is realized by lengthening the sliding rod (sliding length 1700mm); stress deformation problem.
二)通过采用在裙楼的屋面板上分层块逐次成型,逐次倒挂,并在完成整体成型倒挂后实施整体提升和整体提升后空中整体滑移的施工方法,解决了超限高(68m)、大跨度悬空钢连廊缺少作业面,利用裙楼楼面作业,楼面荷载力不足,采用整体提升无可靠提升点的施工难题。避免了全部采用分件高空散装,减少了高空组装和高空焊接的工作量,无需大型的吊装机械设备,利用现场现有的设备就能满足吊装要求,而且解决了高空组拼胎架(搭设高度68.63米)无法搭设的问题,降低了安全、质量风险,节约了施工成本,降低了施工难度;将高空作业量降至最少,有利于钢结构现场安装的安全、质量以及工期的控制。2) By adopting the construction method of forming layered blocks on the roof panel of the podium one by one, hanging them upside down one by one, and implementing the overall lifting after the overall forming upside down, and the overall sliding in the air after the overall lifting, the over-limit height (68m) was solved , The long-span suspended steel corridor lacks a working surface, and the podium floor is used for operation, the floor load capacity is insufficient, and the overall lifting has no reliable lifting points. It avoids all the high-altitude bulk packaging by parts, reduces the workload of high-altitude assembly and high-altitude welding, does not need large-scale hoisting machinery and equipment, and can meet the hoisting requirements by using the existing equipment on site, and solves the problem of high-altitude tire assembly frame (building height 68.63 meters) can not be erected, which reduces safety and quality risks, saves construction costs, and reduces construction difficulty; minimizes the amount of high-altitude operations, which is conducive to the safety, quality and construction period control of steel structure on-site installation.
三)采用整体提升+提升后滑移的方法施工,通过充分考虑被提升结构的受力体系特点,在不改变结构受力体系,使提升吊装过程中结构的应力比以及变形情况均控制在规范允许范围内的前提下,合理布置多个提升滑移点,成功地实现了整体提升后多点位高空水平方向长距离滑移(滑移距离1700mm)。上述方法的优势在于:3) The method of overall lifting + sliding after lifting is used for construction. By fully considering the characteristics of the stress system of the lifted structure and without changing the structural stress system, the stress ratio and deformation of the structure during the hoisting process are controlled within the specification Under the premise of the allowable range, multiple lifting slip points are reasonably arranged, and the multi-point high-altitude horizontal long-distance sliding (sliding distance 1700mm) has been successfully realized after the overall lifting. The advantages of the above method are:
1)合理地利用永久结构,采用多种提升拼装方式,针对性强,并结合高空拼装、整体吊装就位法、同步液压提升的特点,使得三种方法的优点最大化。节约了工时,材料费,设备费,并满足了施工工艺、质量、安全、进度及成本等多方面的整体控制的要求。1) Rationally utilize the permanent structure, adopt multiple lifting and assembling methods, which are highly targeted, and combine the characteristics of high-altitude assembly, overall hoisting in place method, and synchronous hydraulic lifting to maximize the advantages of the three methods. It saves man-hours, material costs, and equipment costs, and meets the requirements for overall control of construction technology, quality, safety, progress, and costs.
2)采用超大型液压同步提升施工技术,提升过程十分安全,并且构件可以在提升过程中的任意位置锁定,任一提升器亦可单独调整,调整精度高,有效地提高了结构提升过程中安装精度的可控性。采用柔性索具承重,有合理的承重吊点,提升高度不受限制。提升过程中构件保持平稳的提升姿态,同步控制精度高设备自动化程度高,操作方便灵活,安全性好,可靠性高,使用面广,通用性强。2) The super-large hydraulic synchronous lifting construction technology is adopted, the lifting process is very safe, and the components can be locked at any position during the lifting process, and any lifter can also be adjusted independently, with high adjustment accuracy, which effectively improves the installation during the structure lifting process. Controllability of precision. Flexible rigging is used for load bearing, with reasonable load-bearing lifting points, and the lifting height is not limited. During the lifting process, the components maintain a stable lifting posture, the synchronous control precision is high, the equipment is highly automated, the operation is convenient and flexible, the safety is good, the reliability is high, the use is wide, and the versatility is strong.
3)高空滑移无需胎架,吊装过程的安全性有保证。提升设备体积小、自重轻、承载能力大,特别适宜于大型构件的提升作业。3) High-altitude skidding does not require a tire frame, and the safety of the hoisting process is guaranteed. The lifting equipment is small in size, light in weight and large in carrying capacity, and is especially suitable for lifting large components.
4)提升吊点等主要临时结构利用主体结构设置,加之液压同步提升动荷载极小的优点,以及提升平台、提升滑移平台和不同吨位的提升专用吊具的重复利用,可以使提升临时设施用量降至最小,有利于施工成本控制。4) The main temporary structures such as hoisting points are set by the main structure, combined with the advantage of the minimal dynamic load of hydraulic synchronous lifting, and the repeated use of lifting platforms, lifting sliding platforms and lifting special spreaders of different tonnages, can make lifting temporary facilities The consumption is reduced to a minimum, which is conducive to the control of construction costs.
综上所述,本发明采用分次提升、倒挂加重后整体提升滑移的方法,通过提升设备的扩展组合,使提升重量、跨度和面积均有较大提高。通过钢结构的整体吊装,将高空作业量降至最少,加之液压提升作业绝对时间较短,能够有效保证钢结构安装的总体工期。打破了目前大跨度悬挑异形超限结构钢连廊施工的限制。To sum up, the present invention adopts the method of step-by-step lifting, upside-down weighting and overall lifting and sliding, and through the expansion and combination of lifting equipment, the lifting weight, span and area are greatly improved. Through the overall hoisting of the steel structure, the amount of high-altitude operations is reduced to the minimum, and the absolute time of the hydraulic lifting operation is relatively short, which can effectively guarantee the overall construction period of the steel structure installation. It breaks the current limitations of the construction of large-span cantilevered special-shaped overrun structural steel corridors.
附图说明Description of drawings
图1为本发明应用的结构示意图;Fig. 1 is the structural representation of application of the present invention;
图2为本发明步骤1)的示意图;Fig. 2 is the schematic diagram of step 1) of the present invention;
图3-1为本发明应用的提升滑移装置Ⅰ的结构示意图;Fig. 3-1 is the schematic structural diagram of the lifting and sliding device I applied in the present invention;
图3-2为本发明应用的提升滑移装置Ⅰ的支座Ⅰ、推拉器Ⅰ和滑移拉杆Ⅰ连接示意图;Figure 3-2 is a schematic diagram of the connection of the support I, the push-pull device I and the sliding rod I of the lifting and sliding device I applied in the present invention;
图4为本发明应用的提升滑移装置Ⅱ的结构示意图;Fig. 4 is the schematic structural diagram of the lifting and sliding device II applied in the present invention;
图5为本发明应用的提升滑移装置Ⅲ的结构示意图;Fig. 5 is the schematic structural view of the lifting and sliding device III applied in the present invention;
图6-1为本发明应用的提升滑移装置Ⅳ的主视图;Fig. 6-1 is the front view of the lifting and sliding device IV applied in the present invention;
图6-2为图6-1的侧视图;Figure 6-2 is a side view of Figure 6-1;
图6-3为本发明应用的提升滑移装置Ⅳ的滑移梁(包含滑移梁)以下部分的俯视图;Fig. 6-3 is the top view of the following part of the sliding beam (including the sliding beam) of the lifting sliding device IV applied in the present invention;
图7本发明步骤2)的示意图;Fig. 7 is a schematic diagram of step 2) of the present invention;
图8为本发明步骤3)的示意图;Fig. 8 is the schematic diagram of step 3) of the present invention;
图9为本发明步骤4)的示意图。Fig. 9 is a schematic diagram of step 4) of the present invention.
具体实施方式detailed description
为能进一步了解本发明的发明内容、特点及功效,兹例举以下实施例,并配合附图详细说明如下:In order to further understand the invention content, characteristics and effects of the present invention, the following examples are given, and detailed descriptions are as follows in conjunction with the accompanying drawings:
请参阅附图,一种大跨度悬挑异形超限结构钢连廊1,所述钢连廊1连接A塔楼2和B塔楼3,主要由桁架连接而成的上部钢结构和下挂层钢结构组成,所述钢连廊1整体平面呈矩形,包括左右两部分,左边部分与A塔楼2连接,由位于A塔楼2楼面板上的连廊结构内部分和与其连接的连廊悬挑部分组成,右边部分是将A塔楼2和B塔楼3连接在一起的连廊悬空部分,所述连廊悬空部分和所述连廊悬挑部分在同一平面内呈L形布置。上述连廊悬挑部分是大跨度悬空钢连廊,所述悬空钢连廊连接在A塔楼2和B塔楼3之间,主要由桁架连接而成的上部钢结构和下挂层钢结构组成,所述大跨度悬空钢连廊整体平面呈矩形。Please refer to the accompanying drawings, a steel corridor 1 of a large-span cantilevered special-shaped overrun structure, the steel corridor 1 connects the A tower 2 and the B tower 3, and the upper steel structure and the lower hanging layer steel are mainly connected by trusses. Structural composition, the overall plane of the steel corridor 1 is rectangular, including left and right parts, the left part is connected to A tower 2, and the inner part of the corridor structure located on the 2nd floor panel of A tower and the cantilevered part of the corridor connected to it Composition, the right part is the suspended part of the corridor connecting Tower A 2 and Tower B 3 together, and the suspended part of the corridor and the suspended part of the corridor are arranged in an L shape in the same plane. The cantilevered part of the above-mentioned corridor is a large-span suspended steel corridor. The suspended steel corridor is connected between the A tower 2 and the B tower 3, and is mainly composed of an upper steel structure and a lower hanging steel structure connected by trusses. The overall plane of the long-span suspended steel corridor is rectangular.
上述大跨度悬空钢连廊的施工工法采用以下步骤:The construction method of the above-mentioned large-span suspended steel corridor adopts the following steps:
1)在A塔楼2靠近B塔楼3端的顶部从内至外依次设置提升滑移装置Ⅰ4-1和提升滑移装置Ⅱ4-2;在B塔楼3的楼顶靠近A塔楼的边部设置与所述提升滑移装置Ⅰ4-1和所述提升滑移装置Ⅱ4-2一一对应的提升滑移装置Ⅲ4-3和提升滑移装置Ⅳ4-4。1) On the top of Tower A 2 close to Tower B 3, install lifting and sliding device Ⅰ 4-1 and lifting and sliding device Ⅱ 4-2 from inside to outside; The lifting and sliding device I4-1 and the lifting and sliding device II4-2 correspond one-to-one to the lifting and sliding device III4-3 and the lifting and sliding device IV4-4.
所述提升滑移装置Ⅰ4-1固定在A塔楼2的结构柱5上,在所述提升滑移装置Ⅰ4-1上设有外伸的提升滑移梁Ⅰ4-1-1,所述提升滑移梁Ⅰ4-1-1与A塔楼2的端立面垂直,在所述提升滑移梁Ⅰ上从外至内依次设有支座Ⅰ4-1-2、推拉器Ⅰ4-1-3和滑移推杆Ⅰ4-1-4,所述支座Ⅰ4-1-2与所述提升滑移梁Ⅰ4-1-1滑动连接,所述推拉器Ⅰ4-1-3的伸缩端与所述支座Ⅰ4-1-2铰接,所述推拉器Ⅰ4-1-3的内端与所述滑移推杆Ⅰ4-1-4铰接,在所述滑移推杆Ⅰ4-1-4上设有沿轴向布置的多个卡板Ⅰ4-1-6,在所述提升滑移梁Ⅰ4-1-1上固定有限位挡板Ⅰ4-1-5,所述卡板Ⅰ4-1-6顶压在所述限位挡板Ⅰ4-1-5的外端面上;在所述支座Ⅰ4-1-1上固装有提升器Ⅰ4-1-7。The lifting and sliding device I4-1 is fixed on the structural column 5 of the A tower 2, and the lifting and sliding device I4-1 is provided with an outstretched lifting and sliding beam I4-1-1, and the lifting and sliding device I4-1 The moving beam I4-1-1 is perpendicular to the end facade of A tower 2, and the lifting and sliding beam I is provided with a support I4-1-2, a push-pull I4-1-3 and a slide in sequence from the outside to the inside. Move the push rod I4-1-4, the support I4-1-2 is slidingly connected with the lifting sliding beam I4-1-1, the telescopic end of the push-pull I4-1-3 is connected with the support I4-1-2 is hinged, the inner end of the push-pull I4-1-3 is hinged with the sliding push rod I4-1-4, and the sliding push rod I4-1-4 is provided with a shaft A plurality of clamping plates I4-1-6 arranged in the direction, the limit baffle plate I4-1-5 is fixed on the lifting and sliding beam I4-1-1, and the clamping plate I4-1-6 is pressed against the The outer end surface of the limit baffle I4-1-5; the lifter I4-1-7 is fixed on the support I4-1-1.
在所述提升滑移装置Ⅱ4-2上设有外伸的提升滑移梁Ⅱ4-2-1,所述提升滑移梁Ⅱ4-2-1与A塔楼2的端立面垂直,在所述提升滑移梁Ⅱ4-2-1上从外至内依次设有支座Ⅱ4-2-2、推拉器Ⅱ4-2-3和滑移推杆Ⅱ4-2-4,所述支座Ⅱ4-2-2与所述提升滑移梁Ⅱ4-2-1滑动连接,所述推拉器Ⅱ4-2-3的伸缩端与所述支座Ⅱ4-2-2铰接,所述推拉器Ⅱ4-2-3的内端与所述滑移推杆Ⅱ4-2-4铰接,在所述滑移推杆Ⅱ4-2-4上设有沿轴向布置的多个卡板Ⅱ4-2-6,在所述提升滑移梁Ⅱ4-2-1上固定有限位挡板Ⅱ4-2-5,所述卡板Ⅱ4-2-6顶压在所述限位挡板Ⅱ4-2-5的外端面上;在所述支座Ⅱ4-2-2上固装有提升器Ⅱ4-2-7。An outstretched lifting and sliding beam II4-2-1 is provided on the lifting and sliding device II4-2, and the lifting and sliding beam II4-2-1 is perpendicular to the end elevation of A Tower 2, and Lifting and sliding beam II4-2-1 is provided with support II4-2-2, push-pull device II4-2-3 and sliding push rod II4-2-4 sequentially from outside to inside, and the support II4-2 -2 is slidingly connected with the lifting and sliding beam II4-2-1, the telescopic end of the push-pull II4-2-3 is hinged with the support II4-2-2, and the push-pull II4-2-3 The inner end is hinged with the sliding push rod II4-2-4, and a plurality of clamping plates II4-2-6 arranged in the axial direction are arranged on the sliding push rod II4-2-4. The limit baffle II 4-2-5 is fixed on the lifting sliding beam II 4-2-1, and the clamping plate II 4-2-6 presses against the outer end face of the limit baffle II 4-2-5; The lifter II4-2-7 is fixedly mounted on the support II4-2-2.
所述提升滑移装置Ⅲ4-3位于B塔楼3的楼顶边部中间区域,在所述提升滑移装置Ⅲ4-3上设有外伸的提升滑移梁Ⅲ4-3-1,所述提升滑移梁Ⅲ4-3-1与A塔楼2的端立面垂直,在所述提升滑移梁Ⅲ4-3-1上从外至内依次设有支座Ⅲ4-3-2、推拉器Ⅲ4-3-3和滑移拉杆Ⅲ4-3-4,所述支座Ⅲ4-3-2与所述提升滑移梁Ⅲ4-3-1滑动连接,所述推拉器Ⅲ4-3-3的伸缩端与所述支座Ⅲ4-3-2铰接,所述推拉器Ⅲ4-3-3的内端与所述滑移拉杆Ⅲ4-3-4铰接,在所述滑移拉杆Ⅲ4-3-4上设有沿轴向布置的多个卡板Ⅲ4-3-6,在所述提升滑移梁Ⅲ4-3-1上固定有限位挡板Ⅲ4-3-5,所述卡板Ⅲ4-3-6拉压在所述限位挡板Ⅲ4-3-5的内端面上;在所述支座Ⅲ4-3-2上固装有提升器Ⅲ4-3-7。The lifting and sliding device III4-3 is located in the middle area of the edge of the roof of Tower B 3, and the lifting and sliding device III4-3 is provided with an extended lifting and sliding beam III4-3-1. The sliding beam III4-3-1 is perpendicular to the end facade of A Tower 2, and the lifting sliding beam III4-3-1 is provided with supports III4-3-2, push-pulls III4- 3-3 and sliding pull rod III 4-3-4, the support III 4-3-2 is slidingly connected with the lifting sliding beam III 4-3-1, and the telescopic end of the push-pull III 4-3-3 is connected to The support III4-3-2 is hinged, the inner end of the push-pull III4-3-3 is hinged with the sliding rod III4-3-4, and the sliding rod III4-3-4 is provided with A plurality of clamping plates III4-3-6 arranged in the axial direction, the limit baffle plate III4-3-5 is fixed on the lifting and sliding beam III4-3-1, and the clamping plate III4-3-6 is pulled and pressed On the inner end surface of the limit baffle plate III4-3-5; on the support III4-3-2, a lifter III4-3-7 is fixedly installed.
所述提升滑移装置Ⅳ4-4位于B塔楼3楼顶的边角部区域,所述提升滑移装置Ⅳ4-4包括与楼顶板固接的提升梁Ⅰ4-4-8和提升梁Ⅱ4-4-9,所述提升梁Ⅰ4-4-8沿与B塔楼侧立面垂直的方向伸出,所述提升梁Ⅱ4-4-9偏向B塔楼3的侧立面伸出,在所述提升梁Ⅰ4-4-8和所述提升梁Ⅱ4-4-9的外伸端部上固装有滑移梁4-4-1,所述滑移梁4-4-1位于B塔楼1的侧边之外,所述滑移梁4-4-1与B塔楼3的侧立面平行,在所述提升梁Ⅰ4-4-8和所述提升梁Ⅱ4-4-9的下方分别设有斜撑4-4-10,所述斜撑4-4-10的下端与B塔楼固接。The lifting and sliding device IV4-4 is located in the corner area of the roof of Tower B 3, and the lifting and sliding device IV4-4 includes lifting beams I4-4-8 and lifting beams II4-4 fixedly connected to the roof slab. 4-9, the lifting beam I 4-4-8 protrudes in a direction perpendicular to the side facade of the B tower, and the lifting beam II 4-4-9 protrudes toward the side facade of the B tower 3. A sliding beam 4-4-1 is fixed on the extended end of the beam I 4-4-8 and the lifting beam II 4-4-9, and the sliding beam 4-4-1 is located on the side of the B tower 1 Outside the edge, the sliding beam 4-4-1 is parallel to the side façade of Tower B 3, and inclined Bracing 4-4-10, the lower end of the diagonal bracing 4-4-10 is fixedly connected to the B tower.
在所述滑移梁4-4-1上从外至内依次设有支座Ⅳ4-4-2、推拉器Ⅳ4-4-3和滑移拉杆Ⅳ4-4-4,所述支座Ⅳ4-4-2与所述滑移梁4-4-1滑动连接,所述推拉器Ⅳ4-4-3的伸缩端与所述支座Ⅳ4-4-2铰接,所述推拉器Ⅳ4-4-3的内端与所述滑移拉杆Ⅳ4-4-4铰接,在所述滑移拉杆Ⅳ4-4-4上设有沿轴向布置的多个卡板Ⅳ4-4-6,在所述滑移梁4-4-1上固定有一个限位挡板Ⅳ4-4-5,所述卡板Ⅳ4-4-6拉压在所述限位挡板Ⅳ4-4-5的内端面上;在所述支座Ⅳ4-4-2上固装有提升器Ⅳ4-4-7;在裙楼6的屋面板上完成所述悬空钢连廊的上部钢结构成型作业。The sliding beam 4-4-1 is provided with support IV 4-4-2, push-pull device IV 4-4-3 and sliding pull rod IV 4-4-4 from outside to inside in sequence, and the support IV 4- 4-2 is slidingly connected with the sliding beam 4-4-1, the telescopic end of the push-pull IV 4-4-3 is hinged with the support IV 4-4-2, and the push-pull IV 4-4-3 The inner end is hinged with the sliding pull rod IV4-4-4, and a plurality of clamping plates IV4-4-6 arranged in the axial direction are arranged on the sliding pull rod IV4-4-4. A limit baffle IV4-4-5 is fixed on the beam 4-4-1, and the clamp IV4-4-6 is pulled and pressed on the inner end surface of the limit baffle IV4-4-5; The lifter IV4-4-7 is fixedly installed on the support IV4-4-2; the upper steel structure forming operation of the suspended steel corridor is completed on the roof panel of the podium 6.
2)启动所述提升器Ⅰ4-1-7、所述提升器Ⅱ4-2-7、所述提升器Ⅲ4-3-7和所述提升器Ⅳ4-4-7,将成型后的所述悬空钢连廊的上部钢结构提升至第一设定高度。2) Start the lifter I4-1-7, the lifter II4-2-7, the lifter III4-3-7 and the lifter IV4-4-7, and the formed suspended The upper steel structure of the steel corridor is raised to the first set height.
3)在裙楼6的屋面板上完成所述悬空钢连廊的第一下挂层钢结构的成型作业,然后将成型后的所述悬空钢连廊的第一下挂层钢结构连接在所述悬空钢连廊的上部钢结构的下方,启动所述提升器Ⅰ4-1-7、所述提升器Ⅱ4-2-7、所述提升器Ⅲ4-3-7和所述提升器Ⅳ4-4-7,将所述连廊悬空部分的上部钢结构提升至第二设定高度。3) Complete the forming operation of the first lower hanging layer steel structure of the suspended steel corridor on the roof panel of the podium 6, and then connect the first lower hanging layer steel structure of the formed suspended steel corridor to the Below the upper steel structure of the suspended steel corridor, start the lifter I4-1-7, the lifter II4-2-7, the lifter III4-3-7 and the lifter IV4- 4-7. Lift the upper steel structure of the suspended part of the corridor to the second set height.
4)重复步骤3),直至完成所述悬空钢连廊的所有下挂层钢结构的连接。4) Step 3) is repeated until the connection of all lower hanging layer steel structures of the suspended steel corridor is completed.
5)启动所述提升器Ⅰ4-1-7、所述提升器Ⅱ4-2-7、所述提升器Ⅲ4-3-7和所述提升器Ⅳ4-4-7,将整个所述悬空钢连廊整体同步提升至安装设计高度。5) Start the lifter I4-1-7, the lifter II4-2-7, the lifter III4-3-7 and the lifter IV4-4-7, connect the entire suspended steel The corridor as a whole is simultaneously raised to the installation design height.
6)启动所述推拉器Ⅰ4-1-3、所述推拉器Ⅱ4-2-3、所述推拉器Ⅲ4-3-3和所述推拉器Ⅳ4-4-3,在空中将整个所述悬空钢连廊整体水平向右逐步滑移就位,使所述悬空钢连廊的右端支承在滑移支座上,所述滑移支座固定在牛腿上,所述牛腿设置在B塔楼3的结构柱上;然后将所述悬空钢连廊的左端与A塔楼2上的永久结构连接在一起。6) Start the push-pull I4-1-3, the push-pull II4-2-3, the push-pull III4-3-3 and the push-pull IV4-4-3, and suspend the entire The overall level of the steel corridor slides gradually to the right in place, so that the right end of the suspended steel corridor is supported on the sliding support, and the sliding support is fixed on the corbel, and the corbel is set on the B tower 3; then connect the left end of the suspended steel corridor with the permanent structure on Tower A 2.
上述分层块逐步成型逐步下挂提起的方法能够解决裙房楼面板承载能力不足的问题。在施工单元的提升过程中,对提升区域杆件需要进行临时加固以满足整体提升需求,抵消吊装中自重应力产生的变形,使其形成稳定的整体以便提升,采用现有技术,在此不再赘述。与提升滑移装置连接的结构部分需要进行临时加强以满足提升重量需求,采用现有技术,在此不再赘述。The above-mentioned method of gradually forming layered blocks and gradually lowering and lifting can solve the problem of insufficient bearing capacity of the podium floor slab. During the lifting process of the construction unit, the rods in the lifting area need to be temporarily reinforced to meet the overall lifting needs, offset the deformation caused by the self-weight stress in the hoisting, and make it form a stable whole for lifting. Using the existing technology, no longer repeat. The structural part connected with the lifting and sliding device needs to be temporarily strengthened to meet the lifting weight requirement, and the existing technology is adopted, which will not be repeated here.
尽管上面结合附图对本发明的优选实施例进行了描述,但是本发明并不局限于上述的具体实施方式,上述的具体实施方式仅仅是示意性的,并不是限制性的,本领域的普通技术人员在本发明的启示下,在不脱离本发明宗旨和权利要求所保护的范围的情况下,还可以作出很多形式,这些均属于本发明的保护范围之内。Although the preferred embodiments of the present invention have been described above in conjunction with the accompanying drawings, the present invention is not limited to the above-mentioned specific embodiments. The above-mentioned specific embodiments are only illustrative and not restrictive. Those of ordinary skill in the art Under the enlightenment of the present invention, people can also make many forms without departing from the purpose of the present invention and the scope of protection of the claims, and these all belong to the protection scope of the present invention.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610420915.7A CN106065661B (en) | 2016-06-13 | 2016-06-13 | The hanging steel corridor construction engineering method of large span |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201610420915.7A CN106065661B (en) | 2016-06-13 | 2016-06-13 | The hanging steel corridor construction engineering method of large span |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN106065661A true CN106065661A (en) | 2016-11-02 |
| CN106065661B CN106065661B (en) | 2018-03-20 |
Family
ID=57420644
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201610420915.7A Active CN106065661B (en) | 2016-06-13 | 2016-06-13 | The hanging steel corridor construction engineering method of large span |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN106065661B (en) |
Cited By (22)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106437178A (en) * | 2016-10-21 | 2017-02-22 | 中建八局第三建设有限公司 | Integral lifting construction method and integral lifting construction device of veranda of multi-layer steel structure |
| CN106522361A (en) * | 2016-12-07 | 2017-03-22 | 上海市机械施工集团有限公司 | Combined installation method for multi-layer heavy steel space corridor |
| CN106703423A (en) * | 2016-12-07 | 2017-05-24 | 上海市机械施工集团有限公司 | Automatic hovering wind-resistant device for integral lifting of air joint gallery |
| CN106759845A (en) * | 2016-12-29 | 2017-05-31 | 上海市机械施工集团有限公司 | A kind of construction method of Steel corridor |
| CN106930541A (en) * | 2017-05-10 | 2017-07-07 | 中国建筑第二工程局有限公司 | Construction method of hanging type steel corridor |
| CN107012949A (en) * | 2017-05-10 | 2017-08-04 | 中国建筑第二工程局有限公司 | Lifting method of large-span steel corridor |
| CN107060105A (en) * | 2017-05-10 | 2017-08-18 | 中国建筑第二工程局有限公司 | Lifting construction method for multiple steel galleries between tower buildings |
| CN108532743A (en) * | 2018-05-31 | 2018-09-14 | 上海建工四建集团有限公司 | The aerial steel vestibule Lift-on/Lift-off System of multilayer and its application method |
| CN108571061A (en) * | 2018-03-19 | 2018-09-25 | 中建三局基础设施建设投资有限公司 | A kind of large public building suspension type shelter bridge structure |
| CN109779272A (en) * | 2019-03-18 | 2019-05-21 | 济南四建(集团)有限责任公司 | A kind of high-altitude steel structure corridor construction method |
| CN109826312A (en) * | 2019-02-21 | 2019-05-31 | 深圳市建筑设计研究总院有限公司 | A kind of the segmented assembly method and high level conjoined structure of high level conjoined structure |
| CN109941894A (en) * | 2019-03-15 | 2019-06-28 | 上海建工七建集团有限公司 | Double-layer lifting point lifting frame for integral lifting and translation of steel corridor and its installation method |
| CN109989588A (en) * | 2019-03-15 | 2019-07-09 | 上海建工七建集团有限公司 | The installation of steel vestibule is promoted and high-altitude translation device and its installation method with whole |
| CN110777938A (en) * | 2019-11-21 | 2020-02-11 | 香港华艺设计顾问(深圳)有限公司 | Suspension structure for additionally arranging prestressed steel stay cable in steel truss |
| CN110778127A (en) * | 2019-11-12 | 2020-02-11 | 上海宝冶集团有限公司 | In-situ assembling and lifting construction aligning method for multilayer steel truss |
| CN112523357A (en) * | 2020-09-04 | 2021-03-19 | 浙大城市学院 | Steel supporting cylinder-lower hanging type truss system with arc-shaped vertical face and large open hole and application |
| CN114319576A (en) * | 2022-01-17 | 2022-04-12 | 深圳嘉西亚建筑设计有限公司 | A kind of steel structure corridor structure and its hoisting method |
| CN114541567A (en) * | 2022-03-04 | 2022-05-27 | 中建八局第二建设有限公司 | Construction method for irregular conjoined steel corridor in narrow and small site |
| CN118241879A (en) * | 2024-04-09 | 2024-06-25 | 中铁四局集团有限公司 | A lifting bracket tooling for protruding roof staircase working conditions |
| CN118601133A (en) * | 2024-05-22 | 2024-09-06 | 中国建筑第二工程局有限公司 | A construction method for layered lifting and high-altitude assembly of steel structure corridors |
| CN118958478A (en) * | 2024-07-24 | 2024-11-15 | 中国五冶集团有限公司 | A method for installing a corridor in a confined space |
| WO2025091946A1 (en) * | 2023-11-03 | 2025-05-08 | 中铁四局集团有限公司 | Assembling method for large-span truss |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN103075025A (en) * | 2013-01-30 | 2013-05-01 | 中国十九冶集团有限公司 | A construction method for overall lifting of a giant cantilevered steel asymmetric structure of a high-rise building |
| CN203559597U (en) * | 2013-10-23 | 2014-04-23 | 广州建筑股份有限公司 | Sliding device convenient to operate |
| CN103835369A (en) * | 2014-03-05 | 2014-06-04 | 江苏南通六建建设集团有限公司 | Extensible high-altitude conjoined steel structure |
| CN104060844A (en) * | 2014-04-30 | 2014-09-24 | 浙江东南网架股份有限公司 | Sliding device and lifting device for truss frame of steel structural transfer floor of the high-rise building and construction method thereof |
| JP6059526B2 (en) * | 2012-12-18 | 2017-01-11 | 積水化学工業株式会社 | Existing piping removal device and existing piping removal method |
-
2016
- 2016-06-13 CN CN201610420915.7A patent/CN106065661B/en active Active
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP6059526B2 (en) * | 2012-12-18 | 2017-01-11 | 積水化学工業株式会社 | Existing piping removal device and existing piping removal method |
| CN103075025A (en) * | 2013-01-30 | 2013-05-01 | 中国十九冶集团有限公司 | A construction method for overall lifting of a giant cantilevered steel asymmetric structure of a high-rise building |
| CN203559597U (en) * | 2013-10-23 | 2014-04-23 | 广州建筑股份有限公司 | Sliding device convenient to operate |
| CN103835369A (en) * | 2014-03-05 | 2014-06-04 | 江苏南通六建建设集团有限公司 | Extensible high-altitude conjoined steel structure |
| CN104060844A (en) * | 2014-04-30 | 2014-09-24 | 浙江东南网架股份有限公司 | Sliding device and lifting device for truss frame of steel structural transfer floor of the high-rise building and construction method thereof |
Cited By (29)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106437178A (en) * | 2016-10-21 | 2017-02-22 | 中建八局第三建设有限公司 | Integral lifting construction method and integral lifting construction device of veranda of multi-layer steel structure |
| CN106522361A (en) * | 2016-12-07 | 2017-03-22 | 上海市机械施工集团有限公司 | Combined installation method for multi-layer heavy steel space corridor |
| CN106703423A (en) * | 2016-12-07 | 2017-05-24 | 上海市机械施工集团有限公司 | Automatic hovering wind-resistant device for integral lifting of air joint gallery |
| CN106759845A (en) * | 2016-12-29 | 2017-05-31 | 上海市机械施工集团有限公司 | A kind of construction method of Steel corridor |
| CN106759845B (en) * | 2016-12-29 | 2019-03-08 | 上海市机械施工集团有限公司 | A kind of construction method of Steel corridor |
| CN107060105A (en) * | 2017-05-10 | 2017-08-18 | 中国建筑第二工程局有限公司 | Lifting construction method for multiple steel galleries between tower buildings |
| CN107012949A (en) * | 2017-05-10 | 2017-08-04 | 中国建筑第二工程局有限公司 | Lifting method of large-span steel corridor |
| CN107060105B (en) * | 2017-05-10 | 2018-11-13 | 中国建筑第二工程局有限公司 | Lifting construction method for multiple steel galleries between tower buildings |
| CN106930541A (en) * | 2017-05-10 | 2017-07-07 | 中国建筑第二工程局有限公司 | Construction method of hanging type steel corridor |
| CN107012949B (en) * | 2017-05-10 | 2019-06-07 | 中国建筑第二工程局有限公司 | Lifting method of large-span steel corridor |
| CN108571061A (en) * | 2018-03-19 | 2018-09-25 | 中建三局基础设施建设投资有限公司 | A kind of large public building suspension type shelter bridge structure |
| CN108532743A (en) * | 2018-05-31 | 2018-09-14 | 上海建工四建集团有限公司 | The aerial steel vestibule Lift-on/Lift-off System of multilayer and its application method |
| CN109826312B (en) * | 2019-02-21 | 2024-03-15 | 深圳市建筑设计研究总院有限公司 | Sectional assembly method of high-rise integrated structure and high-rise integrated structure |
| CN109826312A (en) * | 2019-02-21 | 2019-05-31 | 深圳市建筑设计研究总院有限公司 | A kind of the segmented assembly method and high level conjoined structure of high level conjoined structure |
| CN109941894A (en) * | 2019-03-15 | 2019-06-28 | 上海建工七建集团有限公司 | Double-layer lifting point lifting frame for integral lifting and translation of steel corridor and its installation method |
| CN109989588A (en) * | 2019-03-15 | 2019-07-09 | 上海建工七建集团有限公司 | The installation of steel vestibule is promoted and high-altitude translation device and its installation method with whole |
| CN109779272A (en) * | 2019-03-18 | 2019-05-21 | 济南四建(集团)有限责任公司 | A kind of high-altitude steel structure corridor construction method |
| CN110778127A (en) * | 2019-11-12 | 2020-02-11 | 上海宝冶集团有限公司 | In-situ assembling and lifting construction aligning method for multilayer steel truss |
| CN110777938A (en) * | 2019-11-21 | 2020-02-11 | 香港华艺设计顾问(深圳)有限公司 | Suspension structure for additionally arranging prestressed steel stay cable in steel truss |
| CN110777938B (en) * | 2019-11-21 | 2022-05-03 | 香港华艺设计顾问(深圳)有限公司 | Suspension structure for additionally arranging prestressed steel stay cable in steel truss |
| CN112523357A (en) * | 2020-09-04 | 2021-03-19 | 浙大城市学院 | Steel supporting cylinder-lower hanging type truss system with arc-shaped vertical face and large open hole and application |
| CN112523357B (en) * | 2020-09-04 | 2022-06-17 | 浙大城市学院 | Steel supporting cylinder-lower hanging type truss system with arc-shaped vertical face and large open hole and application |
| CN114319576A (en) * | 2022-01-17 | 2022-04-12 | 深圳嘉西亚建筑设计有限公司 | A kind of steel structure corridor structure and its hoisting method |
| CN114541567A (en) * | 2022-03-04 | 2022-05-27 | 中建八局第二建设有限公司 | Construction method for irregular conjoined steel corridor in narrow and small site |
| WO2025091946A1 (en) * | 2023-11-03 | 2025-05-08 | 中铁四局集团有限公司 | Assembling method for large-span truss |
| CN118241879A (en) * | 2024-04-09 | 2024-06-25 | 中铁四局集团有限公司 | A lifting bracket tooling for protruding roof staircase working conditions |
| CN118601133A (en) * | 2024-05-22 | 2024-09-06 | 中国建筑第二工程局有限公司 | A construction method for layered lifting and high-altitude assembly of steel structure corridors |
| CN118601133B (en) * | 2024-05-22 | 2025-10-14 | 中国建筑第二工程局有限公司 | A construction method for layered lifting and high-altitude assembly of steel structure corridors |
| CN118958478A (en) * | 2024-07-24 | 2024-11-15 | 中国五冶集团有限公司 | A method for installing a corridor in a confined space |
Also Published As
| Publication number | Publication date |
|---|---|
| CN106065661B (en) | 2018-03-20 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN106065661B (en) | The hanging steel corridor construction engineering method of large span | |
| CN106013419B (en) | Long-span Cantilever abnormity transfinites structural steel corridor construction engineering method | |
| CN103669832B (en) | A kind of standard type Bailey bracket assembled jacking formwork system | |
| CN102587646B (en) | Hydraulic lifting self-ascending template system of intelligent independent unit structure | |
| CN205742991U (en) | A kind of truss-like hydraulic pressure integral steel platform jumping formwork | |
| CN108033367B (en) | Synchronous lifting device and lifting method for steel column and cylinder frame alternately supported steel platform and tower crane | |
| WO2021120687A1 (en) | Method for entire removal of space truss and assistive support mechanism | |
| CN204781929U (en) | Convenient intelligent hydraulic pressure jacking die carrier system of standard form shellfish thunder frame of assembling | |
| CN206722429U (en) | A kind of roofing color corrugated sheet steel transportation system | |
| CN106013453B (en) | Long-span Cantilever transfinites structure construction engineering method | |
| CN204804298U (en) | Building material hoist and mount construction scaffold | |
| CN101892736A (en) | High altitude moving hanging basket construction method | |
| CN109881590A (en) | Bridge steel box girder aerial work platform and construction method | |
| CN206722428U (en) | A kind of building roof lighting Zhongting steel construction jacking apparatus | |
| CN106567542A (en) | Super high-rise double tower building steel structure corridor assembling method | |
| CN208071235U (en) | A kind of bearing and lifting system of steel truss frame integral hoisting | |
| CN206088946U (en) | A integrally lift up displacement device for unsettled steel gallery of large -span | |
| CN204778237U (en) | Can have enough to meet need construction elevator layer door connects material platform | |
| CN106948261A (en) | A kind of synchronous folding truss | |
| CN109763639A (en) | A kind of super high-rise ceiling special construction work platform and construction method thereof | |
| CN105625732B (en) | Superelevation overhanging steel structure truss support free construction method | |
| CN104060846A (en) | Construction device and construction method for steel beam connection platform | |
| CN219031629U (en) | Lifting equipment for indoor plate installation | |
| CN205857749U (en) | A kind of overall sliding and lifting device of the structure that transfinites for Long-span Cantilever | |
| CN208734045U (en) | Monoblock type mould bases for Super High fission conjoined composite structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| TR01 | Transfer of patent right |
Effective date of registration: 20200323 Address after: 300451 No. 72, Hangzhou Road, Binhai New Area, Tianjin Co-patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd. Patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING BUREAU INSTALLATION ENGINEERING Co.,Ltd. Address before: 300456 No. 75, Xingang Road, Tanggu District, Tianjin Co-patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd. Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION NO.3 CONSTRUCTION ENGINEERING Co.,Ltd. |
|
| TR01 | Transfer of patent right | ||
| CP03 | Change of name, title or address | ||
| CP03 | Change of name, title or address |
Address after: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province Patentee after: China Construction Sixth Engineering Bureau Northwest Construction Co.,Ltd. Patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd. Address before: No. 72 Hangzhou Road, Tianjin Binhai New Area, 300451 Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING BUREAU INSTALLATION ENGINEERING Co.,Ltd. Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd. |
|
| CP01 | Change in the name or title of a patent holder | ||
| CP01 | Change in the name or title of a patent holder |
Address after: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province Patentee after: The First Construction Co.,Ltd. of China Construction Sixth Engineering Bureau Patentee after: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd. Address before: 710075 room 11001, 10th floor, building 3, Fengxi new town headquarters economic Park project, Xixian New District, Xi'an, Shaanxi Province Patentee before: China Construction Sixth Engineering Bureau Northwest Construction Co.,Ltd. Patentee before: CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd. |
|
| EE01 | Entry into force of recordation of patent licensing contract | ||
| EE01 | Entry into force of recordation of patent licensing contract |
Application publication date: 20161102 Assignee: Shaanxi Jiujiuruihe Construction Engineering Co.,Ltd. Assignor: The First Construction Co.,Ltd. of China Construction Sixth Engineering Bureau|CHINA CONSTRUCTION SIXTH ENGINEERING DIVISION Corp.,Ltd. Contract record no.: X2025980031424 Denomination of invention: The construction method of large span suspended steel corridor Granted publication date: 20180320 License type: Common License Record date: 20251030 |