CN109763639A - A kind of Super High furred ceiling special type construction operation platform and its construction method - Google Patents

A kind of Super High furred ceiling special type construction operation platform and its construction method Download PDF

Info

Publication number
CN109763639A
CN109763639A CN201811578916.XA CN201811578916A CN109763639A CN 109763639 A CN109763639 A CN 109763639A CN 201811578916 A CN201811578916 A CN 201811578916A CN 109763639 A CN109763639 A CN 109763639A
Authority
CN
China
Prior art keywords
construction
platform
guide rail
electric block
ceiling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811578916.XA
Other languages
Chinese (zh)
Inventor
叶建
史晓亮
温杰
李友元
魏恒
凡淑敏
夏华盛
慕志涛
陈芬芬
赵川阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Third Engineering Bureau Group Co Ltd
Original Assignee
China Construction Third Engineering Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Third Engineering Bureau Group Co Ltd filed Critical China Construction Third Engineering Bureau Group Co Ltd
Priority to CN201811578916.XA priority Critical patent/CN109763639A/en
Publication of CN109763639A publication Critical patent/CN109763639A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses a kind of Super High furred ceiling special type construction operation platforms, including ceiling construction job that requires special skills platform, electric block and guide rail, guide rail is fixed on structure truss lower edge by connecting flange plate, the electric block is mounted on guide rail, it can move linearly along rail length direction, the ceiling construction job that requires special skills platform hanging is below electric block, it can be driven by electric block and do vertical displacement movement, it can also be moved together along guide rail with electric block, ceiling construction job that requires special skills platform is the frame structure being welded by table top side rail and platform floor.The present invention is when in use, it is moved horizontally using electric block along structure truss lower edge guide rail, and itself draw extraordinary construction operation platform vertical lift, to realize the construction operation to the high ceiling decoration of entire Super High, it is compared with conventional construction method, the construction method operation of the job that requires special skills platform is convenient, at low cost, it is highly-safe, it can be widely used for the construction of similar structures.

Description

A kind of Super High furred ceiling special type construction operation platform and its construction method
Technical field
The invention belongs to technical field of building construction, and in particular to a kind of Super High furred ceiling special type construction operation platform and its Construction method.
Background technique
As people are higher and higher to architectural appearance and its functional requirement, the high ceiling decoration of Super High generallys use full hall foot The construction method of hand cradle, the construction method is at high cost, long in time limit, and safety is low, controls the cost control of engineering project, duration There are large effects with safety in production, and how to reduce cost, reduction duration and reduction safety accident becomes Super High height and hang Push up the task of top priority of decoration construction.
Summary of the invention
In order to overcome the high ceiling decoration construction cost of Super High is high, long in time limit, work progress is dangerous in the prior art etc. Technological deficiency, the present invention provides a kind of Super High furred ceiling special type construction operation platform and its construction methods, utilize electric block It is moved horizontally along structure truss lower edge guide rail and itself draws extraordinary construction operation platform vertical lift, thus realization pair The construction operation of the high ceiling decoration of entire Super High, solves above-mentioned technical problem.
The present invention is achieved through the following technical solutions above-mentioned purpose, a kind of Super High furred ceiling special type construction operation platform, Including ceiling construction job that requires special skills platform, electric block, connecting flange plate and guide rail, guide rail is fixed by the installation of connecting flange plate In structure truss lower edge, the electric block is mounted on guide rail, can be moved linearly along rail length direction, the furred ceiling The hanging of job that requires special skills platform construct below electric block, can be driven by electric block and do vertical displacement movement, acceptable and electricity Dynamic cucurbit is moved along guide rail together.
A kind of above-mentioned Super High furred ceiling special type construction operation platform, the ceiling construction job that requires special skills platform is by table top The frame structure that side rail and platform floor are welded, the table top side rail and platform floor use standard type angle steel, slot Steel or square steel tube production.
A kind of above-mentioned Super High furred ceiling special type construction operation platform, the vertical lift stroke of the electric block are 20- 25m, the moving distance along rail length direction are 0-10m.
The present invention is using, and building for support trolley is mainly completed by following construction procedure, and to mid-board side wall Concrete realizes effectively support, prevents side wall from sidesway occurs:
S1: computer simulation is carried out using work progress of the simulation analysis software to the special type construction operation platform, checks the spy The safety of structure and reliability of kind construction operation platform;
S2: guide rail is fixed on structure truss lower edge by connecting flange plate, is joined to levelness, straightness of guide rail etc. Number is checked, guarantees that the installation of guide rail meets construction operation requirement;
Both S3: electric block is mounted on guide rail, and ceiling construction job that requires special skills platform is hung below electric block, realize Connection, unloaded commissioning test is carried out to ceiling construction job that requires special skills platform, guarantees that the operation of ceiling construction job that requires special skills platform is steady It is fixed;
S4: it is moved horizontally on guide rail using electric block driving ceiling construction job that requires special skills platform, below long cantilever construction Furred ceiling curtain wall various processes are constructed;
S5: after various processes have been constructed, ceiling construction job that requires special skills platform is transferred to ground and is torn open using electric block, then Electric block, connecting flange plate and guide rail are successively removed, entire work progress is completed.
In general, through the invention it is contemplated above technical scheme is compared with the prior art, can achieve following has Beneficial effect: a kind of Super High furred ceiling special type construction operation platform of the present invention, using electric block along structure truss lower edge Guide rail moves horizontally and itself draws extraordinary construction operation platform vertical lift, hangs to realize to entire Super High height The construction operation for pushing up decoration, using the construction method of the special type construction operation platform compared with conventional construction method, it is convenient to operate, It is at low cost, it is highly-safe, it can be widely used for the construction of similar structures.
Detailed description of the invention
Specific embodiments of the present invention are further described in detail with reference to the accompanying drawing, in which:
Fig. 1 is a kind of overall structure diagram of Super High furred ceiling special type construction operation platform of the present invention;
Fig. 2 is the connection relationship diagram of electric block of the present invention, connecting flange plate and guide rail;
In figure: 1- ceiling construction job that requires special skills platform, 2- table top side rail, 3- platform floor, 4- electric block, 5- connecting flange Plate, 6- guide rail.
Specific embodiment
As shown in Figure 1, for a kind of overall structure diagram of Super High furred ceiling special type construction operation platform of the present invention, including Ceiling construction job that requires special skills platform 1, electric block 4, connecting flange plate 5 and guide rail 6, guide rail 6 are solid by the installation of connecting flange plate 5 It is scheduled on structure truss lower edge, the electric block 4 is mounted on guide rail 6, it can move linearly along the length direction of guide rail 6, The hanging of ceiling construction job that requires special skills platform 1 can be driven by electric block 4 below electric block 4 and do vertical displacement movement, It can also be moved together along guide rail 6 with electric block 4.
Ceiling construction job that requires special skills platform 1 is the frame structure being welded by table top side rail 2 and platform floor 3, institute Table top side rail 2 and platform floor 3 are stated using standard type angle steel, channel steel or square steel tube production, the vertical lift of electric block 4 Stroke is 20-25m, can moving distance be 0-10m along the length direction of guide rail 6.
The present invention is using, mainly by following construction procedure come:
Step 1: computer simulation, review are carried out using work progress of the simulation analysis software to the special type construction operation platform The safety of structure and reliability of the special type construction operation platform;
Step 2: guide rail 6 is fixed on structure truss lower edge by connecting flange plate 5, to the levelness of guide rail 6, straight The parameters such as dimension are checked, guarantee that the installation of guide rail 6 meets construction operation requirement;
Step 3: electric block 4 is mounted on guide rail 6, and ceiling construction job that requires special skills platform 1 is hung below electric block 4, The connection for realizing the two carries out unloaded commissioning test to ceiling construction job that requires special skills platform 1, guarantees that ceiling construction job that requires special skills is flat Platform 1 is stable;
Step 4: ceiling construction job that requires special skills platform 1 is driven to move horizontally on guide rail 6 using electric block 4, to absolute altitude The following furred ceiling curtain wall various processes of 22.95m long cantilever construction are constructed, construction height 13m;
Step 5: after the following furred ceiling curtain wall various processes of 22.95m long cantilever construction have been constructed, furred ceiling is applied using electric block 4 The decentralization of work job that requires special skills platform 1 is to ground and tears open, then successively removes electric block 4, connecting flange plate 5 and guide rail 6, completes whole A work progress.
As it will be easily appreciated by one skilled in the art that the foregoing is merely illustrative of the preferred embodiments of the present invention, it is not used to The limitation present invention, any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should all include Within protection scope of the present invention.

Claims (4)

1. a kind of Super High furred ceiling special type construction operation platform, including ceiling construction job that requires special skills platform (1), electric block (4), Connecting flange plate (5) and guide rail (6), it is characterised in that: the guide rail (6) is fixed on structure by connecting flange plate (5) Truss lower edge, the electric block (4) are mounted on guide rail (6), can move linearly along rail length direction, the furred ceiling Job that requires special skills platform (1) hanging construct below electric block (4), can be driven by electric block (4) and do vertical displacement movement, also It can be mobile along guide rail (6) together with electric block (4).
2. a kind of Super High furred ceiling special type construction operation platform according to claim 1, it is characterised in that: the furred ceiling is applied Work job that requires special skills platform (1) is the frame structure being welded by table top side rail (2) and platform floor (3), the table top side Guardrail (2) and platform floor (3) are using standard type angle steel, channel steel or square steel tube production.
3. a kind of Super High furred ceiling special type construction operation platform according to claim 1, it is characterised in that: the electronic calabash The vertical lift stroke of reed (4) is 20-25m, and the moving distance along guide rail (6) length direction is 0-10m.
4. a kind of construction method of Super High furred ceiling special type construction operation platform, it is characterised in that: the construction method mainly includes Following steps:
S1: computer simulation is carried out using work progress of the simulation analysis software to the special type construction operation platform, checks the spy The safety of structure and reliability of kind construction operation platform;
S2: guide rail (6) are fixed on structure truss lower edge by connecting flange plate (5), to the levelness of guide rail (6), The parameters such as straightness are checked, guarantee that the installation of guide rail (6) meets construction operation requirement;
S3: electric block (4) is mounted on guide rail (6), and ceiling construction job that requires special skills platform (1) is hung in electric block (4) The connection of the two is realized in lower section, carries out unloaded commissioning test to ceiling construction job that requires special skills platform (1), guarantees that ceiling construction is special Kind job platform (1) is stable;
S4: it is moved horizontally on guide rail (6) using electric block (4) driving ceiling construction job that requires special skills platform (1), to large cantilever The following furred ceiling curtain wall various processes of structure are constructed;
S5: after various processes have been constructed, ceiling construction job that requires special skills platform (1) is transferred to ground simultaneously using electric block (4) It tears open, then successively removes electric block (4), connecting flange plate (5) and guide rail (6), complete entire work progress.
CN201811578916.XA 2018-12-24 2018-12-24 A kind of Super High furred ceiling special type construction operation platform and its construction method Pending CN109763639A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811578916.XA CN109763639A (en) 2018-12-24 2018-12-24 A kind of Super High furred ceiling special type construction operation platform and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811578916.XA CN109763639A (en) 2018-12-24 2018-12-24 A kind of Super High furred ceiling special type construction operation platform and its construction method

Publications (1)

Publication Number Publication Date
CN109763639A true CN109763639A (en) 2019-05-17

Family

ID=66451995

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811578916.XA Pending CN109763639A (en) 2018-12-24 2018-12-24 A kind of Super High furred ceiling special type construction operation platform and its construction method

Country Status (1)

Country Link
CN (1) CN109763639A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1217411A (en) * 1998-11-10 1999-05-26 万剑啸 Two-dimension suspension scaffold
CN101514586A (en) * 2009-01-14 2009-08-26 北京江河幕墙股份有限公司 Hanger rail type electric hanging boat and high-rise long span house, bridge building construction method and use thereof
CN204676869U (en) * 2015-04-23 2015-09-30 中国建筑第八工程局有限公司 For the travelling cradle of curtain wall construction
CN105888230A (en) * 2016-04-21 2016-08-24 江河创建集团股份有限公司 Lifting device for building curtain wall construction and construction method thereof
CN206800973U (en) * 2017-05-28 2017-12-26 江苏省苏中建设集团股份有限公司 A kind of packaged type building hanging basket
CN207144450U (en) * 2017-08-23 2018-03-27 蒋彬松 A kind of cradle for constructional engineering
CN207177305U (en) * 2017-09-06 2018-04-03 中交路桥建设有限公司 Prefabricated beam stretching jack suspension door frame

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1217411A (en) * 1998-11-10 1999-05-26 万剑啸 Two-dimension suspension scaffold
CN101514586A (en) * 2009-01-14 2009-08-26 北京江河幕墙股份有限公司 Hanger rail type electric hanging boat and high-rise long span house, bridge building construction method and use thereof
CN204676869U (en) * 2015-04-23 2015-09-30 中国建筑第八工程局有限公司 For the travelling cradle of curtain wall construction
CN105888230A (en) * 2016-04-21 2016-08-24 江河创建集团股份有限公司 Lifting device for building curtain wall construction and construction method thereof
CN206800973U (en) * 2017-05-28 2017-12-26 江苏省苏中建设集团股份有限公司 A kind of packaged type building hanging basket
CN207144450U (en) * 2017-08-23 2018-03-27 蒋彬松 A kind of cradle for constructional engineering
CN207177305U (en) * 2017-09-06 2018-04-03 中交路桥建设有限公司 Prefabricated beam stretching jack suspension door frame

Similar Documents

Publication Publication Date Title
CN102900022B (en) Cable stayed bridge leaning tower hydraulic climbing mould construction method
CN201158933Y (en) High-rise maintaining scaffold device with extruding structure
CN104453197B (en) High Large Cantilever concrete structural steel shape supports platform
CN204804298U (en) Building material hoist and mount construction scaffold
CN201417657Y (en) Installation device of indoor transformer
CN102987981A (en) Hydraulic lifting platform for window cleaning machine
CN104563528B (en) The quick positioning apparatus of prefabrication prefabricated panel and method
CN105064717B (en) A kind of construction method of steel slideway jacking architecture adding-floor
CN203821720U (en) High-altitude large roof panel installing tool trolley
CN202751338U (en) Rail type suspension basket
CN103711323B (en) Utilize the anti-ceiling board construction method of portable tubular truss stage+module roofing
CN101413341B (en) Elevator well internal formwork construction method and elevator well internal formwork construction support
CN108545628B (en) A kind of mobile hanging device of Super High and its hanging method
CN203654692U (en) Overhanging type mobile scaffold
CN104895314A (en) Truss platform for high and large space top plate concrete construction
CN105298099A (en) Modular suspension type steel tube fastener scaffold operating platform and erecting method thereof
CN103711301A (en) Construction method and device for two-track movable electric basket and lifting hoist
CN103924777A (en) Suspension platform special for building exterior wall decoration construction
CN203296166U (en) Supporting structure of main module unit in module building
CN104314299A (en) Foldable hanging basket
CN204216515U (en) The mounting structure of distribution engineering cable testing bridge
CN106065661A (en) Large span unsettled steel corridor construction engineering method
CN104831846A (en) Hoisting method for indoor inclined curtain wall super-large glass
CN107190964A (en) A kind of construction method of prefabricated hoistway operation platform
CN202577571U (en) Structure of inner barrel-outer frame clip-shaped steel framework building

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination