CN107060105A - Lifting construction method for multiple steel galleries between tower buildings - Google Patents

Lifting construction method for multiple steel galleries between tower buildings Download PDF

Info

Publication number
CN107060105A
CN107060105A CN201710326724.9A CN201710326724A CN107060105A CN 107060105 A CN107060105 A CN 107060105A CN 201710326724 A CN201710326724 A CN 201710326724A CN 107060105 A CN107060105 A CN 107060105A
Authority
CN
China
Prior art keywords
steel
area
steel vestibule
lifting
vestibule
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201710326724.9A
Other languages
Chinese (zh)
Other versions
CN107060105B (en
Inventor
苏铠
张益民
雷志强
刘培
程志军
朱早孙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
China Construction Second Engineering Bureau Yangguang Intelligent Manufacturing Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN201710326724.9A priority Critical patent/CN107060105B/en
Publication of CN107060105A publication Critical patent/CN107060105A/en
Application granted granted Critical
Publication of CN107060105B publication Critical patent/CN107060105B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B2001/3588Extraordinary methods of construction, e.g. lift-slab, jack-block using special lifting or handling devices, e.g. gantries, overhead conveying rails

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to a lifting construction method for a plurality of steel galleries among tower buildings, wherein the lifting sequence is low-region steel gallery, middle-region steel gallery and high-region steel gallery, firstly, preassembling rod pieces are arranged at the elevations of the low-region steel gallery, the middle-region steel gallery and the high-region steel gallery, a lifting platform is arranged, and meanwhile, a hydraulic lifter is arranged; then assembling the low-area steel gallery on the ground and lifting the low-area steel gallery to the elevation, erecting a jig frame on the low-area steel gallery for assembling the middle-area steel gallery, and lifting the low-area steel gallery to the elevation; and then building a jig frame on the middle area steel gallery to assemble the high area steel gallery, and lifting the high area steel gallery to the elevation to complete construction. The construction of a plurality of steel vestibules between tower buildings is not general, the construction method can obviously improve the construction efficiency through engineering practice, ensure the construction safety, greatly reduce the workload of hoisting, save the energy consumption and time, reduce the construction cost and the installation construction difficulty, accord with the national green construction requirement, can provide reference and guidance for the construction of a plurality of steel vestibules between similar double tower buildings in the future, and have the prospect of popularization and application.

Description

A kind of lifting construction method of multiple steel vestibules between high building
Technical field
The present invention relates to construction steel structure installation Technology field, multiple steel vestibules carries between more particularly to a kind of high building Rise construction method.
Background technology
Pursuit with the growing tension of urban built-up land, people to the art of architecture is improved constantly and construction cost Day by day increase severely, the multiple aerial long-span heavy type steel vestibules of Super High two tall buildings also will be increasing, big for span, highly high Building, the mode integrally lifted using hydraulic pressure is preferred, but the multiple steel vestibule forms of two tall buildings are different, and weight differs, suitably Method for improving must take into account cost, security and easy construction.
Vestibule is one kind in Complex Tall Building system, and it is a kind of connector, perpendicular to building lateral arrangement, only The Project case for installing a vestibule is very more, and the construction of multiple steel vestibules is not universal between two tall buildings, the construction referred to Example is extremely limited, moreover, steel vestibule is in installation on ground, during overall lifting, larger due to conducting oneself with dignity, and lifting construction is there is originally Difficulty is big, lifting and the problems such as high installation requirement.At present, the lifting operation of multiple steel vestibules is also based on single steel vestibule lifting work Industry mode:The first step, sets assembled moulding bed on basement roof, and hydraulic rockshaft is set at high area's steel vestibule absolute altitude and is carried Peaceful, using truck crane, tower crane on assembled moulding bed assembled high area's steel vestibule;Second step, lifts high area's steel vestibule, on ground Hydraulic rockshaft and lifting platform are set at steel vestibule in area's in assembly, Bing Zhong areas steel vestibule absolute altitude;Area's steel in 3rd step, lifting Vestibule, sets hydraulic rockshaft and lifting platform at the low area's steel vestibule of installation on ground, Bing Di areas steel vestibule absolute altitude;4th Step, lifts low area's steel vestibule.
The problem of existing one:Each steel vestibule lifting need to all set corresponding hydraulic rockshaft in the high building built up With lifting platform, the installation measure amount that three steel vestibule liftings need is big, consumes substantial amounts of material, time, adds construction Cost.Problem two:Three steel gallery structure weight are very huge, if three steel vestibules continue the assembly on basement roof, Long-time is in great stress by basement roof, and its bearing capacity is much not enough, easily produces cracking, and security is obtained Less than guarantee, it is necessary to be reinforced to basement roof, using shaped steel, full hall scaffold return back to top supports or in basement knot Increase in structure reinforced concrete column, steel frame beam substantial amounts of material is consumed to strengthen the bearing capacity of basement roof, so, it is artificial and when Between, drag slowly construction speed, add construction cost.The report multiple steel vestibule lifting constructions high building is there is no at this stage.
The content of the invention
To solve the above problems, the present invention provides a kind of lifting construction method of multiple steel vestibules between high building, it is intended to reduce The difficulty of construction of the build process of multiple steel vestibules between two tall buildings, is constructed into while shortening basement roof load time, saving Originally, reduction difficulty of construction.
To achieve the above object, the present invention is adopted the following technical scheme that:
The present invention provides a kind of lifting construction method of multiple steel vestibules between high building, and lifting order is low area's steel vestibule 6, middle area's steel Vestibule 9, high area's steel vestibule 10, comprise the following steps:
Step 1, prepackage rod member 1 is respectively mounted at low area's steel vestibule 6, middle area's steel vestibule 9, the designed elevation of high area's steel vestibule 10, Lifting platform 3, and the installation hydraulic rockshaft 2 on every group of lifting platform 3 are set on high area's steel vestibule 10 prepackage rod member 1;
Hydraulic synchronizing lifting system equipment, including hydraulic pump source system, hydraulic rockshaft 2, biography are installed on the lifting platform 3 Sensor, hydraulic oil pipe etc.;
Step 2, using the assembly under the projection of low area's steel vestibule 6 predetermined installation site of truck crane 8, according to low area's steel vestibule 6 Loading characteristic, debugging hydraulic rockshaft 2 and steel strand wires 5, and check whether low area's steel vestibule 6 meets design requirement;
Step 3, after checking that confirmation is errorless, hydraulic rockshaft 2 takes the method for hierarchical loading to be preloaded, and utilizes hydraulic pressure lift Device 2 drives steel strand wires 5 that low area's steel vestibule 6 is carried out into lifting 11 for the first time, departs from assembled moulding bed 7, basement roof is not stressed, It is promoted to the low designed elevation of area's steel vestibule 6;
Step 4, after low area's steel vestibule 6 checks that confirmation is errorless, assembled moulding bed 7 is set in the low top of area's steel vestibule 6, tower is utilized Area's steel vestibule 9 in assembly is hung on assembled moulding bed 7;
Step 5, after checking that confirmation is errorless, repeat step 2, hydraulic rockshaft 2 takes the method for hierarchical loading to be preloaded, profit Drive steel strand wires 5 that middle area's steel vestibule 9 is carried out into second of lifting 12 with hydraulic rockshaft 2, depart from assembled moulding bed 7, in being promoted to The designed elevation of area's steel vestibule 9;
Step 6, area's steel vestibule 9 and prepackage rod member 1 in welding, whether area's steel vestibule 9 meets design requirement in inspection, confirms errorless Afterwards, assembled moulding bed 7 is set in the top of middle area's steel vestibule 9, using tower crane on assembled moulding bed 7 assembled high area's steel vestibule 10;
Step 7, after checking that confirmation is errorless, repeat step 2, hydraulic rockshaft 2 takes the method for hierarchical loading to be preloaded, profit Drive steel strand wires 5 that high area's steel vestibule 10 is carried out into third time lifting 13 with hydraulic rockshaft 2, depart from assembled moulding bed 7, lifted paramount The designed elevation of area's steel vestibule 10, welds high area's steel vestibule 10 and prepackage rod member 1;
Step 8, unloading hydraulic rockshaft 2 is fully relaxed to steel strand wires 5, removes measure for improvement, the deadweight of steel vestibule is transferred to tower On building 4, the erection & lift work of low area's steel vestibule 6, middle area's steel vestibule 9, high area's steel vestibule 10 is completed.
Further, check to carry out low area's steel vestibule 6, middle area's steel vestibule 9, high area's steel vestibule 10 described in step 1~step 7 The visual examination of carrying out flaw detection and weld seam 11.
Further, the hydraulic rockshaft 2 uses steel strand wires 5 as lifting load-bearing rigging, and steel strand wires are installed from the bottom to top 5, suspender, wear earth anchor;The steel strand wires 5 are cut on demand, after equating of polishing, respectively with low 6 two ends of area's steel vestibule symmetrically arranged 4 Individual suspension centre is fixedly connected;Tension steel strand 5, makes its uniform stressed, locks earth anchor;The hydraulic synchronizing lifting system is debugged, is examined Whether all interim measures for looking into hydraulic synchronizing lifting meet design requirement.
Further, the hydraulic rockshaft 2 is stretched cylinder pressure and gradually raised, the 20%, 40% of pressure needed for being followed successively by, at all In the case of all normal, it can continue to be loaded into 60%, 70%, 80%, 90%, 95%, 100%;
Further, the hierarchical loading should be noted:Each step hierarchical loading is finished, and all should be suspended and be checked before the loading of steel vestibule Deformation afterwards and the stability of the structure of high building 4.
Further, observing time at least reserved 10 minutes between each adjacent load step, until vestibule lift unit Depart from assembled moulding bed 7.
Further, when the high area's steel vestibule 10 of area's steel vestibule 9/ in low area's steel vestibule 6/ in step 2/ step 4/ step 6 When being promoted to away from designed elevation 1000mm, pause lifting is locked using hydraulic rockshaft 2, and aerial stop makees complete for more than 12 hours Face checked, suspension centre structure, bearing system, lifting means, truss and the deformation of weld seam and stressing conditions etc. are checked emphatically, is measured low The each point actual size of the high area's steel vestibule 10 of area's steel vestibule 6/middle area's steel vestibule 9/ and the prepackage interface of rod member 1, collation process, drop Low lifting speed, is continued to lift up to absolute altitude;Weld and check in low area's steel vestibule 6/ whether is the high area's steel vestibule 10 of area's steel vestibule 9/ Design requirement is met, so far the lifting construction of the high area's steel vestibule 10 of area's steel vestibule 9/ is completed in low area's steel vestibule 6/, with high building 4 As an entirety.
Further, the step 8 lifting suspension centre is progressively unloaded, and unloading classification is carried out by 20%, and knot is observed after unloading 20% Structure deformation, continues to unload 20% without abnormal conditions, and until load, all unloading is completed.
Beneficial effects of the present invention are embodied in:
1)Shaped steel, full hall scaffold need not be used to carry out the support that returns back to top, or increase reinforced concrete column, reinforcing bar in basement structure Beam is to strengthen the bearing capacity of basement roof;Vestibule rectangular structure top surface only needs assembled low area's steel vestibule, and assembling duration is short, it is to avoid Basement roof is reinforced on a large scale, basement roof do not allow to be also easy to produce cracking, saved substantial amounts of reinforcement material, Engineering time and cost of labor, while the duration is shortened, reduce integral construction cost;
2)Do not need each steel vestibule lifting that corresponding hydraulic rockshaft and lifting are all set in the high building built up in advance Platform, the engineering method passes through engineering practice, it is only necessary to set corresponding hydraulic pressure to carry in the high building at high area's steel vestibule absolute altitude Rise device and lifting platform;The installation measure of steel vestibule lifting is greatlyd save, spillage of material is reduced, has saved artificial And the time;
3)Set on low/medium area's steel vestibule after assembled moulding bed, assembled medium/high area's steel vestibule and lifted absolute altitude, this is applied Work method, substantially reduces the vertical-lift distance of super large heavy-duty steel vestibule, has saved energy consumption and time, reduced construction cost With installation difficulty, meet national green construction requirement, it is favourable in construction quality, construction safety and operation construction period etc.;
4)The construction of multiple steel vestibules is not universal between two tall buildings, and the construction method can be improved significantly by engineering practice Efficiency of construction, ensures construction safety, and the reduction of the workload amplitude peak of lifting can connect for the multiple steel of similar two tall buildings later Corridor engineering construction is offered reference and instructed, the prospect with popularization and application.
Other features and advantages of the present invention will be illustrated in the following description, and partly becomes from specification It is clear that or being understood by implementing the present invention.The main object of the present invention and further advantage can be by specification, power Specifically noted scheme is realized and obtained in sharp claim.
Brief description of the drawings
The present invention will be further described in detail below in conjunction with the accompanying drawings.
Fig. 1 is step 1 schematic diagram of the present invention.
Fig. 2 is that step 2 of the present invention lifts schematic diagram for the first time.
Fig. 3 is step 3 schematic diagram of the present invention.
Fig. 4 is second of lifting schematic diagram of step 4 of the present invention.
Fig. 5 is step 5 schematic diagram of the present invention.
Fig. 6 is that step 6 of the present invention lifts schematic diagram for the third time.
Reference:1- prepackages rod member, 2- hydraulic rockshafts, 3- liftings platform, 4- high buildings, 5- steel strand wires, 6- Area's steel vestibule, the high area's steel vestibules of 10-, the lifting of 11- first times, 12- in the assembled moulding bed of low area's steel vestibule, 7-, 8- truck cranes, 9- Second of lifting, 13- third times are lifted.
Embodiment
Below in conjunction with the accompanying drawings and the present invention is further described embodiment:
Multiple steel vestibules between two tall buildings, it is desirable to which assembled completion is carried out again one by one on basement roof so heavy steel construction The lifting of certain distance, then carries out necessarily required connection construction with high building, and difficulty of construction is big, and lifting is high with installation requirement, Assembled process duration especially on basement roof top is long, basement roof is in great stress shape for a long time Under state, its bearing capacity is much not enough, easily produces cracking, and security cannot be guaranteed.
The lifting construction method of multiple steel vestibules between a kind of high building of the present invention, multiple steel vestibules are connected between two tall buildings 4, Lifting order is low area's steel vestibule 6, middle area's steel vestibule 9, high area's steel vestibule 10, is comprised the following steps:
Step 1, prepackage rod member 1 is respectively mounted at low area's steel vestibule 6, middle area's steel vestibule 9, the designed elevation of high area's steel vestibule 10, Lifting platform 3 is set on the prepackage rod member 1 of Jin Gao areas steel vestibule 10, four groups of lifting platforms 3 are set altogether, and it is flat in every group of lifting One hydraulic rockshaft 2 is installed on platform 3;Hydraulic synchronizing lifting system equipment, including hydraulic pump source system, hydraulic rockshaft are installed 2nd, sensor etc.;
The quantity of hydraulic rockshaft 2 extends according to the weight of steel vestibule in step 1.
Using the assembly under the projection of low area's steel vestibule 6 predetermined installation site of truck crane 8, according to the stress of low area's steel vestibule 6 Feature, debugging hydraulic rockshaft 2 and steel strand wires 5, and it is as shown in Figure 1 to check whether low area's steel vestibule 6 meets design requirement;
The hydraulic rockshaft 2 uses steel strand wires 5 as lifting load-bearing rigging, and steel strand wires 5 are installed from the bottom to top, suspender, wear ground Anchor;The steel strand wires 5 are cut on demand, after equating of polishing, and are fixed respectively with symmetrically arranged 4 suspension centres in low 6 two ends of area's steel vestibule Connection;Tension steel strand 5, makes its uniform stressed, locks earth anchor;The hydraulic synchronizing lifting system is debugged, hydraulic synchronization is checked Whether all interim measures of lifting meet design requirement;
Hydraulic rockshaft 2 only needs to set in the high building at the high absolute altitude of area's steel vestibule 10, greatlys save multiple steel and connects The installation measure of corridor lifting;Wherein, the quantity of suspension centre is set according to actual conditions such as absolute altitude, steel vestibule weight;
Step 2, after checking that confirmation is errorless, hydraulic rockshaft 2 takes the method for hierarchical loading to be preloaded, and utilizes hydraulic pressure lift Device 2 drives steel strand wires 5 that low area's steel vestibule 6 is carried out into lifting 11 for the first time, departs from assembled moulding bed 7, basement roof is not stressed, It is promoted to 6 designed elevations of low area's steel vestibule as shown in Figure 2;
If low area's steel vestibule 6 has movement when just starting lifting, Suspend Job is needed, hydraulic test system pressure is kept.To liquid Pressure synchronization lifting system equipment is checked comprehensively, is confirming integrally-built stability and the no problem definitely situation of security Under, it could start to continue to lift up.If there is the situation that each point is liftoff when different, lifting speed should be now reduced, and see closely The liftoff situation of each point is looked into, " single-point is moved " lifting is done if necessary to ensure the levelness of low area's steel vestibule 6.It is promoted to away from designed elevation During 1000mm, pause lifting is locked using hydraulic rockshaft 2, and aerial stop is made to check comprehensively for more than 12 hours, checks hang emphatically Point structure, bearing system, lifting means, truss and the deformation of weld seam and stressing conditions etc., measure low area's steel vestibule 6 and prepackage bar The each point actual size of the interface of part 1, collation process, reduction lifting speed is continued to lift up to absolute altitude.Weld low area's steel vestibule 6 with Rod member 1 is pre-installed, checks whether low area's steel vestibule 6 meets design requirement, so far the lifting construction of low area's steel vestibule 6 is completed, it is and double High building 4 turns into a complete entirety.
It must be noted that in construction:During hierarchical loading, each step hierarchical loading is finished, and all should be suspended and be checked, such as Deformation before and after the loading of the low grade of area's steel vestibule 6, and main building structure stability situations such as.In situation about all going well Under, continue next step hierarchical loading;Wherein, the hydraulic rockshaft 2 is stretched cylinder pressure and gradually raised, pressure needed for being followed successively by 20%, 40%, in the case where Everything is fine, it can continue to be loaded into 60%, 70%, 80%, 90%, 95%, 100%, it is adjacent every time to add Observing time at least reserved 10 minutes between load step, until vestibule lift unit departs from assembled moulding bed 7.
Step 3, after low area's steel vestibule 6 checks that confirmation is errorless, assembled moulding bed 7 is set in the low top of area's steel vestibule 6, tower is utilized Area's steel vestibule 9 in assembly is hung on assembled moulding bed 7, as shown in Figure 3.
Step 4, shown in Fig. 4, after checking that confirmation is errorless, hydraulic rockshaft 2 takes the method for hierarchical loading to be preloaded, Drive steel strand wires 5 that middle area's steel vestibule 9 is carried out into second of lifting 12 using hydraulic rockshaft 2, depart from assembled moulding bed 7, be promoted to The middle designed elevation of area's steel vestibule 9.Wherein, the method for hierarchical loading, the points for attention of lifting process are identical with step 2.
Step 5, area's steel vestibule 9 and prepackage rod member in welding, whether area's steel vestibule 9 meets design requirement in inspection, confirms After errorless, assembled moulding bed 7 is set in the top of middle area's steel vestibule 9, using tower crane on assembled moulding bed 7 assembled high area's steel vestibule 10. Wherein, the method for hierarchical loading, the points for attention of lifting process are identical with step 2.
Step 6, after checking that confirmation is errorless, hydraulic rockshaft 2 takes the method for hierarchical loading to be preloaded, and utilizes hydraulic pressure Lifter 2 drives steel strand wires 5 that high area's steel vestibule 10 is carried out into third time lifting 13, departs from assembled moulding bed 7, lifts paramount area's steel and connects The designed elevation of corridor 10.Wherein, the method for hierarchical loading, the points for attention of lifting process are identical with step 2.
After installation, the synchronous load shedding of each suspension centre of hydraulic synchronizing lifting system equipment is fully relaxed to steel strand wires 5, makes The deadweight of steel vestibule is transferred on high building 4, removes measure for improvement, completes the erection & lift work of Gao Qu, middle area, low area's steel vestibule As shown in Figure 6.
To sum up, the lifting construction method of multiple steel vestibules between a kind of high building that the present invention is announced,
1)Whole process only needs the corresponding hydraulic rockshaft of interior setting at high area's steel vestibule absolute altitude and lifting platform i.e. Can;The installation measure of steel vestibule lifting is greatlyd save, spillage of material is reduced, the artificial and time has been saved;
2)Set on low/medium area's steel vestibule after assembled moulding bed, assembled medium/high area's steel vestibule and lifted absolute altitude, this is applied Work method, substantially reduces the vertical-lift distance of super large heavy-duty steel vestibule, has saved energy consumption and time, reduced construction cost With installation difficulty, meet national green construction requirement, it is favourable in construction quality, construction safety and operation construction period etc.;
3)Shaped steel, full hall scaffold need not be used to carry out the support that returns back to top, or increase reinforced concrete column, reinforcing bar in basement structure Beam is to strengthen the bearing capacity of basement roof;Vestibule rectangular structure top surface only needs assembled low area's steel vestibule, and assembling duration is short, it is to avoid Basement roof is reinforced on a large scale, basement roof do not allow to be also easy to produce cracking, saved substantial amounts of reinforcement material, Engineering time and cost of labor, while the duration is shortened, reduce integral construction cost;
4)The construction of multiple steel vestibules is not universal between two tall buildings, and the construction method can be improved significantly by engineering practice Efficiency of construction, ensures construction safety, and the reduction of the workload amplitude peak of lifting can connect for the multiple steel of similar two tall buildings later Corridor engineering construction is offered reference and instructed, the prospect with popularization and application.
In the lifting process of construction cell, lifting region rod member is needed to carry out temperature pier to meet overall lifting need Ask, offset the deformation that weight stress is produced in lifting, form it into it is stable overall to be lifted, using prior art, herein Repeat no more.The installation of hydraulic synchronizing lifting system equipment, debugging, using, unloading prior art is used, will not be repeated here.
The present invention preferably embodiment is the foregoing is only, but protection scope of the present invention is not limited thereto, Any one skilled in the art the invention discloses technical scope in the change or replacement expected, should all contain Cover within protection scope of the present invention.

Claims (8)

1. a kind of lifting construction method of multiple steel vestibules between high building, it is characterised in that lifting order is low area's steel vestibule(6)、 Middle area's steel vestibule(9), high area's steel vestibule(10), comprise the following steps:
Step 1, in low area's steel vestibule(6), middle area's steel vestibule(9), high area's steel vestibule(10)Designed elevation at be respectively mounted prepackage Rod member(1), in high area's steel vestibule(10)Pre-install rod member(1)It is upper that lifting platform is set(3), and in every group of lifting platform(3)On Hydraulic rockshaft is installed(2);
Step 2, using truck crane(8)In low area's steel vestibule(6)The predetermined lower assembly of installation site projection, according to low Qu Ganglian Corridor(6)Loading characteristic, debug hydraulic rockshaft(2)And steel strand wires(5), and check low area's steel vestibule(6)Whether satisfaction is designed It is required that;
Step 3, after checking that confirmation is errorless, hydraulic rockshaft(2)Take the method for hierarchical loading to be preloaded, carried using hydraulic pressure Rise device(2)Drive steel strand wires(5)By low area's steel vestibule(6)Carry out first time lifting(11), depart from assembled moulding bed(7), make underground Ceiling plate does not stress, and is promoted to low area's steel vestibule(6)Designed elevation;
Step 4, low area's steel vestibule(6)After checking that confirmation is errorless, in low area's steel vestibule(6)Top sets assembled moulding bed(7), Using tower crane in assembled moulding bed(7)Area's steel vestibule in upper assembly(9);
Step 5, after checking that confirmation is errorless, hydraulic rockshaft(2)Take the method for hierarchical loading to be preloaded, carried using hydraulic pressure Rise device(2)Drive steel strand wires(5)By middle area's steel vestibule(9)Second is carried out to be lifted(12), depart from assembled moulding bed(7), it is promoted to Middle area's steel vestibule(9)Designed elevation;
Step 6, steel vestibule in area's in welding(9)With prepackage rod member(1), steel vestibule in area's in inspection(9)Whether design requirement is met, really Recognize it is errorless after, in middle area's steel vestibule(9)Top sets assembled moulding bed(7), using tower crane in assembled moulding bed(7)Upper assembled high area's steel Vestibule(10);
Step 7, after checking that confirmation is errorless, hydraulic rockshaft(2)Take the method for hierarchical loading to be preloaded, carried using hydraulic pressure Rise device(2)Drive steel strand wires(5)By high area's steel vestibule(10)Carry out third time lifting(13), depart from assembled moulding bed(7), it is promoted to High area's steel vestibule(10)Designed elevation, welds high area's steel vestibule(10)With prepackage rod member(1);
Step 8, hydraulic rockshaft is unloaded(2)To steel strand wires(5)It is fully relaxed, measure for improvement is removed, makes the deadweight transfer of steel vestibule To high building(4)On, complete low area's steel vestibule(6), middle area's steel vestibule(9), high area's steel vestibule(10)Erection & lift work.
2. lifting construction method as claimed in claim 1, it is characterised in that check to be to low area described in step 1~step 7 Steel vestibule(6), middle area's steel vestibule(9), high area's steel vestibule(10)Carry out carrying out flaw detection and weld seam(11)Visual examination.
3. lifting construction method as claimed in claim 1, it is characterised in that the hydraulic rockshaft(2)Use steel strand wires(5) As lifting load-bearing rigging, steel strand wires are installed from the bottom to top(5), suspender, wear earth anchor;Tension steel strand(5), make it uniform by Power, locks earth anchor.
4. lifting construction method as claimed in claim 1, it is characterised in that the hydraulic rockshaft(2)Stretch cylinder pressure gradually Up-regulation, the 20%, 40% of pressure, in the case where Everything is fine, can continue to be loaded into 60%, 70%, 80% needed for being followed successively by, 90%, 95%, 100%.
5. lifting construction method as claimed in claim 1, it is characterised in that the hierarchical loading should be noted:Each step point Level loaded, all should suspend and check the deformation and high building before and after the loading of steel vestibule(4)The stability of structure.
6. lifting construction method as claimed in claim 1, it is characterised in that 10 points are at least reserved between adjacent load step The observing time of clock, until steel vestibule lift unit departs from assembled moulding bed(7).
7. lifting construction method as claimed in claim 1, it is characterised in that when the low area in step 2/ step 4/ step 6 Steel vestibule(6)/ middle area's steel vestibule(9)/ high area's steel vestibule(10)When being promoted to away from designed elevation 1000mm, pause lifting is utilized Hydraulic rockshaft(2)Locking, more than 12 hours works of aerial stop are checked comprehensively, and suspension centre structure, bearing system, lifting are checked emphatically Equipment, the deformation of truss and weld seam and stressing conditions etc., measure low area's steel vestibule(6)/ middle area's steel vestibule(9)/ high area's steel vestibule (10)With prepackage rod member(1)The each point actual size of interface, collation process, reduction lifting speed is continued to lift up to absolute altitude;Welding And check low area's steel vestibule(6)/ middle area's steel vestibule(9)/ high area's steel vestibule(10)Whether design requirement is met, so far low Qu Ganglian Corridor(6)/ middle area's steel vestibule(9)/ high area's steel vestibule(10)Lifting construction complete, with high building(4)As an entirety.
8. lifting construction method as claimed in claim 1, it is characterised in that the step 8 lifting suspension centre is progressively unloaded, and is unloaded Classification is carried out by 20%, observation structure deformation after unloading 20%, continues to unload 20% without abnormal conditions, until load is complete Portion's unloading is completed.
CN201710326724.9A 2017-05-10 2017-05-10 Lifting construction method for multiple steel galleries between tower buildings Active CN107060105B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710326724.9A CN107060105B (en) 2017-05-10 2017-05-10 Lifting construction method for multiple steel galleries between tower buildings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710326724.9A CN107060105B (en) 2017-05-10 2017-05-10 Lifting construction method for multiple steel galleries between tower buildings

Publications (2)

Publication Number Publication Date
CN107060105A true CN107060105A (en) 2017-08-18
CN107060105B CN107060105B (en) 2018-11-13

Family

ID=59597580

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710326724.9A Active CN107060105B (en) 2017-05-10 2017-05-10 Lifting construction method for multiple steel galleries between tower buildings

Country Status (1)

Country Link
CN (1) CN107060105B (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109083268A (en) * 2018-10-29 2018-12-25 中国冶集团有限公司 Narrow more barrier zone bilayer differing tilt angles vestibules once lift installation method
CN109826447A (en) * 2019-02-28 2019-05-31 五冶集团上海有限公司 A kind of method of hydraulic lifting apparatus steel strand wires high-altitude Fast Installation
CN109881890A (en) * 2019-02-21 2019-06-14 深圳市建筑设计研究总院有限公司 A kind of more corridor construction methods of super high-rise building
CN112049439A (en) * 2020-10-14 2020-12-08 中冶建工集团重庆钢结构有限公司 Method for integrally lifting and mounting steel platform in limited space
WO2021012971A1 (en) * 2019-07-22 2021-01-28 中建三局集团有限公司 Integral lifting construction method for ultra-large hyperbolic integrated unit aluminium plate curtain walls
CN113152687A (en) * 2021-04-21 2021-07-23 上海宝冶集团南京建筑有限公司 Structure and method for improving layering reverse order of hollow steel gallery
CN113494127A (en) * 2021-07-09 2021-10-12 上海宝冶集团有限公司 Construction method for layered lifting of large-span open-web corridor steel platform
CN115262991A (en) * 2022-06-15 2022-11-01 中国五冶集团有限公司 Corridor lifting and folding structure and construction method thereof
CN115492252A (en) * 2022-11-04 2022-12-20 中国十七冶集团有限公司 Overall hoisting facility and construction method of high-altitude long-span steel structure corridor based on BIM technology
CN117052157A (en) * 2023-08-03 2023-11-14 中冶(上海)钢结构科技有限公司 An overall lifting construction method and construction device for a multi-layer column-free steel corridor
CN117702899A (en) * 2023-11-14 2024-03-15 中交四航局第六工程有限公司 Installation construction method of ultra-large span heavy steel corridor
CN118241874A (en) * 2024-04-08 2024-06-25 中国五冶集团有限公司 Integral lifting method for high-altitude multilayer multi-channel steel corridor

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5577362A (en) * 1993-05-14 1996-11-26 Mitsubishi Jukogyo Kabushiki Kaisha Module construction method in a steel structure building zone
CN1908335A (en) * 2005-08-02 2007-02-07 浙江耀江建设集团股份有限公司 Suspension holder construction method
CN104100095A (en) * 2013-04-12 2014-10-15 中建四局第三建筑工程有限公司 Method and device for mounting large-sized operating platform between two tower buildings
CN106065661A (en) * 2016-06-13 2016-11-02 中建六局第三建筑工程有限公司 Large span unsettled steel corridor construction engineering method
CN106401198A (en) * 2016-06-14 2017-02-15 中天建设集团有限公司 Large-span steel gallery lifting equipment and construction method
CN106522362A (en) * 2016-12-29 2017-03-22 上海市机械施工集团有限公司 Construction device and construction method of steel structure beam of corridor system
CN106522361A (en) * 2016-12-07 2017-03-22 上海市机械施工集团有限公司 Combined installation method for multi-layer heavy steel space corridor

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5577362A (en) * 1993-05-14 1996-11-26 Mitsubishi Jukogyo Kabushiki Kaisha Module construction method in a steel structure building zone
CN1908335A (en) * 2005-08-02 2007-02-07 浙江耀江建设集团股份有限公司 Suspension holder construction method
CN104100095A (en) * 2013-04-12 2014-10-15 中建四局第三建筑工程有限公司 Method and device for mounting large-sized operating platform between two tower buildings
CN106065661A (en) * 2016-06-13 2016-11-02 中建六局第三建筑工程有限公司 Large span unsettled steel corridor construction engineering method
CN106401198A (en) * 2016-06-14 2017-02-15 中天建设集团有限公司 Large-span steel gallery lifting equipment and construction method
CN106522361A (en) * 2016-12-07 2017-03-22 上海市机械施工集团有限公司 Combined installation method for multi-layer heavy steel space corridor
CN106522362A (en) * 2016-12-29 2017-03-22 上海市机械施工集团有限公司 Construction device and construction method of steel structure beam of corridor system

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109083268A (en) * 2018-10-29 2018-12-25 中国冶集团有限公司 Narrow more barrier zone bilayer differing tilt angles vestibules once lift installation method
CN109881890A (en) * 2019-02-21 2019-06-14 深圳市建筑设计研究总院有限公司 A kind of more corridor construction methods of super high-rise building
CN109826447A (en) * 2019-02-28 2019-05-31 五冶集团上海有限公司 A kind of method of hydraulic lifting apparatus steel strand wires high-altitude Fast Installation
WO2021012971A1 (en) * 2019-07-22 2021-01-28 中建三局集团有限公司 Integral lifting construction method for ultra-large hyperbolic integrated unit aluminium plate curtain walls
CN112049439A (en) * 2020-10-14 2020-12-08 中冶建工集团重庆钢结构有限公司 Method for integrally lifting and mounting steel platform in limited space
CN113152687A (en) * 2021-04-21 2021-07-23 上海宝冶集团南京建筑有限公司 Structure and method for improving layering reverse order of hollow steel gallery
CN113494127A (en) * 2021-07-09 2021-10-12 上海宝冶集团有限公司 Construction method for layered lifting of large-span open-web corridor steel platform
CN115262991A (en) * 2022-06-15 2022-11-01 中国五冶集团有限公司 Corridor lifting and folding structure and construction method thereof
CN115492252A (en) * 2022-11-04 2022-12-20 中国十七冶集团有限公司 Overall hoisting facility and construction method of high-altitude long-span steel structure corridor based on BIM technology
CN117052157A (en) * 2023-08-03 2023-11-14 中冶(上海)钢结构科技有限公司 An overall lifting construction method and construction device for a multi-layer column-free steel corridor
CN117702899A (en) * 2023-11-14 2024-03-15 中交四航局第六工程有限公司 Installation construction method of ultra-large span heavy steel corridor
CN118241874A (en) * 2024-04-08 2024-06-25 中国五冶集团有限公司 Integral lifting method for high-altitude multilayer multi-channel steel corridor

Also Published As

Publication number Publication date
CN107060105B (en) 2018-11-13

Similar Documents

Publication Publication Date Title
CN107060105B (en) Lifting construction method for multiple steel galleries between tower buildings
CN107012949B (en) Lifting method of large-span steel corridor
CN106930541B (en) Construction method of hanging type steel corridor
CN108457188B (en) A walking multi-point synchronous jacking construction method
CN107060070A (en) Load transfer device and construction method for hoisting steel gallery by using same
CN103075025B (en) Integral lifting construction method for giant cantilever steel asymmetric structure of high-rise building
CN111794119B (en) Temporary supporting system and hoisting method for basket type steel box tie bar arch
CN102926333B (en) External prestressed reinforcement structure for old bridge and construction method thereof
CN110374008A (en) A method of the erection of cable-stayed bridge steel truss is carried out in marine environment
CN211034860U (en) Hydraulic lifting construction device for steel structure net rack
CN101736697A (en) Construction method for pushing and furling complete bracket of steel box girders
CN104141383A (en) Bailey beam suspension formwork supporting system and construction method thereof
CN107401113A (en) Stiff skeleton straining beam structure and construction method built in a kind of high pier
CN203947771U (en) A kind of Bailey beam pendent form support system
CN106437178A (en) Integral lifting construction method and integral lifting construction device of veranda of multi-layer steel structure
WO2023056721A1 (en) Construction method for repairing over-limit rotation angle fault of high-speed railway bridge bearing
CN115749298A (en) Construction method for steel structure of main body of high-speed rail station house
CN102777044B (en) Hoisting method of steel-structured spraying layer of urea prilling tower
CN102877657B (en) Large-span H-shaped plane composite structure beam string upper-air cable replacement construction method
CN118257428A (en) Method for sectionally lifting asymmetrical large-span overhanging steel structure corridor
CN206428974U (en) A kind of multi-storey steel structure vestibule integral hoisting construction device
CN105484166A (en) Ladder-shaped mast type cantilever assembling crane
CN111779274A (en) Construction method for integrally lifting temporary hoisting point of large-span unequal-height steel structure net rack
CN220598198U (en) A beam body reinforcement and support replacement device
CN207244425U (en) Part earth anchored suspension bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190213

Address after: 100054 Zhongjian two Bureau building, 42 Guanganmen South Street, Xicheng District, Beijing.

Co-patentee after: CHINA CONSTRUCTION SECOND BUREAU GUANGDONG CONSTRUCTION BASE Co.,Ltd.

Patentee after: CHINA CONSTRUCTION SECOND ENGINEERING BUREAU Ltd.

Address before: 100054 Zhongjian two Bureau building, 42 Guanganmen South Street, Xicheng District, Beijing.

Patentee before: CHINA CONSTRUCTION SECOND ENGINEERING BUREAU Ltd.

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 100054 China Xicheng District 42 South Street, Guanganmen, China Construction Bureau, two, Beijing

Co-patentee after: China Construction Second Engineering Bureau sunshine Intelligent Manufacturing Co.,Ltd.

Patentee after: CHINA CONSTRUCTION SECOND ENGINEERING BUREAU Ltd.

Address before: 100054 China Xicheng District 42 South Street, Guanganmen, China Construction Bureau, two, Beijing

Co-patentee before: CHINA CONSTRUCTION SECOND BUREAU GUANGDONG CONSTRUCTION BASE Co.,Ltd.

Patentee before: CHINA CONSTRUCTION SECOND ENGINEERING BUREAU Ltd.