CN107060105B - A kind of lifting construction method of multiple steel vestibules between high building - Google Patents

A kind of lifting construction method of multiple steel vestibules between high building Download PDF

Info

Publication number
CN107060105B
CN107060105B CN201710326724.9A CN201710326724A CN107060105B CN 107060105 B CN107060105 B CN 107060105B CN 201710326724 A CN201710326724 A CN 201710326724A CN 107060105 B CN107060105 B CN 107060105B
Authority
CN
China
Prior art keywords
steel
area
steel vestibule
vestibule
promoted
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201710326724.9A
Other languages
Chinese (zh)
Other versions
CN107060105A (en
Inventor
苏铠
张益民
雷志强
刘培
程志军
朱早孙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Second Engineering Bureau Co Ltd
China Construction Second Engineering Bureau Yangguang Intelligent Manufacturing Co Ltd
Original Assignee
China Construction Second Engineering Bureau Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Second Engineering Bureau Co Ltd filed Critical China Construction Second Engineering Bureau Co Ltd
Priority to CN201710326724.9A priority Critical patent/CN107060105B/en
Publication of CN107060105A publication Critical patent/CN107060105A/en
Application granted granted Critical
Publication of CN107060105B publication Critical patent/CN107060105B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B2001/3588Extraordinary methods of construction, e.g. lift-slab, jack-block using special lifting or handling devices, e.g. gantries, overhead conveying rails

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The lifting construction method of multiple steel vestibules between a kind of high building of the present invention, promotion sequence is low area's steel vestibule, middle area's steel vestibule, high area's steel vestibule, area low first, Zhong Qu, high area's steel vestibule absolute altitude at installation prepackage rod piece, setting promotes platform, while installing hydraulic rockshaft;Then, it is promoted to absolute altitude in the low area's steel vestibule of installation on ground, area's steel vestibule in moulding bed assembly is set up on low area's steel vestibule, and be promoted to absolute altitude;The assembled high area's steel vestibule of moulding bed is set up on the areas Zai Zhong steel vestibule, is promoted to absolute altitude and completes construction.The construction of multiple steel vestibules is not universal between high building, the construction method can significantly improve construction efficiency by engineering practice, ensure construction safety, the reduction of the workload amplitude peak of lifting, energy consumption and time have been saved, construction cost and installation difficulty are reduced, has met national green construction requirement, it can be to offer reference and instruct similar to multiple steel vestibule engineering constructions between two tall buildings later, there is the foreground promoted and applied.

Description

A kind of lifting construction method of multiple steel vestibules between high building
Technical field
The present invention relates to construction steel structure installation Technology field, more particularly to multiple steel vestibules carries between a kind of high building Rise construction method.
Background technology
With the growing tension of urban built-up land, the pursuit of the art of architecture is continuously improved people and construction cost Day by day increase severely, the multiple aerial long-span heavy type steel vestibules of Super High two tall buildings also will be increasing, big for span, and height is high Building is preferred using the mode that hydraulic pressure is integrally promoted, but the multiple steel vestibule forms of two tall buildings are different, and weight differs, suitably Method for improving must take into account cost, safety and easy construction.
Vestibule is one kind in Complex Tall Building system, it is a kind of connector, perpendicular to building transverse direction cloth It sets, the Project case for only installing a vestibule is very more, and the construction of multiple steel vestibules is not universal between two tall buildings, can refer to Example of constructing is extremely limited, moreover, steel vestibule is larger due to conducting oneself with dignity in installation on ground, whole promotion, there is lifting originally Difficulty of construction is big, promotes the problems such as high with installation requirement.It is carried currently, the promotion operation of multiple steel vestibules is still based on single steel vestibule Rise operating type:Assembled moulding bed is arranged on basement roof, hydraulic rockshaft is arranged at high area's steel vestibule absolute altitude for the first step With promote platform, using truck crane, tower crane on assembled moulding bed assembled high area's steel vestibule;Second step promotes high area's steel vestibule, Steel vestibule in area's in installation on ground setting hydraulic rockshaft and promotes platform at the areas Bing Zhong steel vestibule absolute altitude;Third walks, in promotion Hydraulic rockshaft is arranged at the low area's steel vestibule of installation on ground, the areas Bing Di steel vestibule absolute altitude and promotes platform for area's steel vestibule;The Four steps promote low area's steel vestibule.
There are the problem of one:Corresponding hydraulic rockshaft need to be all arranged in each steel vestibule promotion in the high building built up With promotion platform, the installation measure amount that three steel vestibules promote needs is big, consumes a large amount of material, time, increases construction Cost.Problem two:Three steel gallery structure weight are very huge, if three steel vestibules continue the assembly on basement roof, Basement roof will be for a long time in great stress, and bearing capacity is much insufficient, easy to produce cracking, and safety obtains It less than guarantee, needs to reinforce basement roof, using shaped steel, full hall scaffold return back to top supports or in basement knot Increase reinforced concrete column, steel frame beam in structure to enhance the bearing capacity of basement roof, do so consume a large amount of material, it is artificial and when Between, it dragged slowly construction speed, increased construction cost.It there is no the report of multiple steel vestibule lifting constructions between high building at this stage.
Invention content
To solve the above problems, the present invention provides a kind of lifting construction method of multiple steel vestibules between high building, it is intended to reduce The difficulty of construction of the build process of multiple steel vestibules between two tall buildings, at the same shorten the basement roof load time, save be constructed into Originally difficulty of construction, is reduced.
To achieve the above object, the present invention adopts the following technical scheme that:
The present invention provides a kind of lifting construction method of multiple steel vestibules between high building, promotion sequence be low area's steel vestibule 6, in Area's steel vestibule 9, high area's steel vestibule 10, include the following steps:
Step 1, low area's steel vestibule 6, middle area's steel vestibule 9, high area's steel vestibule 10 designed elevation at be respectively mounted prepackage bar Part 1, setting promotes platform 3 on high area's steel vestibule 10 prepackage rod piece 1, and installs hydraulic pressure lift on every group of promotion platform 3 Device 2;
Hydraulic synchronizing lifting system equipment, including hydraulic pump source system, hydraulic rockshaft are installed on the promotion platform 3 2, sensor, hydraulic oil pipe etc.;
Step 2, assembled under the 6 predetermined installation site of low area's steel vestibule projection using truck crane 8, connect according to low area's steel The loading characteristic of corridor 6 debugs hydraulic rockshaft 2 and steel strand wires 5, and checks whether low area's steel vestibule 6 meets design requirement;
Step 3, after checking that confirmation is errorless, the method that hydraulic rockshaft 2 takes hierarchical loading is preloaded, and hydraulic pressure is utilized Lifter 2 drives steel strand wires 5 to carry out low area's steel vestibule 6 to promote 11 for the first time, is detached from assembled moulding bed 7, makes basement roof not Stress is promoted to low 6 designed elevation of area's steel vestibule;
Step 4, after low area's steel vestibule 6 checks that confirmation is errorless, assembled moulding bed 7, profit are set above low area's steel vestibule 6 With tower crane on assembled moulding bed 7 area's steel vestibule 9 in assembly;
Step 5, after checking that confirmation is errorless, step 2 is repeated, the method that hydraulic rockshaft 2 takes hierarchical loading carries out pre-add It carries, drives steel strand wires 5 that middle area's steel vestibule 9 is carried out second using hydraulic rockshaft 2 and promote 12, be detached from assembled moulding bed 7, promoted To middle 9 designed elevation of area's steel vestibule;
Step 6, area's steel vestibule 9 and prepackage rod piece 1 in welding, whether area's steel vestibule 9 meets design requirement in inspection, confirms After errorless, assembled moulding bed 7 is set above middle area's steel vestibule 9, using tower crane on assembled moulding bed 7 assembled high area's steel vestibule 10;
Step 7, after checking that confirmation is errorless, step 2 is repeated, the method that hydraulic rockshaft 2 takes hierarchical loading carries out pre-add It carries, drives steel strand wires 5 that high area's steel vestibule 10 is carried out third time using hydraulic rockshaft 2 and promote 13, be detached from assembled moulding bed 7, carry High 10 designed elevation of area's steel vestibule is risen to, high area's steel vestibule 10 and prepackage rod piece 1 are welded;
Step 8, unloading hydraulic rockshaft 2 is fully relaxed to steel strand wires 5, removes measure for improvement, makes the dead weight transfer of steel vestibule To high building 4, the promotion installment work of low area's steel vestibule 6, middle area's steel vestibule 9, high area's steel vestibule 10 is completed.
Further, it is checked as to low area's steel vestibule 6, middle area's steel vestibule 9, high area's steel vestibule 10 described in step 1~step 7 Carry out the visual examination of carrying out flaw detection and weld seam 11.
Further, the hydraulic rockshaft 2 uses steel strand wires 5 as load-bearing rigging is promoted, and installs steel strand wires from the bottom to top 5,Mounting hanger,Wear earth anchor;The steel strand wires 5 after cutting, polishing equating, are symmetrically set with low 6 both ends of area's steel vestibule respectively on demand 4 suspension centres set are fixedly connected;Tension steel strand 5 makes its uniform stressed, locks earth anchor;Debug the hydraulic synchronizing lifting system System, checks whether all interim measures of hydraulic synchronizing lifting meet design requirement.
Further, the hydraulic rockshaft 2 is stretched cylinder pressure and is gradually raised, and is followed successively by the 20% of required pressure, and 40%, at all In the case of all normal, it can continue to be loaded into 60%, 70%, 80%, 90%, 95%, 100%;
Further, the hierarchical loading needs to pay attention to:Each step hierarchical loading finishes, and should all suspend and check that steel vestibule adds Carry the stability of front and back 4 structure of deformation and high building.
Further, the observing time that 10 minutes are at least reserved between each adjacent load step, until vestibule lift unit It is detached from assembled moulding bed 7.
Further, in the step 3, when low area's steel vestibule 6 is promoted to away from designed elevation 1000mm, pause is promoted, profit It is locked with hydraulic rockshaft 2, aerial stop 12 hours or more is made to check comprehensively, checks suspension centre structure, bearing system, promotion emphatically Equipment, the deformation of truss and weld seam and stressing conditions measure low area's steel vestibule 6 and pre-install each point actual size of 1 interface of rod piece, Collation process reduces and promotes speed, continues to lift up to absolute altitude;It welds and checks whether low area's steel vestibule 6 meets design requirement;
In the step 5, when area's steel vestibule 9 is promoted to away from designed elevation 1000mm in the middle, pause is promoted, and is carried using hydraulic pressure It rises device 2 to lock, aerial stop 12 hours or more is made to check comprehensively, checks suspension centre structure, bearing system, lifting means, purlin emphatically The deformation of frame and weld seam and stressing conditions, each point actual size of area's steel vestibule 9 and prepackage 1 interface of rod piece in measurement, at verification Reason reduces and promotes speed, continues to lift up to absolute altitude;Whether area's steel vestibule 9 meets design requirement in welding and checking;
In the step 7, when high area's steel vestibule 10 is promoted to away from designed elevation 1000mm, pause is promoted, and utilizes hydraulic pressure Lifter 2 locks, and aerial stop 12 hours or more is made to check comprehensively, check emphatically suspension centre structure, bearing system, lifting means, The deformation of truss and weld seam and stressing conditions measure high area's steel vestibule 10 and pre-install each point actual size of 1 interface of rod piece, verification Processing reduces and promotes speed, continues to lift up to absolute altitude;It welds and checks whether high area's steel vestibule 10 meets design requirement;
So far the lifting construction of low area's steel vestibule 6, middle area's steel vestibule 9 and high area's steel vestibule 10 is completed, and becomes one with high building 4 A entirety.
Further, the step 8 promotes suspension centre and gradually unloads, and unloading classification is carried out by 20%, and knot is observed after unloading 20% Structure deformation, no abnormal conditions continue unloading 20%, until load all complete by unloading.
Beneficial effects of the present invention are embodied in:
1)Shaped steel, full hall scaffold need not be used to carry out the support that returns back to top, or in basement structure increase reinforced concrete column, Steel frame beam is to enhance the bearing capacity of basement roof;Vestibule rectangular structure top surface only needs assembled low area's steel vestibule, and assembling duration is short, It avoids and basement roof is reinforced on a large scale, basement roof is not allowed to be also easy to produce cracking, has saved a large amount of reinforcing Material, construction time and cost of labor reduce integral construction cost while shortening the construction period;
2)Do not need the promotion of each steel vestibule be all arranged in the high building built up in advance corresponding hydraulic rockshaft and Platform is promoted, which has already passed through engineering practice, it is only necessary to corresponding liquid be arranged in the high building at high area's steel vestibule absolute altitude It presses lifter and promotes platform;The installation measure of steel vestibule promotion is greatly saved, reduces spillage of material, saves The artificial and time;
3)Assembled moulding bed is set on low/medium area's steel vestibule, after assembled medium/high area's steel vestibule and is promoted absolute altitude, This construction method substantially reduces the vertical-lift distance of super large heavy-duty steel vestibule, has saved energy consumption and time, reduces construction Cost and installation difficulty, meet national green construction requirement, have in construction quality, construction safety and operation construction period etc. Profit;
4)The construction of multiple steel vestibules is not universal between two tall buildings, which can be apparent by engineering practice Construction efficiency is improved, ensures that construction safety, the reduction of the workload amplitude peak of lifting can be that similar two tall buildings are multiple later Steel vestibule engineering construction is offered reference and is instructed, and has the foreground promoted and applied.
Other features and advantages of the present invention will be illustrated in the following description, and partly becomes from specification It is clear that understand through the implementation of the invention.The main object of the present invention and further advantage can be by specification, power Specifically noted scheme is realized and is obtained in sharp claim.
Description of the drawings
The present invention will be further described in detail below in conjunction with the accompanying drawings.
Fig. 1 is step 1 schematic diagram of the present invention.
Fig. 2 is that step 2 of the present invention promotes schematic diagram for the first time.
Fig. 3 is step 3 schematic diagram of the present invention.
Fig. 4 is second of promotion schematic diagram of step 4 of the present invention.
Fig. 5 is step 5 schematic diagram of the present invention.
Fig. 6 is that step 6 of the present invention promotes schematic diagram for the third time.
Reference numeral:1- pre-installs rod piece, 2- hydraulic rockshafts, 3- and promotes platform, 4- high buildings, 5- steel strand wires, 6- Area's steel vestibule, the areas 10- high steel vestibule, the promotion of 11- first times, 12- in low area's steel vestibule, 7- assembly moulding bed, 8- truck cranes, 9- Second of promotion, 13- third times are promoted.
Specific implementation mode
Below in conjunction with the accompanying drawings and the present invention is further described in embodiment:
Multiple steel vestibules between two tall buildings, it is desirable to which assembly is completed again one by one on basement roof so heavy steel construction The promotion of certain distance is carried out, then carries out necessarily required connection construction with high building, difficulty of construction is big, promotion and installation requirement Height, it is especially long in the assembled process duration on basement roof top, make basement roof for a long time be in greatly by Under power state, bearing capacity is much insufficient, easy tos produce cracking, and safety cannot be guaranteed.
The lifting construction method of multiple steel vestibules, multiple steel vestibules are connected between two tall buildings 4 between a kind of high building of the present invention, Promotion sequence is low area's steel vestibule 6, middle area's steel vestibule 9, high area's steel vestibule 10, is included the following steps:
Step 1, low area's steel vestibule 6, middle area's steel vestibule 9, high area's steel vestibule 10 designed elevation at be respectively mounted prepackage bar Part 1, the areas Jin Gao steel vestibule 10 pre-install setting on rod piece 1 and promote platform 3, four groups of promotion platforms 3 are arranged altogether, and carry at every group One hydraulic rockshaft 2 is installed on peaceful 3;Hydraulic synchronizing lifting system equipment is installed, including hydraulic pump source system, hydraulic pressure carry Rise device 2, sensor etc.;
The quantity of hydraulic rockshaft 2 is extended according to the weight of steel vestibule in step 1.
It is assembled under the projection of 6 predetermined installation site of low area's steel vestibule using truck crane 8, according to the stress of low area's steel vestibule 6 Feature debugs hydraulic rockshaft 2 and steel strand wires 5, and it is as shown in Figure 1 to check whether low area's steel vestibule 6 meets design requirement;
The hydraulic rockshaft 2 uses steel strand wires 5 as load-bearing rigging is promoted, and installs steel strand wires 5 from the bottom to top, installation is hung Tool, wears earth anchor;The steel strand wires 5 on demand cutting, polishing equating after, respectively with 6 both ends of low area's steel vestibule symmetrically arranged 4 hang Point is fixedly connected;Tension steel strand 5 makes its uniform stressed, locks earth anchor;The hydraulic synchronizing lifting system is debugged, checks liquid Whether all interim measures of pressure Synchronous lifting meet design requirement;
Hydraulic rockshaft 2 only needs to be arranged in the high building at high 10 absolute altitude of area's steel vestibule, is greatly saved multiple The installation measure of steel vestibule promotion;Wherein, the quantity of suspension centre is arranged according to actual conditions such as absolute altitude, steel vestibule weight;
Step 2, after checking that confirmation is errorless, the method that hydraulic rockshaft 2 takes hierarchical loading is preloaded, and hydraulic pressure is utilized Lifter 2 drives steel strand wires 5 to carry out low area's steel vestibule 6 to promote 11 for the first time, is detached from assembled moulding bed 7, makes basement roof not It is as shown in Figure 2 to be promoted to 6 designed elevations of low area's steel vestibule for stress;
If low area's steel vestibule 6 has movement when just starting promotion, Suspend Job is needed, keeps hydraulic test system pressure. Hydraulic synchronizing lifting system equipment is checked comprehensively, in the no problem definitely feelings of the integrally-built stability of confirmation and safety Under condition, it could start to continue to lift up.Liftoff situation when if there is each point difference should reduce promotion speed at this time, and closely The liftoff situation of each point is looked into sight, is done " single-point is dynamic " when necessary and is promoted to ensure the levelness of low area's steel vestibule 6.It is promoted to and is marked away from design When high 1000mm, pause is promoted, and is locked using hydraulic rockshaft 2, and aerial stop 12 hours or more is made to check comprehensively, checks emphatically Suspension centre structure, bearing system, lifting means, the deformation of truss and weld seam and stressing conditions etc., measure low area's steel vestibule 6 and prepackage The each point actual size of 1 interface of rod piece, collation process reduce and promote speed, continue to lift up to absolute altitude.Weld low area's steel vestibule 6 With prepackage rod piece 1, check whether low area's steel vestibule 6 meets design requirement, so far the lifting construction of low area's steel vestibule 6 is completed, with Two tall buildings 4 become a complete entirety.
It must be noted that in construction:During hierarchical loading, each step hierarchical loading finishes, and should all suspend and check, such as Situations such as stability of the load such as low area's steel vestibule 6 front and back deformation and main building structure.The case where all going well Under, continue next step hierarchical loading;Wherein, the hydraulic rockshaft 2 is stretched cylinder pressure and is gradually raised, and is followed successively by required pressure 20%, 40%, in the case where Everything is fine, can continue to be loaded into 60%, 70%, 80%, 90%, 95%, 100%, it is adjacent every time to add At least reserved 10 minutes observing times between load step, until vestibule lift unit is detached from assembled moulding bed 7.
Step 3, after low area's steel vestibule 6 checks that confirmation is errorless, assembled moulding bed 7 is set above low area's steel vestibule 6, utilizes tower Area's steel vestibule 9 in assembly is hung on assembled moulding bed 7, as shown in Figure 3.
Step 4, shown in Fig. 4, after checking that confirmation is errorless, the method that hydraulic rockshaft 2 takes hierarchical loading is preloaded, It drives steel strand wires 5 that middle area's steel vestibule 9 is carried out second using hydraulic rockshaft 2 to promote 12, be detached from assembled moulding bed 7, be promoted to Middle 9 designed elevation of area's steel vestibule.Wherein, the method for hierarchical loading, the points for attention of lifting process are identical as step 2.
Step 5, area's steel vestibule 9 and prepackage rod piece in welding, whether area's steel vestibule 9 meets design requirement in inspection, confirms After errorless, assembled moulding bed 7 is set above middle area's steel vestibule 9, using tower crane on assembled moulding bed 7 assembled high area's steel vestibule 10. Wherein, the method for hierarchical loading, the points for attention of lifting process are identical as step 2.
Step 6, after checking that confirmation is errorless, the method that hydraulic rockshaft 2 takes hierarchical loading is preloaded, and hydraulic pressure is utilized Lifter 2 drives steel strand wires 5 that high area's steel vestibule 10 is carried out third time and promotes 13, is detached from assembled moulding bed 7, promotes supreme area's steel and connects 10 designed elevation of corridor.Wherein, the method for hierarchical loading, the points for attention of lifting process are identical as step 2.
After installation is complete, each suspension centre synchronization load shedding of hydraulic synchronizing lifting system equipment is fully relaxed to steel strand wires 5, makes Steel vestibule dead weight is transferred on high building 4, remove measure for improvement, complete Gao Qu, middle area, low area's steel vestibule promotion installment work such as Shown in Fig. 6.
To sum up, the lifting construction method of multiple steel vestibules between a kind of high building that the present invention is announced,
1)Whole process only needs the corresponding hydraulic rockshaft of interior setting at high area's steel vestibule absolute altitude and promotion platform ?;The installation measure of steel vestibule promotion is greatly saved, reduces spillage of material, has saved the artificial and time;
2)Assembled moulding bed is set on low/medium area's steel vestibule, after assembled medium/high area's steel vestibule and is promoted absolute altitude, This construction method substantially reduces the vertical-lift distance of super large heavy-duty steel vestibule, has saved energy consumption and time, reduces construction Cost and installation difficulty, meet national green construction requirement, have in construction quality, construction safety and operation construction period etc. Profit;
3)Shaped steel, full hall scaffold need not be used to carry out the support that returns back to top, or in basement structure increase reinforced concrete column, Steel frame beam is to enhance the bearing capacity of basement roof;Vestibule rectangular structure top surface only needs assembled low area's steel vestibule, and assembling duration is short, It avoids and basement roof is reinforced on a large scale, basement roof is not allowed to be also easy to produce cracking, has saved a large amount of reinforcing Material, construction time and cost of labor reduce integral construction cost while shortening the construction period;
4)The construction of multiple steel vestibules is not universal between two tall buildings, which can be apparent by engineering practice Construction efficiency is improved, ensures that construction safety, the reduction of the workload amplitude peak of lifting can be that similar two tall buildings are multiple later Steel vestibule engineering construction is offered reference and is instructed, and has the foreground promoted and applied.
In the lifting process of construction cell, lifting region rod piece is needed to carry out temperature pier to meet whole promotion need It asks, offsets the deformation that weight stress generates in lifting, form it into stable entirety to be promoted, using the prior art, herein It repeats no more.Installation, debugging, use, the unloading of hydraulic synchronizing lifting system equipment use the prior art, and details are not described herein.
The foregoing is merely the preferable specific implementation modes of the present invention, but scope of protection of the present invention is not limited thereto, The change or replacement that any one skilled in the art is expected in the technical scope disclosed by the present invention should all be contained Lid is within protection scope of the present invention.

Claims (8)

1. a kind of lifting construction method of multiple steel vestibules between high building, which is characterized in that promotion sequence is low area's steel vestibule(6), Middle area's steel vestibule(9), high area's steel vestibule(10), include the following steps:
Step 1, in low area's steel vestibule(6), middle area's steel vestibule(9), high area's steel vestibule(10)Designed elevation at be respectively mounted prepackage Rod piece(1), in high area's steel vestibule(10)Pre-install rod piece(1)Upper setting promotes platform(3), and in every group of promotion platform(3)On Hydraulic rockshaft is installed(2);
Step 2, using truck crane(8)In low area's steel vestibule(6)The predetermined lower assembly of installation site projection, connects according to low area's steel Corridor(6)Loading characteristic, debug hydraulic rockshaft(2)And steel strand wires(5), and check low area's steel vestibule(6)Whether satisfaction designs It is required that;
Step 3, after checking that confirmation is errorless, hydraulic rockshaft(2)The method for taking hierarchical loading is preloaded, and is carried using hydraulic pressure Rise device(2)Drive steel strand wires(5)By low area's steel vestibule(6)Carry out first time promotion(11), it is detached from assembled moulding bed(7), make underground Ceiling plate does not stress, and is promoted to low area's steel vestibule(6)Designed elevation;
Step 4, low area's steel vestibule(6)After checking that confirmation is errorless, in low area's steel vestibule(6)The assembled moulding bed of top setting(7), Using tower crane in assembled moulding bed(7)Area's steel vestibule in upper assembly(9);
Step 5, after checking that confirmation is errorless, hydraulic rockshaft(2)The method for taking hierarchical loading is preloaded, and is carried using hydraulic pressure Rise device(2)Drive steel strand wires(5)By middle area's steel vestibule(9)Second is carried out to be promoted(12), it is detached from assembled moulding bed(7), it is promoted to Middle area's steel vestibule(9)Designed elevation;
Step 6, steel vestibule in area's in welding(9)With prepackage rod piece(1), steel vestibule in area's in inspection(9)Whether design requirement is met, really Recognize it is errorless after, in middle area's steel vestibule(9)The assembled moulding bed of top setting(7), using tower crane in assembled moulding bed(7)The upper high area's steel of assembly Vestibule(10);
Step 7, after checking that confirmation is errorless, hydraulic rockshaft(2)The method for taking hierarchical loading is preloaded, and is carried using hydraulic pressure Rise device(2)Drive steel strand wires(5)By high area's steel vestibule(10)Carry out third time promotion(13), it is detached from assembled moulding bed(7), it is promoted to High area's steel vestibule(10)Designed elevation welds high area's steel vestibule(10)With prepackage rod piece(1);
Step 8, hydraulic rockshaft is unloaded(2)To steel strand wires(5)It is fully relaxed, measure for improvement is removed, the dead weight transfer of steel vestibule is made To high building(4)On, complete low area's steel vestibule(6), middle area's steel vestibule(9), high area's steel vestibule(10)Promotion installment work.
2. lifting construction method as described in claim 1, which is characterized in that checked as to low area described in step 1~step 7 Steel vestibule(6), middle area's steel vestibule(9), high area's steel vestibule(10)Carry out carrying out flaw detection and weld seam(11)Visual examination.
3. lifting construction method as described in claim 1, which is characterized in that the hydraulic rockshaft(2)Use steel strand wires(5) As load-bearing rigging is promoted, steel strand wires are installed from the bottom to top(5), mounting hanger wears earth anchor;Tension steel strand(5), make it uniformly Stress locks earth anchor.
4. lifting construction method as described in claim 1, which is characterized in that the hydraulic rockshaft(2)It is gradual to stretch cylinder pressure Up-regulation, is followed successively by the 20% of required pressure, and 40%, in the case where Everything is fine, can continue to be loaded into 60%, 70%, 80%, 90%, 95%, 100%.
5. lifting construction method as described in claim 1, which is characterized in that the hierarchical loading needs to pay attention to:Each step point Grade loaded should all suspend and check the load of steel vestibule front and back deformation and high building(4)The stability of structure.
6. lifting construction method as described in claim 1, which is characterized in that at least 10 points reserved between adjacent load step The observing time of clock, until steel vestibule lift unit is detached from assembled moulding bed(7).
7. lifting construction method as described in claim 1, which is characterized in that in the step 3, when low area's steel vestibule(6)It carries When rising to away from designed elevation 1000mm, pause is promoted, and utilizes hydraulic rockshaft(2)Locking, it is aerial stop 12 hours or more make it is complete Face checks, check emphatically suspension centre structure, bearing system, lifting means, truss and weld seam deformation and stressing conditions, measure low area Steel vestibule(6)With prepackage rod piece(1)The each point actual size of interface, collation process reduce and promote speed, continue to lift up to mark It is high;It welds and checks low area's steel vestibule(6)Whether design requirement is met;
In the step 5, area's steel vestibule in the middle(9)When being promoted to away from designed elevation 1000mm, pause is promoted, and utilizes hydraulic pressure lift Device(2)Locking, aerial stop 12 hours or more make to check comprehensively, checks suspension centre structure, bearing system, lifting means, purlin emphatically The deformation of frame and weld seam and stressing conditions, steel vestibule in area's in measurement(9)With prepackage rod piece(1)The each point actual size of interface, core To processing, reduces and promote speed, continue to lift up to absolute altitude;Steel vestibule in area's in welding and checking(9)Whether design requirement is met;
In the step 7, when high area's steel vestibule(10)When being promoted to away from designed elevation 1000mm, pause is promoted, and is carried using hydraulic pressure Rise device(2)Locking, aerial stop 12 hours or more make to check comprehensively, check emphatically suspension centre structure, bearing system, lifting means, The deformation of truss and weld seam and stressing conditions measure high area's steel vestibule(10)With prepackage rod piece(1)The each point actual size of interface, Collation process reduces and promotes speed, continues to lift up to absolute altitude;It welds and checks high area's steel vestibule(10)Whether satisfaction design is wanted It asks;
So far low area's steel vestibule(6), middle area's steel vestibule(9)With high area's steel vestibule(10)Lifting construction complete, with high building(4)At For an entirety.
8. lifting construction method as described in claim 1, which is characterized in that the step 8 promotes suspension centre and gradually unloads, and unloads Classification is carried out by 20%, and observation structure deformation after unloading 20%, no abnormal conditions continue unloading 20%, until load is complete Portion's unloading is completed.
CN201710326724.9A 2017-05-10 2017-05-10 A kind of lifting construction method of multiple steel vestibules between high building Active CN107060105B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710326724.9A CN107060105B (en) 2017-05-10 2017-05-10 A kind of lifting construction method of multiple steel vestibules between high building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710326724.9A CN107060105B (en) 2017-05-10 2017-05-10 A kind of lifting construction method of multiple steel vestibules between high building

Publications (2)

Publication Number Publication Date
CN107060105A CN107060105A (en) 2017-08-18
CN107060105B true CN107060105B (en) 2018-11-13

Family

ID=59597580

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710326724.9A Active CN107060105B (en) 2017-05-10 2017-05-10 A kind of lifting construction method of multiple steel vestibules between high building

Country Status (1)

Country Link
CN (1) CN107060105B (en)

Families Citing this family (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109083268A (en) * 2018-10-29 2018-12-25 中国冶集团有限公司 Narrow more barrier zone bilayer differing tilt angles vestibules once lift installation method
CN109881890B (en) * 2019-02-21 2021-07-23 深圳市建筑设计研究总院有限公司 Multi-corridor construction method for super high-rise building
CN109826447A (en) * 2019-02-28 2019-05-31 五冶集团上海有限公司 A kind of method of hydraulic lifting apparatus steel strand wires high-altitude Fast Installation
CN110374236B (en) * 2019-07-22 2020-08-18 中建三局集团有限公司 Integral lifting construction method for aluminum plate curtain wall of ultra-large hyperbolic integrated unit
CN112049439B (en) * 2020-10-14 2021-11-02 中冶建工集团重庆钢结构有限公司 Method for integrally lifting and mounting steel platform in limited space
CN113494127A (en) * 2021-07-09 2021-10-12 上海宝冶集团有限公司 Construction method for layered lifting of large-span open-web corridor steel platform
CN115262991A (en) * 2022-06-15 2022-11-01 中国五冶集团有限公司 Corridor lifting and folding structure and construction method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5577362A (en) * 1993-05-14 1996-11-26 Mitsubishi Jukogyo Kabushiki Kaisha Module construction method in a steel structure building zone
CN1908335A (en) * 2005-08-02 2007-02-07 浙江耀江建设集团股份有限公司 Suspension holder construction method
CN104100095A (en) * 2013-04-12 2014-10-15 中建四局第三建筑工程有限公司 Method and device for mounting large-sized operating platform between two tower buildings
CN106065661A (en) * 2016-06-13 2016-11-02 中建六局第三建筑工程有限公司 Large span unsettled steel corridor construction engineering method
CN106401198A (en) * 2016-06-14 2017-02-15 中天建设集团有限公司 Large-span steel gallery lifting equipment and construction method
CN106522362A (en) * 2016-12-29 2017-03-22 上海市机械施工集团有限公司 Construction device and construction method of steel structure beam of corridor system
CN106522361A (en) * 2016-12-07 2017-03-22 上海市机械施工集团有限公司 Combined installation method for multi-layer heavy steel space corridor

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5577362A (en) * 1993-05-14 1996-11-26 Mitsubishi Jukogyo Kabushiki Kaisha Module construction method in a steel structure building zone
CN1908335A (en) * 2005-08-02 2007-02-07 浙江耀江建设集团股份有限公司 Suspension holder construction method
CN104100095A (en) * 2013-04-12 2014-10-15 中建四局第三建筑工程有限公司 Method and device for mounting large-sized operating platform between two tower buildings
CN106065661A (en) * 2016-06-13 2016-11-02 中建六局第三建筑工程有限公司 Large span unsettled steel corridor construction engineering method
CN106401198A (en) * 2016-06-14 2017-02-15 中天建设集团有限公司 Large-span steel gallery lifting equipment and construction method
CN106522361A (en) * 2016-12-07 2017-03-22 上海市机械施工集团有限公司 Combined installation method for multi-layer heavy steel space corridor
CN106522362A (en) * 2016-12-29 2017-03-22 上海市机械施工集团有限公司 Construction device and construction method of steel structure beam of corridor system

Also Published As

Publication number Publication date
CN107060105A (en) 2017-08-18

Similar Documents

Publication Publication Date Title
CN107060105B (en) A kind of lifting construction method of multiple steel vestibules between high building
CN107012949B (en) A kind of method for improving of large-span steel vestibule
CN106930541B (en) Construction method of hanging type steel corridor
CN104878693B (en) Lateral girder erection structure for truss double-girder type bridge girder erection machine, construction method of erection structure, and lateral girder erection method based on erection structure
CN103806658B (en) High-cleanness, high electronic workshop steel work integral slipping and discharging method
CN103075025B (en) Wholly lifting construction method for asymmetric structure of huge overhang steel of high-rise building
CN107401113B (en) Stiff skeleton straining beam structure and construction method built in a kind of high pier
CN107060070A (en) Load transfer device and the construction method that steel vestibule is lifted with the device
CN106836498A (en) A kind of super-span Stadium roof system steel truss lifting construction engineering method
CN104153303B (en) A kind of self-balancing back pressure type bridge single support replacing options
CN105781124A (en) Method for installing corridor with ultra-high double-tower steel structure
CN203947771U (en) A kind of Bailey beam pendent form support system
CN208702197U (en) A kind of big displacement integral jacking Compact Mounts
CN106437178A (en) Integral lifting construction method and integral lifting construction device of veranda of multi-layer steel structure
CN106522101A (en) Construction method of superlong cable beam-free sections of cable-stayed bridge
CN104652293A (en) Cable-stayed bridge structure used for reinforcing PSC (Pre-stressed Concrete) continuous box girder bridge and construction method
CN106087765A (en) High pier pier top Cast-in-place concrete bracket precompressed charger
CN104652244B (en) A kind of Suspension bridge structure for reinforcing PSC Continuous Box Girder Bridge and construction method
CN105155418A (en) Construction method for bridge horizontal movement
CN102877657B (en) Large-span H-shaped plane composite structure beam string upper-air cable replacement construction method
CN206828969U (en) A kind of high pier stud bearing platform counter-force prepressing device
CN114134991B (en) High-rise building construction method with conversion structure
CN105603890A (en) Extradosed type external cable reinforced girder bridge
CN109505404A (en) The intelligent recognition and restraint system of roof system deformation
CN201883694U (en) Integral lifting device for high-rise long-span door type truss

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20190213

Address after: 100054 Zhongjian two Bureau building, 42 Guanganmen South Street, Xicheng District, Beijing.

Co-patentee after: China Construction two bureau Guangdong construction base Co., Ltd.

Patentee after: China Construction Second Engineering Bureau Co., Ltd.

Address before: 100054 Zhongjian two Bureau building, 42 Guanganmen South Street, Xicheng District, Beijing.

Patentee before: China Construction Second Engineering Bureau Co., Ltd.

TR01 Transfer of patent right
CP01 Change in the name or title of a patent holder

Address after: 100054 China Xicheng District 42 South Street, Guanganmen, China Construction Bureau, two, Beijing

Co-patentee after: China Construction Second Engineering Bureau sunshine Intelligent Manufacturing Co., Ltd

Patentee after: CHINA CONSTRUCTION SECOND ENGINEERING BUREAU Co.,Ltd.

Address before: 100054 China Xicheng District 42 South Street, Guanganmen, China Construction Bureau, two, Beijing

Co-patentee before: CHINA CONSTRUCTION SECOND BUREAU GUANGDONG CONSTRUCTION BASE Co.,Ltd.

Patentee before: CHINA CONSTRUCTION SECOND ENGINEERING BUREAU Co.,Ltd.

CP01 Change in the name or title of a patent holder