CN113494127A - Construction method for layered lifting of large-span open-web corridor steel platform - Google Patents

Construction method for layered lifting of large-span open-web corridor steel platform Download PDF

Info

Publication number
CN113494127A
CN113494127A CN202110776502.3A CN202110776502A CN113494127A CN 113494127 A CN113494127 A CN 113494127A CN 202110776502 A CN202110776502 A CN 202110776502A CN 113494127 A CN113494127 A CN 113494127A
Authority
CN
China
Prior art keywords
lifting
steel platform
layer
corridor
hollow
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110776502.3A
Other languages
Chinese (zh)
Inventor
陈辉
周霞菊
杨璠
胡杉杉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN202110776502.3A priority Critical patent/CN113494127A/en
Publication of CN113494127A publication Critical patent/CN113494127A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B1/3511Lift-slab; characterised by a purely vertical lifting of floors or roofs or parts thereof
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/0046Loggias
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/342Structures covering a large free area, whether open-sided or not, e.g. hangars, halls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B2001/3561Extraordinary methods of construction, e.g. lift-slab, jack-block adding living space above existing structures
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/35Extraordinary methods of construction, e.g. lift-slab, jack-block
    • E04B2001/3588Extraordinary methods of construction, e.g. lift-slab, jack-block using special lifting or handling devices, e.g. gantries, overhead conveying rails

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The application relates to a construction method for layered lifting of a large-span hollow corridor steel platform, and belongs to the technical field of construction and installation of building steel structures. In order to solve the problem that the corridor steel platform needs to be hoisted layer by layer when a multi-layer large-span corridor is constructed between high-rise buildings, the corridor steel platform is hoisted from bottom to top by utilizing a traditional method, and the requirement on a construction site is high so as to solve the problem of the standing position of hoisting equipment. The upper steel platform is assembled on the basis of the lower steel platform and then hoisted, and the problem of poor safety caused by insufficient construction surface exists. According to the steel platform lifting construction method, the girder brackets are installed on buildings on two sides to serve as pre-installation parts, and the length of the girder brackets is shortened layer by layer from top to bottom; the length of the main beam of the steel platform is increased layer by layer from top to bottom; and integrally assembling the hollow corridor steel platform on the ground, and then lifting and installing the hollow corridor steel platform layer by layer from top to bottom. Compare traditional construction scheme, belong to reverse operation, the construction is quick, easy operation, whole occupation of land is little.

Description

Construction method for layered lifting of large-span open-web corridor steel platform
Technical Field
The application relates to the technical field of construction and installation of building steel structures, in particular to a construction method for layered lifting of a large-span hollow corridor steel platform.
Background
With the increasing shortage of urban building land, the pursuit of people for building art is continuously improved, and the construction cost is increased dramatically day by day. In the definition of modern architecture, a corridor is one of complex high-rise building structural systems, and generally means that two or more high-rise buildings are connected with each other by an overhead connector so as to meet the requirements of building shape and service function. The connecting body is a corridor. The span is several meters long and also several tens of meters long. The vestibules are arranged one by one or a plurality of in the vertical direction of the building.
For the rapid and efficient construction of multi-layer vestibules among buildings, the traditional method is to install a vestibule steel platform which is equivalent to the foundation part of the vestibule and then carry out the integral construction of the vestibule on the steel platform. Because vestibule steel platform is mostly fretwork form girder steel structure, also is called empty stomach vestibule steel platform. When a multi-layer large-span corridor is constructed between high-rise buildings, cost, safety and construction simplicity must be considered for a proper lifting method of a hollow corridor steel platform.
When the vestibule height is not very high, generally set up the support pylon, adopt the mode of large-scale crane hoist and mount, from up successive layer installation completion down, if the vestibule height is too high, the plane dimension is too big, and when the construction site does not possess large-scale loop wheel station yet, just need consider assembling at ground or floor normal position, the mode of successive layer whole hydraulic lifting realizes, promote hoisting point fixes on the building subject at top layer vestibule place during successive layer promotes, because install the pre-assembly at the installation layer in advance, just so can only from up successive layer lifting steel platform down, but lower floor steel platform installation back, upper steel platform need bypass lower floor steel platform from the side and promote the installation again, lead to the hoist and mount place big, hoist and mount inefficiency. Although the multi-layer platforms can be assembled and stacked on the ground in situ, the operation is difficult in practice.
In the prior art, the patent number CN201710326724.9 provides a lifting construction method for a plurality of steel galleries between tower buildings; the essence of the method is that on the basis that the lower steel platform is installed, the upper steel platform is assembled on the lower steel platform and then integrally lifted. Because the hollow corridor steel platform is only a basic frame of the corridor, the hollow corridor steel platform has no actual construction working surface, and the safety performance of the hollow corridor steel platform serving as an assembling working surface is poor. Meanwhile, the problem of the standing position of the auxiliary crane is also considered during the actual assembly operation.
Disclosure of Invention
To solve the problems and the defects in the prior art, the construction method for the layered lifting of the large-span hollow corridor steel platform is provided, the girder brackets are installed on buildings on two sides to serve as pre-installation parts, and the length of the girder brackets is reduced layer by layer from top to bottom; the length of the main beam of the steel platform is increased layer by layer from top to bottom; and integrally assembling the hollow corridor steel platform on the ground, and then lifting and installing the hollow corridor steel platform layer by layer from top to bottom. Compare traditional construction scheme, belong to reverse operation, the construction is quick, easy operation, whole occupation of land is little.
In order to solve the technical problem, the following technical scheme is adopted in the application:
a construction method for the layered lifting of a large-span hollow corridor steel platform is characterized in that a plurality of layers of hollow corridor steel platforms are connected between buildings on two sides from top to bottom; a plurality of main beams are arranged on each layer of the hollow corridor steel platform along the horizontal direction and are used for connecting the buildings on two sides; a plurality of secondary beams which are vertical to or cross-connected with the main beam are also arranged; each main beam is divided into a steel platform main beam and main beam brackets on two sides along the horizontal direction, and the main beam brackets on the two sides are relatively and fixedly arranged on the buildings on the two sides; every layer of continuous corridor steel platform on an empty stomach promotes according to from last to down layering and installs, specifically includes following step:
s1, determining the length of a main beam of an open-web corridor steel platform according to the length distance between buildings on two sides, wherein the length of a bracket of the main beam is gradually shortened from top to bottom layer by layer, and the length of the main beam of the steel platform is gradually increased from top to bottom layer by layer; the arrangement ensures that the length of the girder of each layer of the hollow corridor steel platform is the same, the whole structure is stable, and meanwhile, when the steel platform is hoisted from top to bottom in a layered mode, the steel platform and the pre-connecting pieces of buildings on two sides, namely the girder brackets, are mutually staggered, so that the hoisting is ensured to be smooth and free of blocking.
S2, after the capping construction of the main body structures of the buildings on the two sides is completed or the main body structures exceed the top height of the corridor; mounting main beam brackets on each layer of main structure of buildings on two sides; after the installation is finished, installing lifting platforms on the main beam brackets on the two sides of the top layer, installing lifting equipment on the lifting platforms and vertically installing lifting ropes;
s3, arranging a ground jig frame on the ground, and assembling a top layer hollow corridor steel platform on the ground jig frame;
s4, after the assembly of the hollow abdominal corridor steel platform of S3 is completed, utilizing lifting equipment in S2 to perform a hollow corridor steel platform lifting procedure, and after the hollow abdominal corridor steel platform is lifted to a designed elevation, fixedly connecting a main beam of the steel platform and a main beam bracket, namely completing a top-layer hollow corridor steel platform installation procedure;
and S5, lowering the lifting rope to the ground, and repeating the steps S3-S4 to complete the installation process of the hollow corridor steel platform until the installation work of the hollow corridor steel platforms among all the building layers is completed.
Specifically, when the lifting platform is installed in step S2, the lifting platform includes a plurality of cantilever beams, a plurality of columns, and a staggered lifting transfer beam; the cantilever beam is arranged on the upper side of the main beam bracket in parallel through the upright post, one end of the cantilever beam extends to the upper side of the main body structure of the building, and the other end of the cantilever beam extends to the outer side of the main beam bracket and is fixedly connected with the staggered lifting transfer beam. Set up like this and promote the platform, mainly be in order to realize the effectual whole load of lifting means, guarantee to promote the security.
Specifically, in step S2, the lifting device is a plurality of hydraulic lifters, each hydraulic lifter is fixedly mounted on the offset lifting transfer beam at intervals, and each mounting point of each hydraulic lifter is offset from the main beam corbel in the vertical direction. The hydraulic lifting is utilized in the arrangement, and efficient lifting force is guaranteed. The mounting points of the hydraulic lifters are arranged in a staggered mode relative to the main beam brackets, so that the lifting ropes and the main beam brackets do not cross and conflict in the lifting process; both can realize that the lifting rope can all pass each layer steel platform, also can realize when every layer of continuous corridor steel platform location installation on an empty stomach, the quick location of steel platform girder and girder bracket improves the installation effectiveness.
Specifically, when the hollow corridor steel platform is assembled on the ground jig frame in the step S3, the ground jig frame is provided with a lifting joist; assembling an open-web corridor steel platform on a lifting joist, wherein a plurality of through holes are formed in the lifting joist; the lifting rope penetrates through the through hole and is fixedly connected with the detachable connecting piece, and lifting operation is carried out on the lifting joist. The lifting joist is arranged to realize the overall stability of the hollow corridor steel platform during lifting operation, and when the lifting joist is fixedly connected with the main beam bracket, the lifting joist can be quickly positioned and locally finely adjusted integrally, so that the working efficiency is improved.
Specifically, when the hollow corridor steel platform is repeatedly lifted in the step S5, after the upper-layer hollow corridor steel platform is installed, the lifting joist can be lowered to the ground through the lifting device, and can also be lifted to the ground through the on-site tower crane or other lifting devices. Different descending modes can be selected according to the whole weight of the lifting joist, and the operation speed of the hydraulic lifter is generally slower in order to ensure the safety of the lifting process due to the large whole weight of the hollow corridor steel platform. If the whole lifting joist is heavy, the lifting joist can be lowered to the ground by using a hydraulic lifter; if the whole weight of the lifting joist is small, in order to protect the hydraulic lifter from being damaged due to long-time no-load operation, the lifting joist can be selectively lowered to the ground by using a tower crane or other hoisting equipment.
Compared with the prior art, the beneficial effect of this application lies in:
1. through with the vestibule steel platform girder on an empty stomach from last successive layer dislocation set down, can realize that each layer vestibule steel platform on an empty stomach installs from last to going backwards, the efficiency of construction is high, and auxiliary assembly takes up an area of for a short time, and the security is high.
2. Through the girder dislocation set with hydraulic lifting mechanism mounting point and open-web vestibule steel platform, can realize quick hoist and mount operation, hoist and mount process is smooth and easy not have the hindrance, and is safe high-efficient.
3. The lifting joist and the lifting rope are detachably connected, meanwhile, the lifting joist has various descending modes, the lifting process can be optimized, the protection of lifting equipment is also considered, and the operation is simple.
Drawings
FIG. 1 is a schematic diagram illustrating an initial state of lifting a top-layer hollow corridor steel platform according to an embodiment;
FIG. 2 is a schematic diagram of the top-layer hollow corridor steel platform of the embodiment after being assembled;
FIG. 3 is a schematic view illustrating a process of lowering the lifting joist to the ground according to embodiment 1;
FIG. 4 is a front view of an embodiment of an initial lifting state of an intermediate layer hollow corridor steel platform;
FIG. 5 is a side view of the completed assembly of the intermediate layer hollow corridor steel platform in the embodiment;
FIG. 6 is a front view of the lifting installation of the lowermost hollow corridor steel platform of the embodiment;
FIG. 7 is a side view of the lifting installation of the lowest hollow corridor steel platform of the embodiment
FIG. 8 is a top view of an embodiment of a lifting device mounted in a misaligned configuration with respect to a lifting platform;
FIG. 9 is a front view of the lifting apparatus of the embodiment installed in a misaligned configuration with respect to the lifting platform;
FIG. 10 is a schematic view illustrating the installation of a lifting joist and a tower crane or other hoisting equipment in embodiment 2;
fig. 11 is a schematic view illustrating a process of lowering the lifting joist to the ground according to embodiment 2.
In the figure: 1. a hydraulic lifter; 2. lifting the transfer beam in a staggered manner; 3. a cantilever beam; 4. a column; 5. a steel strand; 6. a ground anchor; 7. lifting the joist; 8. a ground jig frame; 9. a main beam; 9a, a steel platform girder; 9b, main beam brackets; 10. a secondary beam; 11. a building body structure; 12. hoisting the fixed rope; 13. and (4) a lifting hook.
Detailed Description
In order that the objects and advantages of the present application will become more apparent, the present application will be described in detail with reference to the following examples. It is to be understood that the following text is merely illustrative of one or more specific embodiments of the application and does not strictly limit the scope of the claims which specifically recite this application.
Referring to fig. 1-11, the present application provides a construction method for layered lifting of a large-span hollow corridor steel platform, wherein a multi-layer hollow corridor steel platform is connected between buildings on two sides from top to bottom; a plurality of main beams 9 are arranged on each layer of the hollow corridor steel platform along the horizontal direction and are used for connecting the buildings on two sides; a plurality of secondary beams 10 which are vertical to or cross-connected with the main beam 9 are also arranged; each main beam 9 is divided into a steel platform main beam 9a and main beam brackets 9b at two sides along the horizontal direction, and the main beam brackets 9b at two sides are relatively and fixedly arranged on the buildings at two sides; every layer of continuous corridor steel platform on an empty stomach promotes according to from last to down layering and installs, specifically includes following step:
s1, determining the length of a main beam 9 of the hollow corridor steel platform according to the length distance between buildings on two sides, wherein the length of a bracket 9b of the main beam is reduced layer by layer from top to bottom, and the length of a main beam 9a of the steel platform is increased layer by layer from top to bottom;
s2, after the capping construction of the main body structures of the buildings on the two sides is completed or the main body structures exceed the top height of the corridor; mounting main beam brackets 9b on main structures 11 of each layer of buildings on two sides; after the installation is finished, a lifting platform is installed on the main beam brackets 9b on the two sides of the top layer, lifting equipment is installed on the lifting platform, and the steel stranded ropes 5 are vertically installed on the lifting platform;
s3, arranging a ground jig frame 8 on the ground, and assembling a top layer hollow corridor steel platform on the ground jig frame 8;
s4, after the assembly of the S3 hollow belly corridor steel platform is completed, utilizing the lifting equipment in S2 to perform a hollow corridor steel platform lifting process, and after the hollow belly corridor steel platform is lifted to a designed elevation, fixedly connecting a steel platform main beam 9a with a main beam bracket 9b to complete a top layer hollow corridor steel platform installation process; refer to fig. 1-2.
And S5, lowering the steel stranded ropes 5 to the ground, and repeating the steps of S3-S4 to complete the installation process of the hollow corridor steel platforms until the installation work of the hollow corridor steel platforms among all the building layers is completed. Refer to fig. 3-7.
Further, when the lifting platform is installed in the step S2, the lifting platform includes a plurality of cantilever beams 3, a plurality of upright posts 4 and a staggered lifting transfer beam 2; the cantilever beam 3 is arranged on the upper side of the main beam bracket 9b in parallel through the upright post 4, one end of the cantilever beam extends to the upper side of the building main body structure 11, and the other end of the cantilever beam extends to the outer side of the main beam bracket 9b and is fixedly connected with the dislocation lifting conversion beam 2.
Further, in step S2, the lifting devices are a plurality of hydraulic lifters 1, each hydraulic lifter 1 is fixedly mounted on the offset lifting transfer beam 2 at intervals, and each mounting point thereof is offset from the main beam corbel 9b in the vertical direction. Refer to fig. 8 and 9.
Further, when the hollow corridor steel platform is assembled on the ground jig frame 8 in the step S3, the ground jig frame 8 is provided with the lifting joist 7; assembling an open-web corridor steel platform on the lifting joist 7, wherein a plurality of through holes are arranged on the lifting joist 7; the steel stranded rope 5 penetrates through the through hole and is fixedly connected with the detachable ground anchor 6 to lift the lifting joist 7.
Further, when the hollow corridor steel platform is repeatedly lifted in step S5, after the upper-layer hollow corridor steel platform is installed, the lifting joist 7 is lowered to the ground through the hydraulic lifter 1.
Example 2; the difference between the embodiment 2 and the embodiment 1 is that when the hollow corridor steel platform is repeatedly lifted in step S5, after the upper-layer hollow corridor steel platform is installed, the lifting joists 7 are fixed by the lifting fixing ropes 12 connected to the lifting hooks 13 of the tower crane or other lifting devices, and are lowered to the ground. Refer to fig. 10 and 11.
The working principle is as follows: according to the design requirements of the corridor between the buildings at two sides, the main beam corbels 9b of each layer are manufactured firstly. After the main structure 11 of the buildings at two sides is capped, a main grain bracket 9b is installed on each layer of the main structure 11 of the building, and the length of each layer of the main beam bracket 9b is reduced by 50mm-100mm from top to bottom layer by layer; a lifting platform is arranged on the top girder bracket 9b and consists of a cantilever beam 3, an upright post 4 and a staggered lifting conversion beam 2; and a hydraulic lifter 1 is fixedly arranged on the dislocation lifting conversion beam 2. And (3) assembling a top layer hollow corridor steel platform on the lifting joist 7 of the ground jig frame 8, and after assembling is finished. And a steel stranded rope 5 is installed, one end of the steel stranded rope penetrates through a through hole in the lifting joist 7 and is fixedly connected with the lifting joist through an earth anchor 6, and the other end of the steel stranded rope is also connected with the hydraulic lifter 1. And lifting the top layer hollow corridor steel platform by using a hydraulic lifter, and after reaching a designed elevation, fixedly welding and connecting the steel platform main beam 9a of the hollow corridor steel platform and the main beam bracket 9 b. After the top layer hollow corridor steel platform is installed, the lifting joist 7 is lowered to the ground, the lower layer hollow corridor steel platform is repeatedly assembled, the lifting installation process is repeated, and all installation work is completed after all layers of hollow corridor steel platforms are installed.
The embodiments of the present application have been described in detail with reference to the examples, but the present application is not limited to the embodiments, and those skilled in the art can make various equivalent changes and substitutions without departing from the principle of the present application after learning the content of the present application, and these equivalent changes and substitutions should be considered as belonging to the protection scope of the present application.

Claims (5)

1. A construction method for layered lifting of a large-span open-web corridor steel platform is characterized by comprising the following steps: a plurality of layers of the hollow corridor steel platforms are connected between the buildings on the two sides from top to bottom; a plurality of main beams are arranged on each layer of the hollow corridor steel platform along the horizontal direction and are used for connecting buildings on two sides; a plurality of secondary beams which are vertical to or cross-connected with the main beam are also arranged; each main beam is divided into a steel platform main beam and main beam brackets on two sides along the horizontal direction, and the main beam brackets on the two sides are relatively and fixedly installed on buildings on the two sides; every layer the empty stomach vestibule steel platform is installed according to from last layering promotion extremely down, specifically includes following steps:
s1, determining the length of a main beam of the hollow corridor steel platform according to the length distance between buildings on two sides, wherein the length of a bracket of the main beam is reduced layer by layer from top to bottom, and the length of the main beam of the steel platform is increased layer by layer from top to bottom;
s2, after the capping construction of the main body structures of the buildings on the two sides is completed or the main body structures exceed the top height of the corridor; mounting the main beam brackets on the main structure of each layer of the building on two sides; after the installation is finished, installing lifting platforms on the main beam brackets on the two sides of the top layer, installing lifting equipment on the lifting platforms and vertically installing lifting ropes;
s3, arranging a ground jig frame on the ground, and assembling the top layer of the hollow corridor steel platform on the ground jig frame;
s4, after the assembly of the hollow corridor steel platform in the S3 is completed, utilizing the lifting equipment in the S2 to carry out the lifting process of the hollow corridor steel platform, and after the hollow corridor steel platform is lifted to a designed elevation, fixedly connecting a girder of the steel platform and a girder bracket, namely completing the installation process of the hollow corridor steel platform at the top layer;
and S5, lowering the lifting rope to the ground, and repeating the steps S3-S4 to complete the installation process of the hollow corridor steel platform until the installation work of the hollow corridor steel platforms among all the building layers is completed.
2. The construction method for the layered lifting of the large-span open-web corridor steel platform according to the claim 1, characterized in that: when the lifting platform is installed in the step S2, the lifting platform comprises a plurality of cantilever beams, a plurality of upright posts and staggered lifting transfer beams; the cantilever beam passes through stand parallel mount be in girder bracket upside, and its one end extends to building main body structure top, and the other end extends to the girder bracket outside, and with dislocation promotes crossover girder fixed connection.
3. The construction method for the layered lifting of the large-span open-web corridor steel platform according to the claim 2, characterized in that: in the step S2, the lifting device is a plurality of hydraulic lifters, each of the hydraulic lifters is fixedly mounted on the staggered lifting transfer beam at intervals, and each mounting point is staggered with the girder bracket in the vertical direction.
4. The construction method for the layered lifting of the large-span open-web corridor steel platform according to the claim 1, characterized in that: when the hollow corridor steel platform is assembled on the ground jig frame in the step S3, a lifting joist is arranged on the ground jig frame; assembling the hollow corridor steel platform on the lifting joist, wherein the lifting joist is provided with a plurality of through holes; the lifting rope penetrates through the through hole and is fixedly connected with the detachable connecting piece, and the lifting operation is carried out on the lifting joist.
5. The construction method for the layered lifting of the large-span hollow corridor steel platform according to the claim 4, characterized in that: when the fasting corridor steel platform is repeatedly lifted in the step S5, the installation of the fasting corridor steel platform on the upper layer is completed, the lifting joist can be lowered to the ground through the lifting equipment, and the lifting joist can also be lifted to the ground through the field tower crane or other lifting equipment.
CN202110776502.3A 2021-07-09 2021-07-09 Construction method for layered lifting of large-span open-web corridor steel platform Pending CN113494127A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110776502.3A CN113494127A (en) 2021-07-09 2021-07-09 Construction method for layered lifting of large-span open-web corridor steel platform

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110776502.3A CN113494127A (en) 2021-07-09 2021-07-09 Construction method for layered lifting of large-span open-web corridor steel platform

Publications (1)

Publication Number Publication Date
CN113494127A true CN113494127A (en) 2021-10-12

Family

ID=77995865

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110776502.3A Pending CN113494127A (en) 2021-07-09 2021-07-09 Construction method for layered lifting of large-span open-web corridor steel platform

Country Status (1)

Country Link
CN (1) CN113494127A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114182963A (en) * 2021-11-10 2022-03-15 浙江精工钢结构集团有限公司 Construction method for reverse-order layered lifting of plane-overlapped multi-layer large-span truss structure

Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2601002A1 (en) * 2006-09-11 2008-03-11 John W. Hanlon Building system using modular precast concrete components
CN204663003U (en) * 2015-02-12 2015-09-23 中天建设集团有限公司 Anchor ear type vestibule truss Steel Structure hoisting hanger
CN106401198A (en) * 2016-06-14 2017-02-15 中天建设集团有限公司 Large-span steel gallery lifting equipment and construction method
CN106437178A (en) * 2016-10-21 2017-02-22 中建八局第三建设有限公司 Integral lifting construction method and integral lifting construction device of veranda of multi-layer steel structure
CN106522361A (en) * 2016-12-07 2017-03-22 上海市机械施工集团有限公司 Combined installation method for multi-layer heavy steel space corridor
CN106930541A (en) * 2017-05-10 2017-07-07 中国建筑第二工程局有限公司 A kind of construction method of suspension type steel vestibule
CN107060105A (en) * 2017-05-10 2017-08-18 中国建筑第二工程局有限公司 A kind of lifting construction method of multiple steel vestibules between high building
CN208415485U (en) * 2018-05-31 2019-01-22 上海建工四建集团有限公司 The aerial steel vestibule Lift-on/Lift-off System of multilayer
CN109610834A (en) * 2019-02-02 2019-04-12 南通职业大学 The high-altitude construction method of Long-span Multi-storey Frame heavy duty concrete structure
CN111333193A (en) * 2020-03-09 2020-06-26 广州市环境保护工程设计院有限公司 Layered basket type constructed wetland filler structure and installation method thereof
CN111519767A (en) * 2020-05-12 2020-08-11 上海建工一建集团有限公司 Integral lifting reverse construction system and method for multi-channel connected truss
CN112267556A (en) * 2020-10-10 2021-01-26 广东省构建工程建设有限公司 Large-span steel structure corridor assembling construction process for narrow space
CN113006588A (en) * 2021-02-09 2021-06-22 中国华冶科工集团有限公司 Inverted construction method of chimney platform

Patent Citations (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CA2601002A1 (en) * 2006-09-11 2008-03-11 John W. Hanlon Building system using modular precast concrete components
CN204663003U (en) * 2015-02-12 2015-09-23 中天建设集团有限公司 Anchor ear type vestibule truss Steel Structure hoisting hanger
CN106401198A (en) * 2016-06-14 2017-02-15 中天建设集团有限公司 Large-span steel gallery lifting equipment and construction method
CN106437178A (en) * 2016-10-21 2017-02-22 中建八局第三建设有限公司 Integral lifting construction method and integral lifting construction device of veranda of multi-layer steel structure
CN106522361A (en) * 2016-12-07 2017-03-22 上海市机械施工集团有限公司 Combined installation method for multi-layer heavy steel space corridor
CN106930541A (en) * 2017-05-10 2017-07-07 中国建筑第二工程局有限公司 A kind of construction method of suspension type steel vestibule
CN107060105A (en) * 2017-05-10 2017-08-18 中国建筑第二工程局有限公司 A kind of lifting construction method of multiple steel vestibules between high building
CN208415485U (en) * 2018-05-31 2019-01-22 上海建工四建集团有限公司 The aerial steel vestibule Lift-on/Lift-off System of multilayer
CN109610834A (en) * 2019-02-02 2019-04-12 南通职业大学 The high-altitude construction method of Long-span Multi-storey Frame heavy duty concrete structure
CN111333193A (en) * 2020-03-09 2020-06-26 广州市环境保护工程设计院有限公司 Layered basket type constructed wetland filler structure and installation method thereof
CN111519767A (en) * 2020-05-12 2020-08-11 上海建工一建集团有限公司 Integral lifting reverse construction system and method for multi-channel connected truss
CN112267556A (en) * 2020-10-10 2021-01-26 广东省构建工程建设有限公司 Large-span steel structure corridor assembling construction process for narrow space
CN113006588A (en) * 2021-02-09 2021-06-22 中国华冶科工集团有限公司 Inverted construction method of chimney platform

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114182963A (en) * 2021-11-10 2022-03-15 浙江精工钢结构集团有限公司 Construction method for reverse-order layered lifting of plane-overlapped multi-layer large-span truss structure

Similar Documents

Publication Publication Date Title
CN107399656B (en) Outdoor elevator and construction method thereof
CN101537976B (en) Dual-tower-mast giant self-lifting crane and following-carrying lifting method thereof
CN108625483B (en) Equipment for jacking construction of assembled additional elevator shaft structure
CN111519767A (en) Integral lifting reverse construction system and method for multi-channel connected truss
CN201376848Y (en) Large-scale double-tower automatic-elevation hoisting equipment
CN113494127A (en) Construction method for layered lifting of large-span open-web corridor steel platform
CN108584646B (en) Assembled type additional elevator shaft structure suitable for jacking construction
CN111236613A (en) Protection platform for building construction and use method thereof
CN216549362U (en) Assembling and hoisting device for components above foundation pit
CN115680286A (en) Nuclear island reactor factory building construction equipment integration platform and climbing method thereof
CN211769640U (en) Quick installation positioner of module elevator skeleton
CN111196566A (en) Construction structure and construction method of super high-rise inner climbing tower crane
CN214941062U (en) Structure for improving layering reverse order of hollow steel gallery
CN116181041B (en) Building machine of multilayer quick construction
CN116335398B (en) Multilayer rapid construction method
CN113152687A (en) Structure and method for improving layering reverse order of hollow steel gallery
CN114150856B (en) Installation method of sectional type climbing frame
CN112551366B (en) Lifting and transporting frame integrated building erecting machine construction equipment and construction method thereof
CN217053072U (en) Multifunctional steel cable tower cap and stay cable installation device
CN115095163B (en) Inverted steel structure hanging frame construction method and steel column positioning tool
CN221093498U (en) Tower crane construction intelligent building platform is exempted from in assembled house engineering
CN219098539U (en) Hoisting device for large ship lift platform
CN212053814U (en) Hoisting structure for installation of prefabricated staircase
CN212954042U (en) Lattice formula cable saddle hoist and mount portal
CN221002026U (en) Auxiliary tower favorable for installation of roof large-span steel structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20211012

RJ01 Rejection of invention patent application after publication