CN104100095A - Method and device for mounting large-sized operating platform between two tower buildings - Google Patents
Method and device for mounting large-sized operating platform between two tower buildings Download PDFInfo
- Publication number
- CN104100095A CN104100095A CN201310126569.8A CN201310126569A CN104100095A CN 104100095 A CN104100095 A CN 104100095A CN 201310126569 A CN201310126569 A CN 201310126569A CN 104100095 A CN104100095 A CN 104100095A
- Authority
- CN
- China
- Prior art keywords
- bailey bracket
- high building
- bailey
- operation layer
- hands
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 238000000034 method Methods 0.000 title claims abstract description 31
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 17
- 239000010959 steel Substances 0.000 claims abstract description 17
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 26
- 229910052742 iron Inorganic materials 0.000 claims description 13
- 238000010276 construction Methods 0.000 abstract description 8
- 238000010586 diagram Methods 0.000 description 5
- 238000009435 building construction Methods 0.000 description 1
- 238000007596 consolidation process Methods 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 235000015170 shellfish Nutrition 0.000 description 1
Abstract
The invention discloses a method and a device for mounting a large-sized operating platform between two tower buildings. The method comprises the following steps of splicing spare products to form a section of bailey frame in an operating layer of a tower building A, prying the bailey frame towards a tower building B with a pry bar by an operator, connecting a section of bailey frame to the rear end of the bailey frame as a counterweight when the weight of the bailey frame on a floor slab is 1.5 times that of the suspended bailey frame, prying the bailey frame towards the tower building B again to ensure that the weight of the bailey frame on the floor slab is always greater than 1.5 times that of the suspended bailey frame, disassembling the bailey frame serving as the counterweight; erecting two bailey frames by using the same method, erecting transverse H-shaped steel between the two bailey frames, and laying a template on the transverse H-shaped steel to form the operating platform. According to the method and the device, simplicity in construction, high speed and economy are ensured, and the feasibility of erecting the operating platform when large-sized components cannot enter a floor by virtue of a tower crane can be achieved; moreover, personnel for aloft work are not required, so that safety is ensured.
Description
Technical field
the present invention relates to a kind of method and device that large operation platform is installed between two high buildings, belong to technical field of building construction.
Background technology
in building engineering construction, for handled easily, often need between two high buildings, set up large operation platform, large operation platform adopts Bailey bracket to support conventionally.The method of setting up at present large operation platform is first on ground, shellfish thunder platform to be assembled into an integral body, then by tower crane, two Bailey brackets are lifted on to the operation layer between two high buildings, then between two Bailey brackets, set up i iron, forming operating platform after finally laying template on i iron.If but spacing is excessive between two high buildings, Bailey bracket is longer, when weight is heavier, can exceed the permission hoisting weight of tower crane, cannot use tower crane to lift.Likely exist after platform is finished using, whole platform is closed in building simultaneously, and the phenomenon that tower crane cannot carry out handling needs to find in addition a kind of method that large operation platform is installed.
Summary of the invention
the object of the invention is to, a kind of method and device that large operation platform is installed between two high buildings is provided, to solve because spacing between two high buildings is excessive, Bailey bracket weight is heavier, the technical problem that cannot use tower crane to lift.
technical scheme of the present invention:
a kind of method that large operation platform is installed between two high buildings, the method is by one section of Bailey bracket of assembly in the operation layer of A high building, then by operating personnel, with crowbar, to B high building direction, prize Bailey bracket, the Bailey bracket weight on floor is unsettled Bailey bracket 1.5 times time; In Bailey bracket rear end, connect again one section of Bailey bracket as counterweight, and then prize Bailey bracket to B high building direction, make Bailey bracket weight on floor be greater than all the time 1.5 times of unsettled Bailey bracket weight, until Bailey bracket front end rides over B high building operation layer, then remove the Bailey bracket as counterweight; With same method, between A high building operation layer and B high building operation layer, set up two Bailey brackets, then between two Bailey brackets, set up i iron, form operating platform after finally laying template on i iron.
in preceding method, described Bailey bracket front end is connected with the bottle gouard moved by hands at B high building operation layer top with the bottle gouard moved by hands at A high building operation layer top respectively; When operating personnel prize Bailey bracket with crowbar to B high building direction, can be by the weight of the bottle gouard moved by hands at A high building operation layer top and the bottle gouard moved by hands balance Bailey bracket overhanging portion at B high building operation layer top.
in preceding method, described one section of Bailey bracket bottom with assembly is provided with one group of steel pipe vertical with Bailey bracket moving direction, to reduce the frictional resistance of Bailey bracket and operation layer bottom surface.
in preceding method, the bottle gouard moved by hands at described A high building operation layer top is mentioned Bailey bracket front end, and the bottle gouard moved by hands at B high building operation layer top slowly pulls forward Bailey bracket to alleviate operating personnel, to prize the labour intensity of Bailey bracket; Bailey bracket is in prizing process, and the bottle gouard moved by hands at the bottle gouard moved by hands at A high building operation layer top and B high building operation layer top is all the time in tension.
what by preceding method, form installs the device of large operation platform between two high buildings, comprises the A bottle gouard moved by hands that is arranged on A high building operation layer top and the B bottle gouard moved by hands that is arranged on B high building operation layer top; A bottle gouard moved by hands is connected with Bailey bracket top through wire rope, and B bottle gouard moved by hands is connected with Bailey bracket front end through wire rope.
in aforementioned means, described Bailey bracket bottom is provided with one group of steel pipe, and steel pipe arranges with Bailey bracket length direction is vertical.
in aforementioned means, described Bailey bracket rear end is provided with for prizing the crowbar of Bailey bracket.
compared with prior art, the present invention is by using loose mail on-site consolidation Bailey bracket at A operation layer, then in Bailey bracket bottom, place one group of steel pipe, to reduce the frictional force between Bailey bracket and operation layer ground, so that operating personnel prize Bailey bracket rear end with crowbar, make Bailey bracket front end make Bailey bracket front end ride over B high building edge from unsettled interval of crossing between two high buildings, A high building edge, form the girder truss of large operation platform, then between two girder trusses, set up i iron, form operating platform after finally laying template on i iron.It is simple, quick, economical that the present invention constructs, and can meet the feasibility of setting up operating platform when large-scale component cannot be used tower crane to enter floor, and without personnel's work high above the ground, guarantee safety.
Accompanying drawing explanation
fig. 1 is construction sequence 1 schematic diagram of the present invention;
fig. 2 is construction sequence 2 schematic diagrames of the present invention;
fig. 3 is construction sequence 3 schematic diagrames of the present invention;
fig. 4 is construction sequence 4 schematic diagrames of the present invention;
fig. 5 is the large operation platform structure schematic diagram that the present invention builds.
being labeled as in accompanying drawing: 1-A bottle gouard moved by hands, 2-B bottle gouard moved by hands, 3-A high building operation layer, 4-B high building operation layer, 5-steel pipe, 6-crowbar, 7-Bailey bracket, 8-i iron, 9-template.
The specific embodiment
below in conjunction with accompanying drawing, the present invention is described in further detail, but not as any limitation of the invention.
a kind of method that large operation platform is installed between two high buildings, as shown in Figures 1 to 4, the method is by one section of Bailey bracket of assembly in the operation layer of A high building, then by operating personnel, with crowbar, to B high building direction, prize Bailey bracket, the Bailey bracket weight on floor is unsettled Bailey bracket 1.5 times time; In Bailey bracket rear end, connect again one section of Bailey bracket as counterweight, and then prize Bailey bracket to B high building direction, make Bailey bracket weight on floor be greater than all the time 1.5 times of unsettled Bailey bracket weight, until Bailey bracket front end rides over B high building operation layer, then remove the Bailey bracket as counterweight; With same method, between A high building operation layer and B high building operation layer, set up two Bailey brackets, then between two Bailey brackets, set up i iron, form operating platform after finally laying template on i iron.Described Bailey bracket front end is connected with the bottle gouard moved by hands at B high building operation layer top with the bottle gouard moved by hands at A high building operation layer top respectively; When operating personnel prize Bailey bracket with crowbar to B high building direction, can be by the weight of the bottle gouard moved by hands at A high building operation layer top and the bottle gouard moved by hands balance Bailey bracket overhanging portion at B high building operation layer top.Described one section of Bailey bracket bottom with assembly is provided with one group of steel pipe vertical with Bailey bracket moving direction, to reduce the frictional resistance of Bailey bracket and operation layer bottom surface.The bottle gouard moved by hands at described A high building operation layer top is mentioned Bailey bracket front end, and the bottle gouard moved by hands at B high building operation layer top slowly pulls forward Bailey bracket to alleviate operating personnel, to prize the labour intensity of Bailey bracket; Bailey bracket is in prizing process, and the bottle gouard moved by hands at the bottle gouard moved by hands at A high building operation layer top and B high building operation layer top is all the time in tension.
what by preceding method, form installs the device of large operation platform between two high buildings, as shown in Figure 2, comprises the A bottle gouard moved by hands 1 that is arranged on A high building operation layer top and the B bottle gouard moved by hands 2 that is arranged on B high building operation layer top; A bottle gouard moved by hands 1 is connected with Bailey bracket 7 tops through wire rope, and B bottle gouard moved by hands 2 is connected with Bailey bracket 7 front ends through wire rope.Bailey bracket 7 bottoms are provided with one group of steel pipe 5, steel pipe 5 and vertical setting of Bailey bracket 7 length directions.Bailey bracket 7 rear ends are provided with for prizing the crowbar 6 of Bailey bracket 7.
Embodiment
during concrete enforcement, as shown in Figures 1 to 5, implement according to the following steps
step 1, as shown in Figure 1, interior by one section of Bailey bracket 7 of assembly at A high building operation layer 3, between Bailey bracket 7 bottoms and the ground of A high building operation layer 3, place the steel pipe 5 of one group of φ 48mm, steel pipe 5 is perpendicular to the length direction of Bailey bracket 7.The bottle gouard moved by hands 1 at A high building operation layer top and the bottle gouard moved by hands 2 at B high building operation layer top are installed respectively on the upper floor plated construction beam of A high building operation layer 3 and B high building operation layer 4, and the bottle gouard moved by hands 1 at A high building operation layer top is sling in the interior one section of Bailey bracket with assembly of A high building operation layer 3.The bottle gouard moved by hands 2 at B high building operation layer top is through tying up at Bailey bracket 7 front ends with wire rope.
step 2, as shown in Figure 2, pulls the bottle gouard moved by hands 1 at A high building operation layer top, and Bailey bracket body 7 is upwards promoted, and pulls the bottle gouard moved by hands 2 at B high building operation layer top simultaneously, makes to tie up wire rope at Bailey bracket 7 front ends all the time in tension.Then operating personnel use crowbar to prize Bailey bracket 7 rear ends, make Bailey bracket 7 move forward front end and stretch out A high building operation layer 3 edges in vacant state.
step 3, as shown in Figure 3, when the length of stretching out A high building operation layer 3 edges when Bailey bracket 7 is Bailey bracket 7 length approximately 2/5, the bottle gouard moved by hands 2 that stops prizing Bailey bracket 7 rear ends and pull B high building operation layer top, in Bailey bracket 7 rear ends, install again a joint Bailey bracket additional as counterweight, installed the rear bottle gouard moved by hands 2 that continues to prize Bailey bracket 7 rear ends and pull B high building operation layer top additional.Every hauling-out is installed a joint Bailey bracket additional again once joint Bailey bracket, makes Bailey bracket weight on floor be greater than all the time 1.5 times of unsettled Bailey bracket weight, guarantees that Bailey bracket can weightlessness not fall.
step 4, as shown in Figure 4, when the front end of Bailey bracket 7 rides over behind the edge of B high building operation layer 4 smoothly, adjusts lap length, and the length that Bailey bracket 7 rides over two high buildings is not less than 1 meter.Finally unclamp bottle gouard moved by hands, remove the steel pipe 5 of counterweight Bailey bracket and Bailey bracket bottom.
step 5, as shown in Figure 5, installs a Bailey bracket 7 again by step 1-4, then between two Bailey brackets 7, sets up i iron 8, finally on i iron 7, lays the installation that completes large operation platform after template 9.
aforementioned Bailey bracket 7 adopts assembly type steel bridge on highway trussed construction.By top-bottom chord, montant and brace, be welded.One end of top-bottom chord is cloudy head, and the other end is positive head.Negative and positive head has pin hole.During connection, the sun head of a joint is inserted in the cloudy head of another joint, aim at pinhole, plug pin.It is simple, quick, economical that the present invention constructs, and can meet the feasibility of setting up operating platform when large-scale component cannot be used tower crane to enter floor, and without personnel's work high above the ground, guarantee safety.
Claims (7)
1. the method that large operation platform is installed between two high buildings, it is characterized in that: the method is by one section of Bailey bracket of assembly in the operation layer of A high building, then by operating personnel, with crowbar, to B high building direction, prize Bailey bracket, the Bailey bracket weight on floor is unsettled Bailey bracket 1.5 times time; In Bailey bracket rear end, connect again one section of Bailey bracket as counterweight, and then prize Bailey bracket to B high building direction, make Bailey bracket weight on floor be greater than all the time 1.5 times of unsettled Bailey bracket weight, until Bailey bracket front end rides over B high building operation layer, then remove the Bailey bracket as counterweight; With same method, between A high building operation layer and B high building operation layer, set up two Bailey brackets, then between two Bailey brackets, set up i iron, form operating platform after finally laying template on i iron.
2. method according to claim 1, is characterized in that: described Bailey bracket front end is connected with the bottle gouard moved by hands at B high building operation layer top with the bottle gouard moved by hands at A high building operation layer top respectively; When operating personnel prize Bailey bracket with crowbar to B high building direction, can be by the weight of the bottle gouard moved by hands at A high building operation layer top and the bottle gouard moved by hands balance Bailey bracket overhanging portion at B high building operation layer top.
3. method according to claim 1, is characterized in that: described one section of Bailey bracket bottom with assembly is provided with one group of steel pipe vertical with Bailey bracket moving direction, to reduce the frictional resistance of Bailey bracket and operation layer bottom surface.
4. method according to claim 1, it is characterized in that: the bottle gouard moved by hands at described A high building operation layer top is mentioned Bailey bracket front end, the bottle gouard moved by hands at B high building operation layer top slowly pulls forward Bailey bracket to alleviate operating personnel, to prize the labour intensity of Bailey bracket; Bailey bracket is in prizing process, and the bottle gouard moved by hands at the bottle gouard moved by hands at A high building operation layer top and B high building operation layer top is all the time in tension.
5. what by method described in the arbitrary claim of claim 1-4, form installs the device of large operation platform between two high buildings, it is characterized in that: comprise the A bottle gouard moved by hands (1) that is arranged on A high building operation layer top and the B bottle gouard moved by hands (2) that is arranged on B high building operation layer top; A bottle gouard moved by hands (1) is connected with Bailey bracket (7) top through wire rope, and B bottle gouard moved by hands (2) is connected with Bailey bracket (7) front end through wire rope.
6. install according to claim 5, it is characterized in that: described Bailey bracket (7) bottom is provided with one group of steel pipe (5), steel pipe (5) and vertical setting of Bailey bracket (7) length direction.
7. install according to claim 5, it is characterized in that: described Bailey bracket (7) rear end is provided with the crowbar (6) for prizing Bailey bracket (7).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310126569.8A CN104100095B (en) | 2013-04-12 | 2013-04-12 | A kind of method installing large operation platform between two high buildings |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310126569.8A CN104100095B (en) | 2013-04-12 | 2013-04-12 | A kind of method installing large operation platform between two high buildings |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104100095A true CN104100095A (en) | 2014-10-15 |
CN104100095B CN104100095B (en) | 2016-08-03 |
Family
ID=51668608
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310126569.8A Expired - Fee Related CN104100095B (en) | 2013-04-12 | 2013-04-12 | A kind of method installing large operation platform between two high buildings |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104100095B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107060105A (en) * | 2017-05-10 | 2017-08-18 | 中国建筑第二工程局有限公司 | A kind of lifting construction method of multiple steel vestibules between high building |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06167118A (en) * | 1992-11-30 | 1994-06-14 | Takenaka Komuten Co Ltd | Construction by use of large size units of external wall panel for tower and hanging device |
CN102108788A (en) * | 2010-12-31 | 2011-06-29 | 华煜建设集团有限公司 | Method for constructing hanging in the air large-span support |
CN102777026A (en) * | 2011-12-06 | 2012-11-14 | 中建四局第三建筑工程有限公司 | Method for constructing ultra-long rear casting plate supporting system by using Bailey frames |
-
2013
- 2013-04-12 CN CN201310126569.8A patent/CN104100095B/en not_active Expired - Fee Related
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06167118A (en) * | 1992-11-30 | 1994-06-14 | Takenaka Komuten Co Ltd | Construction by use of large size units of external wall panel for tower and hanging device |
CN102108788A (en) * | 2010-12-31 | 2011-06-29 | 华煜建设集团有限公司 | Method for constructing hanging in the air large-span support |
CN102777026A (en) * | 2011-12-06 | 2012-11-14 | 中建四局第三建筑工程有限公司 | Method for constructing ultra-long rear casting plate supporting system by using Bailey frames |
Non-Patent Citations (2)
Title |
---|
史西华: "利用贝雷架作现浇混凝土结构模板支撑架平台", 《山西建筑》 * |
梁铨泽: "浅谈塔楼屋顶贝雷架支模施工技术", 《科学之友》 * |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107060105A (en) * | 2017-05-10 | 2017-08-18 | 中国建筑第二工程局有限公司 | A kind of lifting construction method of multiple steel vestibules between high building |
CN107060105B (en) * | 2017-05-10 | 2018-11-13 | 中国建筑第二工程局有限公司 | A kind of lifting construction method of multiple steel vestibules between high building |
Also Published As
Publication number | Publication date |
---|---|
CN104100095B (en) | 2016-08-03 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108532465B (en) | A kind of construction method of the main bridge of Through Steel case arch bridge | |
CN100557168C (en) | A kind of method for high altitude installation of large span steel truss | |
CN103882812B (en) | Across the construction method of girder in stayed-cable bridge | |
CN105317008B (en) | A kind of Integral lifting method of steel truss girder cable-stayed bridge steel truss girder segment | |
CN106087752B (en) | Multispan cable-carried arch bridge construction method | |
CN103711301A (en) | Construction method and device for two-track movable electric basket and lifting hoist | |
CN106436573B (en) | Superelevation Sarasota large span upper beam bracket steel truss stand construction method | |
CN101177959A (en) | Curtain wall unit hanging equipment and construction method thereof | |
CN101446074B (en) | Installation and closure construction method for steel sliding roadway arch on top surface of steel trussed beam bridge | |
CN101476292B (en) | Method and equipment for mounting precast beam | |
CN203794498U (en) | Built-in self-elevating tower crane device | |
CN105256728B (en) | A kind of cantilever erection method of the Chinese human relations formula steel truss girder of cable-stayed bridge | |
CN106241618A (en) | A kind of curtain wall profiles boom hoisting | |
CN103993745B (en) | A kind of conversion beam integral hoisting device for rapid and hanging method thereof | |
CN105317205B (en) | The construction method and equipment therefor of a kind of elevator | |
CN104762882A (en) | Bridge segment lifting device and method | |
CN105019664B (en) | The air translation Method for Installation of case room formula electric panel room | |
CN107022958A (en) | The method in cable-stayed bridge across girder is installed using cable crane | |
CN105484165B (en) | Integrated prestress tensioning frame structure and manufacturing and using methods thereof | |
CN104153586A (en) | Construction method for installing purline through suspension cable cranes | |
CN203795311U (en) | Multi-leg high pier and slip form construction device | |
CN205241086U (en) | Template hoist and mount and ann gun carriage of disassembling and using | |
CN104100095A (en) | Method and device for mounting large-sized operating platform between two tower buildings | |
CN105040592B (en) | A kind of horizontal drawing cable bridge and its erection method | |
CN103979442B (en) | The method of 6400 tons of Hydraulic double-type crane lifting cost tropsch reactors |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CP03 | Change of name, title or address | ||
CP03 | Change of name, title or address |
Address after: No. 57, Beijing Road, Honghuagang District, Zunyi City, Guizhou Province Patentee after: The Third Construction Co.,Ltd. of China Construction Fourth Engineering Bureau Address before: Beijing road 563003 in Guizhou province Zunyi city Honghuagang District No. 57 Patentee before: THE THIRD CONSTRUCTION & ENGINEERING Co. OF CCFED |
|
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20160803 |