CN106436573B - Construction method of steel truss support for super high cable tower with large span upper beam corbel - Google Patents

Construction method of steel truss support for super high cable tower with large span upper beam corbel Download PDF

Info

Publication number
CN106436573B
CN106436573B CN201510710052.2A CN201510710052A CN106436573B CN 106436573 B CN106436573 B CN 106436573B CN 201510710052 A CN201510710052 A CN 201510710052A CN 106436573 B CN106436573 B CN 106436573B
Authority
CN
China
Prior art keywords
steel truss
bracket
support
construction
bridge
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201510710052.2A
Other languages
Chinese (zh)
Other versions
CN106436573A (en
Inventor
徐登云
韩永刚
赵飞
孙小猛
张少飞
宋显先
姜泛金
刘昌建
闫明赛
朱利荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Second Engineering Co Ltd of CTCE Group
Original Assignee
China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Second Engineering Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Tiesiju Civil Engineering Group Co Ltd CTCE Group, Second Engineering Co Ltd of CTCE Group filed Critical China Tiesiju Civil Engineering Group Co Ltd CTCE Group
Priority to CN201510710052.2A priority Critical patent/CN106436573B/en
Publication of CN106436573A publication Critical patent/CN106436573A/en
Application granted granted Critical
Publication of CN106436573B publication Critical patent/CN106436573B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明涉及一种超高索塔大跨度上横梁牛腿钢桁支架施工方法,属于建筑施工技术领域。该方法包括以下步骤:安装预埋件、安装提升设备、提升钢桁架、安装牛腿支撑、整体提升到位并固定。本发明提供的超高索塔大跨度上横梁牛腿钢桁支架施工方法,有效的解决了现有上横梁多采用落地式支架施工方法,普通大跨度无落地牛腿支架在大跨度上横梁施工过程中易造成大悬臂柔性索塔偏位,影响施工质量的难题,具有投入小、施工周期短、安全风险低、施工过程有序可控的特点,为类似的桥梁施工提供了参考。

This invention relates to a construction method for a steel truss bracket support for the upper crossbeam of a super-high cable tower with a large span, belonging to the field of building construction technology. The method includes the following steps: installing embedded parts, installing lifting equipment, lifting the steel truss, installing the bracket support, and lifting and fixing the entire structure into place. The construction method for the steel truss bracket support for the upper crossbeam of a super-high cable tower with a large span provided by this invention effectively solves the problem that existing methods often use ground-mounted supports for the upper crossbeam, and that ordinary large-span upper crossbeams without ground-mounted bracket supports are prone to causing displacement of the large cantilever flexible cable tower during construction, affecting construction quality. This method features low investment, short construction period, low safety risk, and an orderly and controllable construction process, providing a reference for similar bridge construction.

Description

超高索塔大跨度上横梁牛腿钢桁支架施工方法Construction method of steel truss support for super high cable tower with large span upper beam corbel

技术领域technical field

本发明涉及一种斜拉及悬索桥梁的大跨度上横梁牛腿钢桁支架施工方法,属于桥梁建筑施工技术领域。The invention relates to a construction method for a large-span upper beam corbel steel truss support of a cable-stayed and suspension bridge, and belongs to the technical field of bridge construction.

背景技术Background technique

从20世纪70年代开始,斜拉桥及悬索桥在世界范围内开始应用,至90年代发展迅速。我国斜拉桥及悬索桥目前正朝着超高、重载、复杂、大跨的方向发展。索塔是斜拉桥及悬索桥的主承重构件,H型索塔因其结构简单、承载能力优良、受力特性明确而广受设计师的青睐,已越来越广泛的应用于我国大型桥梁的建设之中。Since the 1970s, cable-stayed bridges and suspension bridges have been applied all over the world, and developed rapidly in the 1990s. my country's cable-stayed bridges and suspension bridges are currently developing in the direction of super-high, heavy-load, complex and long-span. Cable towers are the main load-bearing components of cable-stayed bridges and suspension bridges. H-type cable towers are widely favored by designers because of their simple structure, excellent bearing capacity, and clear force characteristics. They have been more and more widely used in large bridges in my country. under construction.

现代桥梁所采用的H型索塔,多具有中、上塔柱内倾,下、上横梁间距相对较小,下横梁跨度及高度均较上横梁大等特点,超高H型索塔则可能设置多道横梁。该类H型索塔上横梁可采用传统的落地式钢管支架施工,即以施工完成的下道横梁作为上道横梁临时支架承重系统,施工工序简单,支架承载能力大,安全系数相对较高。Most of the H-shaped cable towers used in modern bridges have the characteristics of inward inclination of the middle and upper tower columns, relatively small spacing between the lower and upper beams, and the span and height of the lower beams are larger than the upper beams. Super-high H-shaped cable towers may be installed Multiple beams. The upper beam of this type of H-type cable tower can be constructed with traditional floor-standing steel pipe supports, that is, the completed lower beams are used as the temporary support load-bearing system of the upper beams. The construction process is simple, the support has a large bearing capacity, and the safety factor is relatively high.

考虑到索塔结构的外观造型,同时兼顾工程量投入,部分H型索塔设计具有双塔肢内侧无变坡,上横梁设计位置高、跨度大、混凝土方量多,上下横梁净距大的特点。上述H型索塔若采用传统的落地式钢管支架施工存在以下诸多缺陷:Considering the appearance and shape of the cable tower structure, and taking into account the amount of engineering investment, some H-shaped cable towers are designed with no slope change inside the double tower limbs, the design position of the upper beam is high, the span is large, the amount of concrete is large, and the clear distance between the upper and lower beams is large. features. If the above-mentioned H-type cable tower is constructed with traditional floor-standing steel pipe supports, there are many defects as follows:

1、钢管立柱加工及安装周期均较长,安装过程中,长期占用塔吊,影响塔肢主体结构施工,后期拆除工作量巨大;1. The processing and installation period of the steel pipe column is long. During the installation process, the tower crane is occupied for a long time, which affects the construction of the main structure of the tower limb, and the subsequent demolition workload is huge;

2、超长钢管立柱安装垂直度及整体稳定性难以控制;2. It is difficult to control the verticality and overall stability of the ultra-long steel pipe column installation;

3、所用材料数量较大,投入大,经济性较差。3. The amount of materials used is large, the investment is large, and the economy is poor.

上述H型索塔宜采用无落地支架法进行施工,在现有公开技术中,如公开号:CN104109999 A《桥塔横梁的施工方法》,介绍了一种H型索塔多横梁无落地支架施工方法,其技术方法是:吊装横梁支架至上横梁施工位置处,完成上横梁施工,然后将横梁支架通过穿心式千斤顶下方至中横梁施工位置,待中横梁施工完成后,再将横梁支架下方至地面拆除。但该技术仅强调安装方法未具体涉及横梁支架结构及布置形式,同时大跨度上横梁支架自重相对较大,技术方法中仅强调支架的整体卸落,并未明确采用何种方法将横梁支架吊装至上横梁施工位置。The above-mentioned H-type cable tower should be constructed by using the method without floor supports. In the existing public technology, such as the publication number: CN104109999 A "Construction Method for Bridge Tower Beams", which introduces a kind of H-type cable tower multi-beam without floor support construction. The method, the technical method is: hoist the beam support to the construction position of the upper beam, complete the construction of the upper beam, then pass the beam support under the through-hole jack to the construction position of the middle beam, and after the construction of the middle beam is completed, then lower the beam support to Ground demolition. However, this technology only emphasizes the installation method and does not specifically involve the structure and layout of the beam bracket. At the same time, the weight of the beam bracket on the long-span is relatively large. The top beam construction position.

如公开号:CN 103352428 A《悬索桥索塔横梁无支架施工方法》,介绍了一种悬索桥索塔横梁无支架施工方法,其技术方法是:焊接一钢桁架,在钢桁架上安装悬吊系统,利用悬吊系统提升并固定底模。该技术方法将钢桁架作为永久结构浇筑至横梁内部,可能影响横梁整体结构特性,同时造成材料浪费,具有一定的局限性。For example, the publication number: CN 103352428 A "Construction Method for Cable Tower Crossbeam of Suspension Bridge without Support", introduces a construction method for suspension bridge cable tower beam without support. The technical method is: welding a steel truss, installing a suspension system on the steel truss, Use the suspension system to lift and fix the bottom form. This technical method pours the steel truss into the beam as a permanent structure, which may affect the overall structural properties of the beam and cause material waste, which has certain limitations.

发明内容Contents of the invention

本发明为解决的技术问题是:提出一种采用无落地式刚性支架的超高索塔大跨度上横梁牛腿钢桁支架施工方法。The technical problem to be solved by the present invention is to propose a construction method for a super-high cable tower large-span upper beam corbel steel truss support without a floor-type rigid support.

为了解决上述技术问题,本发明提出的技术方案是:一种超高索塔大跨度上横梁牛腿钢桁支架施工方法,所述牛腿钢桁支架包括钢桁架和牛腿支撑;该方法包括以下步骤:In order to solve the above-mentioned technical problems, the technical solution proposed by the present invention is: a construction method for a super-high cable tower large-span upper beam corbel steel truss support, wherein the corbel steel truss support includes a steel truss and a corbel support; the method includes the following step:

(1)在所述桥梁塔柱施工过程中,根据所述牛腿钢桁支架的安装位置,依次预留牛腿支撑预埋件、下弦杆预埋件、上弦杆预埋件和提升支架预埋件;(1) During the construction of the bridge tower column, according to the installation position of the corbel steel truss bracket, the corbel support embedded parts, lower chord embedded parts, upper chord embedded parts and lifting bracket pre-embedded parts are reserved in sequence. Embedded parts;

(2)在所述提升支架埋件上焊接安装提升支架;在所述提升支架上安装穿心式连续千斤顶;(2) Weld and install the lifting bracket on the embedded parts of the lifting bracket; install the through-type continuous jack on the lifting bracket;

(3)将地面加工完成的钢桁架整体吊装至所述桥梁塔柱的下横梁顶部,所述穿心式连续千斤顶穿入钢绞线,所述钢绞线底部与所述钢桁架上的吊点连接;(3) Hoist the steel truss finished on the ground as a whole to the top of the lower beam of the bridge tower column, the through-type continuous jack penetrates the steel strand, and the bottom of the steel strand is connected with the hoist on the steel truss. point connection;

(4)启动所述穿心式连续千斤顶,将所述钢桁架提升至其与所述塔柱的下横梁之间可容纳所述牛腿支撑的高度,并将所述钢桁架临时固定在所述塔柱上;(4) Start the through-type continuous jack, lift the steel truss to a height that can accommodate the corbel support between it and the lower beam of the tower column, and temporarily fix the steel truss on the on the pylon;

(5)将地面加工完成的所述牛腿支撑吊装至所述钢桁架下方,并与所述钢桁架焊接组成所述牛腿钢桁支架;(5) hoisting the corbel support that has been processed on the ground below the steel truss, and welding it with the steel truss to form the corbel steel truss support;

(6)解除所述钢桁架与所述桥梁塔柱之间的临时固定,并启动所述穿心式连续千斤顶,将所述牛腿钢桁支架提升至安装位置下方;(6) Release the temporary fixation between the steel truss and the bridge tower, and start the through-type continuous jack to lift the corbel steel truss support below the installation position;

(7)启动所述穿心式连续千斤顶,将所述牛腿钢桁支架提升至设计位置,并与埋件焊接固定;(7) Start the through-type continuous jack, lift the corbel steel truss support to the design position, and weld and fix it with the embedded parts;

(8)在所述牛腿支撑埋件上安装承重支点,采用横向连接系将桥梁两侧的塔柱上的所述牛腿钢桁支架连接成整体。(8) Load-bearing fulcrums are installed on the corbel support embedded parts, and the corbel steel truss supports on the tower columns on both sides of the bridge are connected into a whole by using a transverse connection system.

上述方案进一步的改进在于:所述牛腿支撑是由钢结构的双肢斜腿及所述斜腿之间的平联组成的刚性牛腿支撑。A further improvement of the above solution is that: the corbel support is a rigid corbel support composed of steel structure slanted legs and parallel connections between the slanted legs.

上述方案进一步的改进在于:所述钢桁架由上弦杆、下弦杆、竖杆及斜杆组成。A further improvement of the above solution is that: the steel truss is composed of an upper chord, a lower chord, a vertical bar and a diagonal bar.

本发明提供的超高索塔大跨度上横梁牛腿钢桁支架施工方法,有效的解决了现有上横梁多采用落地式支架施工方法中投入大、周期长、风险高、控制难的问题,为类似的桥梁施工提供了参考。超高索塔大跨度上横梁牛腿钢桁支架该支架采用无落地式刚性支架结构形式,施工前无需进行预压试验,缩短了施工周期,同时具有承载能力大、传力途径明确、结构稳定、安拆方便等特点,钢桁架及刚性牛腿的加工及拼装均在地面完成,减少了高空作业,大大增加了施工安全性,对提高超高索塔大跨度上横梁施工技术具有较大的推动和促进作用。同时,针对该领域所进行的创新性地设计研发及应用研究使超高索塔大跨度上横梁牛腿钢桁支架及施工方法具有更广阔的推广价值。The construction method of the super-high cable tower large-span upper beam corbel steel truss support effectively solves the problems of large investment, long period, high risk and difficult control in the existing upper beam construction method that mostly adopts floor-standing brackets. A reference is provided for similar bridge construction. Super-high cable tower large-span upper beam corbel steel truss support The support adopts a non-floor rigid support structure, which does not require preloading tests before construction, shortens the construction period, and has large bearing capacity, clear force transmission path, and stable structure , easy installation and disassembly, etc. The processing and assembly of steel trusses and rigid corbels are all completed on the ground, which reduces high-altitude operations and greatly increases construction safety. Promote and facilitate. At the same time, the innovative design, development and application research carried out in this field make the super-high cable tower large-span upper beam corbel steel truss bracket and construction method have a wider promotion value.

附图说明Description of drawings

图1为本发明一个优选的实施例结构示意图。Fig. 1 is a schematic structural diagram of a preferred embodiment of the present invention.

图2为步骤(3)完成结构示意图。Figure 2 is a schematic diagram of the completed structure of step (3).

图3为步骤(5)完成结构示意图。Fig. 3 is a schematic diagram of the completed structure of step (5).

图4为步骤(6)完成结构示意图。Fig. 4 is a schematic diagram of the completed structure of step (6).

图5为牛腿和钢桁架结构示意图。Figure 5 is a schematic diagram of the corbel and steel truss structure.

图6为图1的侧视结构示意图。FIG. 6 is a schematic side view of the structure of FIG. 1 .

图中标号示意如下:Z1-钢桁架,Z2-牛腿支撑,Z3-预埋件体系,Z4-提升系统,1-上弦杆,2-下弦杆,3-竖杆,4-斜杆,5-钢桁架连系梁,6-双肢斜腿,7-平联,8-牛腿支撑预埋件,9-下弦杆预埋件,10-上弦杆预埋件,11-提升支架预埋件,12-提升支架,13-穿心式连续千斤顶,14-塔柱临时横撑。The symbols in the figure are as follows: Z1-steel truss, Z2-corbel support, Z3-embedded system, Z4-lifting system, 1-top chord, 2-bottom chord, 3-vertical bar, 4-slanting bar, 5 -Steel truss connecting beam, 6-slanted legs of both legs, 7-flat connection, 8-embedded part of corbel support, 9-embedded part of lower chord, 10-embedded part of upper chord, 11-embedded lifting bracket pieces, 12-lifting bracket, 13-through-heart continuous jack, 14-temporary cross brace of tower column.

具体实施方式Detailed ways

实施例Example

本实施例的超高索塔大跨度上横梁牛腿钢桁支架施工方法,包括以下步骤:The super-high cable tower large-span upper beam corbel steel truss support construction method of the present embodiment comprises the following steps:

(1)如图1中所示,在所述桥梁塔柱施工过程中,根据所述牛腿钢桁支架的安装位置,依次预留牛腿支撑预埋件8、下弦杆预埋件9、上弦杆预埋件10和提升支架预埋件11;(1) As shown in Figure 1, during the construction of the bridge tower column, according to the installation position of the corbel steel truss bracket, the corbel support embedded parts 8, lower chord embedded parts 9, Upper chord embedded parts 10 and lifting bracket embedded parts 11;

(2)在提升支架预埋件11上焊接安装提升系统Z4;提升系统Z4包括:与提升支架预埋件11焊接固定的提升支架12和安装在提升支架12上安装穿心式连续千斤顶13;(2) Weld and install the lifting system Z4 on the lifting bracket embedded part 11; the lifting system Z4 includes: the lifting bracket 12 welded and fixed with the lifting bracket embedded part 11 and the through-type continuous jack 13 installed on the lifting bracket 12;

(3)如图2所示,将地面加工完成的钢桁架Z1整体吊装至桥梁塔柱的下横梁顶,钢桁架Z1间采用横向连接系联接,穿心式连续千斤顶13穿入钢绞线,钢绞线底部与钢桁架Z1上的吊点连接;(3) As shown in Figure 2, hoist the steel truss Z1 that has been processed on the ground to the top of the lower beam of the bridge tower. The steel truss Z1 is connected by a horizontal connection system, and the continuous jack 13 is inserted into the steel strand. The bottom of the steel strand is connected to the lifting point on the steel truss Z1;

(4)如图3所示,启动穿心式连续千斤顶13,将钢桁架Z1提升至其与桥梁塔柱的下横梁之间可容纳牛腿支撑Z2的高度,并将钢桁架Z1临时放置在外伸牛腿装置上;(4) As shown in Figure 3, start the through-type continuous jack 13, lift the steel truss Z1 to a height that can accommodate the corbel support Z2 between it and the lower beam of the bridge tower column, and temporarily place the steel truss Z1 outside On the corbel stretcher;

(5)如图3所示,将地面加工完成的牛腿支撑Z2吊装至钢桁架Z1之下,并与钢桁架Z1焊接组成整体的牛腿钢桁架;(5) As shown in Figure 3, the corbel support Z2 that has been processed on the ground is hoisted under the steel truss Z1, and welded with the steel truss Z1 to form an integral corbel steel truss;

(6)如图4所示,解除钢桁架Z1与桥梁塔柱之间的临时固定,并启动穿心式连续千斤顶,将钢桁架Z1和牛腿支撑Z2提升至安装位置;(6) As shown in Figure 4, remove the temporary fixation between the steel truss Z1 and the bridge tower column, and start the through-type continuous jack to lift the steel truss Z1 and the corbel support Z2 to the installation position;

(7)启动所述穿心式连续千斤顶13,将所述牛腿钢桁支架提升至设计位置,并与埋件焊接固定。(7) Start the through-type continuous jack 13, lift the corbel steel truss support to the design position, and weld and fix it with the embedded parts.

(8)在所述牛腿支撑埋件8上安装承重支点,采用钢桁架连接系5将桥梁两侧的塔柱上的所述牛腿钢桁支架连接成整体。(8) Load-bearing fulcrums are installed on the corbel support embedded parts 8, and the corbel steel truss supports on the tower columns on both sides of the bridge are connected into a whole by using a steel truss connection system 5.

后续如拆除穿心式连续千斤顶13等工作不再赘述。Subsequent tasks such as dismantling the through-type continuous jack 13 will not be repeated.

在上述方法中,钢桁架Z1如图1和图5所示,由上弦杆1、下弦杆2、竖杆3、斜杆4构成,钢桁架Z1之间通过钢桁架连系梁5联接成整体,其中,上弦杆1、下弦杆2的两侧端部具有与下弦杆预埋件9、上弦杆预埋件10配合的预埋件体系Z3。为了应对热胀冷缩带等带来的尺寸变化,上弦杆1、下弦杆2的尺寸要比设计长度稍长,然后,在步骤(7)中,首先,选择温度恒定时段,多次测量上弦杆1、下弦杆2的合龙口宽度及钢桁架Z1长度,根据测量结果再进行现场配切上弦杆1、下弦杆2。In the above method, the steel truss Z1 is composed of upper chord 1, lower chord 2, vertical rod 3, and oblique rod 4, as shown in Figure 1 and Figure 5, and the steel truss Z1 is connected as a whole by steel truss connecting beam 5 , wherein, both ends of the upper chord 1 and the lower chord 2 have an embedded part system Z3 that cooperates with the lower chord embedded part 9 and the upper chord embedded part 10 . In order to cope with the dimensional changes caused by thermal expansion and contraction, the size of the upper chord 1 and the lower chord 2 should be slightly longer than the design length. Then, in step (7), firstly, select a constant temperature period and measure the upper chord several times. According to the measurement results for the closing width of the rod 1 and the lower chord 2 and the length of the steel truss Z1, the upper chord 1 and the lower chord 2 are matched and cut on site.

如图1和图5所示,牛腿支撑Z2,由双肢斜腿6及平联7组成。As shown in Fig. 1 and Fig. 5, the corbel support Z2 is composed of oblique legs 6 and parallel joints 7 of both limbs.

下弦杆预埋件9、上弦杆预埋件10和提升支架预埋件11;于桥梁两侧的塔柱施工过程中埋设,上横梁荷载通过预埋件体系传递至塔身。钢桁架Z1的上弦杆1两端的预埋件外露端长度为0.5m,下弦杆2预埋件外露端长度为0.3m;钢桁架Z1加工成梯形,下弦杆2比上弦杆1略长,即上弦杆1单侧比设计短0.5m,下弦杆2单侧比设计短0.3m。这样,可保证钢桁架Z1原位整体提升过程中,顺利起升至设计位置。由于钢桁架Z1的梯形设计,为了防止底部过宽影响提升,在牛腿支撑Z2上的牛腿预埋件8,所以待整体提升到位后安装。The lower chord embedded parts 9, the upper chord embedded parts 10 and the lifting bracket embedded parts 11 are buried during the construction of the tower columns on both sides of the bridge, and the load of the upper beam is transmitted to the tower body through the embedded parts system. The length of the exposed end of the embedded part at both ends of the upper chord 1 of the steel truss Z1 is 0.5m, and the length of the exposed end of the embedded part of the lower chord 2 is 0.3m; the steel truss Z1 is processed into a trapezoid, and the lower chord 2 is slightly longer than the upper chord 1, namely The upper chord 1 is 0.5m shorter than the design on one side, and the lower chord 2 is 0.3m shorter than the design on one side. In this way, it can be ensured that the steel truss Z1 can be lifted smoothly to the design position during the in-situ overall lifting process. Due to the trapezoidal design of the steel truss Z1, in order to prevent the lifting from being too wide at the bottom, the corbel embedded part 8 on the corbel support Z2 should be installed after the overall lifting is in place.

如图1至图4所示,如果钢桁架Z1提升过程中与塔柱临时横撑14设计位置形成空间干扰,则可按照图5所示,将钢桁架Z1分成左右两部分,暂不装钢桁架连系梁5,然后分两次,从下横梁顶整体提升至设计位置即可。As shown in Figures 1 to 4, if the lifting process of the steel truss Z1 forms space interference with the design position of the temporary cross brace 14 of the tower column, the steel truss Z1 can be divided into left and right parts as shown in Figure 5, and the steel truss Z1 will not be installed temporarily. The truss connecting beam 5 is then divided into two parts, and can be lifted from the top of the lower beam to the design position as a whole.

本发明的不局限于上述实施例所述的具体技术方案,凡采用等同替换形成的技术方案均为本发明要求的保护范围。The present invention is not limited to the specific technical solutions described in the above embodiments, and all technical solutions formed by equivalent replacement are within the scope of protection required by the present invention.

Claims (3)

1. a kind of superelevation Sarasota large span upper beam bracket steel truss stand construction method, the bracket steel truss holder includes steel truss And corbels support;This approach includes the following steps:
(1)In bridge king-post work progress, according to the installation site of the bracket steel truss holder, it is pre- that corbels support is reserved successively Embedded part, lower boom built-in fitting, top boom built-in fitting and lifting bracket built-in fitting;
(2)The welding installation lifting bracket on the lifting bracket built-in fitting;It is continuous that punching is installed on the lifting bracket Jack;
(3)At the top of the steel truss integral hoisting that ground is machined to the bottom end rail of the bridge king-post, the punching connects Continuous jack penetrates steel strand wires, and the steel strand wires bottom is connect with the suspension centre on the steel truss;
(4)Start the punching continuous jack, by the steel truss be promoted to its bottom end rail with the bridge king-post it Between can accommodate the height of the corbels support, and the steel truss is temporarily fixed on the bridge king-post;
(5)The corbels support that ground machines is lifted to below the steel truss, and with the Welding steel truss group At the bracket steel truss holder;
(6)Being fixed temporarily between the steel truss and the bridge king-post is released, and starts the punching continuous jack, Below the bracket steel truss support lift to installation site;
(7)Start the punching continuous jack, by the bracket steel truss support lift to design position, and utilizes the ox The bracket steel truss holder is weldingly fixed on the bridge tower by leg supporting embedded part, lower boom built-in fitting and top boom built-in fitting On column;
(8)Load-bearing fulcrum is installed on the corbels support built-in fitting, using lateral connection system by the bridge of bridge both sides Bracket steel truss holder connection on king-post is integral.
2. superelevation Sarasota large span upper beam bracket steel truss stand construction method according to claim 1, it is characterised in that:Institute State the rigid corbels support that corbels support is made of the lateral between double limb battered legs of steel construction and the battered leg.
3. superelevation Sarasota large span upper beam bracket steel truss stand construction method according to claim 1, it is characterised in that:Institute Steel truss is stated to be made of top boom, lower boom, montant and brace.
CN201510710052.2A 2015-10-28 2015-10-28 Construction method of steel truss support for super high cable tower with large span upper beam corbel Expired - Fee Related CN106436573B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510710052.2A CN106436573B (en) 2015-10-28 2015-10-28 Construction method of steel truss support for super high cable tower with large span upper beam corbel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510710052.2A CN106436573B (en) 2015-10-28 2015-10-28 Construction method of steel truss support for super high cable tower with large span upper beam corbel

Publications (2)

Publication Number Publication Date
CN106436573A CN106436573A (en) 2017-02-22
CN106436573B true CN106436573B (en) 2018-08-21

Family

ID=58093987

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510710052.2A Expired - Fee Related CN106436573B (en) 2015-10-28 2015-10-28 Construction method of steel truss support for super high cable tower with large span upper beam corbel

Country Status (1)

Country Link
CN (1) CN106436573B (en)

Families Citing this family (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107806019A (en) * 2017-11-07 2018-03-16 中交路桥华南工程有限公司 Large-span suspension bridge gate Sarasota construction method
CN109267498A (en) * 2018-11-28 2019-01-25 中国铁建大桥工程局集团有限公司 A kind of bridge main tower stull construction method
CN109555025B (en) * 2018-12-28 2023-10-20 中交路桥华南工程有限公司 Support system and support frame dismantling method
CN110241727A (en) * 2019-07-29 2019-09-17 中交一公局第三工程有限公司 A kind of cable tower structure and bridge
CN110512523B (en) * 2019-08-05 2022-04-15 中铁七局集团有限公司 Construction method of large-span door type upper cross beam split support
CN110886227B (en) * 2019-12-03 2021-09-14 湖北省路桥集团有限公司 Main tower cast-in-place lower cross beam support system and construction method
CN111321880B (en) * 2020-04-02 2025-03-11 中国建筑第四工程局有限公司 A high-altitude large cantilever cast-in-place structure spanning space combined load-bearing steel platform
CN111533003B (en) * 2020-06-09 2025-04-11 中铁十一局集团第一工程有限公司 A cable-stayed bridge cable installation and lifting device
CN112900269A (en) * 2021-01-12 2021-06-04 中铁七局集团武汉工程有限公司 Construction process of cable tower cross beam
CN115094767A (en) * 2022-06-28 2022-09-23 湖北棋盘洲长江公路大桥有限公司 Bracket for cable tower upper cross beam construction and cable tower upper cross beam forming method
CN116289637B (en) * 2022-09-08 2025-03-14 中铁广州工程局集团有限公司 Construction method for integrally mounting and dismounting cast-in-situ bracket of upper beam of high tower
CN116289567B (en) * 2023-01-10 2025-09-30 安徽省公路桥梁工程有限公司 High tower large span upper beam working platform and construction method
CN116411517A (en) * 2023-02-18 2023-07-11 中国铁建港航局集团有限公司 Concrete beam bracket-free integral lifting construction method
CN116575308A (en) * 2023-06-28 2023-08-11 中铁四局集团有限公司 A cable-stayed steel truss suspension cable-stiffened bridge structure with round steel damping and vibration reduction

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101446135A (en) * 2008-12-25 2009-06-03 上海市第一建筑有限公司 Integral hoisting system for superaltitude overlong jumbo beam by truss method and construction method thereof
CN103306208A (en) * 2013-07-05 2013-09-18 中南大学 Formwork creeping method for novel 1.6 parabola-shaped four-column type hollow variable section high pier
CN103898836A (en) * 2014-03-03 2014-07-02 中铁港航局集团有限公司 Method for construction of high upper beam steel oblique leg prestress support of H-shaped cable bent tower of cable-stayed bridge
JP2015098683A (en) * 2013-11-18 2015-05-28 大成建設株式会社 Temporary mount and structure construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101446135A (en) * 2008-12-25 2009-06-03 上海市第一建筑有限公司 Integral hoisting system for superaltitude overlong jumbo beam by truss method and construction method thereof
CN103306208A (en) * 2013-07-05 2013-09-18 中南大学 Formwork creeping method for novel 1.6 parabola-shaped four-column type hollow variable section high pier
JP2015098683A (en) * 2013-11-18 2015-05-28 大成建設株式会社 Temporary mount and structure construction method
CN103898836A (en) * 2014-03-03 2014-07-02 中铁港航局集团有限公司 Method for construction of high upper beam steel oblique leg prestress support of H-shaped cable bent tower of cable-stayed bridge

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
重庆寸滩长江大桥桥塔横梁支架设计与施工;胡雄伟;《世界桥梁》;20150328;第43卷(第2期);全文 *
鼓山大桥主塔上横梁支架设计与施工;马慧华等;《科技风》;20130425(第8期);第138-139页 *

Also Published As

Publication number Publication date
CN106436573A (en) 2017-02-22

Similar Documents

Publication Publication Date Title
CN106436573A (en) Construction method of steel truss support for super high cable tower with large span upper beam corbel
CN104453197B (en) High Large Cantilever concrete structural steel shape supports platform
CN109231006B (en) Construction method of lower hanging structure of steel structure truss
CN103911956B (en) A kind of large span stayed-cable bridge steel truss girder mounting method
CN204690605U (en) The self-propelled triangular truss hanging basket of large span beam bridge
CN103643800B (en) The erection & lift system of buckling-restrained bracing member and construction method thereof
CN114781026B (en) A construction control method for a single-tilted-tower cable-stayed bridge
CN104389419A (en) Cantilevered formwork platform installation structure and construction method
CN102364012A (en) Method for expanding existing large-span truss
CN103469735B (en) The installation method of the formwork of the solid section of the pier top of the hollow column and slab pier with curved superelevation
CN110656723B (en) Rail support for sliding construction of cylindrical arch shell roof
CN107604827A (en) A kind of porous large-span freely-supported steel truss girder bridge erection method
CN104805769B (en) A kind of self-balancing arc beam cast-in-place support and construction method thereof
CN103061514B (en) Long-span steel structure corridor construction method
CN102659027B (en) Variable-span transit method for girder-erecting gantry crane
CN208534068U (en) A traction-slip system for erecting prefabricated crane beams in a power plant
CN111593874B (en) Support system and construction method for super-high-rise residential transfer layer super-heavy cantilevered components
CN206233656U (en) Steel frame mill building structure
CN105220609B (en) Composite beam self-anchored suspension bridge and its construction technology
CN204282803U (en) To encorbelment formwork structure for mounting platform
CN107419670A (en) Hybrid structure of arch and beam formula continuous rigid frame bridge winds up walking cradle construction device and method
CN106758855B (en) Arc-shaped pier cap construction arch support component and arc-shaped pier cap construction method
CN105464215A (en) Reverse construction method construction method of hanging structure incapable of being provided with vertical temporary support
CN104963410B (en) Beam column of steel structure is slidably connected node
CN204418372U (en) The steel beam column venue be made up of arch component space tubular truss

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180821

CF01 Termination of patent right due to non-payment of annual fee