CN105649076A - Outer pile inner hole soil retaining flapper-type pile tip used for prestressed concrete pipe (PHC) pile sleeving construction - Google Patents
Outer pile inner hole soil retaining flapper-type pile tip used for prestressed concrete pipe (PHC) pile sleeving construction Download PDFInfo
- Publication number
- CN105649076A CN105649076A CN201410632260.0A CN201410632260A CN105649076A CN 105649076 A CN105649076 A CN 105649076A CN 201410632260 A CN201410632260 A CN 201410632260A CN 105649076 A CN105649076 A CN 105649076A
- Authority
- CN
- China
- Prior art keywords
- pile
- phc
- flapper
- stud
- flap valve
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Abstract
The invention provides an outer pile inner hole soil retaining flapper-type pile tip used for prestressed concrete pipe (PHC) pile sleeving construction. An inner PHC pile (2) is sleeved with an outer PHC pile (1). A plurality of positioning and guiding rings (3) are pre-buried in the inner wall of the outer PHC pile (1) in a spaced mode. The outer pile inner hole soil retaining flapper-type pile tip comprises the outer PHC pile and flapper baffles (6). The outer pile inner hole soil retaining flapper-type pile tip is characterized in that four hinge pin sleeves (4) are uniformly welded to the periphery of a pre-buried flange at the end of the pile head of the outer PHC pile (1); the four flapper baffles (6) are arranged, wherein the diameter of the flapper baffles (6) is equal to that of the outer PHC pile (1), and the four flapper baffles can be spliced to meet the dimension requirement for the inner diameter of the outer PHC pile (1); and hinge pins (5) are welded and fixed to the bottom ends of the flapper baffles so that the flapper baffles can be matched with the hinge pin sleeves (4), and each flapper baffle (6) can be opened downwards freely. The flapper-type pile tip has the advantages that the structure is simple, manufacturing is convenient, the outer pile can enter an inner hole in a soilless mode in the pile sinking process, the internal soil digging procedure of the outer pile is omitted, the inner pile can be piled smoothly in a sleeved mode, and the working efficiency is improved.
Description
Technical field
The present invention relates to the reinforced concrete pipe pile in a kind of pile foundation engineering, specifically, be a kind of stud endoporus gear soil flapper-type pile top for the dress construction of PHC pile protection.
Background technology
PHC stake (reinforced concrete pipe pile) is the main method of construction of structures foundation bearing, is widely used. The pile sinking process of PHC stake mainly adopts crawler type piling machine hammer piling. In the test pile of the newly-built coal yard silo project of present Baosteel plant area, have employed the pile-type of timber pile inner hole sleeve paxilla, usual this pile-type is rarely employed in pile foundation engineering.
Construction is coaling silo project by Baosteel in Coal Stack Yard, the concrete silo 30 of newly-built diameter 24m, high 46m, wall thickness 450mm in two stockyards of E/F. In the design phase of pile foundation, design has carried out the test pile of 4 kinds of pile-type together with owner, determines final Pile Foundations Design scheme. The pile-type having a kind of test pile in Pile Foundations Design test pile scheme is diameter-variable pile test, require first to squeeze into the stud of 1000mm, stud length 10 meters, soil 10 meters deep in stud need to be drawn out, play the interior stake of 600mm again in stud inner sleeve, interior stake is long 57 meters, finally pours into C30 pea gravel concreten between interior stud, after maintenance 28 days, the horizontal bearing capacity of test pile. In this testing program will by stud in soil 10 meters deep draw out, self-evident its is taken a lot of work effort, delays the test duration.
The set piling construction of therefore known timber pile inner hole sleeve paxilla also exists above-mentioned all inconvenience and problem.
Summary of the invention
The purpose of the present invention, is in that to propose not make soil enter the stud endoporus gear soil flapper-type pile top for the dress construction of PHC pile protection in outer stake holes in a kind of work progress.
For achieving the above object, the technical solution of the present invention is:
A kind of stud endoporus gear soil flapper-type pile top for the dress construction of PHC pile protection, in PHC, pile protection is contained in PHC stud, and PHC stud inwall pre-buried setting position guide ring, including PHC stud and flap valve baffle plate, it is characterised in that:
Decile 4 joint pin axle sleeves of welding on the pre-buried circumference of flange of the outer pile head end of described PHC;
Thering is provided the flap valve baffle plate that 4 lobes are identical with PHC stud diameter, make 4 lobe flap valve baffle plates can piece together the internal diameter size of PHC stud, flap valve baffle plate bottom is welded and fixed bearing pin to coordinate with joint pin axle sleeve, and makes every lobe flap valve baffle plate freely to open downwards.
The stud endoporus gear soil flapper-type pile top for the dress construction of PHC pile protection of the present invention can also be further achieved by the following technical measures.
Being previously described for the stud endoporus gear soil flapper-type pile top of PHC pile protection dress construction, in the middle of wherein said flap valve baffle plate, one reinforcement of welding increases flap valve baffle plate intensity.
Being previously described for the stud endoporus gear soil flapper-type pile top of PHC pile protection dress construction, wherein said flap valve baffle plate is >=10mm steel plate.
Being previously described for the stud endoporus gear soil flapper-type pile top of PHC pile protection dress construction, wherein, the length of described joint pin axle sleeve is 50mm.
Being previously described for the stud endoporus gear soil flapper-type pile top of PHC pile protection dress construction, the length of wherein said bearing pin is 360mm.
After adopting technique scheme, the stud endoporus gear soil flapper-type pile top for the dress construction of PHC pile protection of the present invention has the advantage that
1, flapper-type pile top simple in construction, easy to make;
2, realize stud in pile sinking without soil enter endoporus, decrease the operation of soil digging in stud make interior stake smoothly overlap beat, improve work efficiency;
3, engineering cost is reduced, it is ensured that the schedule requirement of engineering.
Accompanying drawing explanation
Fig. 1 is the structural representation during stud endoporus gear soil flapper-type pile top use state of the embodiment of the present invention;
Fig. 2 is the bottom view of the stud endoporus gear soil flapper-type pile top of the embodiment of the present invention.
In figure: 1PHC stud, stake in 2PHC, 3 positioning and guiding rings, 4 pin sleeves, 5 bearing pins, 6 flap valve baffle plates, 7 stiffened panels.
Detailed description of the invention
Below in conjunction with embodiment and accompanying drawing thereof, the present invention is illustrated further.
Embodiment 1
The stud endoporus gear soil flapper-type pile top for the dress construction of PHC pile protection of the present invention, in 600mmPHC, stake 2 is sleeved in 1000mmPHC stud 1, and PHC stud 1 inwall pre-buried setting position guide ring 3, including PHC stud and flap valve baffle plate 6.
Structural representation during state is used referring now to the stud endoporus gear soil flapper-type pile top that Fig. 1, Fig. 1 are the embodiment of the present invention. As it can be seen, 4 joint pin axle sleeves 4 of decile welding on the pre-buried circumference of flange of described PHC stud 1 pile crown end, the length of joint pin axle sleeve 4 is 50mm.
The flap valve baffle plate 6 that 4 lobes are identical with PHC stud 1 diameter is provided, make 4 lobe flap valve baffle plates can piece together the internal diameter size of PHC stud 1, flap valve baffle plate bottom is welded and fixed bearing pin 5 to coordinate with joint pin axle sleeve 4, and the length of described bearing pin 5 is 360mm, and makes every lobe flap valve baffle plate 6 freely to open downwards. Fig. 2 is the bottom view of the stud endoporus gear soil flapper-type pile top of the embodiment of the present invention, the flap valve unfolding mode that where the dotted line signifies that stud endoporus gear soil flapper-type pile top is in use washed open by stake in PHC 2. Described flap valve baffle plate 6 is 10mm steel plate, and in the middle of described flap valve baffle plate 6, one reinforcement 7 of welding increases flap valve baffle plate intensity.
Embodiment 2
The manufacture method of the stud endoporus gear soil flapper-type pile top of the embodiment of the present invention:
Pile top for the 1000mmPHC stud 1 of set piling is designed to flapper pile tip pattern, pile top adopts 10mm steel plate, and cutting into diameter is 820mm circle, then equalization is cut and is segmented into 4 lobes, every lobe welds with the hinge axis of the pre-buried flange welding of pile crown, and makes every lobe freely to open downwards. One reinforcement of welding in the middle of every flap valve, it is prevented that during pile sinking, flap valve curves inwardly, earth enters in stake holes. The remainder of the embodiment of the present invention is with embodiment 1.
Embodiment 3
The using method of the stud endoporus gear soil flapper-type pile top of the embodiment of the present invention:
First squeeze into 1000mmPHC stud 1, reach the predetermined immersed tube degree of depth, it is ensured that in work progress, soil does not enter in stake holes, squeeze into stake in 600mmPHC again, ensure that in PHC, flap valve can be effectively washed in stake 2 construction open, it is prevented that during pile sinking, flap valve curves inwardly, and earth enters in stake holes simultaneously.Positioning and guiding ring 3 in PHC stud stake holes is the pre-buried positioning and guiding ring of stud inner hole wall, plays positioning and guiding effect when interior pile protection is beaten, and is unlikely to interior stake skew, damages stud, it is ensured that the axiality of interior stud. Thus reach soil digging in the stud endoporus gear soil flapper-type pile top subduction stake of the embodiment of the present invention, save operating expenses, reduce the test pile duration. The remainder of the embodiment of the present invention is with embodiment 1.
The present invention has substantive distinguishing features and significant technological progress, the stud endoporus gear soil flapper-type pile top for the dress construction of PHC pile protection of the present invention designs stake endoporus gear soil flap valve at the pile top place of PHC 1000mm stake, ensure that in work progress, soil does not enter in stake holes, ensure that PHCF600mm pile driving construction can effectively wash flap valve open simultaneously. Soil digging in subduction stake, saves operating expenses, reduces the test pile duration.
The stud endoporus gear soil flapper-type pile top for the dress construction of PHC pile protection of the present invention is in company limited of Baogang Stocks Trading Co., coal yard E, F material strip reconstruction silo project that will go into operation, Pile Foundations Design for this project, the special experiment carrying out different type pile in construction place, use to determine in the design pile-type engineering of silo project stake, effect is notable, obtains exploiting entity, supervisor and owner's abundant affirmation.
Above example is used for illustrative purposes only, but not limitation of the present invention, person skilled in the relevant technique, without departing from the spirit and scope of the present invention, it is also possible to make various conversion or change. Therefore, all equivalent technical schemes also should belong to scope of the invention, should be limited by each claim.
Claims (5)
1. the stud endoporus gear soil flapper-type pile top for the dress construction of PHC pile protection, stake in PHC (2) is sleeved in PHC stud (1), PHC stud (1) inwall be between shape every burying some positioning and guiding rings (3) in advance underground, including PHC stud and flap valve baffle plate (6), it is characterised in that:
4 joint pin axle sleeves (4) of decile welding on the pre-buried circumference of flange of described PHC stud (1) pile crown end;
The flap valve baffle plate (6) that 4 lobes are identical with PHC stud (1) diameter is provided, make 4 lobe flap valve baffle plates can piece together the internal diameter size of PHC stud (1), flap valve baffle plate bottom is welded and fixed bearing pin (5) to coordinate with joint pin axle sleeve (4), and makes every lobe flap valve baffle plate (6) freely to open downwards.
2. the stud endoporus gear soil flapper-type pile top for the dress construction of PHC pile protection as claimed in claim 1, it is characterised in that in the middle of described flap valve baffle plate (6), one reinforcement (7) of welding increases flap valve baffle plate intensity.
3. the stud endoporus gear soil flapper-type pile top for the dress construction of PHC pile protection as claimed in claim 1, it is characterised in that described flap valve baffle plate (6) is >=10mm steel plate.
4. the stud endoporus gear soil flapper-type pile top for the dress construction of PHC pile protection as claimed in claim 1, it is characterised in that the length of described joint pin axle sleeve (4) is 50mm.
5. the stud endoporus gear soil flapper-type pile top for the dress construction of PHC pile protection as claimed in claim 1, it is characterised in that the length of described bearing pin (5) is 360mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410632260.0A CN105649076B (en) | 2014-11-11 | 2014-11-11 | A kind of stud inner hole earth-retaining flapper-type pile top for the dress construction of PHC pile protection |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201410632260.0A CN105649076B (en) | 2014-11-11 | 2014-11-11 | A kind of stud inner hole earth-retaining flapper-type pile top for the dress construction of PHC pile protection |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105649076A true CN105649076A (en) | 2016-06-08 |
CN105649076B CN105649076B (en) | 2019-03-15 |
Family
ID=56483017
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201410632260.0A Active CN105649076B (en) | 2014-11-11 | 2014-11-11 | A kind of stud inner hole earth-retaining flapper-type pile top for the dress construction of PHC pile protection |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105649076B (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108265724A (en) * | 2018-03-30 | 2018-07-10 | 中铁北京工程局集团第工程有限公司 | A kind of brill stake holes concrete secondary back cover device for casting |
CN113789755A (en) * | 2021-10-21 | 2021-12-14 | 中水东北勘测设计研究有限责任公司 | Ecological gabion cell revetment structure and construction method thereof |
CN117071556A (en) * | 2023-10-13 | 2023-11-17 | 兴化市杰俊机械有限公司 | Ocean pile driving ship |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN87205950U (en) * | 1987-03-31 | 1987-11-25 | 交通部第二航务工程局科研设计所 | Pile pipe endcover device |
JPH0280712A (en) * | 1988-09-16 | 1990-03-20 | Nippon Concrete Ind Co Ltd | All-steel-plate shoe for concrete pile and its manufacturing |
CN1221056A (en) * | 1998-11-24 | 1999-06-30 | 谢庆道 | Construction method for concrete barrel embedded in subgrade and press-in type disposable holing apparatus |
CN1600996A (en) * | 2004-10-19 | 2005-03-30 | 吴金钿 | Self-support expander of tube-sinking cast-in-situ pile |
CN102733380A (en) * | 2012-06-17 | 2012-10-17 | 张永忠 | Lag pile and construction method thereof |
CN102808409A (en) * | 2011-05-30 | 2012-12-05 | 宝山钢铁股份有限公司 | Coaxially-nested multi-section prefabricated tube pile and construction method thereof |
CN203174597U (en) * | 2013-01-15 | 2013-09-04 | 五冶集团上海有限公司 | Flap type pile point of tube-sinking cast-in-situ pile |
-
2014
- 2014-11-11 CN CN201410632260.0A patent/CN105649076B/en active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN87205950U (en) * | 1987-03-31 | 1987-11-25 | 交通部第二航务工程局科研设计所 | Pile pipe endcover device |
JPH0280712A (en) * | 1988-09-16 | 1990-03-20 | Nippon Concrete Ind Co Ltd | All-steel-plate shoe for concrete pile and its manufacturing |
CN1221056A (en) * | 1998-11-24 | 1999-06-30 | 谢庆道 | Construction method for concrete barrel embedded in subgrade and press-in type disposable holing apparatus |
CN1600996A (en) * | 2004-10-19 | 2005-03-30 | 吴金钿 | Self-support expander of tube-sinking cast-in-situ pile |
CN102808409A (en) * | 2011-05-30 | 2012-12-05 | 宝山钢铁股份有限公司 | Coaxially-nested multi-section prefabricated tube pile and construction method thereof |
CN102733380A (en) * | 2012-06-17 | 2012-10-17 | 张永忠 | Lag pile and construction method thereof |
CN203174597U (en) * | 2013-01-15 | 2013-09-04 | 五冶集团上海有限公司 | Flap type pile point of tube-sinking cast-in-situ pile |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108265724A (en) * | 2018-03-30 | 2018-07-10 | 中铁北京工程局集团第工程有限公司 | A kind of brill stake holes concrete secondary back cover device for casting |
CN108265724B (en) * | 2018-03-30 | 2023-09-15 | 中铁北京工程局集团第一工程有限公司 | Bored pile hole concrete secondary back cover pouring device |
CN113789755A (en) * | 2021-10-21 | 2021-12-14 | 中水东北勘测设计研究有限责任公司 | Ecological gabion cell revetment structure and construction method thereof |
CN117071556A (en) * | 2023-10-13 | 2023-11-17 | 兴化市杰俊机械有限公司 | Ocean pile driving ship |
CN117071556B (en) * | 2023-10-13 | 2024-02-09 | 兴化市杰俊机械有限公司 | Ocean pile driving ship |
Also Published As
Publication number | Publication date |
---|---|
CN105649076B (en) | 2019-03-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN205259190U (en) | Strenghthened type interlock stake | |
CN205399418U (en) | Sharp structure of stake that reinforcing PHC tubular pile pile sinking broke ground | |
CN101280563B (en) | Pretensioned prestressing pipe pile construction method under weak expansion soil condition | |
CN105649076A (en) | Outer pile inner hole soil retaining flapper-type pile tip used for prestressed concrete pipe (PHC) pile sleeving construction | |
CN110424383A (en) | A kind of Spiral digging machine combination side chisel head excavates square pile construction method | |
CN104480929B (en) | A kind of pile wall interaction construction method that interlocking pile is applied to permanent outer wall of basement | |
CN102828533B (en) | Vertical pressure resistance static load test pile head advanced processing node of cast-in-place pile and construction method | |
CN207277344U (en) | Guiding tool for the backfill of narrow Deep Foundation Pit Excavation | |
CN204097889U (en) | A kind of piling and the built bridge abutment structure of increase platform cap composite reinforcement | |
CN102220764A (en) | Deep foundation pit bracing system and construction method thereof | |
CN207143929U (en) | A kind of Dragsaw type steel-pipe pile | |
CN202064350U (en) | Collapsible soil hole-forming pile tube | |
CN104480947A (en) | Construction method of prestress cast-in-place pile and soil cement pile engagement support | |
CN102286976B (en) | Method for making pile foundation construction follow long steel pile casing construction in karst area | |
CN203701089U (en) | Structure for manual hole digging and pile splicing on reinforced concrete drain pipe retaining wall | |
CN203924037U (en) | Cast-in-situs type external prestressing steel tube concrete pile and supporting piling wall | |
CN209816868U (en) | Built-in truss assembled cylinder spliced pile | |
CN210636449U (en) | Prevention of seepage water structure of diaphragm wall seam crossing | |
CN204530693U (en) | The pile top anti-sticking immersed tube of castinplace pile | |
CN104099923B (en) | Cast-type external prestressing steel tube concrete pile and construction method thereof and supporting piling wall | |
CN201933496U (en) | Novel pile tip for soft clay foundation treatment | |
CN202787336U (en) | Vertical compression resistance static load test pile head advanced treatment node of pouring pile | |
CN218148318U (en) | Curtain type pile casing structure for deep sludge cement mixing pile | |
CN102155022B (en) | Construction method for immersed tube tunnel pile foundation | |
CN215367223U (en) | Pile head structure for post-grouting of rock-socketed pile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |