CN207277344U - Guiding tool for the backfill of narrow Deep Foundation Pit Excavation - Google Patents

Guiding tool for the backfill of narrow Deep Foundation Pit Excavation Download PDF

Info

Publication number
CN207277344U
CN207277344U CN201721292350.5U CN201721292350U CN207277344U CN 207277344 U CN207277344 U CN 207277344U CN 201721292350 U CN201721292350 U CN 201721292350U CN 207277344 U CN207277344 U CN 207277344U
Authority
CN
China
Prior art keywords
backfill
horizontal frame
foundation pit
deep foundation
roller
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201721292350.5U
Other languages
Chinese (zh)
Inventor
曾友明
孙青松
邓云兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Baoye Group Corp Ltd
Original Assignee
Shanghai Baoye Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Baoye Group Corp Ltd filed Critical Shanghai Baoye Group Corp Ltd
Priority to CN201721292350.5U priority Critical patent/CN207277344U/en
Application granted granted Critical
Publication of CN207277344U publication Critical patent/CN207277344U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The utility model discloses a kind of guiding tool for the backfill of narrow Deep Foundation Pit Excavation, this instrument includes horizontal frame, hopper housing and roller, the hopper housing is arranged on the horizontal frame bottom surface between two parties, and the roller is respectively arranged on horizontal frame bottom surface corner by wheel carrier.The defects of this instrument overcomes tradition to get rid of earthen backfill, avoids the fish tail and waterproof layer caused by the earthwork is impacted from failing, improves backfill quality and efficiency, reduction are done over again, reduce later stage leak stopping cost.

Description

Guiding tool for the backfill of narrow Deep Foundation Pit Excavation
Technical field
It the utility model is related to a kind of guiding tool for the backfill of narrow Deep Foundation Pit Excavation.
Background technology
With the Rapid Expansion of urban construction, building site day is becoming tight, and the project place of building is increasingly narrow, this is resulted in Gap between underground agent structure and deep foundation pit supporting structure is less and less, and usually narrow Deep Foundation Pit Excavation can only when backfilling The mode for getting rid of earthen backfill is taken, the fish tail and waterproof layer that underground agent structure is inevitably impacted during soil is got rid of, causes to prevent The damage of water conservation layer and coiled material, or even waterproof roll occur and integrally slide, add the process and cost of later stage plugging operations; Earthen backfill is got rid of at the same time and improves labor intensity, reduces backfill efficiency and quality.
The content of the invention
Technical problem to be solved in the utility model is to provide a kind of guiding work for the backfill of narrow Deep Foundation Pit Excavation The defects of tool, this instrument overcomes tradition to get rid of earthen backfill, avoid the fish tail and waterproof layer caused by the earthwork is impacted from failing, improve backfill Quality and efficiency, reduction are done over again, and reduce later stage leak stopping cost.
In order to solve the above technical problems, the guiding tool that the utility model is used for the backfill of narrow Deep Foundation Pit Excavation includes level Frame, hopper housing and roller, the hopper housing are arranged on the horizontal frame bottom surface between two parties, and the roller is distinguished by wheel carrier Arranged on horizontal frame bottom surface corner.
Further, this instrument further includes stiffener plate, and the stiffener plate is respectively arranged on the hopper housing side wall and water Between flat frame.
Further, the horizontal frame is made of I-steel welding, and the hopper housing is made of steel plate welding.
The guiding tool for being used for the backfill of narrow Deep Foundation Pit Excavation due to the utility model employs above-mentioned technical proposal, i.e., originally Instrument includes horizontal frame, hopper housing and roller, and the hopper housing is arranged on the horizontal frame bottom surface, the roller between two parties Horizontal frame bottom surface corner is respectively arranged on by wheel carrier.The defects of this instrument overcomes tradition to get rid of earthen backfill, avoids because of the earthwork Fish tail and waterproof layer caused by impact fails, and improves backfill quality and efficiency, reduction are done over again, reduce later stage leak stopping cost.
Brief description of the drawings
The utility model is described in further detail with embodiment below in conjunction with the accompanying drawings:
Fig. 1 is the guiding tool structure diagram that the utility model is used for the backfill of narrow Deep Foundation Pit Excavation;
Fig. 2 is the top view of Fig. 1.
Embodiment
As depicted in figs. 1 and 2, the guiding tool that the utility model is used for the backfill of narrow Deep Foundation Pit Excavation includes water to embodiment Flat frame 1, hopper housing 2 and roller 3, the hopper housing 2 are arranged on 1 bottom surface of horizontal frame between two parties, and the roller 3 passes through Wheel carrier 31 is respectively arranged on the 1 bottom surface corner of horizontal frame.
Preferably, this instrument further includes stiffener plate 4, the stiffener plate 4 be respectively arranged on 2 side wall of hopper housing with Between horizontal frame 1.
Preferably, the horizontal frame 1 is made of I-steel welding, and the hopper housing 2 is made of steel plate welding.
Horizontal frame 1, hopper housing 2 and roller 3 are transported to respectively needs the foundation pit side that backfills to be assembled, and when assembling adopts Coordinated with tower crane or crane.This instrument is lifted to above foundation pit after assembling, and roller 3 is seated underground main body knot respectively 6 top surface of Guan Liang of 5 top surface of structure wall and foundation pit supporting construction.This instrument can get rid of soil to funnel chamber after installation is complete using digging machine In body 2, in hopper housing 2 earthwork fall into and backfilling of earthwork realized in foundation pit, during which slowly promoted by roller 3 using hand fit This instrument so that hopper housing 2 is moved along foundation pit, reaches the requirement of cubic metre of earth back-filling in layers., can be by this work after the completion of backfilling of earthwork Tool is removed on Integral lifting to level land, and when dismounting first tears roller 3 open, then removes hopper housing 2, finally tears horizontal frame 1 open, with It is standby to reuse again.
It can solve the problems, such as that backfill impacts waterproof layer well using this instrument, avoid the waterproof caused by the earthwork is impacted Failure, improves backfill quality, and reduction is done over again, and reduces later stage leak stopping cost.This tool construction is simple, easy to make, can be once Processing, recycling, achievees the purpose that to reduce construction cost.

Claims (3)

  1. A kind of 1. guiding tool for the backfill of narrow Deep Foundation Pit Excavation, it is characterised in that:This instrument includes horizontal frame, funnel Cavity and roller, the hopper housing are arranged on the horizontal frame bottom surface between two parties, and the roller is respectively arranged on described by wheel carrier Horizontal frame bottom surface corner.
  2. 2. the guiding tool according to claim 1 for the backfill of narrow Deep Foundation Pit Excavation, it is characterised in that:This instrument is also Including stiffener plate, the stiffener plate is respectively arranged between the hopper housing side wall and horizontal frame.
  3. 3. the guiding tool according to claim 1 for the backfill of narrow Deep Foundation Pit Excavation, it is characterised in that:The level Frame is made of I-steel welding, and the hopper housing is made of steel plate welding.
CN201721292350.5U 2017-10-09 2017-10-09 Guiding tool for the backfill of narrow Deep Foundation Pit Excavation Expired - Fee Related CN207277344U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721292350.5U CN207277344U (en) 2017-10-09 2017-10-09 Guiding tool for the backfill of narrow Deep Foundation Pit Excavation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721292350.5U CN207277344U (en) 2017-10-09 2017-10-09 Guiding tool for the backfill of narrow Deep Foundation Pit Excavation

Publications (1)

Publication Number Publication Date
CN207277344U true CN207277344U (en) 2018-04-27

Family

ID=61988752

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721292350.5U Expired - Fee Related CN207277344U (en) 2017-10-09 2017-10-09 Guiding tool for the backfill of narrow Deep Foundation Pit Excavation

Country Status (1)

Country Link
CN (1) CN207277344U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109469073A (en) * 2018-11-13 2019-03-15 上海建工五建集团有限公司 Sliding slot equipment and its construction method, the construction method of stemming operation
CN109537664A (en) * 2018-12-06 2019-03-29 安徽省人防建筑设计研究院 A kind of civil air defense constructions and installations building backfilling apparatus
CN113846655A (en) * 2021-10-12 2021-12-28 中国建筑第八工程局有限公司 Conveying device suitable for backfill blanking of narrow ultra-deep foundation trench

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109469073A (en) * 2018-11-13 2019-03-15 上海建工五建集团有限公司 Sliding slot equipment and its construction method, the construction method of stemming operation
CN109469073B (en) * 2018-11-13 2024-01-05 上海建工五建集团有限公司 Chute equipment and construction method thereof, and construction method of backfilling engineering
CN109537664A (en) * 2018-12-06 2019-03-29 安徽省人防建筑设计研究院 A kind of civil air defense constructions and installations building backfilling apparatus
CN113846655A (en) * 2021-10-12 2021-12-28 中国建筑第八工程局有限公司 Conveying device suitable for backfill blanking of narrow ultra-deep foundation trench
CN113846655B (en) * 2021-10-12 2022-10-18 中国建筑第八工程局有限公司 Conveying device suitable for backfill blanking of narrow ultra-deep foundation trench

Similar Documents

Publication Publication Date Title
CN108442382B (en) In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method
CN207277344U (en) Guiding tool for the backfill of narrow Deep Foundation Pit Excavation
CN103526766B (en) Method for plugging relief well of deep foundation pit
CN203625893U (en) Rock-embedded cast-in-place pile
CN103437339A (en) Construction method for sealing karst cave near trench wall of underground continuous wall in karst stratum
CN105239598A (en) Integral sinking construction method for well-type full-automatic stereo garage
CN105863648A (en) Underground-excavation shallow-covering large-cross-section tunnel construction method
CN105019913A (en) Base rock uplift region shielding tool-changing in-situ reinforcement method
CN105569062A (en) Dewatering method implemented through permeation, weakening and emission reduction
CN101864962A (en) Soft soil layer channel freezing underground excavation in-situ remediation construction method
CN212641468U (en) Pit-in-pit rapid construction structure
CN111764396A (en) Construction method for water-rich stratum pit-in-pit
CN111139854A (en) Construction method for treating piping of exploration hole of foundation pit by drainage grouting method
CN104594367B (en) A kind of combined type cofferdam structure and construction method
CN103953054B (en) A kind of dry sealing concrete pile foundation and construction method thereof protecting pile crown reinforcing bar
CN106088124A (en) A kind of deep basal pit base plate exterior wall blind drainage secondary utilization method and structure
CN110747861A (en) High-water-level deep foundation pit excavation construction method
CN112854198B (en) Construction method for treating old foundation of underground diaphragm wall
CN204877485U (en) Basement rock massif shield constructs tool changing normal position reinforced structure
CN106988330A (en) Soft soil foundation is layered dewatering construction structure and construction method
CN106013198A (en) Gap pretreatment construction method for foundation pit support structure
CN203960881U (en) The inner pressure-bearing dewatering well of foundation ditch steel sleeve flange connecting apparatus
CN202787293U (en) Open caisson construction device
CN108019211B (en) Water-intercepting curtain in pilot tunnel of water-rich sandy pebble stratum and construction method thereof
CN108661669B (en) It is a kind of suitable for Shallow-buried section and under wear the method for tunnel construction of shallow-buried water-rich section

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20180427