CN105369742B - 适用于顶推法施工的与永久支座合一的滚动支承 - Google Patents
适用于顶推法施工的与永久支座合一的滚动支承 Download PDFInfo
- Publication number
- CN105369742B CN105369742B CN201510660741.7A CN201510660741A CN105369742B CN 105369742 B CN105369742 B CN 105369742B CN 201510660741 A CN201510660741 A CN 201510660741A CN 105369742 B CN105369742 B CN 105369742B
- Authority
- CN
- China
- Prior art keywords
- bearing
- screw
- shell
- applicable
- incremental launching
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
- E01D21/06—Methods or apparatus specially adapted for erecting or assembling bridges by translational movement of the bridge or bridge sections
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
- Rolling Contact Bearings (AREA)
Abstract
一种适用于顶推法施工的与永久支座合一的滚动支承。其包括多个铸钢滚轴、标准砂、滑板、外壳、普通支座、多个螺丝和多根钢柱;其中外壳为上端形成有开口的箱体结构,下端固定在普通支座的上端,并且每个侧面下部至少形成有一个螺孔,且利用螺丝封堵住螺孔,内部装有标准砂;多根钢柱的下端相隔距离固定在外壳的底面上;滑板放置在外壳内标准砂的表面;多个铸钢滚轴分成多列并排设置在滑板的表面。本发明提供的适用于顶推法施工的与永久支座合一的滚动支承可以减小顶推过程中产生的摩擦力,从而减小桥墩的水平位移。另外,本装置结构设计合理、简单、成本低、使用方便,因此能够简化施工操作工艺、省工、省时。
Description
技术领域
本发明属于桥梁设计及建造技术领域,特别是涉及一种适用于顶推法施工的与永久支座合一的滚动支承。
背景技术
顶推法多应用于预应力钢筋混凝土等截面连续梁桥和斜拉桥梁的施工,系指梁体在桥头逐段浇筑或拼装,用千斤顶纵向顶推,使梁体通过各墩顶的临时滑动支座面就位的施工方法。在顶推法施工中,支撑系统分为临时滑动支承和与永久支座合一的滑动支承。使用临时滑动支承顶推时,在主梁顶推就位后需用千斤顶将主梁顶起,然后拆除滑道及滑道底座混凝土垫块,再安放正式支座,此施工工艺的缺点是比较复杂。虽然使用与永久支座合一的滑动支承顶推时可以简化施工工艺,但是此装置结构复杂、造价高,因此在我国采用顶推法施工时多采用临时滑动支承。另外,在上述两种支承系统中产生的均是滑动摩擦,与滚动摩擦相比摩擦较大。由于摩擦产生的水平力会引起桥墩的水平位移,因此会对桥墩产生不利影响,特别是对柔性桥墩产生的影响较大。
发明内容
为了解决上述问题,本发明的目的在于提供一种适用于顶推法施工的与永久支座合一的滚动支承。
为了达到上述目的,本发明提供的适用于顶推法施工的与永久支座合一的滚动支承包括多个铸钢滚轴、标准砂、滑板、外壳、普通支座、多个螺丝和多根钢柱;其中外壳为上端形成有开口的箱体结构,下端固定在普通支座的上端,并且每个侧面下部至少形成有一个螺孔,且利用螺丝封堵住螺孔,内部装有标准砂;多根钢柱的下端相隔距离固定在外壳的底面上;滑板放置在外壳内标准砂的表面;多个铸钢滚轴分成多列并排设置在滑板的表面。
所述的外壳的底部为中间高四周低的斜面。
所述的外壳侧面上的螺孔数量、位置相同且大小相等。
所述的多个铸钢滚轴分成三列设置,每个铸钢滚轴的直径为30mm。
本发明提供的适用于顶推法施工的与永久支座合一的滚动支承可以减小顶推过程中产生的摩擦力,从而减小桥墩的水平位移。另外,本装置结构设计合理、简单、成本低、使用方便,因此能够简化施工操作工艺、省工、省时。
附图说明
图1为本发明提供的适用于顶推法施工的与永久支座合一的滚动支承结构俯视图。
图2为图1中I3—I3向剖视图。
图3为图1中I4—I4向剖视图。
具体实施方式
下面结合附图和具体实施例对本发明提供的适用于顶推法施工的与永久支座合一的滚动支承进行详细说明。
如图1—图3所示,本发明提供的适用于顶推法施工的与永久支座合一的滚动支承包括多个铸钢滚轴1、标准砂6、滑板3、外壳7、普通支座8、多个螺丝10和多根钢柱11;其中外壳7为上端形成有开口的箱体结构,下端固定在普通支座8的上端,并且每个侧面下部至少形成有一个螺孔,且利用螺丝10封堵住螺孔,内部装有标准砂6;多根钢柱11的下端相隔距离固定在外壳7的底面上;滑板3放置在外壳7内标准砂6的表面;多个铸钢滚轴1分成多列并排设置在滑板3的表面。
所述的外壳7的底部为中间高四周低的斜面,以便于标准砂6向外流出。
所述的外壳7侧面上的螺孔数量、位置相同且大小相等,这样有利于标准砂6流出过程中滑板3均匀下降。
所述的多个铸钢滚轴1分成三列设置,每个铸钢滚轴的直径为30mm。
现将本发明提供的适用于顶推法施工的与永久支座合一的滚动支承使用方法阐述如下:首先由施工人员在外壳7内灌入标准砂6并压实压平,然后在其上放置滑板3,使滑板3上的铸钢滚轴1露在外壳7的上端外部,然后开始进行顶推作业,顶推完成后拧开螺丝11使标准砂6通过螺孔向外流出,这时滑板3将落在钢柱11上,待标准砂6全部流出后将水泥浆灌入螺孔进行封孔即可。
Claims (4)
1.一种适用于顶推法施工的与永久支座合一的滚动支承,其特征在于:其包括、标准砂(6)、滑板(3)、外壳(7)、普通支座(8)、多个螺丝(10)、多根钢柱(11)和多个铸钢滚轴(1);其中外壳(7)为上端形成有开口的箱体结构,下端固定在普通支座(8)的上端,并且每个侧面下部至少形成有一个螺孔,且利用螺丝(10)封堵住螺孔,内部装有标准砂(6);多根钢柱(11)的下端相隔距离固定在外壳(7)的底面上;滑板(3)放置在外壳(7)内标准砂(6)的表面;多个铸钢滚轴(1)分成多列并排设置在滑板(3)的表面。
2.根据权利要求1所述的适用于顶推法施工的与永久支座合一的滚动支承,其特征在于:所述的外壳(7)的底部为中间高四周低的斜面。
3.根据权利要求1所述的适用于顶推法施工的与永久支座合一的滚动支承,其特征在于:所述的外壳(7)侧面上的螺孔数量、位置相同且大小相等。
4.根据权利要求1所述的适用于顶推法施工的与永久支座合一的滚动支承,其特征在于:所述的多个铸钢滚轴(1)分成三列设置,每个铸钢滚轴的直径为30mm。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510660741.7A CN105369742B (zh) | 2015-10-14 | 2015-10-14 | 适用于顶推法施工的与永久支座合一的滚动支承 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510660741.7A CN105369742B (zh) | 2015-10-14 | 2015-10-14 | 适用于顶推法施工的与永久支座合一的滚动支承 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN105369742A CN105369742A (zh) | 2016-03-02 |
CN105369742B true CN105369742B (zh) | 2016-11-30 |
Family
ID=55372331
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510660741.7A Expired - Fee Related CN105369742B (zh) | 2015-10-14 | 2015-10-14 | 适用于顶推法施工的与永久支座合一的滚动支承 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105369742B (zh) |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1784824A1 (de) * | 1968-09-23 | 1971-12-02 | Krupp Gmbh | Lager fuer Bruecken und andere Bauwerke |
JP2006283323A (ja) * | 2005-03-31 | 2006-10-19 | Oriental Construction Co Ltd | 橋梁の押出架設装置 |
CN201317909Y (zh) * | 2008-10-23 | 2009-09-30 | 中铁十一局集团第二工程有限公司 | 一种桥梁临时支座 |
CN102080356A (zh) * | 2010-12-17 | 2011-06-01 | 中铁大桥局集团第四工程有限公司 | 一种箱梁定位临时支座及箱梁定位施工方法 |
CN202644412U (zh) * | 2012-06-05 | 2013-01-02 | 中铁工程设计咨询集团有限公司 | 桥梁顶推用主梁限位及纠偏一体化装置 |
CN203603043U (zh) * | 2013-11-27 | 2014-05-21 | 中铁第四勘察设计院集团有限公司 | 永临结合转体支座系统 |
CN104278624A (zh) * | 2014-10-10 | 2015-01-14 | 宁波工程学院 | 一种变高程桥梁支座 |
-
2015
- 2015-10-14 CN CN201510660741.7A patent/CN105369742B/zh not_active Expired - Fee Related
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE1784824A1 (de) * | 1968-09-23 | 1971-12-02 | Krupp Gmbh | Lager fuer Bruecken und andere Bauwerke |
JP2006283323A (ja) * | 2005-03-31 | 2006-10-19 | Oriental Construction Co Ltd | 橋梁の押出架設装置 |
CN201317909Y (zh) * | 2008-10-23 | 2009-09-30 | 中铁十一局集团第二工程有限公司 | 一种桥梁临时支座 |
CN102080356A (zh) * | 2010-12-17 | 2011-06-01 | 中铁大桥局集团第四工程有限公司 | 一种箱梁定位临时支座及箱梁定位施工方法 |
CN202644412U (zh) * | 2012-06-05 | 2013-01-02 | 中铁工程设计咨询集团有限公司 | 桥梁顶推用主梁限位及纠偏一体化装置 |
CN203603043U (zh) * | 2013-11-27 | 2014-05-21 | 中铁第四勘察设计院集团有限公司 | 永临结合转体支座系统 |
CN104278624A (zh) * | 2014-10-10 | 2015-01-14 | 宁波工程学院 | 一种变高程桥梁支座 |
Also Published As
Publication number | Publication date |
---|---|
CN105369742A (zh) | 2016-03-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203393606U (zh) | 一种顶进框构桥线路加固滚动支座 | |
CN106223354B (zh) | 浅基础结构模板的施工方法 | |
CN204126263U (zh) | 一种梁、墙预埋水平套管固定装置 | |
CN203593946U (zh) | 一种阻尼型防落梁装置 | |
CN204023424U (zh) | 一种挂篮油顶反压机构 | |
CN207122129U (zh) | 一种用于楼板含梁、板结构建筑的早拆体系 | |
CN204455856U (zh) | 一种预制墩台的强制就位机构 | |
CN105369742B (zh) | 适用于顶推法施工的与永久支座合一的滚动支承 | |
CN103541300A (zh) | 基于平推法实施的铁路混凝土连续梁及其施工方法 | |
CN202954289U (zh) | 用于连续刚构桥在中跨合龙后顶推起拱的墩底布设结构 | |
EA201101049A1 (ru) | Устройство для усиления несущих конструкций | |
CN209211938U (zh) | 一种顶升限位装置 | |
CN103806923A (zh) | 钢模台车的平移机构 | |
CN203742198U (zh) | 建筑物整体移位滑移装置 | |
CN203498743U (zh) | 一种基于平推法实施的铁路混凝土连续梁 | |
CN203716990U (zh) | 钢模台车的平移机构 | |
CN103696358B (zh) | 一种地震加速度激活的多跨桥梁桥减震装置 | |
CN105239512A (zh) | 适用于顶推法施工的临时滚动支承 | |
CN106223203A (zh) | 钢梁安装支架及其使用方法 | |
CN202830950U (zh) | 铁路门式框架桥顶进限位滑道 | |
Zhao et al. | Buckling failure analysis of truck mounted concrete pump's retractable outrigger | |
CN203346804U (zh) | 桥梁整体驮运的精确定位装置 | |
CN203639940U (zh) | 水利工程挡土墙 | |
CN202882946U (zh) | 随隧道增高段加高模板台车用的活动模块 | |
CN206527866U (zh) | 滚轴式箱梁钢内模安装台车 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |