CN105239512A - 适用于顶推法施工的临时滚动支承 - Google Patents

适用于顶推法施工的临时滚动支承 Download PDF

Info

Publication number
CN105239512A
CN105239512A CN201510660744.0A CN201510660744A CN105239512A CN 105239512 A CN105239512 A CN 105239512A CN 201510660744 A CN201510660744 A CN 201510660744A CN 105239512 A CN105239512 A CN 105239512A
Authority
CN
China
Prior art keywords
plate
rolling bearing
hydraulic jack
steel plate
incremental launching
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510660744.0A
Other languages
English (en)
Inventor
李自林
薛江
刘鹏
吴煜哲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Chengjian University
Original Assignee
Tianjin Chengjian University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Chengjian University filed Critical Tianjin Chengjian University
Priority to CN201510660744.0A priority Critical patent/CN105239512A/zh
Publication of CN105239512A publication Critical patent/CN105239512A/zh
Pending legal-status Critical Current

Links

Abstract

一种适用于顶推法施工的临时滚动支承。其包括多个铸钢滚轴、液压千斤顶、滑板、两个限位板和固定钢板;其中固定钢板水平设置,每个角部连接在一个桥墩顶面的预埋件上;液压千斤顶的下端安装在固定钢板的表面中部;限位板为垂直设置的U形板,两个限位板以开口相对的方式设在固定钢板表面外侧部位;滑板水平设置在由两个限位板围成的空间上部,并且底面中部固定在液压千斤顶上;多个铸钢滚轴分成多列并排设置在滑板的表面。本发明可以减小顶推过程中产生的摩擦力,从而减小桥墩的水平位移;还可以通过液压千斤顶的升降调整梁底标高。另外,本装置结构设计合理、简单、成本低、使用方便,因此能够简化施工操作工艺、省工、省时。

Description

适用于顶推法施工的临时滚动支承
技术领域
本发明属于桥梁设计及建造技术领域,特别是涉及一种适用于顶推法施工的临时滚动支承。
背景技术
顶推法多应用于预应力钢筋混凝土等截面连续梁桥和斜拉桥梁的施工,系指梁体在桥头逐段浇筑或拼装,用千斤顶纵向顶推,使梁体通过各墩顶的临时滑动支座面就位的施工方法。在顶推法施工中,支撑系统分为临时滑动支承和与永久支座合一的滑动支承。使用临时滑动支承顶推时,在主梁顶推就位后需用千斤顶将主梁顶起,然后拆除滑道及滑道底座混凝土垫块,再安放正式支座,此施工工艺的缺点是比较复杂。虽然使用与永久支座合一的滑动支承顶推时可以简化施工工艺,但是此装置结构复杂、造价高,因此在我国采用顶推法施工时多采用临时滑动支承。另外,在上述两种支承系统中产生的均是滑动摩擦,与滚动摩擦相比摩擦较大。由于摩擦产生的水平力会引起桥墩的水平位移,因此会对桥墩产生不利影响,特别是对柔性桥墩产生的影响较大。
发明内容
为了解决上述问题,本发明的目的在于提供一种适用于顶推法施工的临时滚动支承。
为了达到上述目的,本发明提供的适用于顶推法施工的临时滚动支承包括多个铸钢滚轴、液压千斤顶、滑板、两个限位板和固定钢板;其中固定钢板水平设置,每个角部连接在一个桥墩顶面的预埋件上;液压千斤顶的下端安装在固定钢板的表面中部;限位板为垂直设置的U形板,两个限位板以开口相对的方式设在固定钢板表面外侧部位;滑板水平设置在由两个限位板围成的空间上部,并且底面中部固定在液压千斤顶上;多个铸钢滚轴分成多列并排设置在滑板的表面。
所述的多个铸钢滚轴分成三列设置,每个铸钢滚轴的直径为30mm。
本发明提供的适用于顶推法施工的临时滚动支承可以减小顶推过程中产生的摩擦力,从而减小桥墩的水平位移;还可以通过液压千斤顶的升降调整梁底标高。另外,本装置结构设计合理、简单、成本低、使用方便,因此能够简化施工操作工艺、省工、省时。
附图说明
图1为本发明提供的适用于顶推法施工的临时滚动支承结构俯视图。
图2为图1中I1—I1向剖视图。
图3为图1中I2—I2向剖视图。
具体实施方式
下面结合附图和具体实施例对本发明提供的适用于顶推法施工的临时滚动支承进行详细说明。
如图1—图3所示,本发明提供的适用于顶推法施工的临时滚动支承包括多个铸钢滚轴1、液压千斤顶2、滑板3、两个限位板4和固定钢板5;其中固定钢板5水平设置,每个角部连接在一个桥墩顶面的预埋件9上;液压千斤顶2的下端安装在固定钢板5的表面中部;限位板4为垂直设置的U形板,两个限位板4以开口相对的方式设在固定钢板5表面外侧部位;滑板3水平设置在由两个限位板4围成的空间上部,并且底面中部固定在液压千斤顶2上;多个铸钢滚轴1分成多列并排设置在滑板3的表面。
所述的多个铸钢滚轴1分成三列设置,每个铸钢滚轴的直径为30mm。
现将本发明提供的适用于顶推法施工的临时滚动支承使用方法阐述如下:首先由施工人员将临时滚动支承上的固定钢板5角部固定在桥墩顶面的预埋件9上,当需要顶推时,启动液压千斤顶2以使其上推杆向外伸出,由此抬升滑板3,从而使铸钢滚轴1露出限位板4,这时就可以开始进行顶推作业。作业结束后,待安放好正式支座后使液压千斤顶2回落,这时梁底将支承在永久支座上,最后回收本临时滚动支承。

Claims (2)

1.一种适用于顶推法施工的临时滚动支承,其特征在于:所述的适用于顶推法施工的临时滚动支承包括多个铸钢滚轴(1)、液压千斤顶(2)、滑板(3)、两个限位板(4)和固定钢板(5);其中固定钢板(5)水平设置,每个角部连接在一个桥墩顶面的预埋件(9)上;液压千斤顶(2)的下端安装在固定钢板(5)的表面中部;限位板(4)为垂直设置的U形板,两个限位板(4)以开口相对的方式设在固定钢板(5)表面外侧部位;滑板(3)水平设置在由两个限位板(4)围成的空间上部,并且底面中部固定在液压千斤顶(2)上;多个铸钢滚轴(1)分成多列并排设置在滑板(3)的表面。
2.根据权利要求1所述的适用于顶推法施工的临时滚动支承,其特征在于:所述的多个铸钢滚轴(1)分成三列设置,每个铸钢滚轴的直径为30mm。
CN201510660744.0A 2015-10-14 2015-10-14 适用于顶推法施工的临时滚动支承 Pending CN105239512A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510660744.0A CN105239512A (zh) 2015-10-14 2015-10-14 适用于顶推法施工的临时滚动支承

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510660744.0A CN105239512A (zh) 2015-10-14 2015-10-14 适用于顶推法施工的临时滚动支承

Publications (1)

Publication Number Publication Date
CN105239512A true CN105239512A (zh) 2016-01-13

Family

ID=55037313

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510660744.0A Pending CN105239512A (zh) 2015-10-14 2015-10-14 适用于顶推法施工的临时滚动支承

Country Status (1)

Country Link
CN (1) CN105239512A (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108625271A (zh) * 2018-06-29 2018-10-09 李坤华 一种连续梁桥及其采用顶推施工的方法

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS49143971U (zh) * 1973-04-10 1974-12-12
WO2000073589A1 (fr) * 1999-06-01 2000-12-07 Freyssinet International (Stup) Dispositif pour soutenir une charge mobile
CN2797277Y (zh) * 2005-06-16 2006-07-19 郑州华龙机械工程有限公司 辊子式重物移动装置
CN201420240Y (zh) * 2009-05-07 2010-03-10 中铁四局集团第四工程有限公司 可调同步液压支座滑道
CN201671064U (zh) * 2010-06-04 2010-12-15 北京城建道桥建设集团有限公司 滚排滑道
CN101974883A (zh) * 2010-10-14 2011-02-16 中铁九局集团有限公司 桥梁拖拉滑道装置
CN202644412U (zh) * 2012-06-05 2013-01-02 中铁工程设计咨询集团有限公司 桥梁顶推用主梁限位及纠偏一体化装置
CN203921799U (zh) * 2014-06-26 2014-11-05 郑州星航耐磨材料科技有限公司 滚轮组合式重物移动装置

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS49143971U (zh) * 1973-04-10 1974-12-12
WO2000073589A1 (fr) * 1999-06-01 2000-12-07 Freyssinet International (Stup) Dispositif pour soutenir une charge mobile
CN2797277Y (zh) * 2005-06-16 2006-07-19 郑州华龙机械工程有限公司 辊子式重物移动装置
CN201420240Y (zh) * 2009-05-07 2010-03-10 中铁四局集团第四工程有限公司 可调同步液压支座滑道
CN201671064U (zh) * 2010-06-04 2010-12-15 北京城建道桥建设集团有限公司 滚排滑道
CN101974883A (zh) * 2010-10-14 2011-02-16 中铁九局集团有限公司 桥梁拖拉滑道装置
CN202644412U (zh) * 2012-06-05 2013-01-02 中铁工程设计咨询集团有限公司 桥梁顶推用主梁限位及纠偏一体化装置
CN203921799U (zh) * 2014-06-26 2014-11-05 郑州星航耐磨材料科技有限公司 滚轮组合式重物移动装置

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108625271A (zh) * 2018-06-29 2018-10-09 李坤华 一种连续梁桥及其采用顶推施工的方法

Similar Documents

Publication Publication Date Title
CN103924522B (zh) 用于高架、桥梁安装的顶推装置及其顶推方法
CN203613546U (zh) 超大型基坑中钢筋混凝土内支撑的应变补偿装置
CN204266134U (zh) 重载大跨度钢桁梁步履式顶推装置
CN103911953B (zh) 用于高架、桥梁安装的组合顶推装置及其不间歇顶推方法
CN202248941U (zh) 大型钢构件的整体提升就位安装装置
CN111395798A (zh) 杠杆式顶紧固定的建筑物导轨平移装置及施工方法
CN105201219A (zh) 一种结构同步卸载装置及其施工方法
CN201671064U (zh) 滚排滑道
CN103397603B (zh) 桥梁磁悬浮顶推系统及两阶段悬臂建造方法
CN108691277A (zh) 用于节段预制拼装梁在架设过程中定位的三维调整工装
CN105239512A (zh) 适用于顶推法施工的临时滚动支承
CN103952977A (zh) 用于高架、桥梁安装的组合顶推装置及其同步顶推方法
CN203361028U (zh) 铁路及高速铁路组合桥梁磁悬浮顶推系统
CN202954289U (zh) 用于连续刚构桥在中跨合龙后顶推起拱的墩底布设结构
CN204371359U (zh) 一种用于隧道水沟电缆槽砼灌注施工的台车
CN208632979U (zh) 用于节段预制拼装梁在架设过程中定位的三维调整工装
CN201121294Y (zh) 一种液压平推装置
CN203403366U (zh) 一种基座钢锚箱三向式定位装置
CN105369742A (zh) 适用于顶推法施工的与永久支座合一的滚动支承
CN205012596U (zh) 一种防地面不均匀沉降结构
CN203346804U (zh) 桥梁整体驮运的精确定位装置
CN203361019U (zh) 一种用于公路铁路桥梁施工的t梁抬梁装置
CN103911955B (zh) 用于大跨度钢结构施工的液压支架装置及其使用方法
CN204455848U (zh) 大型钢箱梁的安装调位系统
CN203429792U (zh) 一种钢结构整体滑移装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20160113