CN105155560A - Protecting structure and protecting method used for greening high-steep rock slope - Google Patents

Protecting structure and protecting method used for greening high-steep rock slope Download PDF

Info

Publication number
CN105155560A
CN105155560A CN201510649472.4A CN201510649472A CN105155560A CN 105155560 A CN105155560 A CN 105155560A CN 201510649472 A CN201510649472 A CN 201510649472A CN 105155560 A CN105155560 A CN 105155560A
Authority
CN
China
Prior art keywords
side slope
rock slope
holdfast
wire gauze
integument
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201510649472.4A
Other languages
Chinese (zh)
Inventor
张艳
王铁
杨家富
张光权
欧哲
邹明
陈雷
李强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hong Da Guo Yuan (wuhu) Resources And Environment Management Co Ltd
Original Assignee
Hong Da Guo Yuan (wuhu) Resources And Environment Management Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hong Da Guo Yuan (wuhu) Resources And Environment Management Co Ltd filed Critical Hong Da Guo Yuan (wuhu) Resources And Environment Management Co Ltd
Priority to CN201510649472.4A priority Critical patent/CN105155560A/en
Publication of CN105155560A publication Critical patent/CN105155560A/en
Pending legal-status Critical Current

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A10/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE at coastal zones; at river basins
    • Y02A10/23Dune restoration or creation; Cliff stabilisation

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

The invention discloses a protecting structure and protecting method used for greening a high-steep rock slope and belongs to the technical field of high-steep rock slope protecting and greening. The protecting structure comprises cylindrical wrapping layers, and the wrapping layers are made of cloth materials and filled with base material mixtures. A plurality of cylindrical iron wire rings are uniformly distributed outside each wrapping layer. The protecting structure further comprises U-shaped ground anchors which penetrate through the wrapping layers and are connected with the slope in an inserting mode. Each U-shaped ground anchor is connected with the two corresponding wrapping layers in an inserting mode. The protecting structure is simple, and the protecting method is convenient to operate. The high-steep rock slope is protected and greened by using a cylindrical long-strip-shaped steel wire mesh device, on one hand, the stability of the high-steep rock slope is guaranteed, and on the other hand, on-site growing conditions for green recovery of the high-steep rock slope are provided; the establishment of an ecological green recovery system and landscape remaking can be achieved effectively, permanent protection can be achieved, and attractiveness and durability are achieved.

Description

A kind of safeguard structure for greening high precipitous rock slope and means of defence
Technical field
The present invention relates to a kind of safeguard structure for greening high precipitous rock slope and means of defence, belong to high precipitous rock slope protection and greening technique field.
Background technology
At present, slope of highway, the protection of the both sides side slope on railway slope, riverbank generally uses concrete, building block etc. by whole domatic to fixing, sometimes use antislide pile be placed on domatic before, although slope instability and soil erosion can be prevented well, but affect whole domatic attractive in appearance, cause certain visual pollution.For the Slope greening technology of alien earth sparging, when easily affecting by gravity and rainwater, the base material sprayed easily is washed, thickness of sowing grass seeds by duster does not reach requirement, cause necessarily sow grass seeds by duster base material waste and soil erosion, and high gradient slope land occupation condition is poor, vegetation is difficult to survive, and is unfavorable for overall multiple green and landscape effect.
Summary of the invention
For solving the problem, the invention provides a kind of structure simple, easy to operate greening high precipitous rock slope safeguard structure and method.
The technical scheme that the present invention adopts for its problem of solution is:
For a safeguard structure for greening high precipitous rock slope, comprise be made up of cloth material, inside is filled with the cylindrical integument of base material mixture, is evenly distributed with some columned iron wire loops outside described integument; Also comprise and run through described integument and the U-shaped holdfast be plugged in side slope, U-shaped holdfast is plugged with two integuments.
Preferably, the prismatic wire gauze be arranged between described integument and side slope face is also comprised.
Preferably, the distance on described prismatic wire gauze and side slope surface is less than 5cm.
Preferably, the straight holdfast be plugged on by described prismatic wire gauze in side slope is also comprised.
Preferably, in the scope of 1 ㎡ ~ 1.2 ㎡, a straight holdfast is at least set.
For a means of defence for greening high precipitous rock slope, comprise the following steps:
A, arrangement, cleaning side slope face;
B, prismatic wire gauze is set on side slope face, and makes the distance between prismatic wire gauze and side slope face be less than 5cm;
C, run through prismatic wire gauze with straight holdfast, prismatic wire gauze is fixed on side slope face, and in the scope of 1 ㎡ ~ 1.2 ㎡, a straight holdfast is at least set;
D, make many columned iron wire loops, connect successively, form a cylinder;
E, make integument by geotextiles, and fill base material mixture in integument;
F, run through integument and rhombus wire gauze with U-shaped holdfast, be fixed on side slope face.
The invention has the beneficial effects as follows: structure is simple, easy to operate, by to protect high precipitous rock slope with cylindrical strip gauze wire cloth device and afforest, ensure that the stability of high gradient slope on the one hand, on the spot growth conditions is provided on the other hand for high precipitous rock slope is multiple green, can effectively reach zoology green-recovery system constructing and reshaping of landscape, can permanent protection be realized, attractive and durable.
Accompanying drawing explanation
Below in conjunction with drawings and Examples, the invention will be further described:
Fig. 1 is structural representation of the present invention;
Fig. 2 is scheme of installation of the present invention.
In figure: 1, side slope face; 2, prismatic wire gauze; 3, straight holdfast; 4, iron wire loop; 5, U-shaped holdfast; 6, integument; 7, base material mixture.
Detailed description of the invention
A kind of safeguard structure for greening high precipitous rock slope as shown in accompanying drawing 1,2, comprise be made up of cloth material, inside is filled with the cylindrical integument 6 of base material mixture 7, described base material mixture 7 comprises seed, turfy soil, humus soil, grass fiber, adhesive, water-loss reducer, fertilizer etc.Be evenly distributed with some columned iron wire loops 4 outside described integument 6, several iron wire loops 4 connect formation cylinder successively, and the diameter of cylinder is about 10cm.This structure also comprises and runs through described integument 6 and the U-shaped holdfast 5 be plugged on side slope face 1, and U-shaped holdfast 5 is about 30cm, U-shaped holdfast 5 is plugged with two integuments 6.M type holdfast can certainly be adopted, just can grafting three integuments 6.
This safeguard structure also comprises the prismatic wire gauze 2 be arranged between described integument 6 and side slope face 1, and prismatic wire gauze 2 adopts zinc-plated process, and mesh size is 45mm × 45mm to 50mm × 50mm, and iron wire diameter is Φ 2mm ~ Φ 3mm.Described prismatic wire gauze 2 is less than 5cm with the distance on side slope surface, ensures that prismatic wire gauze 2 contacts with side slope face 1 as far as possible.Described prismatic wire gauze 2 is plugged with straight holdfast 3, to be fixedly mounted on side slope face 1 by prismatic wire gauze 2.Straight holdfast 3 adopts reinforcing bar to make, and its length is 45cm ~ 75cm, and the degree of depth that straight holdfast 3 can be deep into side slope face 1 is 35cm ~ 65cm, in the scope of 1 ㎡ ~ 1.2 ㎡, at least arranges a straight holdfast 3, guarantees that prismatic wire gauze 2 is fastened on side slope face 1.
Foregoing safeguard structure, present invention also offers a kind of means of defence for greening high precipitous rock slope, comprises the following steps:
A, arrangement, cleaning side slope face 1.
B, prismatic wire gauze 2 is set on side slope face 1, and makes the distance between prismatic wire gauze 2 and side slope face 1 be less than 5cm.
C, run through prismatic wire gauze 2 with straight holdfast 3, prismatic wire gauze 2 is fixed on side slope face 1, and in the scope of 1 ㎡ ~ 1.2 ㎡, a straight holdfast 3 is at least set.
D, make many columned iron wire loops 4, connect successively, form a cylinder.
E, make integument 6 by geotextiles, and fill base material mixture 7 in integument 6.
F, run through integument 6 and rhombus wire gauze with U-shaped holdfast 5, be fixed on side slope face 1, then regularly carry out maintenance.
The above; be only the present invention's preferably detailed description of the invention; but protection scope of the present invention is not limited thereto; anyly be familiar with those skilled in the art in the technical scope that the present invention discloses; be equal to according to technical scheme of the present invention and inventive concept thereof and replace or change, all should be encompassed within protection scope of the present invention.

Claims (6)

1., for a safeguard structure for greening high precipitous rock slope, it is characterized in that, comprise be made up of cloth material, inside is filled with the cylindrical integument of base material mixture, is evenly distributed with some columned iron wire loops outside described integument; Also comprise and run through described integument and the U-shaped holdfast be plugged in side slope, U-shaped holdfast is plugged with two integuments.
2. a kind of greening high precipitous rock slope safeguard structure according to claim 1, is characterized in that, also comprises the prismatic wire gauze be arranged between described integument and side slope face.
3. a kind of greening high precipitous rock slope safeguard structure according to claim 2, is characterized in that, the distance on described prismatic wire gauze and side slope surface is less than 5cm.
4. a kind of greening high precipitous rock slope safeguard structure according to claim 2, is characterized in that, also comprises the straight holdfast be plugged on by described prismatic wire gauze in side slope.
5. a kind of greening high precipitous rock slope safeguard structure according to claim 4, is characterized in that, in the scope of 1 ㎡ ~ 1.2 ㎡, at least arranges a straight holdfast.
6. for a means of defence for greening high precipitous rock slope, it is characterized in that, comprise the following steps:
A, arrangement, cleaning side slope face;
B, prismatic wire gauze is set on side slope face, and makes the distance between prismatic wire gauze and side slope face be less than 5cm;
C, run through prismatic wire gauze with straight holdfast, prismatic wire gauze is fixed on side slope face, and in the scope of 1 ㎡ ~ 1.2 ㎡, a straight holdfast is at least set;
D, make many columned iron wire loops, connect successively, form a cylinder;
E, make integument by geotextiles, and fill base material mixture in integument;
F, run through integument and rhombus wire gauze with U-shaped holdfast, be fixed on side slope face.
CN201510649472.4A 2015-09-30 2015-09-30 Protecting structure and protecting method used for greening high-steep rock slope Pending CN105155560A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510649472.4A CN105155560A (en) 2015-09-30 2015-09-30 Protecting structure and protecting method used for greening high-steep rock slope

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510649472.4A CN105155560A (en) 2015-09-30 2015-09-30 Protecting structure and protecting method used for greening high-steep rock slope

Publications (1)

Publication Number Publication Date
CN105155560A true CN105155560A (en) 2015-12-16

Family

ID=54796578

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510649472.4A Pending CN105155560A (en) 2015-09-30 2015-09-30 Protecting structure and protecting method used for greening high-steep rock slope

Country Status (1)

Country Link
CN (1) CN105155560A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105862888A (en) * 2016-04-20 2016-08-17 中国水利水电第十工程局有限公司 Comprehensive protecting method for high and steep rock slopes
CN109328892A (en) * 2018-08-15 2019-02-15 江苏绿岩生态技术股份有限公司 A kind of river bank slope ecological restoring method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001279674A (en) * 2000-04-03 2001-10-10 Ibiden Greentec Co Ltd Planting sandbag structure and greening method
JP2003119792A (en) * 2001-10-04 2003-04-23 Shigeto Matsuo Wire-system slope method
CN2873888Y (en) * 2006-02-11 2007-02-28 襄樊学院 Side slope protection afforestation layer structure
CN101543168A (en) * 2009-05-08 2009-09-30 贵州边坡生态防护研究所有限责任公司 method for planting vegetation on the karst area slope
CN203840816U (en) * 2013-11-20 2014-09-24 华艺生态园林股份有限公司 Rock slope vegetation restoration structure
CN205000347U (en) * 2015-09-30 2016-01-27 宏大国源(芜湖)资源环境治理有限公司 A protective structure that is used for high steep rock matter slope planting

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001279674A (en) * 2000-04-03 2001-10-10 Ibiden Greentec Co Ltd Planting sandbag structure and greening method
JP2003119792A (en) * 2001-10-04 2003-04-23 Shigeto Matsuo Wire-system slope method
CN2873888Y (en) * 2006-02-11 2007-02-28 襄樊学院 Side slope protection afforestation layer structure
CN101543168A (en) * 2009-05-08 2009-09-30 贵州边坡生态防护研究所有限责任公司 method for planting vegetation on the karst area slope
CN203840816U (en) * 2013-11-20 2014-09-24 华艺生态园林股份有限公司 Rock slope vegetation restoration structure
CN205000347U (en) * 2015-09-30 2016-01-27 宏大国源(芜湖)资源环境治理有限公司 A protective structure that is used for high steep rock matter slope planting

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
江贤圣: "植生袋生态防护的设计与施工研究", 《安徽农业科学》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105862888A (en) * 2016-04-20 2016-08-17 中国水利水电第十工程局有限公司 Comprehensive protecting method for high and steep rock slopes
CN105862888B (en) * 2016-04-20 2018-05-11 中国水利水电第十一工程局有限公司 A kind of comprehensive protecting method of high precipitous rock slope
CN109328892A (en) * 2018-08-15 2019-02-15 江苏绿岩生态技术股份有限公司 A kind of river bank slope ecological restoring method

Similar Documents

Publication Publication Date Title
CN107893422B (en) A kind of reinforcement type ecological slope protection structure and its construction method
CN106638630B (en) Flexible ceramsite board slope ecological afforestation equipment and its greening method
CN205116187U (en) Rocky slope's revegetation structure
CN105178340A (en) Anti-scouring structure used for ecological regreening of rock slope and concrete material used for anti-scouring structure
CN104186233A (en) Frame beam slope greening method and frame beam slope greening facility
Broda et al. Reclamation of abandoned open mines with innovative meandrically arranged geotextiles
CN203840816U (en) Rock slope vegetation restoration structure
CN102523970A (en) Quick ecological rehabilitation method for steep rock slope
CN110557997B (en) Construction method of slope ecological restoration system
CN204059376U (en) The slope protection greening structure of the steep exposed rock side slope of a kind of urgency
CN204014608U (en) A kind of sash beam greening side slope facility
CN203530993U (en) Steel-bar mesh planting hole
CN105155560A (en) Protecting structure and protecting method used for greening high-steep rock slope
CN212641481U (en) Ecological restoration structure of massif multi-element matrix
CN210827555U (en) Ecological reinforced earth retaining wall slope protection that red mudstone packed
CN105756015B (en) Method for restoring biodiversity dynamic landscape ecological composite system
CN104264697B (en) A kind of high steep rock side-slope greening safeguard structure
CN204098045U (en) A kind of zoology green-recovery system for flinty slope
CN201821698U (en) Plant-climbing rack for ecological rehabilitation
CN107227715A (en) A kind of side slope protection construction method on reservoir gentle slope
CN205000347U (en) A protective structure that is used for high steep rock matter slope planting
CN206289637U (en) Flexible ceramsite board slope ecological afforestation equipment
CN114753387B (en) Water-retaining high-steep slope ecological slope protection structure and construction method
CN109356174A (en) A kind of protecting slope ecology method
CN213625622U (en) Ecological remediation slope surface structure on mine

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20151216

RJ01 Rejection of invention patent application after publication