CN104875847B - 一种集装箱船中间横隔舱的快速搭载方法 - Google Patents
一种集装箱船中间横隔舱的快速搭载方法 Download PDFInfo
- Publication number
- CN104875847B CN104875847B CN201510279679.7A CN201510279679A CN104875847B CN 104875847 B CN104875847 B CN 104875847B CN 201510279679 A CN201510279679 A CN 201510279679A CN 104875847 B CN104875847 B CN 104875847B
- Authority
- CN
- China
- Prior art keywords
- transverse bulkhead
- cofferdam
- ship
- crane
- deck
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims description 13
- 238000004519 manufacturing process Methods 0.000 claims abstract description 12
- 238000003466 welding Methods 0.000 claims abstract description 9
- 238000000465 moulding Methods 0.000 claims abstract description 3
- 229910000831 Steel Inorganic materials 0.000 claims description 4
- 238000007689 inspection Methods 0.000 claims description 4
- 239000010959 steel Substances 0.000 claims description 4
- 230000000694 effects Effects 0.000 abstract description 2
- 238000007747 plating Methods 0.000 abstract 2
- 230000011218 segmentation Effects 0.000 abstract 2
- 235000008331 Pinus X rigitaeda Nutrition 0.000 abstract 1
- 235000011613 Pinus brutia Nutrition 0.000 abstract 1
- 241000018646 Pinus brutia Species 0.000 abstract 1
- 238000010276 construction Methods 0.000 description 5
- 238000005516 engineering process Methods 0.000 description 2
- 230000007547 defect Effects 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
Landscapes
- Filling Or Discharging Of Gas Storage Vessels (AREA)
- Ship Loading And Unloading (AREA)
Abstract
本发明涉及一种集装箱船横隔舱快速搭载技术方案,该方案包括以下步骤:1、将横隔舱在胎架上以卧态形式制造完成;2、验收合格后用起重机将横隔舱吊运到指定位置;3、将横隔舱搁置在内底分段上;4、初步定位后,将横隔舱与内底板接缝处进行间断焊;5、利用横舱壁保距梁,将横隔舱甲板与已完成搭载的横舱壁甲板进行刚性连接固定,起重机松钩;6、对横隔舱与内底板接缝处进行连续焊,完成搭载作业。本发明大大缩短了横隔舱的搭载周期,克服了横隔舱搭载定位的难题,保证了横隔舱搭载定位的精度要求,节省了起重机起运作业时间,为后续舷侧总段/分段的搭载创造了有利条件,从而极大地缩短了船坞周期。
Description
技术领域
本发明涉及船舶建造中集装箱船技术领域,特别是涉及到一种集装 箱船中间横隔舱的快速搭载方法。
背景技术
集装箱船横隔舱由于尺寸大,重心高,建造过程中搭载定位时间长, 精度控制要求高,一直是集装箱船建造过程中的难点问题。针对横隔舱 的搭载技术,一般需先将舷侧的分段/总段搭载定位结束,然后将中间的 横隔舱进行嵌入式搭载,利用舷侧的分段/总段来对横隔舱进行定位。这 种方式对横隔舱制作的精度要求较高,搭载定位时需进行余量俢割,因 此大大增加了搭载定位的难度,影响了船舶建造的进度。
发明内容
本发明的目的在于克服上述现有技术的不足,提供一种集装箱船横 隔舱快速搭载的方法,优化了建造流程,将横隔舱搭载提前到舷侧分段/ 总段搭载之前;借助横舱壁保距梁等工装,对横隔舱快速搭载进行定位、 精度控制。实施这种技术方案,能显著提升搭载定位效率,加快船舶建 造进度,有效控制船舶建造成本。
为了达到上述发明目的,本发明提供的技术方案如下:
一种集装箱船中间横隔舱的快速搭载方法,其特征在于,该方法先将横隔舱以卧态方式搁置在胎架上进行制造 ;验收合格后,用起重机进行起运吊装至指定位置;然后将横隔舱与内底板处接缝进行间断焊固定;通过横舱壁保距梁将横隔舱甲板与已搭载的横隔舱甲板进行连接固定,然后起重机松钩,完成横隔舱与内底板处接缝的烧焊作业。
一种集装箱船中间横隔舱的快速搭载方法,具体步骤如下:
第一步、按照船舶的制造要求,在胎架上制作横隔舱:在制作前检验胎架精度,划出基准线,并将横隔舱以卧态形式放置在胎架上制作横隔舱;
第二步、横隔舱制作完成并验收合格后,用起重机起吊横隔舱,起 吊至一定高度,对横隔舱进行翻身,使横隔舱甲板保持水平,横隔舱的 前、后横舱壁与坞内船舶首尾朝向一致;
第三步、将横隔舱吊运到坞内指定位置,使横隔舱的前、后横舱壁 肋位分别与坞内船舶对应肋位粗对齐,使横隔舱中心线与坞内船舶的船 体中心线粗对齐;
第四步、利用油泵、千斤顶辅助工具,对横隔舱的位置进行微调, 使横隔舱前、后壁肋位与坞内船舶对应肋位线对齐,横隔舱中心线与坞 内船舶的中心线对齐;
第五步、将横隔舱与内底板处接缝进行间断焊固定,用横舱壁保距梁使横隔舱甲板与已搭载的、相邻的横隔舱甲板进行连接固定,使横舱壁保距梁对称布置在横隔舱左舷和右舷;
第六步、在横隔舱前、后壁分别与船舶内底结构之间斜拉钢丝绳,起重机松钩,完成横隔舱与内底板处、接缝的连续焊作业。
基于上述技术方案,本发明的集装箱船横隔舱快速搭载的技术方案 具有如下技术优点:
1、在舷侧分段/总段搭载前,就能进行横隔舱搭载定位,因此能更 快地进行船舶建造;
2、横隔舱搭载定位流程简单快捷,安全性高,能有效节省起重机作 业时间;
3、通过这种方式进行横隔舱搭载,精度控制效果好,为后续的吊箱 试验创造良好的条件,从而有效节省了船舶的建造周期。
附图说明:
图1是本发明的横隔舱制作示意图
图2是本发明的横隔舱吊运示意图
图3是本发明的横隔舱的搭载定位示意图
其中,
1-横隔舱 2-起重机 3-船舶内底结构 4-相邻横隔舱
5-横舱壁保距梁 6-钢丝绳
具体实施方式:
下面结合附图和实施例来对本发明的集装箱船中间横隔舱的快速搭 载方法做进一步的详细阐述,但不能以此来限制本发明的保护范围。
本发明的集装箱船横隔舱快速搭载技术操作步骤如下:
1、横隔舱1以卧态的形式在胎架上制造,如图1所示;
2、在制作完成并验收后,用起重机2将其吊起,并翻身,使舱壁由水 平状态变为垂直状态,吊运到坞内指定位置,如图2所示;
3、将横隔舱1搁置在船舶内底结构3上,调整横隔舱1位置,使其 横舱壁垂直度不大于3mm,横隔舱中心线与船体中心线对准,偏差不大 于2mm,横隔舱1与已搭载的相邻横隔舱4间距在允许范围内,并用横 舱壁保距梁5连接横隔舱1甲板、相邻横隔舱4甲板,固定前、后横隔 舱之间的间距;
4、在横隔舱前、后壁和船舶内底结构3之间斜拉钢丝绳6,完成横 隔舱1与船舶内底结构3之间的接缝,如图3所示。
Claims (1)
1.一种集装箱船中间横隔舱的快速搭载方法,其特征在于,该方法先将横隔舱以卧态方式搁置在胎架上进行制造;验收合格后,用起重机进行起运吊装至指定位置;然后将横隔舱与内底板处接缝进行间断焊固定;通过横舱壁保距梁将横隔舱甲板与已搭载的横隔舱甲板进行连接固定,然后起重机松钩,完成横隔舱与内底板处接缝的烧焊作业;
具体步骤如下:
第一步、按照船舶的制造要求,在胎架上制作横隔舱:在制作前检验胎架精度,划出基准线,并将横隔舱以卧态形式放置在胎架上制作横隔舱;
第二步、横隔舱制作完成并验收合格后,用起重机起吊横隔舱,起吊至一定高度,对横隔舱进行翻身,使横隔舱甲板保持水平,横隔舱的前、后横舱壁与坞内船舶首尾朝向一致;
第三步、将横隔舱吊运到坞内指定位置,使横隔舱的前、后横舱壁肋位分别与坞内船舶对应肋位粗对齐,使横隔舱中心线与坞内船舶的船体中心线粗对齐;
第四步、利用油泵、千斤顶辅助工具,对横隔舱的位置进行微调,使横隔舱前、后壁肋位与坞内船舶对应肋位线对齐,横隔舱中心线与坞内船舶的中心线对齐;
第五步、将横隔舱与内底板处接缝进行间断焊固定,用横舱壁保距梁使横隔舱甲板与已搭载的、相邻的横隔舱甲板进行连接固定,使横舱壁保距梁对称布置在横隔舱左舷和右舷;
第六步、在横隔舱前、后壁分别与船舶内底结构之间斜拉钢丝绳,起重机松钩,完成横隔舱与内底板处接缝的连续焊作业。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510279679.7A CN104875847B (zh) | 2015-05-28 | 2015-05-28 | 一种集装箱船中间横隔舱的快速搭载方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510279679.7A CN104875847B (zh) | 2015-05-28 | 2015-05-28 | 一种集装箱船中间横隔舱的快速搭载方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104875847A CN104875847A (zh) | 2015-09-02 |
CN104875847B true CN104875847B (zh) | 2019-02-05 |
Family
ID=53943590
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510279679.7A Active CN104875847B (zh) | 2015-05-28 | 2015-05-28 | 一种集装箱船中间横隔舱的快速搭载方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104875847B (zh) |
Families Citing this family (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106882326B (zh) * | 2017-03-17 | 2018-03-02 | 广东新船重工有限公司 | 一种不锈钢液货船分段快速搭载定位方法 |
CN107161281A (zh) * | 2017-05-24 | 2017-09-15 | 广船国际有限公司 | 一种船舶分段快速搭载的方法 |
CN107323610A (zh) * | 2017-06-30 | 2017-11-07 | 广船国际有限公司 | 主机座、齿轮箱座总段阶段的安装方法 |
CN109319045B (zh) * | 2018-10-10 | 2020-09-18 | 上海江南长兴造船有限责任公司 | 一种双相不锈钢化学品船隔舱中间产品的建造方法 |
CN109533192B (zh) * | 2018-10-23 | 2021-05-28 | 上海江南长兴造船有限责任公司 | 一种用于超大型集装箱船隔舱总段的搭载松钩约束方法 |
CN109533191B (zh) * | 2018-10-23 | 2020-09-25 | 上海江南长兴造船有限责任公司 | 一种用于双相不锈钢化学品船横隔舱中间分段的吊装方法 |
CN109823467B (zh) * | 2019-02-22 | 2020-03-20 | 中船澄西船舶修造有限公司 | 橙汁船货仓甲板总段吊装工艺 |
CN110466683B (zh) * | 2019-08-22 | 2021-08-20 | 中船黄埔文冲船舶有限公司 | 一种拼接槽形舱壁用定位工装及槽形舱壁的拼接方法 |
CN110937079A (zh) * | 2019-10-24 | 2020-03-31 | 上海江南长兴造船有限责任公司 | 一种大型集装箱船双层底箱位精度控制方法 |
CN111422323B (zh) * | 2020-04-17 | 2021-11-02 | 上海外高桥造船有限公司 | 基于定位基准线的超大型箱船的横舱壁分段建造方法 |
CN111559473B (zh) * | 2020-04-24 | 2022-02-08 | 上海外高桥造船有限公司 | 一种散货船艏部总段的吊装方法 |
CN115593584B (zh) * | 2022-11-08 | 2024-06-11 | 沪东中华造船(集团)有限公司 | 一种lng船横隔舱船坞搭载焊接方法 |
CN115837966B (zh) * | 2022-11-29 | 2024-06-11 | 沪东中华造船(集团)有限公司 | 一种lng船横隔舱总段搭载控制方法及lng船 |
CN116062116A (zh) * | 2023-01-10 | 2023-05-05 | 广州文冲船厂有限责任公司 | 一种插入式横舱壁分段的搭载方法 |
CN115892383A (zh) * | 2023-01-16 | 2023-04-04 | 广州文冲船厂有限责任公司 | 一种船舶的内底板与横舱壁的装配方法 |
Family Cites Families (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN100371211C (zh) * | 2003-08-21 | 2008-02-27 | 沪东中华造船(集团)有限公司 | 横舱壁、抗扭甲板、舱口围和导轨架四位一体预装方法 |
JP4199217B2 (ja) * | 2005-07-27 | 2008-12-17 | 株式会社新来島どっく | 波型隔壁を有する船体ブロック建造法 |
CN101092161A (zh) * | 2007-07-25 | 2007-12-26 | 上海外高桥造船有限公司 | 横隔舱与甲板在船舶上的总组方法 |
CN101570234B (zh) * | 2008-04-29 | 2013-07-03 | 江南造船(集团)有限责任公司 | 一种机舱总段组装方法以及机舱总段的吊装方法 |
CN203199145U (zh) * | 2012-12-28 | 2013-09-18 | 上海中远船务工程有限公司 | Fpso货舱区环形总段分段结构 |
-
2015
- 2015-05-28 CN CN201510279679.7A patent/CN104875847B/zh active Active
Also Published As
Publication number | Publication date |
---|---|
CN104875847A (zh) | 2015-09-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104875847B (zh) | 一种集装箱船中间横隔舱的快速搭载方法 | |
CN109319045B (zh) | 一种双相不锈钢化学品船隔舱中间产品的建造方法 | |
CN102328729B (zh) | 一种船舶水上双岛合拢工艺 | |
CN102874379B (zh) | 海上抛石整平船的制作方法 | |
CN106428420B (zh) | 一种用于超大型集装箱船止裂钢舱口围的安装的方法 | |
US3447503A (en) | Method and apparatus for modular construction of a ship | |
CN109895945A (zh) | 一种矿砂船舷侧总段的纵横舱壁预组装方法 | |
CN109625157B (zh) | 大型集装箱船翼桥分段一体化建造的方法 | |
CN102975817A (zh) | 折叠式舱口盖和舱口围整体安装工艺方法 | |
CN109533192B (zh) | 一种用于超大型集装箱船隔舱总段的搭载松钩约束方法 | |
CN102328727B (zh) | 深水铺管起重船的重型海洋工程起重机底座的分段方法 | |
CN110182313B (zh) | 30万吨浮式生产储油轮艏货舱舷侧总段异地总组工艺 | |
CN107140113A (zh) | 一种油船的舷侧分段与舭部分段的组装方法 | |
CN103661807A (zh) | 预先安装压力导轨架的舷侧分段合拢的定位方法 | |
CN106563867A (zh) | 一种绑扎桥立式总组工艺 | |
CN203094369U (zh) | 货舱c段总装合拢结构 | |
CN209190070U (zh) | 自升式海上平台圆柱形桩腿合拢定位装置 | |
CN105501391B (zh) | 一种全回转推进器从船台安装到船舶底部的安装方法 | |
CN104691704A (zh) | 一种内河船舶的建造方法 | |
CN101591917A (zh) | 钢吊箱施工工艺 | |
CN115092348B (zh) | 一种大型邮轮艏部侧推分段建造工艺 | |
CN114248884B (zh) | 一种船舶首部大型铸钢件的安装方法 | |
CN110979595B (zh) | 一种海损船修复方法 | |
CN114802642A (zh) | 一种集装箱船抗扭箱分段的建造方法及集装箱船 | |
CN109552997B (zh) | 水下栅栏板制备、定位安装方法及其安装系统 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |