CN104652835A - 一种组合梁湿接缝冬季施工电伴热保温方法 - Google Patents
一种组合梁湿接缝冬季施工电伴热保温方法 Download PDFInfo
- Publication number
- CN104652835A CN104652835A CN201510046213.2A CN201510046213A CN104652835A CN 104652835 A CN104652835 A CN 104652835A CN 201510046213 A CN201510046213 A CN 201510046213A CN 104652835 A CN104652835 A CN 104652835A
- Authority
- CN
- China
- Prior art keywords
- layer
- compound beam
- seam
- insulation layer
- winter construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Building Environments (AREA)
Abstract
本发明公开了一种组合梁湿接缝冬季施工电伴热保温方法,该方法先在组合梁上翼缘的上表面浇筑湿接缝,浇筑完成后在所述湿接缝的表面覆盖第一保湿层;然后在所述第一保湿层的上面覆盖复合铝箔防潮层;再在所述防潮层和第一保湿层之间布置加热带,并将感温部件放置在第一保湿层处,将所述加热带和所述感温部件分别与温控箱连接;再在所述防潮层上部覆盖第一保温层;然后在组合梁上翼缘的下表面依次设置第二保湿层和第二保温层,在所述第二保湿层和第二保温层布置加热带和感温部件,并将所述加热带和所述感温部件分别与温控箱连接。本发明适用于钢-混组合梁湿接缝混凝土冬季保温养护,保证混凝土冬季施工质量,加快混凝土冬季施工进度。
Description
技术领域
本发明属于保温防冻的施工方法,特别涉及一种组合梁湿接缝冬季施工电伴热保温方法。
背景技术
工艺钢-混组合梁湿接缝混凝土施工是组合梁施工重要步骤,传统湿接缝混凝土冬季保温养护方法是在湿接缝施工完成后由下至上覆盖塑料膜、土工布、电热毯、麻袋进行保温养护。
传统的覆盖养护法,只是本着“头疼医头,脚疼医脚”的原则,在湿接缝的上表面覆盖养护层,且存在覆盖层数单薄的漏洞,同时电热毯功率低,发热量小,在冬季的施工现场往往起不到作用,温度最好也就5-10度,因此养护时间长,混凝土强度增长慢,混凝土施工质量无法保证,施工周期长。
发明内容
针对现有技术的缺陷或不足,本发明的目的在于,提供一种组合梁湿接缝冬季施工电伴热保温方法,克服了传统覆盖方法中混凝土强度增长慢,强度无法保证的缺点。使用此方法,湿接缝混凝土质量得到提高,养护时间缩短,施工进度加快。
为了实现上述任务,本发明采取如下的技术解决方案:
一种组合梁湿接缝冬季施工电伴热保温方法,该方法按以下步骤进行:
步骤一,在组合梁上翼缘的上表面浇筑湿接缝,浇筑完成后在所述湿接缝的表面覆盖第一保湿层;
步骤二,在所述第一保湿层的上面覆盖复合铝箔防潮层;
步骤三,在所述复合铝箔防潮层和第一保湿层之间布置有多个间隔排列的加热带,并将感温部件放置在第一保湿层处,将所述加热带和所述感温部件分别与温控箱连接;
步骤四,在所述复合铝箔防潮层上部覆盖第一保温层;
步骤五,在组合梁上翼缘的下表面依次设置第二保湿层和第二保温层,并通过铁丝依次穿过所述第二保湿层和所述第二保温层,使所述第二保温层紧贴所述第二保湿层;
步骤六,在所述第二保湿层和第二保温层布置有多个间隔排列的加热带,并将感温部件放置在第二保湿层处,并将所述加热带和所述感温部件分别与温控箱连接。
优选地,所述第一保温层的上部还覆盖平板型太阳能集热器。
优选地,所述第一保温层的端部厚度是其面部厚度的2-3倍。
优选地,所述第一保湿层和第二保湿层的材料相同,均为PET聚酯薄膜,其厚度为10-30mm。
优选地,所述第一保温层和第二保温层的材料相同,均为具有阻燃作用的三聚氰胺改性脲醛泡沫材料,其厚度为40-70mm。
优选地,所述温控箱预设的最高温为40℃,最低温为10℃。
与现有技术相比,本发明的有益效果为:
(1)本发明在组合梁上翼缘的下表面架设保温层,并连入加热设备,使组合梁湿接缝的上下两面均得到加热保温。
(2)本发明采用电热带加热,电热带的加热功率更高,缩短养护时间。
(3)本发明采用PET聚酯薄膜材料的保湿层,能够有效保证混凝土中的水分不流失。
(4)本发明中覆盖平板型太阳能集热器,能够利用太阳能转化成热能,对保温层进行加热,能够进一步对湿接缝保温,并且节约了能源。
(5)本发明中的加温范围设定在10-40℃,既不会使湿接缝的混凝土温度过高,使混凝土开裂,也不会使混凝土温度过低,冻坏混凝土,最大限度的节省电力。
附图说明
图1本发明一种组合梁湿接缝冬季施工电伴热保温方法的施工结构示意图。
具体实施方式
下面结合实施例对本发明作进一步描述,以令本领域技术人员参照说明书文字能够据以实施。
一种组合梁湿接缝冬季施工电伴热保温方法,该方法按以下步骤进行:
步骤一,在组合梁上翼缘1的上表面浇筑湿接缝2,浇筑完成后在所述湿接缝2的表面覆盖第一保湿层3;
步骤二,在所述第一保湿层3的上面覆盖复合铝箔防潮层4;
步骤三,在所述复合铝箔防潮层4和第一保湿层3之间布置有多个间隔排列的加热带7,并将感温部件8放置在第一保湿层3处,将所述加热带7和所述感温部件8分别与温控箱连接;
步骤四,在所述复合铝箔防潮层4上部覆盖第一保温层5;
步骤五,在组合梁上翼缘1的下表面依次设置第二保湿层9和第二保温层10,并通过铁丝11依次穿过所述第二保湿层9和所述第二保温层10,使所述第二保温层10紧贴所述第二保湿层9;
步骤六,在所述第二保湿层9和第二保温层10布置有多个间隔排列的加热带7,并将感温部件8放置在第二保湿层9处,并将所述加热带7和所述感温部件8分别与温控箱连接。本发明在组合梁上翼缘的下表面架设保温层,并连入加热设备,使组合梁湿接缝的上下两面均得到加热保温,且采用电热带加热,电热带的加热功率更高,缩短养护时间。
其中,第一保湿层3与第二保湿层9的材料可选用PET聚酯薄膜、聚氧乙烯、PVC树脂中的一种,第一保温层5与第二保温层10的材料可选用为酚醛泡沫、三聚氰胺改性脲醛泡沫、复合硅酸盐中的一种。
更优的,所述第一保温层5的上部还覆盖平板型太阳能集热器6,所述平板型太阳能集热器6采用黑色铝合金材料,能够利用太阳能转化成热能,对保温层进行加热,能够进一步对湿接缝保温,并且节约了能源
更优的,所述第一保温层5的端部厚度是其面部厚度的2-3倍。
更优的,所述第一保湿层3和第二保湿层9的材料相同,均为PET聚酯薄膜,其厚度为10-30mm。采用PET聚酯薄膜材料的保湿层,能够有效保证混凝土中的水分不流失。
更优的,所述第一保温层5和第二保温层10的材料相同,均为具有阻燃作用的三聚氰胺改性脲醛泡沫材料,其厚度为40-70mm。
所述温控箱预设的最高温为40℃,最低温为10℃,当感温元件检测到温度低于10℃时,电热带开始加热,当温度高于40℃时,电热带停止加热。加温范围设定在10-40℃,既不会使湿接缝的混凝土温度过高,使混凝土开裂,也不会使混凝土温度过低,冻坏混凝土,最大限度的节省电力。
以下是发明人提供的实施例,需要说明的是该实施例是对本发明的进一步解释和说明,本发明并不限于该实施例。
实施例1:
本次混凝土浇筑开始于早上10:00,结束于下午19:00,历时9小时。混凝土拌合水温控制在30℃-50℃,混凝土入模温度在12.1℃左右,出机温度15℃左右,开盘时气温约为5℃。
本次混凝土浇注前未对钢梁进行预热,在逐段浇注完成,抹面后,
步骤一,在组合梁上翼缘的上表面浇筑湿接缝,浇筑完成后在所述湿接缝的表面覆盖PET聚酯薄膜;
步骤二,在所述PET聚酯薄膜的上面覆盖复合铝箔防潮层;
步骤三,在所述复合铝箔防潮层和PET聚酯薄膜之间布置有多个间隔排列的加热带,并将感温部件放置在PET聚酯薄膜处,将所述加热带和所述感温部件分别与温控箱连接;
步骤四,在所述复合铝箔防潮层上部覆盖三聚氰胺改性脲醛泡沫材料;
步骤五,在组合梁上翼缘的下表面依次设置PET聚酯薄膜和三聚氰胺改性脲醛泡沫材料,并通过铁丝依次穿过所述PET聚酯薄膜和所述三聚氰胺改性脲醛泡沫材料,使所述三聚氰胺改性脲醛泡沫材料紧贴所述PET聚酯薄膜;
步骤六,在所述PET聚酯薄膜和三聚氰胺改性脲醛泡沫材料布置有多个间隔排列的加热带,并将感温部件放置在PET聚酯薄膜处,并将所述加热带和所述感温部件分别与温控箱连接。
混凝土同养试块在混凝土最后浇注完成后,开始加热养护,在1.5天时其抗压强度达45MPa,2天时达51MPa,达到预期。因此本发明人在对混凝土加热两天后停止加热。
实施例2
本次混凝土浇筑开始于早上10:00,结束于下午19:00,历时9小时。混凝土拌合水温控制在30℃-50℃,混凝土入模温度在12.1℃左右,出机温度15℃左右,开盘时气温约为5℃。
本次混凝土浇注前未对钢梁进行预热,在逐段浇注完成,抹面后,
步骤一,在组合梁上翼缘的上表面浇筑湿接缝,浇筑完成后在所述湿接缝的表面覆盖PET聚酯薄膜;
步骤二,在所述PET聚酯薄膜的上面覆盖复合铝箔防潮层;
步骤三,在所述复合铝箔防潮层和PET聚酯薄膜之间布置有多个间隔排列的加热带,并将感温部件放置在PET聚酯薄膜处,将所述加热带和所述感温部件分别与温控箱连接;
步骤四,在所述复合铝箔防潮层上部覆盖依次三聚氰胺改性脲醛泡沫材料和平板型太阳能集热器;
步骤五,在组合梁上翼缘的下表面依次设置PET聚酯薄膜和三聚氰胺改性脲醛泡沫材料,并通过铁丝依次穿过所述PET聚酯薄膜和所述三聚氰胺改性脲醛泡沫材料,使所述三聚氰胺改性脲醛泡沫材料紧贴所述PET聚酯薄膜;
步骤六,在所述PET聚酯薄膜和三聚氰胺改性脲醛泡沫材料布置有多个间隔排列的加热带,并将感温部件放置在PET聚酯薄膜处,并将所述加热带和所述感温部件分别与温控箱连接。
混凝土同养试块在混凝土最后浇注完成后,开始加热养护,在1.5天时其抗压强度达47MPa,2天时达53MPa,与实施例1相比效果更好,这是因为本实施例在三聚氰胺改性脲醛泡沫材料的上部还覆盖有平板型太阳能集热器,其采用黑色铝合金板材料,可以吸收太阳能并把太阳能转化成热能传给三聚氰胺改性脲醛泡沫材料,使湿接缝的温度更温暖。本发明人在对混凝土加热两天后停止加热。
实施例3
本次混凝土浇筑开始于早上10:00,结束于下午19:00,历时9小时。混凝土拌合水温控制在30℃-50℃,混凝土入模温度在12.1℃左右,出机温度15℃左右,开盘时气温约为5℃。
本次混凝土浇注前未对钢梁进行预热,在逐段浇注完成,抹面后,
步骤一,在组合梁上翼缘的上表面浇筑湿接缝,浇筑完成后在所述湿接缝的表面覆盖PET聚酯薄膜;
步骤二,在所述PET聚酯薄膜的上面覆盖复合铝箔防潮层;
步骤三,在所述复合铝箔防潮层和PET聚酯薄膜之间布置有多个间隔排列的加热带,并将感温部件放置在PET聚酯薄膜处,将所述加热带和所述感温部件分别与温控箱连接;
步骤四,在所述复合铝箔防潮层上部覆盖依次三聚氰胺改性脲醛泡沫材料和平板型太阳能集热器,三聚氰胺改性脲醛泡沫材料的端部厚度是其面部厚度的2-3倍;
步骤五,在组合梁上翼缘的下表面依次设置PET聚酯薄膜和三聚氰胺改性脲醛泡沫材料,并通过铁丝依次穿过所述PET聚酯薄膜和所述三聚氰胺改性脲醛泡沫材料,使所述三聚氰胺改性脲醛泡沫材料紧贴所述PET聚酯薄膜;
步骤六,在所述PET聚酯薄膜和三聚氰胺改性脲醛泡沫材料布置有多个间隔排列的加热带,并将感温部件放置在PET聚酯薄膜处,并将所述加热带和所述感温部件分别与温控箱连接。
混凝土同养试块在混凝土最后浇注完成后,开始加热养护,在1.5天时其抗压强度达48MPa,2天时达54MPa,比实施例2的效果更好,这是因为本实施例在实施例2的基础上对三聚氰胺改性脲醛泡沫材料的端部进行了加厚,这样能够使三聚氰胺改性脲醛泡沫材料的端部更重,其与PET聚酯薄膜接触的更紧密,进一步降低了水份的丢失。本发明人在对混凝土加热两天后停止加热。
尽管本发明的实施方案已公开如上,但其并不仅仅限于说明书和实施方式中所列运用,它完全可以被适用于各种适合本发明的领域,对于熟悉本领域的人员而言,可容易地实现另外的修改,因此在不背离权利要求及等同范围所限定的一般概念下,本发明并不限于特定的细节和这里示出与描述的图例。
Claims (6)
1.一种组合梁湿接缝冬季施工电伴热保温方法,其特征在于,该方法按以下步骤进行:
步骤一,在组合梁上翼缘的上表面浇筑湿接缝,浇筑完成后在所述湿接缝的表面覆盖第一保湿层;
步骤二,在所述第一保湿层的上面覆盖复合铝箔防潮层;
步骤三,在所述复合铝箔防潮层和第一保湿层之间布置有多个间隔排列的加热带,并将感温部件放置在所述第一保湿层处,将所述加热带和所述感温部件分别与温控箱连接;
步骤四,在所述复合铝箔防潮层上部覆盖第一保温层;
步骤五,在组合梁上翼缘的下表面依次设置第二保湿层和第二保温层,并通过铁丝依次穿过所述第二保湿层和所述第二保温层,使所述第二保温层紧贴所述第二保湿层;
步骤六,在所述第二保湿层和第二保温层之间布置有多个间隔排列的加热带,并将感温部件放置在第二保湿层处,并将所述加热带和所述感温部件分别与温控箱连接。
2.如权利要求1所述的组合梁湿接缝冬季施工电伴热保温方法,其特征在于,所述第一保温层的上部还覆盖平板型太阳能集热器。
3.如权利要求2所述的组合梁湿接缝冬季施工电伴热保温方法,其特征在于,所述第一保温层的端部厚度是其面部厚度的2-3倍。
4.如权利要求3所述的组合梁湿接缝冬季施工电伴热保温方法,其特征在于,所述第一保湿层和第二保湿层的材料相同,均为PET聚酯薄膜,其厚度为10-30mm。
5.如权利要求4所述的组合梁湿接缝冬季施工电伴热保温方法,其特征在于,所述第一保温层和第二保温层的材料相同,均为具有阻燃作用的三聚氰胺改性脲醛泡沫材料,其厚度为40-70mm。
6.如权利要求5所述的组合梁湿接缝冬季施工电伴热保温方法,其特征在于,所述温控箱预设的最高温为40℃,最低温为10℃。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510046213.2A CN104652835B (zh) | 2015-01-29 | 2015-01-29 | 一种组合梁湿接缝冬季施工电伴热保温方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201510046213.2A CN104652835B (zh) | 2015-01-29 | 2015-01-29 | 一种组合梁湿接缝冬季施工电伴热保温方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN104652835A true CN104652835A (zh) | 2015-05-27 |
CN104652835B CN104652835B (zh) | 2016-09-14 |
Family
ID=53244418
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201510046213.2A Active CN104652835B (zh) | 2015-01-29 | 2015-01-29 | 一种组合梁湿接缝冬季施工电伴热保温方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN104652835B (zh) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105021041A (zh) * | 2015-07-29 | 2015-11-04 | 中国一冶集团有限公司 | 用于加热炉支撑梁冬季施工的保温装置 |
CN106239711A (zh) * | 2016-08-26 | 2016-12-21 | 中交第二航务工程局有限公司 | 一种冬季现浇混凝土构件养护方法 |
CN107269012A (zh) * | 2017-07-24 | 2017-10-20 | 北京博艺远景园林养护服务中心 | 冬季基础施工温度控制方法 |
CN110590398A (zh) * | 2019-08-28 | 2019-12-20 | 中铁大桥局集团第一工程有限公司 | 一种钢混结合梁的薄壁混凝土加热养护方法 |
CN110983974A (zh) * | 2019-11-21 | 2020-04-10 | 中交第二航务工程局有限公司 | 混凝土箱梁冬期施工综合养护方法 |
CN112761075A (zh) * | 2020-12-30 | 2021-05-07 | 中化学交通建设集团有限公司 | 一种混凝土桥墩冬季保温装置 |
CN112942113A (zh) * | 2021-01-27 | 2021-06-11 | 中铁十六局集团有限公司 | 一种用于节段梁湿接缝养护的可加温模板 |
CN112982173A (zh) * | 2021-02-25 | 2021-06-18 | 中建八局第四建设有限公司 | 一种桥梁伸缩缝的冬期施工养生方法 |
CN113187254A (zh) * | 2021-04-23 | 2021-07-30 | 中国建筑第八工程局有限公司 | 缓粘结预应力筋张拉升温装置及升温方法 |
CN114717959A (zh) * | 2022-04-14 | 2022-07-08 | 中交第四公路工程局有限公司 | 一种桥梁湿接缝混凝土用蓄热保温养护装置 |
CN114855569A (zh) * | 2022-05-20 | 2022-08-05 | 山西机械化建设集团有限公司 | 高原地区机场道面砼“两布一带一剂”低温养生方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3827655C1 (en) * | 1988-08-16 | 1989-09-14 | Ed. Zueblin Ag, 7000 Stuttgart, De | Process for keeping concrete surfaces moist, and a moisture-storing layer for carrying out the process |
JPH0988348A (ja) * | 1995-09-27 | 1997-03-31 | Taisei Corp | 基礎梁の施工方法 |
CN102092089A (zh) * | 2010-12-15 | 2011-06-15 | 中国建筑第二工程局有限公司 | 冬期混凝土电热丝加热装置及其施工方法 |
CN102363320A (zh) * | 2011-11-01 | 2012-02-29 | 中铁四局集团第一工程有限公司 | 冬季混凝土养生毯施工的方法 |
CN102383365A (zh) * | 2011-11-04 | 2012-03-21 | 广东冠粤路桥有限公司 | 混凝土保湿加温养生装置及其应用方法 |
CN103255920A (zh) * | 2013-04-25 | 2013-08-21 | 中国华冶科工集团有限公司 | 钢柱头混凝土冬季施工保温方法 |
-
2015
- 2015-01-29 CN CN201510046213.2A patent/CN104652835B/zh active Active
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3827655C1 (en) * | 1988-08-16 | 1989-09-14 | Ed. Zueblin Ag, 7000 Stuttgart, De | Process for keeping concrete surfaces moist, and a moisture-storing layer for carrying out the process |
JPH0988348A (ja) * | 1995-09-27 | 1997-03-31 | Taisei Corp | 基礎梁の施工方法 |
CN102092089A (zh) * | 2010-12-15 | 2011-06-15 | 中国建筑第二工程局有限公司 | 冬期混凝土电热丝加热装置及其施工方法 |
CN102363320A (zh) * | 2011-11-01 | 2012-02-29 | 中铁四局集团第一工程有限公司 | 冬季混凝土养生毯施工的方法 |
CN102383365A (zh) * | 2011-11-04 | 2012-03-21 | 广东冠粤路桥有限公司 | 混凝土保湿加温养生装置及其应用方法 |
CN103255920A (zh) * | 2013-04-25 | 2013-08-21 | 中国华冶科工集团有限公司 | 钢柱头混凝土冬季施工保温方法 |
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105021041A (zh) * | 2015-07-29 | 2015-11-04 | 中国一冶集团有限公司 | 用于加热炉支撑梁冬季施工的保温装置 |
CN106239711A (zh) * | 2016-08-26 | 2016-12-21 | 中交第二航务工程局有限公司 | 一种冬季现浇混凝土构件养护方法 |
CN107269012A (zh) * | 2017-07-24 | 2017-10-20 | 北京博艺远景园林养护服务中心 | 冬季基础施工温度控制方法 |
CN110590398A (zh) * | 2019-08-28 | 2019-12-20 | 中铁大桥局集团第一工程有限公司 | 一种钢混结合梁的薄壁混凝土加热养护方法 |
CN110983974A (zh) * | 2019-11-21 | 2020-04-10 | 中交第二航务工程局有限公司 | 混凝土箱梁冬期施工综合养护方法 |
CN110983974B (zh) * | 2019-11-21 | 2021-04-30 | 中交第二航务工程局有限公司 | 混凝土箱梁冬期施工综合养护方法 |
CN112761075A (zh) * | 2020-12-30 | 2021-05-07 | 中化学交通建设集团有限公司 | 一种混凝土桥墩冬季保温装置 |
CN112942113A (zh) * | 2021-01-27 | 2021-06-11 | 中铁十六局集团有限公司 | 一种用于节段梁湿接缝养护的可加温模板 |
CN112982173A (zh) * | 2021-02-25 | 2021-06-18 | 中建八局第四建设有限公司 | 一种桥梁伸缩缝的冬期施工养生方法 |
CN113187254A (zh) * | 2021-04-23 | 2021-07-30 | 中国建筑第八工程局有限公司 | 缓粘结预应力筋张拉升温装置及升温方法 |
CN114717959A (zh) * | 2022-04-14 | 2022-07-08 | 中交第四公路工程局有限公司 | 一种桥梁湿接缝混凝土用蓄热保温养护装置 |
CN114855569A (zh) * | 2022-05-20 | 2022-08-05 | 山西机械化建设集团有限公司 | 高原地区机场道面砼“两布一带一剂”低温养生方法 |
Also Published As
Publication number | Publication date |
---|---|
CN104652835B (zh) | 2016-09-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104652835A (zh) | 一种组合梁湿接缝冬季施工电伴热保温方法 | |
CN203571851U (zh) | 一种节能速热的电热陶瓷地暖砖 | |
CN103982021B (zh) | 一种加强肋保温装饰系统施工工法 | |
CN103465540B (zh) | 非固化橡胶沥青涂料与卷材复合防水层的制备方法和施工方法 | |
CN205897316U (zh) | 一种智能温控发热墙纸 | |
CN103195248B (zh) | 一种用于冬季浇筑高寒高海拔地区混凝土的施工方法 | |
CN111851310A (zh) | 一种冬季施工浇筑模板的加热保温系统、保温方法、施工方法 | |
CN113216482A (zh) | 一种钢桁架楼承板电加热保温系统 | |
CN113404317A (zh) | 冬季施工混凝土智能变功率温控墙体保温模板 | |
CN105155703A (zh) | 一种stp芯材的制备方法 | |
CN103485429B (zh) | Hd-stp建筑外墙超薄真空绝热板及其施工工艺 | |
CN203213532U (zh) | 一种低温地板辐射采暖施工结构 | |
CN104534544B (zh) | 一种抗压防腐防水防潮电热板 | |
CN202412428U (zh) | 多功能混凝土养护模板 | |
CN208396162U (zh) | 一种蓄水隔热屋面 | |
CN216616362U (zh) | 一种气凝胶毡外墙外保温系统 | |
CN103993687A (zh) | 防护-保温-结构一体化的外墙结构及其制造方法 | |
CN209620426U (zh) | 一种亚刚性屋面结构板构造 | |
CN201753315U (zh) | 一种浮法玻璃退火窑 | |
CN207460527U (zh) | 一种混凝土施工恒温电加热装置 | |
CN206538921U (zh) | 屋面结构 | |
CN207390018U (zh) | 一种沥青储罐的保温罐体结构 | |
CN207863199U (zh) | 一种防水保温一体化板 | |
CN215716227U (zh) | 一种用于寒区普通混凝土墙体的养护装置 | |
CN206818574U (zh) | 一种建筑材料测控实验装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |