CN104153352B - Karst geology rotary-drilling bored concrete pile hole forming process - Google Patents

Karst geology rotary-drilling bored concrete pile hole forming process Download PDF

Info

Publication number
CN104153352B
CN104153352B CN201410376534.4A CN201410376534A CN104153352B CN 104153352 B CN104153352 B CN 104153352B CN 201410376534 A CN201410376534 A CN 201410376534A CN 104153352 B CN104153352 B CN 104153352B
Authority
CN
China
Prior art keywords
concrete
pile
conduit
drilling
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201410376534.4A
Other languages
Chinese (zh)
Other versions
CN104153352A (en
Inventor
王家全
黄柳云
朱庆盛
吴辉琴
黄世斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi University of Science and Technology
Original Assignee
Guangxi University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi University of Science and Technology filed Critical Guangxi University of Science and Technology
Priority to CN201410376534.4A priority Critical patent/CN104153352B/en
Publication of CN104153352A publication Critical patent/CN104153352A/en
Application granted granted Critical
Publication of CN104153352B publication Critical patent/CN104153352B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Earth Drilling (AREA)

Abstract

The invention discloses a karst geology rotary-drilling bored concrete pile hole forming process which includes the steps of 1, leveling a field; 2, paying off at a pile foundation; 3, setting a rotary drilling machine in place; 4, embedding a pile casing; 5, preparing mud stabilizing liquid and filling the mud stabilizing liquid into the pile casing; 6, forming holes by means of rotary drilling (with requirements of reducing drilling speed when drilling in karst caves or half rocks, otherwise, drilling to reach designed elevation ); 7, performing primary cleaning of holes and hole depth checking; 8, mounting a reinforced cage and a conduit; 9, performing secondary cleaning through air-lift reverse circulation; 10, pouring underwater concrete (while preparing extra 30-40 cubic meters of concrete with consideration of karst caves so as to prevent pile scrap caused by breakdown of the karst caves and sharp sinking of concrete); and 11, forming a pile and removing the pile casing.

Description

A kind of Karst Geological Landscape rotary digging pouring pile hole technique
Technical field
The present invention relates to a kind of pile foundation construction process, specifically, it is related to a kind of Karst Geological Landscape rotary digging pouring pile hole work Skill.
Background technology
Rotary digging drilling hole bored concrete pile construction technology is the pile foundation construction process of rising in recent years.At present, existing rotary digging drilling hole Construction process of bored concrete pile is:Smooth location → stake position unwrapping wire → rotary drilling rig is in place → embedded casing → casing in supplement stabilizing solution → spiral-digging pore → borehole cleaning, check hole depth → installation steel reinforcement cage and conduit → secondary pile hole cleaning → pour underwater concrete → pile, Extract casing.Existing construction technology quality control standard and construction technology technical standard also do not have specifically national engineering method mark Accurate.Existing construction technology is for general geological condition, if indiscriminately imitated in the complex karst area of geological condition The rotary digging drilling hole bored concrete pile construction technology of general geology will occur different problems, and topmost problem has hole scattering, card Bore, drill bit drops, borehole cleaning is not thorough and broken pile and useless stake phenomenon etc..Install that stability in place is poor due to rig, operation when Rig is installed the reasons such as unstable or drill pipe buckling, ground is weak or soft or hard is uneven and is led to hole scattering;Due to solution cavity and one side of something The presence of rock, if not noting during rotary digging drilling, may result in bit freezing or the problems such as drill bit drops;During the spiral-digging pore of karst region The carg producing is more than in general geology, borehole cleaning not thorough phenomenon will occur with general borehole cleaning mode, thus meeting Lead to pile bottom sediment more, have a strong impact on the quality of pile foundation;Due to the presence of solution cavity, in casting concrete it is possible that molten Hole is breakdown, leads to concrete drastically to decline, thus broken pile and useless stake phenomenon.
Content of the invention
In order to overcome defect present in prior art, the present invention proposes a kind of Karst Geological Landscape rotary digging pouring pile hole work Skill.Its technical scheme is as follows:
A kind of Karst Geological Landscape rotary digging pouring pile hole technique, comprises the following steps:
1) levelling of the land.Removing obstacles before construction, change except weak soil, grinding compacting.Planning travelling line, makes road and boring Position maintains a certain distance and (avoids affecting wall stability, simultaneously it is also contemplated that clearing the side of the earthwork in rotary digging drilling hole construction Just);
2) pile foundation unwrapping wire, rotary drilling rig are in place.Line setting is carried out using total powerstation, unwrapping wire control errors are less than 1cm.Stake Machine is positioned to accurately, and rig center of pilot line, turntable center line, pile foundation center line should be maintained at same straight line;
3) bury casing.Cross hairs is drawn to put four control stakes according to pile foundation anchor point, embedded on the basis of four control stakes Steel sheath cylinder, cylinder is high to be typically no less than 2m, and for protecting hole wall, the height that bassets is typically no less than 0.3m;
4) supplement mud stabilizing solution in the preparation of mud stabilizing solution and casing.During the rotary digging drilling hole of karst region, boring mud is more, So the proportion of control mud stabilizing solution is very crucial, mud balance is controlled to be not less than 1.1, viscosity 20s about, sand factor is less than 4%;
5) rotary digging drilling and forming hole.Run into and will slow down rate of penetration when solution cavity or half rock and (can be controlled in 10~20mm/ Min), it is drilled into designed elevation when not running into solution cavity or half rock;
6) borehole cleaning, an inspection hole depth.First improve drill bit to away from bottom hole 80~100mm, to input proportion be 1.05~ 1.08 new mud stabilizing solution is circulated, and carries out borehole cleaning with pressure fan;
7) steel reinforcement cage and conduit are installed;
8) gas lift reverse circulation secondary pile hole cleaning.It is more thorough that reacting cycle secondary pile hole cleaning makes boring mud clear up, and pile bottom sediment is few, pile body Quality significantly improves, and substantially reduces the borehole cleaning time, improves pore-forming efficiency;
9) pour underwater concrete.Conduit must be tightly it is ensured that conduit bottom be apart from bottom hole 30~50cm;Concrete mixes and stirs Must uniformly, the slump controls in 18~22cm, and will ensure a certain amount of concrete beginning quantity it is ensured that back cover is successful;Coagulation Soil pours must work continuously;Special messenger should be had in casting process to be responsible for record, it is to avoid conduit lifting is too fast or conduit embedment is too deep, Control mouth Transducers Embedded in Concrete depth 2~6m under conduit, prevent broken pile;The top surface absolute altitude of bored concrete pile should higher than design load be not less than 60cm, to guarantee the quality of stake top concrete;
10) pile, extract casing.
Using following optimization can be done in the case of Karst Geological Landscape is using rotary digging construction process of bored concrete pile more commonly matter:(1) During Karst Geological Landscape rotary digging drilling, when entering uneven strata, ramp-like rock stratum or encountering solution cavity or half rock, brill to be slowed down Enter speed (caning be controlled in 10~20mm/min), keep the perpendicularity of kelly, it is to avoid bit freezing or drill bit drop.When boring is inclined When tiltedly, drill bit can be lifted, repeatedly sweep brill several times up and down.If accompanying big boulder or solution cavity in soil layer is in ramp-like distribution, irrigate C15 concrete more than 0.5m to inclined hole, creeps into again to after concrete final set;(2) in Karst Geological Landscape pore-forming after-pouring pile During, complex (being likely that there are solution cavity) two piles of geological condition should be selected according to geologic report and carry out coagulation Soil perfusion pile, when solution cavity may be breakdown under high pressure effect, thus concrete drastically decline phenomenon, leads to this Stake becomes useless stake, can shift to an earlier date 30~40 cubes of concrete of many preparations according to a large amount of site operation experiences, (according to a large amount of site operations Experience, if aperture does not have mud to return out when concrete perfusion, just explanation has the presence of solution cavity), there is this existing As when can supplement concrete in time, need it is specifically intended that now necessarily can not be eager pull out conduit, it is to avoid conduit extract after Start concrete occurs drastically to decline, conduit now will occur and be in above concrete, thus leading to useless stake.
Beneficial effects of the present invention are:
The present invention is improved to existing rotary digging drilling hole bored concrete pile construction technology, is more suitable for geological condition relatively after improvement For complicated karst area, the pile efficiency of karst area rotary digging bored concrete pile can be improved.Improved technology can be kept away effectively Exempt from hole scattering and occur timely solving skew problems during drilling rod deflection;Occur during rotary digging drilling can be effectively prevented from Bit freezing and drill bit drop problem;Can be effectively prevented from because borehole cleaning does not thoroughly lead to sediment blocked up affects bearing capacity of pile foundation; Can be effectively prevented from because solution cavity presence leads to concrete drastically to decline makes pile foundation become useless stake.
Brief description
Fig. 1 is Karst Geological Landscape rotary digging pouring pile hole technological process of the present invention;
Fig. 2 is underwater concreting mode;
Fig. 3 is hopper switch;
Fig. 4 is concrete first watering schematic diagram.
Specific embodiment
With reference to the accompanying drawings and detailed description technical scheme is described in more detail.
With reference to Fig. 1, the technical solution adopted for the present invention to solve the technical problems is:The improved spiral-digging pore in karst region fills Note stake construction technology process be:Smooth location → stake position unwrapping wire → rotary drilling rig is in place → embedded casing → casing in supplement steady Determine liquid → spiral-digging pore (run into and will slow down rate of penetration during solution cavity, be drilled into designed elevation when not running into solution cavity) → borehole cleaning, inspection Look into hole depth → installation steel reinforcement cage and conduit → gas lift reverse circulation secondary pile hole cleaning → pour underwater concrete (consider the presence of solution cavity, Need prepare 30~40 cubes of concrete, prevent solution cavity from puncturing, concrete drastically decline lead to useless stake) → pile, extract casing.
In order to avoid hole scattering in drilling process, Spiral digging machine center of turntable during rigging up, is required to slide with lifting on drilling cramp In same axis, drilling rod position deviation is not more than 20cm to wheel, when entering uneven strata, ramp-like rock stratum or encountering half rock, Slow down rate of penetration.When hole scattering, drill bit can be lifted, repeatedly sweep brill several times up and down.If accompany in soil layer big boulder or Solution cavity is in ramp-like distribution, then irrigate C15 concrete more than 0.5m to inclined hole, again creep into after concrete final set.
Need in view of molten when the complex karst area of geological condition is using rotary digging pouring pile hole construction technology The existing problems in hole, during spiral-digging pore, when rotary digging drill bit runs into solution cavity or half rock, must slow down drilling speed Degree, keeps the perpendicularity of kelly, it is to avoid bit freezing or drill bit drop.
Borehole cleaning work after pore-forming is very crucial, and rotary digging drilling hole bored concrete pile frequently can lead to bearing capacity because bottom hole sediment is blocked up Reduction, has a strong impact on the quality of pile foundation, and the carg producing during the spiral-digging pore of karst region is more than in general geology, uses General borehole cleaning mode would become hard to borehole cleaning thoroughly, thus pile bottom sediment can be led to more, the rotary digging bored concrete pile of therefore karst region exists In time secondary pile hole cleaning is carried out using " gas lift reverse circulation " after putting into steel reinforcement cage, carrying out concreting in time after borehole cleaning will be fine Ground solves the excessive problem of pile bottom sediment.
Pour first it is ensured that conduit has the buried depth of more than 1m during underwater concrete, concrete beginning quantity calculates schematic diagram such as Shown in Fig. 4, beginning quantity is as follows with reference to computing formula:
In formula:V- concrete beginning quantity (m3);
D- stake holes diameter (m);
H1- conduit bottom is to the distance (m) of stake holes bottom, generally 0.4~0.5m;
H2The depth (m) of-first placing concrete rear tube Transducers Embedded in Concrete, generally more than 1m;
h1- stake holes inner concrete reaches H2When, the outer height (m) needed for mud pressure of conduit inner concrete column equilibration conduit;
In order to ensure when pouring underwater concrete first, conduit has the buried depth of more than 1m, underwater concreting is using as schemed 2 shown devices are poured, and by hoist cable, concrete hopper is sling with crane, conduit is connected with hopper, pour when pouring Hopper cuts out by front hopper switch (as shown in Figure 3), treats to fill hopper by concrete that (general hopper is 3m3Left and right, stake footpath is more than With two hoppers stacking during 2.7m) after again by hopper switch open, concrete under gravity, sweeps away along conduit First watering back cover can be completed.In Fig. 3, hopper switch is made up of a steel disk and gusseted, puts before hopper dress concrete Hopper switchs, and gusseted is enclosed within conduit mouth and plays a fixation, is connected with hoist cable in the middle of steel disk, treats that concrete fills With loop wheel machine, steel disk is sling during full hopper, concrete can sweep away along conduit and can complete first watering back cover.
During perfusion bore forming, should be selected according to geologic report and be likely that there are two piles of solution cavity and carry out coagulation Soil perfusion pile, when solution cavity may be breakdown under high pressure effect, thus concrete drastically decline phenomenon, leads to this Stake becomes useless stake, can shift to an earlier date 30~40 cubes of concrete of many preparations according to a large amount of site operation experiences, (according to a large amount of site operations Experience, if aperture does not have mud to return out when concrete perfusion, just explanation has the presence of solution cavity), there is this existing As when can supplement concrete in time, need it is specifically intended that now necessarily can not be eager pull out conduit, it is to avoid conduit extract after Starting concrete occurs drastically to decline, conduit now will occur and be in above concrete, thus leading to useless stake, taking this to arrange Apply and can improve karst region rotary digging filling pile construction benefit to a certain extent.
The above, the only present invention preferably specific embodiment, protection scope of the present invention not limited to this, any ripe Know those skilled in the art in the technical scope of present disclosure, the letter of the technical scheme that can become apparent to Altered or equivalence replacement each fall within protection scope of the present invention.

Claims (1)

1. a kind of Karst Geological Landscape rotary digging pouring pile hole technique is it is characterised in that comprise the following steps:
1) levelling of the land:Removing obstacles before construction, change except weak soil, grinding compacting;Planning travelling line, makes road and bore position Maintain a certain distance;Avoid affecting wall stability, simultaneously it is also contemplated that clearing the convenience of the earthwork in rotary digging drilling hole construction;
2) pile foundation unwrapping wire, rotary drilling rig are in place:Line setting is carried out using total powerstation, unwrapping wire control errors are less than 1cm;Stake machine is fixed Position will accurately, and rig center of pilot line, turntable center line, pile foundation center line should be maintained at same straight line;
3) bury casing:Cross hairs is drawn to put four control stakes according to pile foundation anchor point, embedded steel shield on the basis of four control stakes Sleeve, cylinder high not less than 2m, for protecting hole wall, the height that bassets is not less than 0.3m;
4) supplement mud stabilizing solution in the preparation of mud stabilizing solution and casing:During the rotary digging drilling hole of karst region, control mud balance Not less than 1.1, viscosity 20s, sand factor is less than 4%;
5) rotary digging drilling and forming hole:In order to avoid hole scattering in drilling process, during rigging up require Spiral digging machine center of turntable with On drilling cramp, in same axis, drilling rod position deviation is not more than 20cm to lifting pulley;Run into and drilling when solution cavity or half rock, will be slowed down Speeds control, in 10~20mm/min, is drilled into designed elevation when not running into solution cavity or half rock;If accompanying big orphan in soil layer Stone or solution cavity are in ramp-like distribution, then irrigate C15 concrete more than 0.5m to inclined hole, again creep into after concrete final set;
6) borehole cleaning, an inspection hole depth:First improving drill bit to away from bottom hole 80~100mm, inputting proportion is 1.05~1.08 New mud stabilizing solution is circulated, and carries out borehole cleaning with pressure fan;
7) steel reinforcement cage and conduit are installed;
8) gas lift reverse circulation secondary pile hole cleaning;
9) pour underwater concrete:Pour first during underwater concrete it is ensured that conduit has the buried depth of more than 1m;For guarantee to have 1m with On buried depth, by hoist cable, concrete hopper is sling with crane when pouring, conduit is connected with hopper, pours front hopper and open Close and hopper cut out, fill after hopper after concrete and again hopper switch is opened, concrete under gravity, along conduit Sweep away and can complete first watering back cover;Wherein hopper switch is made up of a steel disk and gusseted, and hopper fills concrete Put down hopper switch, gusseted is enclosed within conduit mouth and plays a fixation before, connected with hoist cable in the middle of steel disk, wait to mix Solidifying soil is filled and with loop wheel machine, steel disk is sling during hopper, and concrete can sweep away along conduit;
Conduit must be tightly it is ensured that conduit bottom be apart from bottom hole 30~50cm;Concrete mixes and stirs must uniformly, and the slump controls 18~22cm, concreting must be worked continuously;Special messenger should be had in casting process to be responsible for record, it is to avoid conduit lifting too fast or Conduit embedment is too deep, controls mouth Transducers Embedded in Concrete depth 2~6m under conduit, prevents broken pile;The top surface absolute altitude of bored concrete pile should ratio set Evaluation is high to be not less than 60cm;
When pouring underwater concrete first, concrete beginning quantity computing formula is as follows:
V ≥ πD 2 ( H 1 + H 2 ) 4 + πd 2 h 1 4
In formula:V- concrete beginning quantity;D- stake holes diameter;H1- conduit bottom, to the distance of stake holes bottom, is 0.4~0.5m;H2- The depth of first placing concrete rear tube Transducers Embedded in Concrete, is more than 1m;h1- stake holes inner concrete reaches H2When, mixed in conduit The outer height needed for mud pressure of solidifying earth pillar balance pipe;
In Karst Geological Landscape pore-forming after-pouring formation of pile, should be selected according to geologic report and be likely that there are two piles of solution cavity and enter Row filling concrete pile, 30~40 cubes of concrete of many preparations in advance, if aperture does not have mud when concrete perfusion Slurry returns out, and just explanation has the presence of solution cavity, occurs to supplement concrete in time during this phenomenon, and can not be eager to pull out conduit;
10) pile, extract casing.
CN201410376534.4A 2014-07-31 2014-07-31 Karst geology rotary-drilling bored concrete pile hole forming process Active CN104153352B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410376534.4A CN104153352B (en) 2014-07-31 2014-07-31 Karst geology rotary-drilling bored concrete pile hole forming process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410376534.4A CN104153352B (en) 2014-07-31 2014-07-31 Karst geology rotary-drilling bored concrete pile hole forming process

Publications (2)

Publication Number Publication Date
CN104153352A CN104153352A (en) 2014-11-19
CN104153352B true CN104153352B (en) 2017-02-15

Family

ID=51878966

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410376534.4A Active CN104153352B (en) 2014-07-31 2014-07-31 Karst geology rotary-drilling bored concrete pile hole forming process

Country Status (1)

Country Link
CN (1) CN104153352B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109056709A (en) * 2018-08-22 2018-12-21 中铁二十二局集团有限公司 A method of using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation

Families Citing this family (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104674780A (en) * 2015-02-06 2015-06-03 中鼎国际工程有限责任公司 Karst stratum stabilization structure
CN104831708A (en) * 2015-03-20 2015-08-12 深圳市工勘岩土集团有限公司 Foundation excavation retaining and protecting cast-in-situ bored pile construction method and equipment thereof
CN105714772B (en) * 2016-02-22 2018-04-03 北龙建设集团有限公司 Karst area embedded rock pile pore-forming bores concrete dado method again
CN106522209A (en) * 2016-10-08 2017-03-22 金陵科技学院 Perfusion construction method of cast-in-situ bored pile for revolving-boring construction of karst cave
CN106836206A (en) * 2017-03-30 2017-06-13 重庆建工住宅建设有限公司 Casing rotary digging bore forming method
CN106930276B (en) * 2017-04-11 2018-11-06 广州智弘建筑物检测与鉴定技术有限公司 The construction method of the deep hole blasting of rotary digging bored concrete pile and conduit rotary digging removing obstacles
CN107246006B (en) * 2017-06-29 2019-11-05 深圳市蛇口招商港湾工程有限公司 The pile-filling method of concrete-pile
CN107386276A (en) * 2017-07-20 2017-11-24 广州市建筑科学研究院新技术开发中心有限公司 A kind of construction method of soft layer super-long and large-diameter bored piles
CN108086342A (en) * 2017-12-22 2018-05-29 中交第三航务工程局有限公司宁波分公司 The construction method of karst strata pile foundation
CN108049397A (en) * 2017-12-22 2018-05-18 中交第三航务工程局有限公司宁波分公司 The construction method of Karst Geological Landscape drilled pile
CN108487286B (en) * 2018-02-06 2020-12-08 广州市市政工程设计研究总院有限公司 Method for constructing continuous bearing stratum of ultralong rock-socketed pile in beaded karst region
CN108442364A (en) * 2018-04-18 2018-08-24 中铁十九局集团轨道交通工程有限公司 Karsts developing area stratum can prevent a full set of cylinder pile-forming apparatus and pile making method of broken pile
CN109056706A (en) * 2018-08-03 2018-12-21 上海宝冶集团有限公司 A kind of Karst Geological Landscape poured pile base construction method
CN109989718A (en) * 2019-03-26 2019-07-09 上海建工二建集团有限公司 Karst area churning driven grog handles borehole cleaning tool and its production and construction method
CN110158579A (en) * 2019-04-26 2019-08-23 中国水利水电第九工程局有限公司 A kind of bored pile construction method
CN110080785A (en) * 2019-05-16 2019-08-02 中铁隧道局集团有限公司 Compound stratum super-large-diameter shield normal pressure warehouse entry reinforced construction method near water
CN111535307B (en) * 2020-05-22 2022-09-06 中冀建勘集团有限公司 Hole forming construction method for rotary drilling cast-in-place pile in reef limestone stratum
CN111677439A (en) * 2020-06-24 2020-09-18 中建四局土木工程有限公司 Drilling hole forming method of reverse circulation rotary drilling machine
CN111733801A (en) * 2020-06-28 2020-10-02 中冶地集团西北岩土工程有限公司 Construction process of rotary drilling bored concrete pile in soft geology
CN111927320A (en) * 2020-07-31 2020-11-13 中国建筑第四工程局有限公司 Ultra-deep large-diameter pile hole forming method
CN113338355B (en) * 2021-05-19 2021-12-14 中国建筑第二工程局有限公司 Construction method for judging rocks and mechanically anchoring anchor rods in strong development karst area
CN113356191A (en) * 2021-06-16 2021-09-07 中交第三航务工程局有限公司 Method for pile foundation construction in karst area to follow up construction of long steel casing
CN113445496A (en) * 2021-06-21 2021-09-28 广东北方基础建筑有限公司 Rotary drilling cast-in-place pile and construction process thereof
CN113931189A (en) * 2021-11-10 2022-01-14 贵州建工集团第一建筑工程有限责任公司 Secondary hole cleaning construction method for cast-in-situ bored pile based on gas lift reverse circulation
CN114059921A (en) * 2021-11-17 2022-02-18 广州铁路投资建设集团有限公司 Hole-forming construction process for cast-in-place pile in karst strong development area
CN114277781A (en) * 2021-11-30 2022-04-05 山东省公路桥梁建设集团有限公司 Karst area pile foundation pore-forming construction method
CN115110520A (en) * 2022-04-27 2022-09-27 中国建筑第七工程局有限公司 Construction method of bridge pile foundation on highway

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5099696A (en) * 1988-12-29 1992-03-31 Takechi Engineering Co., Ltd. Methods of determining capability and quality of foundation piles and of designing foundation piles, apparatus for measuring ground characteristics, method of making hole for foundation pile such as cast-in-situ pile and apparatus therefor
JPH07113229A (en) * 1993-10-19 1995-05-02 Kajima Corp Cast-in-place concrete pile method
CN102966094A (en) * 2012-12-15 2013-03-13 马春根 Method for constructing concrete pile through rotary excavating and pressure irrigation
CN103485716A (en) * 2013-09-27 2014-01-01 福建成森建设集团有限公司 Karst-geology rotary-drill guide-hole construction method

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101109179A (en) * 2007-06-21 2008-01-23 河北建设勘察研究院有限公司 Gas lifting reverse circulation porus cleaning construction method for slurry bulkhead cast-in-situ bored pile
CN102995632A (en) * 2012-11-21 2013-03-27 中国石油天然气集团公司 Cast-in-situ bored pile technique
CN103696417B (en) * 2013-12-20 2016-01-06 中国一冶集团有限公司 Secondary pile hole cleaning device and method bottom a kind of bored pile

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5099696A (en) * 1988-12-29 1992-03-31 Takechi Engineering Co., Ltd. Methods of determining capability and quality of foundation piles and of designing foundation piles, apparatus for measuring ground characteristics, method of making hole for foundation pile such as cast-in-situ pile and apparatus therefor
JPH07113229A (en) * 1993-10-19 1995-05-02 Kajima Corp Cast-in-place concrete pile method
CN102966094A (en) * 2012-12-15 2013-03-13 马春根 Method for constructing concrete pile through rotary excavating and pressure irrigation
CN103485716A (en) * 2013-09-27 2014-01-01 福建成森建设集团有限公司 Karst-geology rotary-drill guide-hole construction method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
BARAKI体育场58m长旋挖成孔灌注桩施工技术;严建峰;《施工技术》;20101130;第39卷(第11期);第62-63页第4节 *
旋挖孔施工工艺和特点;唐进;《工程技术》;20131231(第6期);第44页第二节第2段 *
旋挖钻机在溶洞地层桩基施工中的问题及处理;蔡志舰等;《筑路机械与施工机械化》;20131231(第2期);第79页第2.1节第2段 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109056709A (en) * 2018-08-22 2018-12-21 中铁二十二局集团有限公司 A method of using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation

Also Published As

Publication number Publication date
CN104153352A (en) 2014-11-19

Similar Documents

Publication Publication Date Title
CN104153352B (en) Karst geology rotary-drilling bored concrete pile hole forming process
CN106284313B (en) Long spire based on circulating mud retaining wall is squeezed into rock filling pile construction method
CN103850249B (en) Long spire is squeezed into rock filling pile construction technology
CN104563098B (en) A kind of super-large diameter all steel casing does operation pore-creating filling pile construction method
CN107938676A (en) A kind of pile base construction method for passing through full packing type solution cavity
CN105275381B (en) Impact drill drilling construction method in rich water pebble layer
CN103195058B (en) Be convenient to solution cavity and grow the method that regional bridge pier adopts many casings to construct
CN104532821A (en) Extra-large karst cave bottom treatment construction method
CN106193042B (en) Obstacle pile sweep-out method at ground wall is gone along with sb. to guard him close in underground structure sandy soil layer
CN107938656A (en) Complexity rebuilds base pit engineering pile base construction method
CN101768961A (en) Construction method of section-steel triaxial soil-cement mixing pile
CN104694746A (en) Ion-adsorption-type rare earth in-situ leaching method and leaching system thereof
CN106978807A (en) Existing bridge pile pulling device and construction method are passed through by a kind of weak soil shield driving area
CN108894210A (en) The comprehensive construction method of continuous wall trench under a kind of COMPLEX MIXED formation condition for sea area
CN206308569U (en) It is a kind of to reinforce the road structure for punishing the solution cavity that underlies
CN107246007B (en) A kind of CFG of construction method
CN103774690A (en) Grabbing, drilling and punching combined underground continuous wall grooving construction method
CN108505935A (en) Rectangle pile foundation drilling construction equipment and construction method
CN111236216A (en) Construction method of bridge drilled pile
CN107083932A (en) The installation method of steel pipe column in the clean cycle equipment that drills and pilot tunnel
CN113323584A (en) Drilling method of large vibrating long spiral drilling machine
CN106677166A (en) Flow construction method for forming cast-in-place bored pile for gravel-decomposed rock stratum in double-machine combined mode
CN107653878A (en) Cast-in-situ bored pile is reusable to be longitudinally separated formula steel pile casting construction
CN105369800B (en) One-time forming construction method for inserting steel pipe column into cast-in-situ bored pile in pilot tunnel
CN108049397A (en) The construction method of Karst Geological Landscape drilled pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant