CN104153352A - Karst geology rotary-drilling bored concrete pile hole forming process - Google Patents

Karst geology rotary-drilling bored concrete pile hole forming process Download PDF

Info

Publication number
CN104153352A
CN104153352A CN201410376534.4A CN201410376534A CN104153352A CN 104153352 A CN104153352 A CN 104153352A CN 201410376534 A CN201410376534 A CN 201410376534A CN 104153352 A CN104153352 A CN 104153352A
Authority
CN
China
Prior art keywords
pile
hole
concrete
drilling
conduit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410376534.4A
Other languages
Chinese (zh)
Other versions
CN104153352B (en
Inventor
王家全
黄柳云
朱庆盛
吴辉琴
黄世斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi University of Science and Technology
Original Assignee
Guangxi University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi University of Science and Technology filed Critical Guangxi University of Science and Technology
Priority to CN201410376534.4A priority Critical patent/CN104153352B/en
Publication of CN104153352A publication Critical patent/CN104153352A/en
Application granted granted Critical
Publication of CN104153352B publication Critical patent/CN104153352B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)
  • Earth Drilling (AREA)

Abstract

The invention discloses a karst geology rotary-drilling bored concrete pile hole forming process which includes the steps of 1, leveling a field; 2, paying off at a pile foundation; 3, setting a rotary drilling machine in place; 4, embedding a pile casing; 5, preparing mud stabilizing liquid and filling the mud stabilizing liquid into the pile casing; 6, forming holes by means of rotary drilling (with requirements of reducing drilling speed when drilling in karst caves or half rocks, otherwise, drilling to reach designed elevation ); 7, performing primary cleaning of holes and hole depth checking; 8, mounting a reinforced cage and a conduit; 9, performing secondary cleaning through air-lift reverse circulation; 10, pouring underwater concrete (while preparing extra 30-40 cubic meters of concrete with consideration of karst caves so as to prevent pile scrap caused by breakdown of the karst caves and sharp sinking of concrete); and 11, forming a pile and removing the pile casing.

Description

A kind of Karst Geological Landscape revolves and digs pouring pile hole technique
Technical field
The present invention relates to a kind of pile foundation construction process, specifically, relate to a kind of Karst Geological Landscape and revolve and dig pouring pile hole technique.
Background technology
Rotary digging drilling hole bored concrete pile construction technology is the pile foundation construction process of rising in recent years.At present, existing rotary digging drilling hole bored concrete pile construction technology is: smooth location → stake position unwrapping wire → rotary drilling rig is in place → and bury underground and in casing → casing, supplement stabilizing solution → revolve and scrape out hole → clear hole, check hole depth → installation reinforcing cage and conduit → secondary pile hole cleaning → build underwater concrete → pile, extract casing.Existing construction technology quality control standard and construction technology technical standard also do not have concrete national engineering method standard.Existing construction technology is for general geological condition, to there will be different problems if indiscriminately imitate the rotary digging drilling hole bored concrete pile construction technology of general geology in the comparatively complicated karst area of geological condition, topmost problem has that hole scattering, bit freezing, drill bit drop, clear hole not thoroughly and occur broken pile and useless stake phenomenon etc.During due to rig installation in position poor stability, operation, rig is installed shakiness or drill pipe buckling, ground weakness or soft or hard be inhomogeneous etc. that reason causes hole scattering; Due to the existence of solution cavity and half rock, dig while creeping into and do not note if revolve, will cause the problems such as bit freezing or drill bit drop; Karst region is revolved and is dug the carg producing in pore forming process than many in general geology, will there will be clearly thorough phenomenon of hole by general clear hole mode, thereby can cause pile bottom sediment more, has a strong impact on the quality of pile foundation; Due to the existence of solution cavity, in the time of concreting, may occur that solution cavity is breakdown, cause concrete sharply to decline, thereby occur broken pile and useless stake phenomenon.
Summary of the invention
In order to overcome the defect existing in prior art, the present invention proposes a kind of Karst Geological Landscape and revolve and dig pouring pile hole technique.Its technical scheme is as follows:
A kind of Karst Geological Landscape revolves and digs pouring pile hole technique, comprises the following steps:
1) levelling of the land.Construction before removing obstacles, change except weak soil, grinding compacting.Planning travelling line, makes road and bore position maintain a certain distance (avoid affecting wall stability, also should consider to clear in rotary digging drilling hole construction the convenience of the earthwork simultaneously);
2) pile foundation unwrapping wire, rotary drilling rig are in place.Adopt total powerstation to position unwrapping wire, the control of unwrapping wire error is less than 1cm.Position of p ile machine is wanted accurately, and rig center of pilot line, turntable center line, pile foundation center line should remain on same straight line;
3) bury casing underground.Draw cross hairs to put four according to pile foundation anchor point and control stake, control stake bury steel sheath cylinder underground as benchmark taking four, the high 2m that is generally not less than of cylinder, for protection hole wall, bassets and is highly generally not less than 0.3m;
4) in the preparation of mud stabilizing solution and casing, supplement mud stabilizing solution.In the rotary digging drilling hole process of karst region, boring mud is more, so it is very crucial to control the proportion of mud stabilizing solution, controls mud balance and be not less than 1.1, and viscosity 20s left and right, sand factor is less than 4%;
5) revolve and dig drilling and forming hole.While running into solution cavity or half rock, to slow down rate of penetration (caning be controlled in 10~20mm/min), while not running into solution cavity or half rock, be drilled into design elevation;
6) once clear hole, check hole depth.First drill bit is increased to apart from 80~100mm at the bottom of hole, the new mud stabilizing solution that input proportion is 1.05~1.08 circulates, and carries out hole clearly with pressure fan;
7) reinforcing cage and conduit are installed;
8) gas lift reverse circulation secondary pile hole cleaning.The clear hole of anti-circulation secondary makes boring mud cleaning comparatively thorough, and pile bottom sediment is few, and pile quality obviously improves, and has greatly shortened the clear hole time, improved pore-forming efficiency;
9) build underwater concrete.Conduit must be tight, ensures 30~50cm at the bottom of conduit bottom is apart from hole; Mixing concrete must be evenly, and the slump is controlled at 18~22cm, and will ensure a certain amount of concrete first watering amount, ensures back cover success; Concreting must be worked continuously; In casting process, should there is special messenger to be responsible for record, avoid conduit to promote too fast or conduit and imbedded deeply, control the conduit end opening Transducers Embedded in Concrete degree of depth 2~6m, prevent broken pile; The end face absolute altitude of castinplace pile should be than the high 60cm that is not less than of design load, to guarantee the concrete quality in stake top;
10) pile, extract casing.
Use to revolve to dig under the more general geological condition of construction process of bored concrete pile at Karst Geological Landscape and use and can do following optimization: (1) is revolved and dug in drilling process at Karst Geological Landscape, enter uneven strata, oblique shape rock stratum or encounter solution cavity or when half rock, slow down rate of penetration (caning be controlled in 10~20mm/min), keep the verticality of kelly, avoid bit freezing or drill bit to drop.In the time of hole scattering, can mention drill bit, repeatedly sweep brill several times up and down.Be oblique shape distribution if accompany large boulder or solution cavity in soil layer, pour into C15 concrete to more than the inclined to one side hole 0.5m of place, after concrete final set, again creep into, (2) in Karst Geological Landscape pore-forming after-pouring formation of pile, should select comparatively complicated (probably having solution cavity) two piles of geological condition according to geologic report and carry out filling concrete pile, when solution cavity may be breakdown under high pressure effect, thereby there is the concrete phenomenon that sharply declines, cause this stake to become useless stake, can shift to an earlier date 30~40 cubes of concrete of preparing according to a large amount of site operation experiences more, (known according to a large amount of site operation experiences, if aperture does not have mud to return out in concrete perfusion, just explanation has the existence of solution cavity), while there is this phenomenon, can supplement in time concrete, what need pay special attention to is, the conduit of now necessarily can not being eager to pull out, avoid conduit to extract and just start to occur that concrete sharply declines afterwards, now just there will be conduit above concrete, thereby cause useless stake.
Beneficial effect of the present invention is:
The present invention improves existing rotary digging drilling hole bored concrete pile construction technology, is more suitable for the comparatively complicated karst area of geological condition after improvement, can improve karst area and revolve the pile efficiency of digging castinplace pile.Improved technology solves deflection problem timely when can effectively avoiding hole scattering and occurring drilling rod deflection; Can effectively avoid revolving the bit freezing that occurs in drilling process and the drill bit problem that drops of digging; Can effectively avoid thoroughly not causing the blocked up bearing capacity of pile foundation that affects of sediment because of clear hole; Can effectively avoid making pile foundation become useless stake because solution cavity existence causes concrete sharply to decline.
Brief description of the drawings
Fig. 1 is that Karst Geological Landscape of the present invention revolves and digs pouring pile hole technological process;
Fig. 2 is underwater concreting mode;
Fig. 3 is hopper switch;
Fig. 4 is concrete first watering schematic diagram.
Detailed description of the invention
Below in conjunction with the drawings and specific embodiments, technical scheme of the present invention is described in more detail.
With reference to Fig. 1, the technical solution adopted for the present invention to solve the technical problems is: karst region is improved revolves the construction technology process that scrapes out hole pouring pile and be: smooth location → stake position unwrapping wire → rotary drilling rig is in place → and bury underground and in casing → casing, supplement stabilizing solution → revolve and scrape out hole and (while running into solution cavity, will slow down rate of penetration, while not running into solution cavity, be drilled into design elevation) → clear hole, check hole depth → installations reinforcing cage and conduit → gas lift reverse circulation secondary pile hole cleaning → the build underwater concrete (existence of consideration solution cavity, need 30~40 cubes of concrete of preparing more, prevent that solution cavity from puncturing, concrete sharply declines and causes useless stake) → pile, extract casing.
For fear of hole scattering in drilling process, when rigging up, require on Spiral digging machine center of turntable and drilling cramp lifting pulley at same axis, drilling rod position deviation is not more than 20cm, when entering uneven strata, oblique shape rock stratum or encountering half rock, slow down rate of penetration.In the time of hole scattering, can mention drill bit, repeatedly sweep brill several times up and down.Be oblique shape distribution if accompany large boulder or solution cavity in soil layer, pour into C15 concrete to more than the inclined to one side hole 0.5m of place, after concrete final set, again creep into.
Adopt in the comparatively complicated karst area of geological condition and revolve the existing problems that need to consider solution cavity while digging pouring pile hole construction technology, dig in pore forming process revolving, when revolving when digging drill bit and running into solution cavity or half rock, must slow down rate of penetration, keep the verticality of kelly, avoid bit freezing or drill bit to drop.
Clear hole work after pore-forming is very crucial, sediment is blocked up at the bottom of because of hole tends to cause bearing capacity reduction for rotary digging drilling hole bored concrete pile, have a strong impact on the quality of pile foundation, karst region is revolved and is dug the carg producing in pore forming process than many in general geology, to be difficult to clear hole by general clear hole mode thorough, thereby can cause pile bottom sediment more, therefore revolving of karst region dug castinplace pile and adopted in time " gas lift reverse circulation " to carry out secondary pile hole cleaning putting into after reinforcing cage, carries out in time concreting and will solve well the too much problem of pile bottom sediment behind clear hole.
While building underwater concrete first, guarantee that conduit has buried depth more than 1m, concrete first watering amount is calculated schematic diagram as shown in Figure 4, and first watering amount is as follows with reference to design formulas:
V ≥ π D 2 ( H 1 + H 2 ) 4 + π d 2 h 1 4
In formula: V-concrete first watering amount (m 3);
D-stake bore dia (m);
H 1the distance (m) of bottom, Dao Zhuan hole ,-conduit bottom, is generally 0.4~0.5m;
H 2the degree of depth (m) of-first placing of concrete rear tube Transducers Embedded in Concrete, more than being generally 1m;
H 1-stake hole inner concrete reaches H 2time, the outer required height (m) of mud pressure of conduit inner concrete column equilibration conduit;
Conduit has buried depth more than 1m when building underwater concrete first, underwater concreting adopts device as shown in Figure 2 to build, while building, concrete hopper is sling by hoist cable with crane, conduit and hopper connect, build and frontly with hopper switch (as shown in Figure 3), hopper cuts out, (general hopper is 3m to treat to fill hopper by concrete 3left and right, a stake footpath while being greater than 2.7m with two hoppers that stack) after again by hopper switch opens, concrete, under the effect of gravity, sweeps away and can complete first watering back cover along conduit.In Fig. 3, hopper switch is made up of a steel disk and gusseted, before hopper dress concrete, put down hopper switch, gusseted is enclosed within and in conduit mouth, plays a fixation, in the middle of steel disk, connect with hoist cable, in the time that concrete is filled hopper, with loop wheel machine, steel disk is sling, concrete can sweep away and can complete first watering back cover along conduit.
In perfusion bore forming process, should select and probably exist two piles of solution cavity to carry out filling concrete pile according to geologic report, when solution cavity may be breakdown under high pressure effect, thereby there is the concrete phenomenon that sharply declines, cause this stake to become useless stake, can shift to an earlier date 30~40 cubes of concrete of preparing according to a large amount of site operation experiences more, (known according to a large amount of site operation experiences, if aperture does not have mud to return out in concrete perfusion, just explanation has the existence of solution cavity), while there is this phenomenon, can supplement in time concrete, what need pay special attention to is, the conduit of now necessarily can not being eager to pull out, avoid conduit to extract and just start to occur that concrete sharply declines afterwards, now just there will be conduit above concrete, thereby cause useless stake, taking this measure can improve to a certain extent karst region revolves and digs filling pile construction benefit.
The above; it is only preferably detailed description of the invention of the present invention; protection scope of the present invention is not limited to this; any be familiar with those skilled in the art the present invention disclose technical scope in, the simple change of the technical scheme that can obtain apparently or equivalence replace all fall within the scope of protection of the present invention.

Claims (1)

1. Karst Geological Landscape revolves and digs a pouring pile hole technique, it is characterized in that, comprises the following steps:
1) levelling of the land: construction before removing obstacles, change except weak soil, grinding compacting; Planning travelling line, maintains a certain distance road and bore position;
2) pile foundation unwrapping wire, rotary drilling rig are in place: adopt total powerstation to position unwrapping wire, the control of unwrapping wire error is less than 1cm; Position of p ile machine is wanted accurately, and rig center of pilot line, turntable center line, pile foundation center line should remain on same straight line;
3) bury casing underground: draw cross hairs to put four according to pile foundation anchor point and control stake, control stake bury steel sheath cylinder underground as benchmark taking four, the high 2m that is generally not less than of cylinder, for protection hole wall, bassets and be highly generally not less than 0.3m;
4) in the preparation of mud stabilizing solution and casing, supplement mud stabilizing solution: in the rotary digging drilling hole process of karst region, boring mud is more, so it is very crucial to control the proportion of mud stabilizing solution, controls mud balance and be not less than 1.1, viscosity 20s left and right, sand factor is less than 4%;
5) revolve and dig drilling and forming hole: while running into solution cavity or half rock, will slow down rate of penetration and be controlled at 10~20mm/min, while not running into solution cavity or half rock, be drilled into design elevation;
6) once clear hole, check hole depth: first drill bit is increased to apart from 80~100mm at the bottom of hole, the new mud stabilizing solution that input proportion is 1.05~1.08 circulates, and carries out hole clearly with pressure fan;
7) reinforcing cage and conduit are installed;
8) gas lift reverse circulation secondary pile hole cleaning;
9) build underwater concrete: conduit must be tight, ensure 30~50cm at the bottom of conduit bottom is apart from hole; Mixing concrete must be evenly, and the slump is controlled at 18~22cm, and concreting must be worked continuously; In casting process, should there is special messenger to be responsible for record, avoid conduit to promote too fast or conduit and imbedded deeply, control the conduit end opening Transducers Embedded in Concrete degree of depth 2~6m, prevent broken pile; The end face absolute altitude of castinplace pile should be than the high 60cm that is not less than of design load;
10) pile, extract casing.
CN201410376534.4A 2014-07-31 2014-07-31 Karst geology rotary-drilling bored concrete pile hole forming process Active CN104153352B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410376534.4A CN104153352B (en) 2014-07-31 2014-07-31 Karst geology rotary-drilling bored concrete pile hole forming process

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410376534.4A CN104153352B (en) 2014-07-31 2014-07-31 Karst geology rotary-drilling bored concrete pile hole forming process

Publications (2)

Publication Number Publication Date
CN104153352A true CN104153352A (en) 2014-11-19
CN104153352B CN104153352B (en) 2017-02-15

Family

ID=51878966

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410376534.4A Active CN104153352B (en) 2014-07-31 2014-07-31 Karst geology rotary-drilling bored concrete pile hole forming process

Country Status (1)

Country Link
CN (1) CN104153352B (en)

Cited By (27)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104674780A (en) * 2015-02-06 2015-06-03 中鼎国际工程有限责任公司 Karst stratum stabilization structure
CN104831708A (en) * 2015-03-20 2015-08-12 深圳市工勘岩土集团有限公司 Foundation excavation retaining and protecting cast-in-situ bored pile construction method and equipment thereof
CN105714772A (en) * 2016-02-22 2016-06-29 北龙建设集团有限公司 Re-drilling concrete wall protecting method for hole formation of rock-socketed pile in karst region
CN106522209A (en) * 2016-10-08 2017-03-22 金陵科技学院 Perfusion construction method of cast-in-situ bored pile for revolving-boring construction of karst cave
CN106836206A (en) * 2017-03-30 2017-06-13 重庆建工住宅建设有限公司 Casing rotary digging bore forming method
CN106930276A (en) * 2017-04-11 2017-07-07 广州智弘建筑物检测与鉴定技术有限公司 The deep hole blasting of rotary digging bored concrete pile and the construction method of conduit rotary digging removing obstacles
CN107246006A (en) * 2017-06-29 2017-10-13 深圳市蛇口招商港湾工程有限公司 Concrete-pile reinforcement cage structure and pile-filling method
CN107386276A (en) * 2017-07-20 2017-11-24 广州市建筑科学研究院新技术开发中心有限公司 A kind of construction method of soft layer super-long and large-diameter bored piles
CN108049397A (en) * 2017-12-22 2018-05-18 中交第三航务工程局有限公司宁波分公司 The construction method of Karst Geological Landscape drilled pile
CN108086342A (en) * 2017-12-22 2018-05-29 中交第三航务工程局有限公司宁波分公司 The construction method of karst strata pile foundation
CN108442364A (en) * 2018-04-18 2018-08-24 中铁十九局集团轨道交通工程有限公司 Karsts developing area stratum can prevent a full set of cylinder pile-forming apparatus and pile making method of broken pile
CN108487286A (en) * 2018-02-06 2018-09-04 广州市市政工程设计研究总院 A kind of construction method of the continuous supporting course of beading karst region super long pile
CN109056706A (en) * 2018-08-03 2018-12-21 上海宝冶集团有限公司 A kind of Karst Geological Landscape poured pile base construction method
CN109989718A (en) * 2019-03-26 2019-07-09 上海建工二建集团有限公司 Tool for rotary drilling of ceramic slag treatment and hole cleaning in karst area and manufacturing and construction method thereof
CN110080785A (en) * 2019-05-16 2019-08-02 中铁隧道局集团有限公司 Compound stratum super-large-diameter shield normal pressure warehouse entry reinforced construction method near water
CN110158579A (en) * 2019-04-26 2019-08-23 中国水利水电第九工程局有限公司 A kind of bored pile construction method
CN111535307A (en) * 2020-05-22 2020-08-14 河北建设勘察研究院有限公司 Hole forming construction method for rotary drilling cast-in-place pile in reef limestone stratum
CN111677439A (en) * 2020-06-24 2020-09-18 中建四局土木工程有限公司 Drilling hole forming method of reverse circulation rotary drilling machine
CN111733801A (en) * 2020-06-28 2020-10-02 中冶地集团西北岩土工程有限公司 Construction process of rotary drilling bored concrete pile in soft geology
CN111927320A (en) * 2020-07-31 2020-11-13 中国建筑第四工程局有限公司 Ultra-deep large-diameter pile hole forming method
CN113338355A (en) * 2021-05-19 2021-09-03 中国建筑第二工程局有限公司 Construction method for judging rocks and mechanically anchoring anchor rods in strong development karst area
CN113356191A (en) * 2021-06-16 2021-09-07 中交第三航务工程局有限公司 Method for pile foundation construction in karst area to follow up construction of long steel casing
CN113445496A (en) * 2021-06-21 2021-09-28 广东北方基础建筑有限公司 Rotary drilling cast-in-place pile and construction process thereof
CN113931189A (en) * 2021-11-10 2022-01-14 贵州建工集团第一建筑工程有限责任公司 Secondary hole cleaning construction method for cast-in-situ bored pile based on gas lift reverse circulation
CN114059921A (en) * 2021-11-17 2022-02-18 广州铁路投资建设集团有限公司 Hole-forming construction process for cast-in-place pile in karst strong development area
CN114277781A (en) * 2021-11-30 2022-04-05 山东省公路桥梁建设集团有限公司 Karst area pile foundation pore-forming construction method
CN115110520A (en) * 2022-04-27 2022-09-27 中国建筑第七工程局有限公司 Construction method of bridge pile foundation on highway

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109056709A (en) * 2018-08-22 2018-12-21 中铁二十二局集团有限公司 A method of using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5099696A (en) * 1988-12-29 1992-03-31 Takechi Engineering Co., Ltd. Methods of determining capability and quality of foundation piles and of designing foundation piles, apparatus for measuring ground characteristics, method of making hole for foundation pile such as cast-in-situ pile and apparatus therefor
JPH07113229A (en) * 1993-10-19 1995-05-02 Kajima Corp Cast-in-place concrete pile method
CN101109179A (en) * 2007-06-21 2008-01-23 河北建设勘察研究院有限公司 Gas lifting reverse circulation porus cleaning construction method for slurry bulkhead cast-in-situ bored pile
CN102966094A (en) * 2012-12-15 2013-03-13 马春根 Method for constructing concrete pile through rotary excavating and pressure irrigation
CN102995632A (en) * 2012-11-21 2013-03-27 中国石油天然气集团公司 Cast-in-situ bored pile technique
CN103485716A (en) * 2013-09-27 2014-01-01 福建成森建设集团有限公司 Karst-geology rotary-drill guide-hole construction method
CN103696417A (en) * 2013-12-20 2014-04-02 中国一冶集团有限公司 Secondary hole cleaning device and method of bottom of cast-in-situ bored pile

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5099696A (en) * 1988-12-29 1992-03-31 Takechi Engineering Co., Ltd. Methods of determining capability and quality of foundation piles and of designing foundation piles, apparatus for measuring ground characteristics, method of making hole for foundation pile such as cast-in-situ pile and apparatus therefor
JPH07113229A (en) * 1993-10-19 1995-05-02 Kajima Corp Cast-in-place concrete pile method
CN101109179A (en) * 2007-06-21 2008-01-23 河北建设勘察研究院有限公司 Gas lifting reverse circulation porus cleaning construction method for slurry bulkhead cast-in-situ bored pile
CN102995632A (en) * 2012-11-21 2013-03-27 中国石油天然气集团公司 Cast-in-situ bored pile technique
CN102966094A (en) * 2012-12-15 2013-03-13 马春根 Method for constructing concrete pile through rotary excavating and pressure irrigation
CN103485716A (en) * 2013-09-27 2014-01-01 福建成森建设集团有限公司 Karst-geology rotary-drill guide-hole construction method
CN103696417A (en) * 2013-12-20 2014-04-02 中国一冶集团有限公司 Secondary hole cleaning device and method of bottom of cast-in-situ bored pile

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
严建峰: "BARAKI体育场58m长旋挖成孔灌注桩施工技术", 《施工技术》 *
唐进: "旋挖孔施工工艺和特点", 《工程技术》 *
蔡志舰等: "旋挖钻机在溶洞地层桩基施工中的问题及处理", 《筑路机械与施工机械化》 *

Cited By (30)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104674780A (en) * 2015-02-06 2015-06-03 中鼎国际工程有限责任公司 Karst stratum stabilization structure
CN104831708A (en) * 2015-03-20 2015-08-12 深圳市工勘岩土集团有限公司 Foundation excavation retaining and protecting cast-in-situ bored pile construction method and equipment thereof
CN105714772B (en) * 2016-02-22 2018-04-03 北龙建设集团有限公司 Karst area embedded rock pile pore-forming bores concrete dado method again
CN105714772A (en) * 2016-02-22 2016-06-29 北龙建设集团有限公司 Re-drilling concrete wall protecting method for hole formation of rock-socketed pile in karst region
CN106522209A (en) * 2016-10-08 2017-03-22 金陵科技学院 Perfusion construction method of cast-in-situ bored pile for revolving-boring construction of karst cave
CN106836206A (en) * 2017-03-30 2017-06-13 重庆建工住宅建设有限公司 Casing rotary digging bore forming method
CN106930276A (en) * 2017-04-11 2017-07-07 广州智弘建筑物检测与鉴定技术有限公司 The deep hole blasting of rotary digging bored concrete pile and the construction method of conduit rotary digging removing obstacles
CN107246006A (en) * 2017-06-29 2017-10-13 深圳市蛇口招商港湾工程有限公司 Concrete-pile reinforcement cage structure and pile-filling method
CN107246006B (en) * 2017-06-29 2019-11-05 深圳市蛇口招商港湾工程有限公司 The pile-filling method of concrete-pile
CN107386276A (en) * 2017-07-20 2017-11-24 广州市建筑科学研究院新技术开发中心有限公司 A kind of construction method of soft layer super-long and large-diameter bored piles
CN108049397A (en) * 2017-12-22 2018-05-18 中交第三航务工程局有限公司宁波分公司 The construction method of Karst Geological Landscape drilled pile
CN108086342A (en) * 2017-12-22 2018-05-29 中交第三航务工程局有限公司宁波分公司 The construction method of karst strata pile foundation
CN108487286A (en) * 2018-02-06 2018-09-04 广州市市政工程设计研究总院 A kind of construction method of the continuous supporting course of beading karst region super long pile
CN108442364A (en) * 2018-04-18 2018-08-24 中铁十九局集团轨道交通工程有限公司 Karsts developing area stratum can prevent a full set of cylinder pile-forming apparatus and pile making method of broken pile
CN109056706A (en) * 2018-08-03 2018-12-21 上海宝冶集团有限公司 A kind of Karst Geological Landscape poured pile base construction method
CN109989718A (en) * 2019-03-26 2019-07-09 上海建工二建集团有限公司 Tool for rotary drilling of ceramic slag treatment and hole cleaning in karst area and manufacturing and construction method thereof
CN110158579A (en) * 2019-04-26 2019-08-23 中国水利水电第九工程局有限公司 A kind of bored pile construction method
CN110080785A (en) * 2019-05-16 2019-08-02 中铁隧道局集团有限公司 Compound stratum super-large-diameter shield normal pressure warehouse entry reinforced construction method near water
CN111535307A (en) * 2020-05-22 2020-08-14 河北建设勘察研究院有限公司 Hole forming construction method for rotary drilling cast-in-place pile in reef limestone stratum
CN111677439A (en) * 2020-06-24 2020-09-18 中建四局土木工程有限公司 Drilling hole forming method of reverse circulation rotary drilling machine
CN111733801A (en) * 2020-06-28 2020-10-02 中冶地集团西北岩土工程有限公司 Construction process of rotary drilling bored concrete pile in soft geology
CN111927320A (en) * 2020-07-31 2020-11-13 中国建筑第四工程局有限公司 Ultra-deep large-diameter pile hole forming method
CN113338355A (en) * 2021-05-19 2021-09-03 中国建筑第二工程局有限公司 Construction method for judging rocks and mechanically anchoring anchor rods in strong development karst area
CN113338355B (en) * 2021-05-19 2021-12-14 中国建筑第二工程局有限公司 Construction method for judging rocks and mechanically anchoring anchor rods in strong development karst area
CN113356191A (en) * 2021-06-16 2021-09-07 中交第三航务工程局有限公司 Method for pile foundation construction in karst area to follow up construction of long steel casing
CN113445496A (en) * 2021-06-21 2021-09-28 广东北方基础建筑有限公司 Rotary drilling cast-in-place pile and construction process thereof
CN113931189A (en) * 2021-11-10 2022-01-14 贵州建工集团第一建筑工程有限责任公司 Secondary hole cleaning construction method for cast-in-situ bored pile based on gas lift reverse circulation
CN114059921A (en) * 2021-11-17 2022-02-18 广州铁路投资建设集团有限公司 Hole-forming construction process for cast-in-place pile in karst strong development area
CN114277781A (en) * 2021-11-30 2022-04-05 山东省公路桥梁建设集团有限公司 Karst area pile foundation pore-forming construction method
CN115110520A (en) * 2022-04-27 2022-09-27 中国建筑第七工程局有限公司 Construction method of bridge pile foundation on highway

Also Published As

Publication number Publication date
CN104153352B (en) 2017-02-15

Similar Documents

Publication Publication Date Title
CN104153352A (en) Karst geology rotary-drilling bored concrete pile hole forming process
CN104563098B (en) A kind of super-large diameter all steel casing does operation pore-creating filling pile construction method
CN106284313B (en) Long spire based on circulating mud retaining wall is squeezed into rock filling pile construction method
CN102758430B (en) Large-diameter rotary digging pile construction process for ultra-deep throwing and filling unconsolidated soil body
CN110424381A (en) A kind of process for rotary digging drilling hole stake
CN105804761B (en) Construction method suitable for liquefied sand stratum shield near-distance passing through building
CN105275381B (en) Impact drill drilling construction method in rich water pebble layer
CN104747088B (en) A kind of leafy hosqe bit of cast-in-situ bored pile list waist and drilling construction method
CN106245626A (en) A kind of hard formation churning driven enters method
CN106759379A (en) A kind of construction method of the asymmetric water-stop curtain of foundation ditch
CN104532821A (en) Extra-large karst cave bottom treatment construction method
CN106285715B (en) Closely the construction method of first branch bored tunnel is worn in side to balancing earth-pressure shielding machine
CN103046931B (en) Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode
CN109736811A (en) A kind of vertical shaft machinery tunneling construction method
CN110735600B (en) Mechanical pore-forming pile construction process for karst geology
CN106836206A (en) Casing rotary digging bore forming method
CN109488202A (en) A kind of gravel rock stratum pile foundation drilling construction engineering method containing gravel-boulder bed
CN104455726A (en) Pipe-jacking construction method for pipeline bottom grouting reinforcement
CN109098175A (en) A kind of tri-axes deep mixing pile construction method
CN107448137A (en) A kind of rig that circles round enters the construction method of rock pore-forming
CN104532853A (en) Deep foundation pit supporting method and system characterized by steel reinforced cement-soil piles, bolts easy to detach and automatic monitoring and early warning
CN105714748A (en) Excavating construction method for surge shaft in gravel and sandy soil layer
CN106677166A (en) Flow construction method for forming cast-in-place bored pile for gravel-decomposed rock stratum in double-machine combined mode
CN113323584A (en) Drilling method of large vibrating long spiral drilling machine
CN107653878A (en) Cast-in-situ bored pile is reusable to be longitudinally separated formula steel pile casting construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant