CN109056709A - A method of using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation - Google Patents

A method of using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation Download PDF

Info

Publication number
CN109056709A
CN109056709A CN201810961681.6A CN201810961681A CN109056709A CN 109056709 A CN109056709 A CN 109056709A CN 201810961681 A CN201810961681 A CN 201810961681A CN 109056709 A CN109056709 A CN 109056709A
Authority
CN
China
Prior art keywords
full
sleeve
pile foundation
construction
drill rig
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810961681.6A
Other languages
Chinese (zh)
Inventor
满鑫
程勇军
张金龙
王记才
王峰
张军成
李晓东
李振伦
王瑞强
王孝先
吴红旗
范艳明
武婷婷
秦海同
李会
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 22nd Bureau Group Co Ltd
China Railway 20th Bureau Group Municipal Engineering Co Ltd
China Railway 22th Bureau Group Municipal Engineering Co Ltd
Original Assignee
China Railway 22nd Bureau Group Co Ltd
China Railway 22th Bureau Group Municipal Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 22nd Bureau Group Co Ltd, China Railway 22th Bureau Group Municipal Engineering Co Ltd filed Critical China Railway 22nd Bureau Group Co Ltd
Priority to CN201810961681.6A priority Critical patent/CN109056709A/en
Publication of CN109056709A publication Critical patent/CN109056709A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/20Driving or forcing casings or pipes into boreholes, e.g. sinking; Simultaneously drilling and casing boreholes

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Engineering & Computer Science (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Physics & Mathematics (AREA)
  • Earth Drilling (AREA)

Abstract

The present invention provides a kind of methods using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation, comprising the following steps: (1) measure of pile position setting-out;(2) drilling machine and steel sleeve are in place;(3) driving drilling machine carries out drilling construction until hole depth reaches predetermined design depth;(4) steel reinforcement cage is installed;(5) concreting;(6) casing is extracted.Method provided by the invention using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation, suitable for the Special Geological Conditions pile foundation construction such as karst, not only the safety and stablization of the infrastructure such as Adjacent Buildings and construction equipment ensure that, but also shortened construction period.

Description

A method of using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation
Technical field
The present invention relates to a kind of methods using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation, belong to bridge and apply Work technical field.
Background technique
In the bridge engineering construction of city prosperity block, to complete construction task in effective construction period, reduce because Construction equipment noise caused by urban life crowd, environmental pollution, ensure around existing infrastructure, building and The safety and stablization of crowd are the key that risk controls.It is such as thicker especially when Bored Pile Foundation of Bridge is in special geology Water-rich sand layer, bedrock surface big rise and fall, lithosphere is harder and there are oblique rocks, and karsts developing area is strong, lapies fluid bowl is developed, covered Soil cave development in blinding layer, the solution cavity that solution cavity is very big, buried depth relatively deeply, in beading development, to be not filled by, is partly filled, will protect The safety and stability for demonstrate,proving Bridge Pile Foundation Construction safety and Adjacent Buildings is a significant technology issues.
Summary of the invention
Based on the above deficiency, the technical problem to be solved in the present invention is to provide a kind of application full-sleeve hydraulic drill rig construction rocks The method of molten area bridge pile foundation, is suitable for the Special Geological Conditions pile foundation constructions such as karst, both ensure that Adjacent Buildings etc. The safety and stablization of infrastructure and construction equipment, and shorten construction period.
In order to solve the above technical problems, the invention adopts the following technical scheme:
A method of using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation, comprising the following steps:
(1) measure of pile position setting-out;
(2) drilling machine and steel sleeve are in place;
(3) driving drilling machine carries out drilling construction until hole depth reaches predetermined design depth;
(4) steel reinforcement cage is installed;
(5) concreting;
(6) casing is extracted.
The step (1) specifically includes the following steps:
(11) stake bit plane coordinate data is inputted into total station;
(12) using total station survey setting positioning pile foundation central point;
(13) pile foundation central point is marked using steel nail;
(14) the drilling contour line with stake diameter with size is done centered on central point.
Further include the steps that the verticality for adjusting casing within 1 ‰ in the step (2).
The step (2) the following steps are included:
(21) cutter head section is assembled with standard knot on ground;
(22) assembled cutter head section steel sleeve is lifted by crane, cutter head downwards, is put into drilling machine revolution driving ring;
(23) the hydraulic cohesion device for starting drilling machine, is fixed between the wedge block and steel sleeve of hydraulic cohesion device.
In the step (3), casing is in underground layer or layer of sand stage, and casing is using self weight indentation, and revolution is fast at this time Degree is adjusted to top gear or mid ranger, pressure 0KN, rotary torque 650-1550KNm;Casing enters general soil layer or hard During soil layer, rotational speed is set as middling speed or low speed, pressure control in 500~1500KN, rotary torque control 650~ 1550KN·m;Casing enter in weathering, micro- weathered rock formation when, rotational speed is set as low or first gear, pressure control 1500~ 2500KN, rotary torque are controlled in 1550~2000KNm.According to the variation of geologic lithology, select reasonable drilling pressure and Rate of penetration drills through different geological structure layers, prevents from causing drilling machine chattering, influences the verticality of pile foundation, ensure that into Hole efficiency;
The step (3) further includes the steps that taking out the dregs in casing by grab bucket in boring procedure.
Dregs is cleared out when creeping into sand seam geology, in hole carries out after the drill-through layer of sand of full-sleeve.The operation of out break hole is avoided, is protected Card drilling do not occur reaming, hole problem of collapsing.
It is poured in the step (5) using tremie method.
Keep the conduit of concrete perfusion always in pile foundation center position area, offset controls within 100mm, control The buried depth amount of conduit controls full-sleeve buried depth amount in 4~6m in 2~6m.During pile foundation filling concrete, strict control is led The height of pipe, full-sleeve Transducers Embedded in Concrete, can prevent occur pulling out trustship phenomenon, guarantee that filling concrete is once completed.
In the step (6), in solution cavity region, full-sleeve removes placket inner concrete face absolute altitude and is higher than sleeve bottom Absolute altitude.It avoids because solution cavity fills leakiness, concrete surface declines under pressure, leads to showing in mud sleeve pipe As causing the generation of broken pile and other issues.
Using above technical scheme, the present invention achieves following technical effect:
(1) method provided by the invention using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation, utilizes a full set Pipe carries out drilling pile wall, the hole that solves that karsts developing area geology condition karst cave treatment is difficult, collapsing occurs in water-rich sand layer geology, expanding Technical problem;The security risks such as occur collapsing when avoiding shallow-layer soil cave geotechnical boring pile driving construction, ensure that Adjacent Buildings etc. The safety and stablization of infrastructure and construction equipment;It ensure that drilled pile construction quality, improve drilled pile pore-forming efficiency, Construction speed is accelerated, capital investment has been saved.
Detailed description of the invention
The step of Fig. 1 is method of the present invention using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation is schemed.
Specific embodiment
As shown in Figure 1, the present invention provides a kind of sides using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation Method, it is characterised in that: the following steps are included:
(1) measure of pile position setting-out;Specifically includes the following steps:
(11) stake bit plane coordinate data is inputted into total station;
(12) setting position pile foundation central point is surveyed using total station;
(13) pile foundation central point is marked using steel nail;
(14) the drilling contour line with stake diameter with size is done centered on central point;Contour line drill convenient for full-sleeve alignment Stake position saves stake machine and is directed at the time in place.
(2) drilling machine and steel sleeve are in place;
The fashioned iron backing plate of drilling machine is laid on centered on pile foundation on surrounding ground by 100T crawler crane in intersecting parallels first; Drilling machine is lifted in place on backing plate after leveling, the center line of pile foundation is checked and approved in contraposition, and deviation should be not more than 30mm.After drilling machine is in place The balancing device of drilling machine side is landed, the end of balancing device prevent against fixing because of set using the crawler belt of crawler crane Pipe torsional moment causes drilling machine itself to rotate backward, and prevents the security risk that drilling machine rotation generates.
Then, casing installation is carried out, assembles cutter head section and the standard knot of a 6m long on ground;Then using shoe Band slings assembled cutter head section steel sleeve, and cutter head downwards, is slowly put into drilling machine revolution driving ring;It is hydraulic to start drilling machine Cohesion device, the frictional force using contact surface between wedge block and steel sleeve will be fixed between wedge block and steel sleeve, real Effective transmitting of torque between existing drilling machine revolution driving ring and steel sleeve.The holding and release of clamping structure and steel sleeve, by pressing from both sides Wedge block on locking oil cylinder and revolution driving ring is adjusted, and when clamping cylinder oscilaltion, wedge block is also gone up and down therewith, effectively Gyroscopic drive system is mutually engaged with steel sleeve as overall structure, guarantees that steel sleeve is not fallen out, and provide driving force.Drilling machine folder The fast curvature of tight device wedge shape is consistent with the curvature of steel sleeve, guarantees the wedge shape contact area between steel sleeve fastly, is Steel sleeve transmits torque and provides reliable guarantee.Behind edge of a knife align piles position, hanging down for steel sleeve is adjusted using the vertical hydraulic cylinder of drilling machine Straight degree, the degree control of casing is within 1 ‰.
(3) driving drilling machine carries out drilling construction until hole depth reaches predetermined design depth;
Start hydraulic drill rig, hydraulic motor driving steel sleeve is rotated, and the cutter head of steel bushing tube end and soil are generated Cutting, pile foundation core soil is separated with stake week foundation soil, is pressed into rotation, is achieved the purpose that drilling.Velocity of rotation base area Matter situation is divided into three gears, respectively top gear 0.9rpm, mid ranger 1.5rpm, bottom gear 2.5rpm.
Vertical hydraulic system does not apply pressure when initial, is used as pressure by casing self weight, when penetration rate slows down, starting Vertical hydraulic system pressurization, realizes normal construction.It is also changed correspondingly according to pressure under the variation of geologic lithology, provides and fill for drilling machine The power of foot, drills through different geological structure layers, ensure that pore-forming efficiency.Specifically: casing enters soil layer or layer of sand stage, set Pipe is using self weight indentation, and rotational speed is adjusted to top gear or mid ranger, pressure 0KN, rotary torque 650- at this time 1550KN·m.Casing enters during general soil layer or hard soil layer, and rotational speed is set as middling speed or low speed, pressure control In 500~1500KN, rotary torque is controlled in 650~1550KNm.When casing tripping in middle weathering, micro- weathered rock formation, Ying Jiang Rotational speed is set as low or first gear, and pressure should be controlled according to rock stratum situation in 1500~2500KN at this time, and rotary torque control exists Between 1550~2000KNm, rotary torque maximum is no more than 2000KNm under normal circumstances.Select reasonable drilling pressure And rate of penetration, it prevents from causing drilling machine chattering, influences the verticality of pile foundation.
While drilling, the dregs in casing is taken out using crawler crane lifting machine formula Impact Bucket Grab.Grab bucket takes soil End is made of two panels with the arc-shaped steel plate of blade, and pulley blocks are arranged inside circle grab bucket body, is connected pulley by wirerope, is grabbed Bucket and hanging ring, grab bucket are completed to open and close with the variation of the lifting of wirerope.Dregs, which clears out, when creeping into sand seam geology, in hole wants Carried out after the drill-through layer of sand of full-sleeve, avoid the operation of out break hole, guarantee drilling do not occur reaming, hole problem of collapsing.
When head section cannula tip is higher by drilling machine job platform 1m high, need to connect the second section casing.Connection side between casing Formula is mechanically connected using spigot-and-socket, and it is 400mm that bell and spigot, which connects width, with a thickness of 25mm, along the circumferential direction constant spacing position Setting connection hole and limiting slot, socket tube wall is interior to be arranged screw thread, and bolt connects from outside bellmouth circumferential direction socket rotational fastener It connects.Limiting slot can be improved the precision and installation exercise efficiency of installation, is effectively ensured between casing and is connected close.Casing is carried out After socket joint abutting joint, link bolt hole position is to just, installation connection bolt, after bolt is all installed, then is applied with spanner Add torque screwing bolts, by casing connection close and firm, with this reciprocal connection steel sleeve.Full-sleeve cutter head section length is 1.5m, Standard knot length is divided into 3m, 6m, and casing material is made using manganese steel.Cutter head section uses 50mm thick steel plate;The body of standard knot Portion uses 25mm thick steel plate;The connecting pin 0.53m long range of casing uses 50mm thick steel plate.Casing string passes through machine by more casings The connection of tool screwed joint, concatenates by root to designing pile length according to the depth of drilling.Improve the technique item of drilled pile construction retaining wall Part ensure that the construction quality of pile foundation engineering.Tool bit part is made of the cutter tooth of three kinds of plate tooth, weldering tooth, butterfly tooth models.Plate tooth It is mounted on cannula tip with butterfly tooth, main function is to complete friction drilling construction operation;Weldering tooth is welded on internal surface of sleeve pipe or outer On wall, mainly completion tube wall expands ruler operation, reduces the frictional force between casing and soil, guarantees drilling machine power.
When drilling machine lower part, earth's surface is locally settled, and drilling machine should stop constructing, and is supported using full-sleeve and is risen drilling machine, Withdraw from drilling machine backing plate at bottom, by sand in the use of depression position backfill it is closely knit after, restart drilling after drilling machine is resetted and apply Work.
While drilling, drilling depth is measured using the method for lining rope plus sash weight, the weight satisfaction of sash weight crashes into bottom hole, Guarantee the accuracy that drilling depth measures.After drilling depth reaches designed elevation, in Impact Bucket Grab cleaning hole bottom it is loose Dregs.Stone is larger in casing, and when Impact Bucket Grab cannot be taken out, impact grinding for several times is carried out in casing using jump bit, broken At slag take with Impact Bucket Grab again after fritter, shorten drilling cycle.In cleaning eye when dregs, Impact Bucket Grab is directly fallen to Foot of hole is grabbed, and the block by diameter greater than 30mm is cleaned out.Do not apply freely falling body Height Impact power, prevents to bore Hole stake is backbreak phenomenon.
Inner hole deposition slag uses gas lift reverse circulation borehole cleaning technique, installation conveying compressed air pipe, gas pipeline in conduit Bottom is higher than the height of conduit bottom 0.5m, and air inlet pipe and discharge pipe is arranged in conduit top end socket, and the compression that air compressor machine generates is empty Sediment and slurries are sufficiently mixed, companion by appendix pressurized delivered of the gas by being connected on conduit end socket to stake holes bottom It is raised above with bubble, it is power source that the inside and outside slurries of conduit, which generate density contrast, and bubble lifts the mud containing sediment by leading Pipe is sprayed to outside conduit, while sediment particulate removal in portable hole.The small mud of specific gravity or clear water are supplemented while borehole cleaning into hole, Retaining hole bottom has constant level pressure.
(4) steel reinforcement cage is installed;
Merogenesis is transported to stake position after pile foundation steel bar cage acceptance(check), carries out lifting installation, reinforcing bar using 100t crawler crane By the way of single-sided welding connection, same join domain connector area is 50% for connection, installation reinforcing bar protection on the outside of steel reinforcement cage Layer cushion block prevents scraping collision steel reinforcement cage during promotion full-sleeve, causes rising of steel cage phenomenon.
(5) concreting;
Pile foundation concreting is irrigated using tremie method, and leak test is carried out before catheter installation, has conduit Good sealing performance guarantees the pouring quality of concrete.Concrete slump control in 180~220mm, pile foundation concrete into Row continuous pouring, and all perfusion work are completed before concrete initial set.The conduit of concrete perfusion controls in pile foundation always The heart band of position, offset control within 100mm, and conduit flange is avoided to contact with steel reinforcement cage, avoid causing when promoting conduit Rising of steel cage phenomenon.The elevation location that concrete rises is measured in time, is controlled the buried depth amount of conduit in 2~6m, is calculated simultaneously The length of full-sleeve Transducers Embedded in Concrete part controls full-sleeve buried depth amount full-sleeve in 4~6m, timely removal hole.Pile foundation is mixed In solidifying soil filling process, the depth of strict control conduit, full-sleeve Transducers Embedded in Concrete can prevent occur pulling out trustship phenomenon, protect Card filling concrete is once completed.
(6) casing is extracted.
In solution cavity region, full-sleeve removes placket inner concrete face absolute altitude and is higher than sleeve bottom absolute altitude, and scope control exists 8m or so is avoided because solution cavity fills leakiness, and concrete surface declines under pressure, leads to showing in mud sleeve pipe As causing the generation of broken pile and other issues.
The extraction of full-sleeve is to rotate drilling machine drive ring and drilling direction opposite direction, while slowly being mentioned using hydraulic cylinder Rise full-sleeve.Connecting portion is higher by the position operating platform 1m high and carries out dismantling connection nut, and full-sleeve is carried out disassembly by root and is pulled out Out, the casing disassembled is rinsed using giant, and the bolt hole in connection ring is applied oil guard.
This method carries out drilling pile wall using full-sleeve, solves karsts developing area geology condition karst cave treatment hardly possible, rich water There are the technical problems such as hole, expanding of collapsing in sand seam geology;The safety such as occur collapsing when avoiding shallow-layer soil cave geotechnical boring pile driving construction Hidden danger ensure that the safety and stablization of construction environment.It ensure that drilled pile construction quality, improve drilled pile pore-forming efficiency, add Fast construction speed, has saved capital investment.
For this construction method compared with rotary drilling rig construction method, device structure height is low, good using full-sleeve retaining wall effect, Pore-forming efficiency is high, and full-sleeve is used in turn the effective rate of utilization for often improving various resources, reduces security risk.Together Class geological conditions shortens about 5 working days of construction period, has saved slurrying and compared with thick sand bed pre-pouring grout consolidation process expense With foring good economic benefit.
Finally, it should be noted that these are only the preferred embodiment of the present invention, it is not intended to restrict the invention, although Referring to embodiment, invention is explained in detail, for those skilled in the art, still can be to aforementioned Technical solution documented by each embodiment is modified or equivalent replacement of some of the technical features, but it is all Within the spirit and principles in the present invention, any modification, equivalent replacement, improvement and so on should be included in protection of the invention Within the scope of.

Claims (10)

1. a kind of method using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation, it is characterised in that: including following step It is rapid:
(1) measure of pile position setting-out;
(2) drilling machine and steel sleeve are in place;
(3) driving drilling machine carries out drilling construction until hole depth reaches predetermined design depth;
(4) steel reinforcement cage is installed;
(5) concreting;
(6) casing is extracted.
2. the method according to claim 1 using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation, feature Be: the step (1) specifically includes the following steps:
(11) stake bit plane coordinate data is inputted into total station;
(12) using total station survey setting positioning pile foundation central point;
(13) pile foundation central point is marked using steel nail;
(14) the drilling contour line with stake diameter with size is done centered on central point.
3. the method according to claim 1 using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation, feature It is:
Further include the steps that the verticality for adjusting casing within 1 ‰ in the step (2).
4. the method according to claim 1 using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation, feature It is:
The step (2) the following steps are included:
(21) cutter head section is assembled with standard knot on ground;
(22) assembled cutter head section steel sleeve is lifted by crane, cutter head downwards, is put into drilling machine revolution driving ring;
(23) the hydraulic cohesion device for starting drilling machine, is fixed between the wedge block and steel sleeve of hydraulic cohesion device.
5. the method according to claim 1 using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation, feature It is:
In the step (3), casing is in underground layer or layer of sand stage, and casing is pressed into using self weight, at this time rotational speed tune To top gear or mid ranger, pressure 0KN, rotary torque 650-1550KNm;Casing enters general soil layer or hard soil layer In the process, rotational speed is set as middling speed or low speed, pressure control in 500~1500KN, rotary torque control 650~ 1550KN·m;Casing enter in weathering, micro- weathered rock formation when, rotational speed is set as low or first gear, pressure control 1500~ 2500KN, rotary torque are controlled in 1550~2000KNm.
6. the method according to claim 1 using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation, feature It is:
The step (3) further includes the steps that taking out the dregs in casing by grab bucket in boring procedure.
7. the method according to claim 6 using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation, feature It is:
Dregs is cleared out when creeping into sand seam geology, in hole carries out after the drill-through layer of sand of full-sleeve.
8. the method according to claim 1 using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation, feature It is:
It is poured in the step (5) using tremie method.
9. the method according to claim 8 using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation, feature It is:
Keep the conduit of concrete perfusion always in pile foundation center position area, offset controls within 100mm, controls conduit Buried depth amount in 2~6m, control full-sleeve buried depth amount in 4~6m.
10. the method according to claim 1 using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation, feature Be: in the step (6), in solution cavity region, full-sleeve removes placket inner concrete face absolute altitude and is higher than sleeve bottom mark It is high.
CN201810961681.6A 2018-08-22 2018-08-22 A method of using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation Pending CN109056709A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810961681.6A CN109056709A (en) 2018-08-22 2018-08-22 A method of using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810961681.6A CN109056709A (en) 2018-08-22 2018-08-22 A method of using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation

Publications (1)

Publication Number Publication Date
CN109056709A true CN109056709A (en) 2018-12-21

Family

ID=64687912

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810961681.6A Pending CN109056709A (en) 2018-08-22 2018-08-22 A method of using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation

Country Status (1)

Country Link
CN (1) CN109056709A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113445497A (en) * 2020-03-24 2021-09-28 无锡市市政设施建设工程有限公司 Hole forming process of full-casing full-slewing drilling machine
CN114837209A (en) * 2022-05-19 2022-08-02 中铁三局集团第二工程有限公司 Construction method of deep sand layer large-diameter pile foundation in karst development area
CN115613577A (en) * 2022-12-21 2023-01-17 中铁二十二局集团轨道工程有限公司 Full-rotation full-casing drilling machine and construction method for removing old pile thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110005183A (en) * 2009-07-09 2011-01-17 전동중 Possible to separate and assemble complex soft ground reinforcement method using a top stakes
CN102635113A (en) * 2012-04-20 2012-08-15 深圳市金泰建设工程有限公司 Construction method for hydraulic vibrating sinking pipe cast-in-place piles
CN105887813A (en) * 2016-05-07 2016-08-24 深圳市宏业基基础工程有限公司 Large-diameter super-long pile construction method in karst area through full-casing pipe full rotating and rotary drilling
CN104153352B (en) * 2014-07-31 2017-02-15 广西科技大学 Karst geology rotary-drilling bored concrete pile hole forming process

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20110005183A (en) * 2009-07-09 2011-01-17 전동중 Possible to separate and assemble complex soft ground reinforcement method using a top stakes
CN102635113A (en) * 2012-04-20 2012-08-15 深圳市金泰建设工程有限公司 Construction method for hydraulic vibrating sinking pipe cast-in-place piles
CN104153352B (en) * 2014-07-31 2017-02-15 广西科技大学 Karst geology rotary-drilling bored concrete pile hole forming process
CN105887813A (en) * 2016-05-07 2016-08-24 深圳市宏业基基础工程有限公司 Large-diameter super-long pile construction method in karst area through full-casing pipe full rotating and rotary drilling

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113445497A (en) * 2020-03-24 2021-09-28 无锡市市政设施建设工程有限公司 Hole forming process of full-casing full-slewing drilling machine
CN114837209A (en) * 2022-05-19 2022-08-02 中铁三局集团第二工程有限公司 Construction method of deep sand layer large-diameter pile foundation in karst development area
CN115613577A (en) * 2022-12-21 2023-01-17 中铁二十二局集团轨道工程有限公司 Full-rotation full-casing drilling machine and construction method for removing old pile thereof

Similar Documents

Publication Publication Date Title
CN104631470B (en) The large particle diameter sand gravel of high water level geology deep basal pit combination supporting construction method
CN110230309A (en) Karst region bridge solution cavity pile base construction method
CN106988302B (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN106245626A (en) A kind of hard formation churning driven enters method
CN105275381B (en) Impact drill drilling construction method in rich water pebble layer
CN109594564A (en) A kind of anti-collapse construction method of Metro Deep Excavation open cut
CN108517877B (en) Supporting construction method combining consolidation grouting of hybrid filling ultra-deep foundation pit with double-row steel pipe piles
CN103046931B (en) Method for forming holes of vertical shaft/pilot shaft through impact type drilling machine in impacting mode
CN102912791B (en) Construction method of bored pile
CN109056709A (en) A method of using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation
CN103835661A (en) Local excavation pre-supporting raise boring technology
CN106545007A (en) The method of pile in stratum of the bottom for hard rock stratum
CN102966111A (en) Construction method for anchoring steel pipe pile on steep bare rock without covering layer in deep water and rapids
CN103266603A (en) Construction method for pre-drilling hole-forming base-expanding and grouting of prestressed concrete special-shaped pile
CN112031017A (en) Construction method suitable for deep water pile foundation steel casing under bare rock geological condition
CN103924585A (en) Novel method for constructing wind power rock-embedded pile
CN103526747A (en) Construction method for impact holing of filling pile in tidal environment
CN111594041A (en) Rapid hole forming construction method for large-diameter deep hole pile foundation under karst geology
CN111501781A (en) Supporting method and structure combining consolidation grouting of hybrid filling ultra-deep foundation pit with double rows of steel pipe piles
CN106758759B (en) A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed
CN108194704A (en) One kind wears river technique
CN106677166A (en) Flow construction method for forming cast-in-place bored pile for gravel-decomposed rock stratum in double-machine combined mode
CN112576265A (en) Sedimentation control method for old villages penetrated by shield
CN113431045B (en) Construction method for rotary drilling pore-forming karst leaking stoppage
CN112196494B (en) Construction process and construction equipment for geological pipeline jointed between rock and soil layer

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: 510800 room 1507, No. 95, Yingbin Avenue, Huadu District, Guangzhou City, Guangdong Province

Applicant after: China Railway 22nd Bureau Group Municipal Engineering Co., Ltd.

Applicant after: China Railway Group Co., Ltd.

Address before: 35 Shijingshan Road, Shijingshan District, Beijing

Applicant before: China Railway Group Co., Ltd.

Applicant before: China Railway 22nd Bureau Group Co., Ltd. Municipal Engineering Company

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181221