CN112031017A - Construction method suitable for deep water pile foundation steel casing under bare rock geological condition - Google Patents

Construction method suitable for deep water pile foundation steel casing under bare rock geological condition Download PDF

Info

Publication number
CN112031017A
CN112031017A CN202010951000.5A CN202010951000A CN112031017A CN 112031017 A CN112031017 A CN 112031017A CN 202010951000 A CN202010951000 A CN 202010951000A CN 112031017 A CN112031017 A CN 112031017A
Authority
CN
China
Prior art keywords
construction
casing
pile
pile foundation
bare rock
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010951000.5A
Other languages
Chinese (zh)
Inventor
汪正武
王燎原
彭浩
杨尚
宋磊
柯军
乔清波
李兴勇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 11th Bureau Group Co Ltd
First Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd
Original Assignee
China Railway 11th Bureau Group Co Ltd
First Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 11th Bureau Group Co Ltd, First Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd filed Critical China Railway 11th Bureau Group Co Ltd
Priority to CN202010951000.5A priority Critical patent/CN112031017A/en
Publication of CN112031017A publication Critical patent/CN112031017A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/385Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/66Mould-pipes or other moulds
    • E02D5/665Mould-pipes or other moulds for making piles
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/04Directional drilling
    • E21B7/043Directional drilling for underwater installations
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/12Underwater drilling
    • E21B7/122Underwater drilling with submersible vertically movable guide
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/18Drilling by liquid or gas jets, with or without entrained pellets
    • E21B7/185Drilling by liquid or gas jets, with or without entrained pellets underwater
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0007Production methods using a mold
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0023Cast, i.e. in situ or in a mold or other formwork
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/0061Production methods for working underwater
    • E02D2250/0076Drilling

Abstract

A construction method of a deep water pile foundation steel casing suitable for bare rock geological conditions comprises the following steps: the method comprises the following steps: setting up a construction trestle and a drilling platform → exploring and leveling a riverbed foundation → lowering and positioning an outer water-blocking steel casing → a rotary drilling rig tooth matching wheel cylinder drill bit to grooving the bedrock → embedding the construction casing into an annular slot → lowering yellow clay or underwater concrete by a guide pipe to fill a gap between the construction casing and the bare rock slot → pulling out the outer casing, moving the outer casing and equipment to the next hole site, and sequentially and circularly finishing the construction of casings of other hole sites; the pile foundation steel pile casing construction method can quickly finish pile foundation steel pile casing construction under difficult construction conditions of bare rock, deep water and the like, and the pile foundation construction pile casing can accurately extend into the stable bedrock, so that the pile foundation construction quality is effectively guaranteed, and the pile foundation steel pile casing construction method is safe and reliable in the construction process, short in construction period and good in economic benefit.

Description

Construction method suitable for deep water pile foundation steel casing under bare rock geological condition
Technical Field
The invention relates to the field of bridge pile foundation engineering, in particular to a construction method of a deep-water pile foundation steel casing suitable for bare rock geological conditions.
Background
In the field of bridge pile foundation engineering, bridge structures are commonly adopted for crossing rivers and cross rivers, bridge pile foundation construction on the rivers is commonly existed in various projects, the difficulty degree of underwater pile foundation construction is greatly different according to different geological conditions, hydrological conditions and the like, and the accurate positioning and implantation of a pile casing of bare rock geology under deep water conditions are more difficult; because the riverbed covering layer is shallow, the riverbed bedrock is directly exposed, and the pile foundation steel casing can not be directly sunk in place by adopting a vibration hammer or a pile driver.
At present, the construction of a pile casing under the condition of bare rock of a deepwater pile foundation generally adopts percussion drilling to lead a hole and then transfers a steel pile casing, and the following two defects are mainly existed: firstly, the punching progress of the impact drill is slow, and the construction period is long; and secondly, the hole expansion coefficient of the percussion drilling hole guiding process is large, the hole guiding and the pile casing can not be closely attached, and the bottom opening of the pile casing is easy to leak slurry or even collapse in the later pile foundation construction process, so that large quality hidden troubles are caused for pile foundation construction.
Disclosure of Invention
The invention aims to solve the problems that pile foundation steel casing construction is difficult and slow in progress under bare rock geological conditions, and the bottom opening of the casing is easy to leak slurry or even collapse in the later pile foundation construction process, so that great quality hidden danger is caused to pile foundation construction; the construction method is suitable for the deep water pile foundation steel casing under the bare rock geological condition; the method has the advantages of high installation precision, stable hole opening and high construction speed, improves the pile foundation construction quality under complex conditions, improves the construction efficiency and ensures the construction safety.
The technical scheme of the invention is as follows: a construction method of a deep water pile foundation steel casing suitable for bare rock geological conditions comprises the following steps:
the method comprises the following steps: and (5) erecting a construction trestle and a drilling platform as a platform for the construction of the pile foundation on water.
Step two: and (4) exploring the river bed base, exploring the situation of the river bed base before formal construction, and leveling the river bed base with large unevenness at the pile position.
Step three: and the water-blocking steel protective cylinder is sleeved outside the downward placing sleeve, the size of the protective cylinder can meet the construction space of the bedrock slotting equipment, and the protective cylinder plays a role in guiding and positioning the bedrock slotting construction.
Step four: a rotary drilling rig provides power (torque) for a roller cone drill bit, under the guiding and positioning action of an outer sleeve pile casing, a groove is formed in bedrock to form a circular groove position matched with the size of a construction pile casing, and the depth of the groove is determined according to the water depth and the geological condition.
Step five: after a groove position is formed on the bedrock, the roller cone drill bit is lifted, the construction steel casing is lowered, the construction steel casing is accurately embedded into the cut annular groove position under the guiding of the outer casing, and the construction casing is in place.
Step six: in an annular gap formed between the construction casing and the outer sleeve casing, yellow clay is put down by a guide pipe to seal and fill a gap between the construction casing and a bare rock groove position, so that the sealing effect of the bottom of the construction casing is formed.
Step seven: and pulling out the outer sleeve protection barrel, moving the outer sleeve protection barrel and the equipment to the next hole site, and sequentially and circularly finishing the construction of the protection barrels at other hole sites.
The roller cone drill bit is a roller cone drill bit of a rotary drilling rig, the lower part of the roller cone drill bit is provided with high-strength roller cones in a tooth-shaped staggered arrangement, and a circular groove-shaped structure is formed on bedrock along with the rotary drilling of the roller cone drill bit in the rotary drilling rig.
The sealing and filling material adopts underwater concrete to replace clay to seal and fill the gap between the construction casing and the bare rock slot position when the clay effect is not good, and seals the bottom of the construction casing.
The construction method has the beneficial effects that the construction method of the deep-water pile foundation steel casing under the bare rock geological condition can quickly complete the construction of the pile foundation steel casing under the difficult construction conditions of bare rock, deep water and the like, and the pile foundation construction casing can accurately extend into the stable bedrock, so that the construction quality of the pile foundation is effectively guaranteed; the investment equipment is less, the construction process is safe and reliable, the construction period is short, and the economic benefit is good.
Description of the drawings:
the invention is further explained below with reference to the drawings and the embodiments;
FIG. 1 is an elevational view showing the positional relationship between an outer casing and a construction casing according to the present invention;
FIG. 2 is a top view of the outer casing and the construction casing of FIG. 1;
FIG. 3 is a flow chart of a construction process;
in the figure: 1. the method comprises the following steps of (1) coating a casing, 2. constructing the casing, 3. drilling a platform surface, 4. constructing a water surface, 5. bare rock riverbed top surface and 6. clay sealing layer.
The specific implementation mode is as follows:
in the embodiment of fig. 1, 2 and 3 provided by the invention, the outer sleeve casing 1 is a round steel casing, the wall thickness can be determined according to construction conditions, and the outer sleeve casing can be made of a steel plate with the thickness of 16-25mm generally, and the outer sleeve casing has the functions of blocking the influence of water flow on the roller cone drill bit and guiding and positioning the drill bit.
The construction casing 2 is a steel round casing and is used as a casing structure for pile foundation main body construction.
The size of the cone drum drill bit can be matched with that of the construction pile casing, the rotary drilling rig provides power for the cone drum drill bit to pressurize and rotate the drill bit, the rock surface is cut to form an annular groove position, and the construction pile casing can just fall into the annular groove position.
The method for constructing the bare rock deepwater pile foundation casing comprises the following steps:
the method comprises the following steps: and (5) erecting a construction trestle and a drilling platform to form a drilling platform surface 3.
Step two: and (4) checking the condition of the river bed base, and leveling the pile position with obvious height difference by adopting measures such as a mechanical grab bucket and the like.
Step three: the outer casing protection barrel 1 is put down, and the bottom of the outer casing protection barrel is arranged on the top surface 5 of the bare rock riverbed.
Step four: the rotary drilling rig provides power (torque), a roller cone drill bit is adopted to cut a groove under the guiding action of an outer sleeve protective sleeve, an annular groove matched with the construction protective sleeve is formed within a certain depth range below the top surface 5 of the bare rock riverbed, the depth of the groove can be determined according to the water depth and the bedrock property, the groove depth is generally not less than 1.5m, and the groove width is preferably 10-15 cm.
Step five: the roller cone drill bit is taken out, the construction pile casing 2 is placed by utilizing the guiding effect of the outer sleeve pile casing 1, the construction pile casing 2 is embedded into the annular groove, the bare rock geology has the barrier to the outer sleeve pile casing, no other sundries are left in the groove after the drill bit is withdrawn, and the construction pile casing can be stably and quickly embedded into the groove.
Step six: in the annular clearance that overcoat protects a section of thick bamboo 1 and a construction and protects a section of thick bamboo 2 formation, utilize the pipe to send clay into the construction and protect a section of thick bamboo and the clearance of basement rock trench in, form clay shutoff layer 6, further prevent to protect a section of thick bamboo bottom to leak thick liquid infiltration.
Step seven: and (3) pulling out the outer sleeve pile casing 1, moving the outer sleeve pile casing 1, the roller cone drill bit and other pile casing construction equipment together to a next hole site for construction, and circularly constructing other hole sites in sequence.
In the construction method, when the clay effect is poor, the underwater concrete is adopted to replace the clay to seal and fill the gap between the construction casing and the bare rock slot position, and the bottom of the construction casing is sealed.

Claims (2)

1. A construction method of a deep water pile foundation steel casing suitable for bare rock geological conditions; the method is characterized in that: the construction steps are as follows:
the method comprises the following steps: building a construction trestle and a drilling platform as a platform for the construction of the pile foundation on water;
step two: exploring the river bed base, exploring the situation of the river bed base before formal construction, and leveling the river bed base with large unevenness at the pile position;
step three: a water-blocking steel casing is externally sleeved downwards, the size of the casing can meet the construction space of bedrock slotting equipment, and the casing plays a role in guiding and positioning the bedrock slotting construction;
step four: a rotary drilling rig provides power for a roller cone drill bit, under the guiding and positioning action of an outer sleeve pile casing, grooves are formed in bedrock to form circular groove positions matched with the construction pile casing in size, and the groove cutting depth is determined according to the water depth and the geological condition;
step five: after a groove position is formed on the bedrock, lifting a roller cone drill bit, and lowering a construction steel casing, wherein the construction steel casing is accurately embedded into the cut annular groove position under the guidance of an outer casing, and the construction casing is in place;
step six: in an annular gap formed between the construction casing and the outer sleeve casing, yellow clay is put down by a guide pipe to seal and fill the gap between the construction casing and the bare rock groove position, and the bottom of the construction casing is sealed;
step seven: and pulling out the outer sleeve protection barrel, moving the outer sleeve protection barrel and the equipment to the next hole site, and sequentially and circularly finishing the construction of the protection barrels at other hole sites.
2. The construction method of the deep water pile foundation steel casing applicable to the bare rock geological condition according to claim 1; the method is characterized in that: and underwater concrete replaces clay to seal and fill the gap between the construction pile casing and the bare rock slot, and the bottom of the construction pile casing is sealed.
CN202010951000.5A 2020-09-11 2020-09-11 Construction method suitable for deep water pile foundation steel casing under bare rock geological condition Pending CN112031017A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010951000.5A CN112031017A (en) 2020-09-11 2020-09-11 Construction method suitable for deep water pile foundation steel casing under bare rock geological condition

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010951000.5A CN112031017A (en) 2020-09-11 2020-09-11 Construction method suitable for deep water pile foundation steel casing under bare rock geological condition

Publications (1)

Publication Number Publication Date
CN112031017A true CN112031017A (en) 2020-12-04

Family

ID=73588827

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010951000.5A Pending CN112031017A (en) 2020-09-11 2020-09-11 Construction method suitable for deep water pile foundation steel casing under bare rock geological condition

Country Status (1)

Country Link
CN (1) CN112031017A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113293792A (en) * 2021-05-31 2021-08-24 中国电建集团福建省电力勘测设计院有限公司 Construction method of bored pile based on inclined pile in offshore wind power weathering soil layer
CN113338284A (en) * 2021-07-08 2021-09-03 浙江易通特种基础工程股份有限公司 Construction method for implanting large-diameter permanent steel casing into deep-water inclined bare rock
CN113737839A (en) * 2021-08-10 2021-12-03 广东华蕴海上风电科技有限公司 Offshore wind power rock-socketed single pile construction method based on double pile casing structure and soft soil layer
CN114215049A (en) * 2021-12-09 2022-03-22 中铁大桥局集团第五工程有限公司 Construction method for main steel casing of bored pile under deep water foundation and bare rock environment
CN114250771A (en) * 2022-01-04 2022-03-29 李亮 Rock stratum steel casing inserting and punching method
CN116856408A (en) * 2023-09-04 2023-10-10 中交第一航务工程局有限公司 Sinking method of steel casing suitable for deepwater bare rock area

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201649080U (en) * 2010-02-26 2010-11-24 浙江台州甬台温高速公路有限公司 Steel casing favorable for stable submerging on underwater bare rock surface
CN206646541U (en) * 2017-03-30 2017-11-17 福建省水利水电勘测设计院(水利部福建水利水电勘测设计研究院) A kind of embedding rock single-pile foundation of batholith sea bed offshore wind turbine
CN108560543A (en) * 2018-05-30 2018-09-21 中国二十二冶集团有限公司 Underwater cast-in-place pile casing construction method
CN110359476A (en) * 2019-07-04 2019-10-22 中铁七局集团有限公司 A kind of construction method of steel sheet-pile cofferdam inner support and drilled pile steel pile casting installation operation platform
CN111608173A (en) * 2020-06-04 2020-09-01 石家庄铁道大学 Construction method and device for deep water steep slope bare rock drilled pile

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201649080U (en) * 2010-02-26 2010-11-24 浙江台州甬台温高速公路有限公司 Steel casing favorable for stable submerging on underwater bare rock surface
CN206646541U (en) * 2017-03-30 2017-11-17 福建省水利水电勘测设计院(水利部福建水利水电勘测设计研究院) A kind of embedding rock single-pile foundation of batholith sea bed offshore wind turbine
CN108560543A (en) * 2018-05-30 2018-09-21 中国二十二冶集团有限公司 Underwater cast-in-place pile casing construction method
CN110359476A (en) * 2019-07-04 2019-10-22 中铁七局集团有限公司 A kind of construction method of steel sheet-pile cofferdam inner support and drilled pile steel pile casting installation operation platform
CN111608173A (en) * 2020-06-04 2020-09-01 石家庄铁道大学 Construction method and device for deep water steep slope bare rock drilled pile

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113293792A (en) * 2021-05-31 2021-08-24 中国电建集团福建省电力勘测设计院有限公司 Construction method of bored pile based on inclined pile in offshore wind power weathering soil layer
CN113293792B (en) * 2021-05-31 2022-05-24 中国电建集团福建省电力勘测设计院有限公司 Construction method of bored pile based on inclined pile in offshore wind power weathering soil layer
CN113338284A (en) * 2021-07-08 2021-09-03 浙江易通特种基础工程股份有限公司 Construction method for implanting large-diameter permanent steel casing into deep-water inclined bare rock
CN113737839A (en) * 2021-08-10 2021-12-03 广东华蕴海上风电科技有限公司 Offshore wind power rock-socketed single pile construction method based on double pile casing structure and soft soil layer
CN114215049A (en) * 2021-12-09 2022-03-22 中铁大桥局集团第五工程有限公司 Construction method for main steel casing of bored pile under deep water foundation and bare rock environment
CN114250771A (en) * 2022-01-04 2022-03-29 李亮 Rock stratum steel casing inserting and punching method
CN116856408A (en) * 2023-09-04 2023-10-10 中交第一航务工程局有限公司 Sinking method of steel casing suitable for deepwater bare rock area
CN116856408B (en) * 2023-09-04 2023-11-07 中交第一航务工程局有限公司 Sinking method of steel casing suitable for deepwater bare rock area

Similar Documents

Publication Publication Date Title
CN112031017A (en) Construction method suitable for deep water pile foundation steel casing under bare rock geological condition
CN106245626A (en) A kind of hard formation churning driven enters method
CN106988302B (en) A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method
CN102966111B (en) A kind of steel pipe pile anchoring construction method in deep water torrent intectate steep bare rock
CN101294393A (en) Construction method with dewatering water well equipped outside of foundation pit
CN102979069A (en) Bored pile platform construction method on covering-free steep bare rock in deepwater and rapid stream
CN102953362B (en) A kind of drilled pile platform be arranged in deep water torrent intectate steep bare rock
CN111593728A (en) Embedded rock-socketed pile 'pile-first method' interpolation type jacket foundation construction system
CN101586340A (en) Preconditioning process of continuous wall for weak weathering terrane grooving construction
CN103835648A (en) Raise-boring technology for improving rock stratum performance through ground grouting
CN112482364A (en) Construction process of rotary digging cast-in-place pile under strong corrosive soft geological conditions in coastal region
CN102979039A (en) Elevated trestle bridge construction method on covering-free steep bare rock in deepwater and rapid stream
CN114215049A (en) Construction method for main steel casing of bored pile under deep water foundation and bare rock environment
CN110984132B (en) Construction method for grooving underground diaphragm wall under complex geological condition
CN110700293B (en) Rotary excavating leading hole steel sheet pile cofferdam construction method under deep water sloping rock environment
CN111691397A (en) Karst tunnel bottom filling bead string type karst cave steel pipe pile grouting hole forming method
CN113431045B (en) Construction method for rotary drilling pore-forming karst leaking stoppage
CN110241731A (en) A method of forming rock-socketed pile foundation in seabed
CN109056709A (en) A method of using full-sleeve hydraulic drill rig construction In Karst Areas For Bridge pile foundation
CN111927320A (en) Ultra-deep large-diameter pile hole forming method
CN110672062A (en) Embedding method of monitoring points for monitoring settlement of bedrock
CN113174991B (en) Pile periphery stratum collapse grouting reinforcement method for ocean deepwater inclined piles
CN114320360A (en) TRD and surface deep hole half-section grouting combined advanced waterproof curtain construction method
CN107975376A (en) Tunneling shield push pipe and vertical duct connection structure and construction method
CN211113598U (en) Karst cave handling system for deep foundation pit pile foundation construction in karst area

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20201204