CN106522209A - Perfusion construction method of cast-in-situ bored pile for revolving-boring construction of karst cave - Google Patents

Perfusion construction method of cast-in-situ bored pile for revolving-boring construction of karst cave Download PDF

Info

Publication number
CN106522209A
CN106522209A CN201610875132.8A CN201610875132A CN106522209A CN 106522209 A CN106522209 A CN 106522209A CN 201610875132 A CN201610875132 A CN 201610875132A CN 106522209 A CN106522209 A CN 106522209A
Authority
CN
China
Prior art keywords
concrete
borehole cleaning
situ bored
bored pile
engineering method
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610875132.8A
Other languages
Chinese (zh)
Inventor
薛涛
时逢春
李飞
佘正中
杨海波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jinling Institute of Technology
Original Assignee
Jinling Institute of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Jinling Institute of Technology filed Critical Jinling Institute of Technology
Priority to CN201610875132.8A priority Critical patent/CN106522209A/en
Publication of CN106522209A publication Critical patent/CN106522209A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/385Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to the technical field of pile foundation projects, in particular to a perfusion construction method of a cast-in-situ bored pile for revolving-boring construction of a karst cave. The perfusion construction method comprises the following steps: 1, borehole cleaning; 2, processing of a reinforcement cage; 3, hoisting of the reinforcement cage; 4, mounting of a conduit and a funnel; 5, pouring of first-batch concrete; 6, pouring of concrete to the pile top; and 7, pulling-out of a pile casing. According to the perfusion construction method, as sufficient water head is kept in a borehole during borehole cleaning, borehole collapse can be effectively prevented; as continuous concrete casting is adopted, pile breakage can be effectively prevented; and environmental pollution can be also avoided.

Description

Rotary digging construction solution cavity cast-in-situ bored pile perfusion engineering method
Technical field
The present invention relates to pile foundation engineering technique field, and in particular to rotary digging construction solution cavity cast-in-situ bored pile perfusion engineering method.
Background technology
Quality of the relationship between quality of pile foundation engineering to whole building project subject quality, therefore the construction of pile foundation engineering is necessary There are enough quality assurances.For the pile foundation construction in general stratum site area, existing technological level has been able to ensure stake Base construction quality, and for complicated geological condition, during construction, difficulty is very big, need to also update in terms of technology, It is big just because of difficulty of construction, under existing instillation process, easily there is collapse hole, broken pile, environmental pollution.
The content of the invention
Present invention aims to the defect and deficiency of prior art, there is provided a kind of rotary digging construction solution cavity drill-pouring Stake irrigates engineering method, and its concrete engineering method is:1st, borehole cleaning;2nd, steel reinforcement cage processing;3rd, reinforcing bar cage hoisting;4th, conduit and funnel are installed; 5th, pour first batch of concrete;6th, casting concrete is to stake top;7th, extract casing.
After said structure, the present invention has the beneficial effect that:Rotary digging construction solution cavity cast-in-situ bored pile of the present invention is filled Note engineering method, its enough head in retaining hole when borehole cleaning, can effectively prevent the hole that collapses;It adopts continuous concreting, Broken pile can effectively be prevented;It can also prevent the pollution of the environment.
Specific embodiment
Describe the present invention below in conjunction with specific embodiment in detail, illustrative examples therein and explanation are only used for The present invention is explained, but it is not as a limitation of the invention.
Rotary digging construction solution cavity cast-in-situ bored pile described in this specific embodiment irrigates engineering method, and its concrete engineering method is:1、 Borehole cleaning;2nd, steel reinforcement cage processing;3rd, reinforcing bar cage hoisting;4th, conduit and funnel are installed;5th, pour first batch of concrete;6th, casting concrete To stake top;7th, extract casing.
Further:Using brill rotary digging borehole cleaning under rotary drilling rig during borehole cleaning;Mud displacement method borehole cleaning is adopted during borehole cleaning;Borehole cleaning When retaining hole in enough heads.
Further:Hole position is directed at by human assistance during lower cage, is kept vertical, put down gently, slow play, it is to avoid collision hole wall.
Further:Under conduit, mouth retains 25-40cm with hole bottom distance;Concreting successively should be poured;Pour During measure concrete surface with plummet, calculate the depth of conduit lower end Transducers Embedded in Concrete, and make a record;Should in casting process The mud overflowed in wellhole is drained to into mud pit.
Borehole cleaning:After rotary drilling rig pore-forming, sediment will not be too thick, can generally individually meet design requirement, such as finds sediment thickness More than design standard, can be using rotary digging borehole cleaning be bored under rotary drilling rig, if it is necessary, mud displacement method borehole cleaning may also be employed.Borehole cleaning When it is noted that it is following some:
1. enough heads in retaining hole, prevent the hole that collapses;
2. the method for not handy hole depth of backbreaking substitutes borehole cleaning;
3., after steel reinforcement cage is hung in, before pouring underwater concrete, mud property index and bottom hole precipitation in hole should be checked again for Thickness, such as exceedes regulation, should carry out second borehole cleaning, can pouring underwater concrete after meeting the requirements.
Steel reinforcement cage is processed and is lifted:
Steel reinforcement cage is processed:Steel reinforcement cage is applied in strict accordance with design drawing and related code using live processing and fabricating, processing dimension. According to design drawing calculate stirrup materials length, cage bar distribution segment length, by after required bar straightening with cutting machine in batch Cut it is standby, and the specification according to steel bar meter and numbering difference respectively be listed stack.
Hole position is directed at by human assistance during lower cage, is kept vertical, put down gently, slow play, it is to avoid collision hole wall.If in decentralization process Run into obstacle to stop immediately, ascertain the reason and processed, forbid Gao Timeng to put and force down.During decentralization steel reinforcement cage, technology people Member answers strict control cage top mark on the scene high.
Concreting:
First batch of concrete → the casting concrete of conduit and funnel → pour is installed to stake top → extract casing.Conduit is installed first, Conduit is hung in hole with crane, position keeps placed in the middle, under conduit, mouth retains 25-40cm or so with hole bottom distance.The stake of this engineering method Footpath 790mm, first batch of concreting amount is typically in 2m3, concreting successively should pour.Surveyed with plummet in casting process Measurement concrete surface, calculates the depth of conduit lower end Transducers Embedded in Concrete, and makes a record, and will should overflow in wellhole in casting process Mud be drained to mud pit, arbitrarily must not discharge, prevent pollute environment.
Karst Cave Formation filling concrete key points for operation
General stratum, first batch of concreting amount are not less than 1.0m in ensureing conduit base opening Transducers Embedded in Concrete, lead in casting process Pipe buried depth in the concrete is answered between 2.0m-6.0m, and concreting must be continuous, prevent broken pile.The full mistake of concreting Journey is responsible for and is made a record by engineering department special messenger.
Depth of tremie should suitably be deepened on this basis for Karst Cave Formation concrete perfusion, preferably in 5m or so.Do so Purpose prevent the deadweight in casting concrete excessive, by hole wall at solution cavity wash open to make concrete flow into solution cavity, make concrete Face drastically declines, and causes broken pile.
Rotary digging construction solution cavity cast-in-situ bored pile perfusion engineering method of the present invention, it is enough in retaining hole when borehole cleaning Head, can effectively prevent the hole that collapses;It adopts continuous concreting, can effectively prevent broken pile;It can also prevent the pollution of the environment.
The above is only the better embodiment of the present invention, therefore all constructions according to described in present patent application scope, Equivalence changes or modification that feature and principle are done, are included in the range of present patent application.

Claims (4)

1. rotary digging construction solution cavity cast-in-situ bored pile irrigates engineering method, it is characterised in that:Its concrete engineering method is:1st, borehole cleaning;2nd, reinforcing bar Cage is processed;3rd, reinforcing bar cage hoisting;4th, conduit and funnel are installed;5th, pour first batch of concrete;6th, casting concrete is to stake top;7th, pull out Go out casing.
2. rotary digging construction solution cavity cast-in-situ bored pile according to claim 1 irrigates engineering method, it is characterised in that:Adopt during borehole cleaning Rotary digging borehole cleaning is bored under rotary drilling rig;Mud displacement method borehole cleaning is adopted during borehole cleaning;Enough heads in retaining hole during borehole cleaning.
3. rotary digging construction solution cavity cast-in-situ bored pile according to claim 1 irrigates engineering method, it is characterised in that:By people during lower cage Work auxiliary alignment hole position, keeps vertical, puts down gently, slow play, it is to avoid collision hole wall.
4. rotary digging construction solution cavity cast-in-situ bored pile according to claim 1 irrigates engineering method, it is characterised in that:Under conduit mouth with Hole bottom distance retains 25-40cm;Concreting successively should be poured;With plummet measurement concrete surface in casting process, The depth of conduit lower end Transducers Embedded in Concrete is calculated, and is made a record;Casting process should by wellhole in the mud that overflows be drained to Mud pit.
CN201610875132.8A 2016-10-08 2016-10-08 Perfusion construction method of cast-in-situ bored pile for revolving-boring construction of karst cave Pending CN106522209A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610875132.8A CN106522209A (en) 2016-10-08 2016-10-08 Perfusion construction method of cast-in-situ bored pile for revolving-boring construction of karst cave

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610875132.8A CN106522209A (en) 2016-10-08 2016-10-08 Perfusion construction method of cast-in-situ bored pile for revolving-boring construction of karst cave

Publications (1)

Publication Number Publication Date
CN106522209A true CN106522209A (en) 2017-03-22

Family

ID=58332945

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610875132.8A Pending CN106522209A (en) 2016-10-08 2016-10-08 Perfusion construction method of cast-in-situ bored pile for revolving-boring construction of karst cave

Country Status (1)

Country Link
CN (1) CN106522209A (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06136745A (en) * 1992-04-28 1994-05-17 J D F:Kk Construction method for hollow widened bottom cast-in-place concrete pile
CN102400460A (en) * 2011-11-30 2012-04-04 昆明捷程桩工有限责任公司 Construction method for preventing pile diameter of concrete pouring pile from being varied
CN103603342A (en) * 2013-11-01 2014-02-26 中冶天工上海十三冶建设有限公司 Construction method of ultra-long bored concrete pile with large-diameter casing combination
CN103615001A (en) * 2013-11-27 2014-03-05 宁波盛宏建设工程有限公司 Bored pile construction method for reinforcing cage framework layered installation
CN104153352A (en) * 2014-07-31 2014-11-19 广西科技大学 Karst geology rotary-drilling bored concrete pile hole forming process

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06136745A (en) * 1992-04-28 1994-05-17 J D F:Kk Construction method for hollow widened bottom cast-in-place concrete pile
CN102400460A (en) * 2011-11-30 2012-04-04 昆明捷程桩工有限责任公司 Construction method for preventing pile diameter of concrete pouring pile from being varied
CN103603342A (en) * 2013-11-01 2014-02-26 中冶天工上海十三冶建设有限公司 Construction method of ultra-long bored concrete pile with large-diameter casing combination
CN103615001A (en) * 2013-11-27 2014-03-05 宁波盛宏建设工程有限公司 Bored pile construction method for reinforcing cage framework layered installation
CN104153352A (en) * 2014-07-31 2014-11-19 广西科技大学 Karst geology rotary-drilling bored concrete pile hole forming process

Similar Documents

Publication Publication Date Title
CN104532813B (en) A kind of aquatic building operation platform and erection method, using method
CN106400782B (en) A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit
CN104895092B (en) The method that a kind of interim lattice column of inner support is used as permanent structure post
CN108894214B (en) Karst cave geological environment cast-in-place pile and pile-forming construction method thereof
CN103195058B (en) Be convenient to solution cavity and grow the method that regional bridge pier adopts many casings to construct
CN104120716A (en) Slurry wall protection construction method for bored pile
CN107524142A (en) A kind of holing with slurry wall protection cast-in-place pile construction method
CN105926672B (en) A kind of Underground Subway Station steel pipe column construction method
CN103266600A (en) Occlusion pile of full reinforcement pile and construction method thereof
CN104895093B (en) A kind of half coercion underground continuous wall and its construction method
CN107620311A (en) A kind of mud off pore-creating filling pile prevents the method that aperture casing sinks
CN107503344A (en) The construction method of turnover type merogenesis steel pile casting retaining wall manually digging hole filling pile
CN106545020A (en) A kind of construction method of deep foundation pit support
CN106759269A (en) The construction method of diaphram wall in macrorelief scar stratum
CN102587386A (en) Reverse HPE (hydraulic perpendicular embedding) construction method for steel pipe columns in basement
CN107100164A (en) A kind of long auger guncreting pile construction method
CN204282399U (en) A kind of subway space enclosing structure
CN104895054A (en) Construction method of fiber rib concrete uplift pile
CN107299640A (en) A kind of variable cross-section well shaft type ground continuous wall base and its construction method
CN106522209A (en) Perfusion construction method of cast-in-situ bored pile for revolving-boring construction of karst cave
CN113026723B (en) Special-shaped ribbed plate combined water stop structure of underground continuous wall and construction method
CN108035357A (en) Filling pile construction scheme and its funnel
CN113738272A (en) Rotary drilling hole forming construction method for pile foundation in gravel area with easy hole collapse
CN113756290A (en) Sand-pebble geological variable-section screw pile construction process
CN208167719U (en) Karsts developing area stratum can prevent a full set of cylinder pile-forming apparatus of broken pile

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20170322