CN106400782B - A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit - Google Patents

A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit Download PDF

Info

Publication number
CN106400782B
CN106400782B CN201610483010.4A CN201610483010A CN106400782B CN 106400782 B CN106400782 B CN 106400782B CN 201610483010 A CN201610483010 A CN 201610483010A CN 106400782 B CN106400782 B CN 106400782B
Authority
CN
China
Prior art keywords
stake
construction
concrete
hole
sequence
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201610483010.4A
Other languages
Chinese (zh)
Other versions
CN106400782A (en
Inventor
李志军
郭小龙
王秋林
董小龙
董军
张荣华
雷明星
段杰文
姚远
曹光云
孔祥远
羊红艳
罗苍宁
易定达
邢永辉
张伟
孙超
宋本乐
彭炎锋
叶亮
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Tunnel Group Erchu Co Ltd
Original Assignee
China Railway Tunnel Group Erchu Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Tunnel Group Erchu Co Ltd filed Critical China Railway Tunnel Group Erchu Co Ltd
Priority to CN201610483010.4A priority Critical patent/CN106400782B/en
Publication of CN106400782A publication Critical patent/CN106400782A/en
Application granted granted Critical
Publication of CN106400782B publication Critical patent/CN106400782B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/06Placing concrete under water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

It is a kind of to go along with sb. to guard him construction method described in the construction method of hole-drilling interlocking pile using rotary drilling rig construction foundation pit, including preparation of construction, embedded casing, drilling machine are in place, the processing of mechanical hole building, brush wall, borehole cleaning, steel reinforcement cage and lifting, concreting.Hole-drilling interlocking pile of the present invention has advanced steel sleeve retaining wall in the construction process using all casing drill pore-forming always, so being not necessarily to mud off, to save the expense of mud production, use and waste pulp processing, the soil of taking-up is original soil, is conducive to the civilized construction for doing building site well;This method can reduce project cost, improve speed of application, guarantee supporting construction quality conscientiously.

Description

A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit
Technical field
The present invention relates to a kind of construction methods that hole-drilling interlocking pile is gone along with sb. to guard him using rotary drilling rig construction foundation pit.
Background technique
The tunnel Hong Gu east bank ring road in Nanchang City is close to Jiangxi east embankment, and embankment is Gravity Retaining Wall, and barricade bottom is for jackstone Layer.Former foundation pit enclosure structure is the stake of SMW engineering method, and being influenced mixing pile by barricade bottom jackstone can not construct to rock stratum, and H profile steel It can not be inserted into designed elevation, foundation pit enclosure structure is unable to satisfy sealing and stress problem.
Summary of the invention
The purpose of the present invention is provide a kind of utilization rotary drilling rig construction foundation pit for prior art deficiency and actual needs Go along with sb. to guard him the construction method of hole-drilling interlocking pile.
Construction method technical solution of the present invention is:
850@600mmSMW engineering method stake of ring road foundation pit enclosure φ is improved to the hole-drilling interlocking pile of diameter 1000mm, the brill Hole interlocking pile is divided into a sequence stake i.e. A type stake and two sequence stake Type B stakes, and a sequence stake and two sequence stake elevation of bottom are the same as SMW engineering method stake bottom Absolute altitude;The concrete of two sequence stakes is fused together in insertion occlusive state and forms a continuous whole piling structure;One Sequence stake, that is, A type stake stake spacing 1500mm makees plain stake using underwater casting plastic concrete;Two sequence stakes, that is, Type B stake is underwater C30P8 Drill deposited reinforced concrete pile, 250mm is engaged with a sequence stake, stake spacing 1500mm, steel reinforcement cage elevation of bottom is the same as SMW engineering method stake H profile steel elevation of bottom.
The construction method step are as follows:
(1) preparation of construction
According to stake bit plan and live datum mark, measuring stake position and visible marking is squeezed at the construction field (site), it is ensured that stake position Unwrapping wire is accurate, and protects to datum mark;
(2) casing is buried
Casing internal diameter is 0.2m bigger than bore diameter, excavates stake holes to casing bottom, according to stake holes centralized positioning casing, casing 1.5m below the water level located underground of bottom, casing rise out level of ground water 1.5m~2.0m, and shield cartridge storing mud is higher by underground Water level 0.5m or more;
(3) drilling machine is in place
When rotary drilling rig is in place, held stationary, not run-off the straight displacement, to accurately control drilling depth, on the rack or The scale of control is made on machine pipe, to be observed, to record in construction.
(4) mechanical hole building
The specific gravity and sand factor that slurry coat method is controlled when rotary drilling rig pore-forming, undergauge or collapse hole, rotary digging when preventing from creeping into The dregs of drilling machine pore-forming is transported to interim spoir hole using short vehicle of refuting, and occlusion pile driving construction is one using the construction of stake method, every 9 pile is jumped Construction circulation, A type stake, that is, plastic concrete element stake of first constructing, closes on Type B stake i.e. through constructing again when initial set in 7~9 hours when the stake of A type Reinforced concrete pile;
(5) brush wall, borehole cleaning
A sequence stake plastic concrete is cut when rotary drilling rig two sequence stake of construction, mudcake is attached to cutting face and causes in order to prevent Seam percolating water carries out brush wall using crane suspention drilled pile brush wall device, borehole cleaning is carried out after the completion of brush wall;
After getting into predetermined depth, slurry is changed using sand suction pump borehole cleaning, away from the mud balance 1.15g/m at bottom hole 0.5m3, for Sandy soils, 1.15~1.20g/m of specific gravity of hole bottom slurry after borehole cleaning3, the bottom hole sediment thickness after borehole cleaning is not more than 50mm, filling Infuse repetition measurement sediment thickness before underwater concrete, borehole cleaning again when sediment is more than regulation;
(6) steel reinforcement cage processing and lifting
Steel reinforcement cage complete the process it is qualified by inspection after, utilize whole of crane or segmental hoisting steel reinforcement cage to stake holes;
(7) concreting
Concreting uses tremie method concrete placed under water, and timely measured hole inner concrete face height carries out conduit Promotion and dismounting, control the buried depth of conduit in 2~6m.
A) plastic concrete pours
Before use, checking whether its slump and impression quality meet the requirements, per car concrete takes plastic concrete One group of test specimen monitors its retarding time and slump-loss situation, until the B stake of this two sides is fully completed;
B) normal concrete pours
Rate of flooding suitably slows down when concrete surface is close to steel reinforcement cage bottom end, when concrete enters 2~3m of steel reinforcement cage bottom end Afterwards, conduit, which is promoted, slowly, steadily to avoid discharging from impacting excessive or hook strip steel reinforcement cage, to prevent rising of steel cage.
Beneficial effects of the present invention: hole-drilling interlocking pile uses all casing drill pore-forming, in the construction process, has always advanced Steel sleeve retaining wall, so mud off is not necessarily to, to save the expense of mud production, use and waste pulp processing, the soil of taking-up For original soil, be conducive to the civilized construction for doing building site well;This method can reduce project cost, improve speed of application, guarantee branch conscientiously Protection structure quality.
Detailed description of the invention
Fig. 1 is the step schematic diagram of construction method of the present invention;
In figure: A is A type stake, that is, plastic concrete element stake;B is Type B stake, that is, reinforced concrete pile.
Specific embodiment
As can be seen from FIG. 1, occlusion pile driving construction is a construction circulation, A type of first constructing using the construction of stake method, every 9 pile is jumped Stake (stake of plastic concrete element), (about 7~9 hours) construct again when A type stake initial set closes on Type B stake (reinforced concrete pile), applies Work sequence: A1 → A3 → A5 → A2 → A4 → B1 → B2 → B3 → B4.
Construction method step of the present invention are as follows:
(1) preparation of construction
According to stake bit plan and live datum mark, measuring stake position and visible marking is squeezed at the construction field (site), it is ensured that stake position Unwrapping wire is accurate, and protects to datum mark;
(2) casing is buried
Casing internal diameter is 0.2m bigger than bore diameter, excavates stake holes to casing bottom, according to stake holes centralized positioning casing, casing 1.5m below the water level located underground of bottom, casing rise out level of ground water 1.5m~2.0m, and shield cartridge storing mud is higher by underground Water level 0.5m or more;
(3) drilling machine is in place
When rotary drilling rig is in place, held stationary, not run-off the straight displacement, to accurately control drilling depth, on the rack or The scale of control is made on machine pipe, to be observed, to record in construction.
(4) mechanical hole building
The specific gravity and sand factor that slurry coat method is controlled when rotary drilling rig pore-forming, undergauge or collapse hole, rotary digging when preventing from creeping into The dregs of drilling machine pore-forming is transported to interim spoir hole using short vehicle of refuting, and occlusion pile driving construction is one using the construction of stake method, every 9 pile is jumped Construction circulation, A type stake, that is, plastic concrete element stake of first constructing, closes on Type B stake i.e. through constructing again when initial set in 7~9 hours when the stake of A type Reinforced concrete pile;
(5) brush wall, borehole cleaning
A sequence stake plastic concrete is cut when rotary drilling rig two sequence stake of construction, mudcake is attached to cutting face and causes in order to prevent Seam percolating water carries out brush wall using crane suspention drilled pile brush wall device, borehole cleaning is carried out after the completion of brush wall;
After getting into predetermined depth, slurry is changed using sand suction pump borehole cleaning, away from the mud balance 1.15g/m at bottom hole 0.5m3, for Sandy soils, 1.15~1.20g/m of specific gravity of hole bottom slurry after borehole cleaning3, the bottom hole sediment thickness after borehole cleaning is not more than 50mm, filling Infuse repetition measurement sediment thickness before underwater concrete, borehole cleaning again when sediment is more than regulation;
(6) steel reinforcement cage processing and lifting
Steel reinforcement cage complete the process it is qualified by inspection after, utilize whole of crane or segmental hoisting steel reinforcement cage to stake holes;
(7) concreting
Concreting uses tremie method concrete placed under water, and timely measured hole inner concrete face height carries out conduit Promotion and dismounting, control the buried depth of conduit in 2~6m.
A) plastic concrete pours
Before use, checking whether its slump and impression quality meet the requirements, per car concrete takes plastic concrete One group of test specimen monitors its retarding time and slump-loss situation, until the B stake of this two sides is fully completed;
B) normal concrete pours
Rate of flooding suitably slows down when concrete surface is close to steel reinforcement cage bottom end, when concrete enters 2~3m of steel reinforcement cage bottom end Afterwards, conduit, which is promoted, slowly, steadily to avoid discharging from impacting excessive or hook strip steel reinforcement cage, to prevent rising of steel cage.

Claims (1)

1. a kind of construction method that hole-drilling interlocking pile is gone along with sb. to guard him using rotary drilling rig construction foundation pit, it is characterized in that:
850@600mmSMW engineering method stake of ring road foundation pit enclosure φ is improved to the hole-drilling interlocking pile of diameter 1000mm, the drilling is stung It closes stake and is divided into a sequence stake i.e. A type stake and two sequence stake Type B stakes, a sequence stake and two sequence stake elevation of bottom are the same as SMW engineering method stake elevation of bottom; The concrete of two sequence stakes is fused together in insertion occlusive state and forms a continuous whole piling structure;One sequence stake is A type stake stake spacing 1500mm makees plain stake using underwater casting plastic concrete;Two sequence stakes, that is, Type B stake is underwater C30P8 drilling steel Reinforced concrete bored concrete pile is engaged 250mm with a sequence stake, and stake spacing 1500mm, steel reinforcement cage elevation of bottom is the same as SMW engineering method stake H profile steel Elevation of bottom;
The construction method step are as follows:
(1) preparation of construction
According to stake bit plan and live datum mark, measuring stake position and visible marking is squeezed at the construction field (site), keep stake position unwrapping wire quasi- Really, and to datum mark it protects;
(2) casing is buried
Casing internal diameter is 0.2m bigger than bore diameter, excavates stake holes to casing bottom, according to stake holes centralized positioning casing, the bottom of casing 1.5m below water level located underground, casing rise out level of ground water 1.5m~2.0m, and shield cartridge storing mud is higher by level of ground water 0.5m or more;
(3) drilling machine is in place
When rotary drilling rig is in place, held stationary, not run-off the straight displacement, to accurately control drilling depth, on the rack or machine pipe On make the scale of control, to be observed, to record in construction;
(4) mechanical hole building
The specific gravity and sand factor that slurry coat method is controlled when rotary drilling rig pore-forming, undergauge or collapse hole, rotary drilling rig when preventing from creeping into The dregs of pore-forming is transported to interim spoir hole using short vehicle of refuting, and occlusion pile driving construction is a construction using the construction of stake method, every 9 pile is jumped Circulation, A type stake, that is, plastic concrete element stake of first constructing, closes on Type B stake i.e. reinforcing bar through constructing again when initial set in 7~9 hours when the stake of A type Concrete-pile;
(5) brush wall, borehole cleaning
A sequence stake plastic concrete is cut when rotary drilling rig two sequence stake of construction, mudcake is attached to cutting face and causes seam in order to prevent Percolating water carries out brush wall using crane suspention drilled pile brush wall device, borehole cleaning is carried out after the completion of brush wall;
After getting into predetermined depth, slurry is changed using sand suction pump borehole cleaning, is controlled away from the mud balance at bottom hole 0.5m in 1.15g/m3, right 1.15~1.20g/m of specific gravity of hole bottom slurry after sandy soils, borehole cleaning3, the bottom hole sediment thickness after borehole cleaning is not more than 50mm, Repetition measurement sediment thickness before pouring underwater concrete, borehole cleaning again when sediment is more than regulation;
(6) steel reinforcement cage processing and lifting
Steel reinforcement cage complete the process it is qualified by inspection after, utilize whole of crane or segmental hoisting steel reinforcement cage to stake holes;
(7) concreting
Concreting uses tremie method concrete placed under water, and timely measured hole inner concrete face height carries out mentioning for conduit It rises and removes, control the buried depth of conduit in 2~6m;
A) plastic concrete pours
For plastic concrete before use, checking whether its slump and impression quality meet the requirements, per car concrete takes one group Test specimen monitors its retarding time and slump-loss situation, until the B stake of this two sides is fully completed;
B) normal concrete pours
Rate of flooding suitably slows down when concrete surface is close to steel reinforcement cage bottom end, after concrete enters 2~3m of steel reinforcement cage bottom end, leads Pipe, which is promoted, slowly, steadily to avoid discharging from impacting excessive or hook strip steel reinforcement cage, to prevent rising of steel cage.
CN201610483010.4A 2016-06-28 2016-06-28 A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit Active CN106400782B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610483010.4A CN106400782B (en) 2016-06-28 2016-06-28 A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610483010.4A CN106400782B (en) 2016-06-28 2016-06-28 A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit

Publications (2)

Publication Number Publication Date
CN106400782A CN106400782A (en) 2017-02-15
CN106400782B true CN106400782B (en) 2019-01-04

Family

ID=58006813

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610483010.4A Active CN106400782B (en) 2016-06-28 2016-06-28 A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit

Country Status (1)

Country Link
CN (1) CN106400782B (en)

Families Citing this family (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107975027B (en) * 2017-11-25 2020-05-19 北京建材地质工程有限公司 Construction method for reinforcing soil body at shield launching and arrival end
CN108018849B (en) * 2017-11-25 2020-05-19 北京建材地质工程有限公司 Construction method for reinforcing soil body at shield launching and arrival end
CN107989032A (en) * 2017-11-28 2018-05-04 深圳市工勘岩土技术有限公司 A kind of construction method of punching interlocking pile
CN108625369A (en) * 2018-06-22 2018-10-09 中铁二局第工程有限公司 The hard patterning method construction method of interlocking pile in karst area
CN108797641A (en) * 2018-07-20 2018-11-13 中铁十八局集团有限公司 A kind of structure and its construction method of Underground Subway Station construction period full station sealing
CN109083178A (en) * 2018-07-24 2018-12-25 中交航局第三工程有限公司 It is a kind of element interlocking pile at cut-pff wall water-stop curtain construction method
CN109610524A (en) * 2018-11-29 2019-04-12 北京地矿工程建设有限责任公司 The detection of OPT interlocking pile and course control method for use
CN109948285A (en) * 2019-03-29 2019-06-28 贵州正业工程技术投资有限公司 A kind of large size Karst depression ball crown type mechanism central excavation localization method
CN110093934A (en) * 2019-05-20 2019-08-06 中铁七局集团有限公司 The nothing for going along with sb. to guard him pile driving construction suitable for subway leads wall construction method of interlocking pile
CN110306561A (en) * 2019-07-05 2019-10-08 广州穗岩土木科技股份有限公司 A kind of foundation pit hardness construction method of interlocking pile
CN110512597A (en) * 2019-07-26 2019-11-29 广东厚普建设工程有限公司 A kind of rotary digging cast-in-place pile construction method
CN111305229A (en) * 2020-03-26 2020-06-19 中铁隧道集团二处有限公司 Construction method for constructing sectionwise deep rock drilling secant pile
CN113866277A (en) * 2021-09-22 2021-12-31 合诚工程咨询集团股份有限公司 Nondestructive testing method for pile forming quality of large-diameter secant pile
CN114482861A (en) * 2022-01-13 2022-05-13 中勘资源勘探科技股份有限公司 Automatic deviation rectifying method for drill hole in deep hole drilling of coal field drilling

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101328712A (en) * 2008-07-29 2008-12-24 上海市第二建筑有限公司 Construction method of interlocking pile for soft soil and soil layer with obstacle
CN103388333A (en) * 2013-07-25 2013-11-13 中铁十六局集团有限公司 Construction process for carrying out construction on interlocking pile by adopting rotary drilling rig and mud protection wall method
CN104929136A (en) * 2015-07-14 2015-09-23 上海市水利工程集团有限公司 Urban complex underground obstacle working condition occlusive pile enclosure construction method

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2000001849A (en) * 1998-06-12 2000-01-07 Geotop Corp Cast-in-place knot pile

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101328712A (en) * 2008-07-29 2008-12-24 上海市第二建筑有限公司 Construction method of interlocking pile for soft soil and soil layer with obstacle
CN103388333A (en) * 2013-07-25 2013-11-13 中铁十六局集团有限公司 Construction process for carrying out construction on interlocking pile by adopting rotary drilling rig and mud protection wall method
CN104929136A (en) * 2015-07-14 2015-09-23 上海市水利工程集团有限公司 Urban complex underground obstacle working condition occlusive pile enclosure construction method

Also Published As

Publication number Publication date
CN106400782A (en) 2017-02-15

Similar Documents

Publication Publication Date Title
CN106400782B (en) A kind of construction method for going along with sb. to guard him hole-drilling interlocking pile using rotary drilling rig construction foundation pit
CN103924586B (en) Multi section drill grouting pile construction method
CN107246006B (en) The pile-filling method of concrete-pile
CN101638891B (en) Construction method of all casing precessing isolation pile
CN100572683C (en) The large-diameter ultra-deep rock borehole bottom-expanding filling pile job practices
CN107524142A (en) A kind of holing with slurry wall protection cast-in-place pile construction method
CN203846485U (en) Long pile percussion drill hole forming construction device
CN113445498A (en) Construction process of karst hole pile foundation in complex geology
CN102720186B (en) Underwater once pouring method for variable cross-section bored cast-in-place pile
CN103266599B (en) The dry construction method of digging drilling pile of soil skerry ground churning driven
CN108589707A (en) A kind of full-sleeve long screw auger and churning driven combined type construction
CN100596318C (en) Mass concrete structure deep pore reinforced construction method
CN103388333A (en) Construction process for carrying out construction on interlocking pile by adopting rotary drilling rig and mud protection wall method
CN107724383A (en) Rotary digging cast-in-place pile construction method
CN107246007A (en) A kind of construction method CFG
CN106758759B (en) A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed
CN113404042A (en) Bridge pile position construction method
CN202925575U (en) Pre-buried structure for core-drilling detection of foundation pile
CN110847159A (en) Construction process of in-hole mechanical pile for subway construction
CN107975376A (en) Tunneling shield push pipe and vertical duct connection structure and construction method
CN107675700A (en) The construction method of diaphram wall
CN109113055B (en) The construction method of composite pile
CN113981958A (en) Method for plugging karst cave of mechanical pore-forming cast-in-place pile
CN110984862A (en) Hole guiding device for geological static pressure pile in rich thick sand layer and construction method
CN110792093A (en) Construction method of foundation pit waterproof curtain and waterproof curtain

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information

Inventor after: Li Zhijun

Inventor after: Cao Guangyun

Inventor after: Kong Xiangyuan

Inventor after: Yang Hongyan

Inventor after: Luo Cangning

Inventor after: Yi Dingda

Inventor after: Xing Yonghui

Inventor after: Zhang Wei

Inventor after: Sun Chao

Inventor after: Song Benle

Inventor after: Peng Yanfeng

Inventor after: Guo Xiaolong

Inventor after: Ye Liang

Inventor after: Wang Qiulin

Inventor after: Dong Xiaolong

Inventor after: Dong Jun

Inventor after: Zhang Ronghua

Inventor after: Lei Mingxing

Inventor after: Duan Jiewen

Inventor after: Yao Yuan

Inventor before: Guo Xiaolong

Inventor before: Gao Kun

Inventor before: Shi Yong

Inventor before: Cui Hailong

Inventor before: Wu Kongyong

Inventor before: Pi Zhongqiang

Inventor before: Cai Xiao

Inventor before: Peng Yanfeng

Inventor before: Ye Liang

Inventor before: Li Chengjiao

Inventor before: Kong Xiangyuan

Inventor before: Li Zhijun

Inventor before: Luo Cangning

Inventor before: Xing Yonghui

Inventor before: Zhang Wei

Inventor before: Sun Chao

Inventor before: Liu Wei

Inventor before: Yao Yiwen

Inventor before: Shao Yang

Inventor before: Dong Jun

CB03 Change of inventor or designer information
GR01 Patent grant
GR01 Patent grant