CN107100164A - A kind of long auger guncreting pile construction method - Google Patents
A kind of long auger guncreting pile construction method Download PDFInfo
- Publication number
- CN107100164A CN107100164A CN201710253075.4A CN201710253075A CN107100164A CN 107100164 A CN107100164 A CN 107100164A CN 201710253075 A CN201710253075 A CN 201710253075A CN 107100164 A CN107100164 A CN 107100164A
- Authority
- CN
- China
- Prior art keywords
- steel reinforcement
- reinforcement cage
- cage
- stake
- vibrating arm
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/0023—Cast, i.e. in situ or in a mold or other formwork
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Piles And Underground Anchors (AREA)
Abstract
The invention discloses a kind of long auger guncreting pile construction method, comprise the following steps, S1, measurement and positioning determine the position of guncreting pile hole to be drilled;Steel reinforcement cage, is inserted perpendicularly into stake to designed elevation, above improves lever by S2, well cementing, S3, underthrust steel reinforcement cage using vibrating arm;S4, second pouring concrete and vibration compacting;In the step S3, steel reinforcement cage of the bottom in cone is first made, there is on the steel reinforcement cage extension set along the direction away from bottom at least one cage bar, when the steel reinforcement cage is inserted into designed elevation, the extension is higher by the top of stake holes;In steel reinforcement cage down process, survey is copied to the upper end progress absolute altitude of the extension of the steel reinforcement cage, according to the distance of the upper end of extension to cage top, the actual elevation of steel reinforcement cage is judged.The present invention has steel reinforcement cage underthrust easy construction, and efficiency of construction is higher, is easy to observe the position of steel reinforcement cage, makes steel reinforcement cage underthrust position precisely, the advantages of being conducive to improving construction quality.
Description
Technical field
The present invention relates to technical field of building construction, in particular to a kind of long auger guncreting pile construction method.
Background technology
Long auger cast-with-pressure concrete pile is the cast-with-pressure concrete pile pile skill developed on the basis of long spire dry drill method
Art, the technology is to be drilled using long-spiral drilling machine to projected depth, and drilling rod is passed through using concrete pump while brill is carried
Concrete, is depressed into stake holes by central passage with certain pressure, after filling concrete to designed elevation, then is shaken by special
Dynamic equipment inserts steel reinforcement cage the deposited reinforced concrete pile in concrete to designed elevation formation.
Long-spiral drilling machine pressure fills pile-formation process because construction noise is low, equipment walking is flexible, pile-forming speed is fast, suitable to stratum
Ying Xingqiang and be widely used, be avoided that weak soil, sand soil area pile undergauge, the construction quality problem of broken pile, solve mud
Pollution problem, reduces cost, and can be used successfully to the pile on stratum below level of ground water.
During practice of construction, due to being submerged completely in concrete after steel reinforcement cage underthrust, it is impossible to observe steel reinforcement cage
Position, it is not in place to easily cause steel reinforcement cage underthrust, or underthrust is too deep, so that construction quality is influenceed, in addition, steel reinforcement cage is inserted through under
Cheng Zhong, once there is deflection, it will cause follow-up cage body underthrust difficult, influence construction speed, serious is likely to occur cage body
Occurs useless stake in the oblique insertion side wall soil layer of guiding of vibrating arm.
The content of the invention
For above-mentioned the deficiencies in the prior art, the technical problems to be solved by the invention are:How one kind is provided and is easy to sight
The position of steel reinforcement cage is surveyed, makes steel reinforcement cage underthrust position precisely, is conducive to improving the long auger guncreting pile construction of construction quality
Method.
In order to solve the above-mentioned technical problem, present invention employs following technical scheme:
A kind of long auger guncreting pile construction method, comprises the following steps, S1, measurement and positioning are provided according to Mapping departments
Control point carries out stake position and throws survey, determines the position of guncreting pile hole to be drilled;S2, well cementing, it is deep to predetermined stake holes using stake machine drill
Guncreting after degree;Steel reinforcement cage, is inserted perpendicularly into stake to designed elevation, above improved by S3, underthrust steel reinforcement cage using vibrating arm
Lever;S4, second pouring concrete and vibration compacting;Characterized in that, in the step S3, first making reinforcing bar of the bottom in cone
There is the extension set along the direction away from bottom on cage, the steel reinforcement cage at least one cage bar, make the steel reinforcement cage
When being inserted into designed elevation, the extension is higher by the top of stake holes;In steel reinforcement cage down process, to the extension of the steel reinforcement cage
Upper end carry out absolute altitude copy survey, according to the distance of the upper end of extension to cage top, judge the actual elevation of steel reinforcement cage.
Using the above method, absolute altitude is carried out by the extension top to steel reinforcement cage in down process and copies survey, due to extension
What the distance on the upper end in portion to cage top was to determine, it is possible to judge the actual elevation of steel reinforcement cage, once the actual mark of steel reinforcement cage
When height meets the requirement of designed elevation, you can propose vibrating arm, the underthrust construction of steel reinforcement cage is completed.So so that steel reinforcement cage
Whole down process and underthrust depth can be monitored, so as to ensure steel reinforcement cage being properly inserted in design mark
Height, is conducive to improving the construction quality of engineering.
Further, steel reinforcement cage is in down process, once the actual elevation of steel reinforcement cage higher than designed elevation and with design
When the difference of absolute altitude is less than 100mm, lever is above improved.
Because vibration intensity can cause the uncontrollable of underthrust depth, and on improve lever during, remain in that vibration shape
State so that concrete continues to shake with vibrating arm, and steel reinforcement cage can be caused to continue the segment distance that sinks under gravity.Separately
Outside, during practice of construction, to avoid steel reinforcement cage top anchor length from minus deviation occur, steel reinforcement cage underthrust depth is performed " peaceful high not low "
Principle, the height control of cage top mark is within+100mm.Using the above method, it is higher than designed elevation in the actual elevation of steel reinforcement cage
When, vibrating arm is taken out in advance so that steel reinforcement cage continues to sink under the shake of gravity and concrete, so that steel reinforcement cage energy
Designed elevation is inserted under reaching accurately.
Further, steel reinforcement cage first penetrates vibrating arm in steel reinforcement cage when underthrust is operated, then using crane by reinforcing bar
Cage is sling vertically, makes steel reinforcement cage keep vertical state, alignment aperture to be transferred after being corrected by vibrating arm deadweight, during decentralization,
First realize by the deadweight of vibration hammer, vibrating arm and steel reinforcement cage, when the subsidence velocity of steel reinforcement cage is close to zero, startup is shaken
Dynamic hammer drives steel reinforcement cage vibration to transfer by vibrating arm.
Concrete is than more loose after being filled due to pressure, if directly progress vibration decentralization, easily the concrete in stake is smash shake it is close
Cause cage body underthrust difficult in fact, and stop completely when steel reinforcement cage is being conducted oneself with dignity and, it is possible that because of vibration hammer itself weight
Amount causes vibrating arm inclination to cause follow-up cage body underthrust difficult, and influence construction speed and pile quality, serious is likely to occur cage
There is useless stake in the oblique insertion side wall soil layer of guiding of vibrating arm in body.Therefore, generally connect in the subsidence velocity for treating steel reinforcement cage
When nearly zero, generally when subsidence velocity is less than 150mm/min, Vibration on Start-up hammer drives steel reinforcement cage vibration to transfer by vibrating arm.
Using the above method, when steel reinforcement cage will be stopped using sinking of conducting oneself with dignity, Vibration on Start-up is hammered into shape, can more facilitate fast
The underthrust of prompt completion steel reinforcement cage, is conducive to improving construction quality and efficiency.
Further, the steel reinforcement cage includes cage bar and tie hoop, and the tie hoop is weldingly fixed on main ribs
Outside, the intersection of the tie hoop and main ribs is also banded with steel wire.
Its tie hoop is with cage bar mainly using being welded to connect in manufacturing process for traditional steel reinforcement cage, and vibrating arm is being penetrated
The problems such as stirrup sealing-off being easily caused in steel reinforcement cage.Using said structure, in tie hoop and the intersection of main ribs
Steel wire is also banded with, the cage bar off normal caused by stirrup sealing-off can be avoided, is conducive to improving the construction quality of engineering.
Further, before measurement and positioning, foundation trench excavation is first carried out, the foundation trench bottom land absolute altitude is the superfilled mark of guncreting pile
Height, excavation planar dimension should ensure that is reserved with the wide working faces of 2~3m in foundation trench surrounding, while carrying out clear bottom during excavation, and
Bottom land absolute altitude is carried out during clear bottom to copy survey, the control flume bottom discrepancy in elevation is in -50mm~50mm.
Using above-mentioned setting, because foundation trench bottom land absolute altitude is the superfilled absolute altitude of guncreting pile, by setting foundation trench, Neng Gouji
Shi Faxian concrete it is superfilled, so as to avoid the waste of concrete, be conducive to save construction cost.Reserved around foundation trench
Working face wide 2~3m, is conducive to the operation of a machine.The control flume bottom discrepancy in elevation can be avoided because bottom land is high in -50mm~50mm
Problem that the excessive pile depth brought of difference is not enough.Be conducive to improving the quality of pile.
Further, in the step S2, when specifically drilling, overhead traveling crane center, gyrator center and Zhuan Wei centers be should ensure that
Control is observed to the perpendicularity of drilling rod on same vertical line, and by the horizon rule on drilling rod shaft, meanwhile, also hanging down
It is straight that control is observed to the perpendicularity of drilling rod in being provided with theodolite on the direction of visual lines of driver.
Using above-mentioned setting, control is observed by the perpendicularity in the two directions to drilling rod, it is possible to achieve " double
Control ", can be prevented effectively from drilling rod and be tilted in drilling process, so as to improve the forming quality of stake holes.
Further, in the step S2, after the completion of drilling reaches projected depth and sweeps bottom, concrete pump is started
Concrete is conveyed into drilling tool, drilling tool is allotted in pumping, while making the pressure held stationary of concrete pump.
During construction, pressure fill carried in formation of pile brill and pumping concrete should close fit from beginning to end, drilling tool bottom discharging opening is not
The liquid level of stake material in hole must be higher than, broken pile situation otherwise occurs, the quality of pile is influenceed.Using the above method, by ensureing
Concrete conveyance pump pressure it is steady, it is ensured that carry brill with pumping be adapted, it is to avoid there is the situation of broken pile, be conducive to improve
Pile quality.
In summary, the present invention has steel reinforcement cage underthrust easy construction, and efficiency of construction is higher, is easy to observe the position of steel reinforcement cage
Put, make steel reinforcement cage underthrust position precisely, the advantages of being conducive to improving construction quality.
Brief description of the drawings
Fig. 1 is the schematic diagram of foundation trench in the inventive method.
Fig. 2 is the structural representation of steel reinforcement cage used in the inventive method.
Embodiment
With reference to embodiment, the present invention is described in further detail.
During specific implementation:A kind of long auger guncreting pile construction method, first carries out foundation trench excavation, as shown in figure 1, foundation trench
Excavation answers priority control to excavate planar dimension and cutting depth well, should consider 2-3m work when planar dimension is positioned in foundation trench surrounding
Face width, specifically reserved width should be before fluting with reference to installation model determination, it is to avoid backbreak or working face deficiency causes secondary open
The generation of groove phenomenon;Meanwhile, mechanical equivalent of light excavation should have survey crew to copy survey bottom land mark during should having the clear bottom of hand fit, clear bottom
Height, the bottom land discrepancy in elevation is not more than ± 50mm, it is to avoid the not enough problem of pile depth brought because the bottom land discrepancy in elevation is excessive.Excavation slope should be tied
Run groove soil matter jointly and cutting depth determines slope ratio.When rainy season carries out piling work, drainage works, groove should have been disposed in advance
Interior setting gutter, sump are simultaneously equipped with sufficient amount Yield rainfall relation equipment, it is to avoid because of rainwater bubble groove influence pile quality, stake machine peace
Complete and construction delay phenomenon caused by bubble groove for a long time generation.
Then positioning is measured:The control point that should be provided after the completion of fluting by survey crew according to Mapping departments carries out stake
Position, which is thrown, to be surveyed, and every pile point application steel bar end or welding rod are positioned and be flag of being wounded in action on steel bar end or welding rod, are noted on coloured flag
Bright pile No. carries out mark, in order to be checked in piling.It is more in view of each building stake position, to ensure a level really,
A reference stake position should be discharged during positioning every ten stake positions, this reference stake position should be discharged using timber and steel nail, and in benchmark
A bit number is indicated in stake, adjacent studs position can be checked with this reference stake during construction.
Rig is in place, pore-forming:Before stake machine enters after groove, spudded in, should combine layout design effective length, survey report and scene
The lower drilling depth of the data such as bottom land absolute altitude conversion is surveyed, and mark is carried out on drilling rod, with drilling depth under accurate control, it is to avoid few
Brill, the generation of outdrill phenomenon.Before rig spuds in place, base and top should be steady, in overhead traveling crane center, gyrator center, stake position
The heart should be located on same vertical line, i.e., " sight alignment ", drilling rod perpendicularity can realize single control by shaft horizon rule, be true before spudding in
Drilling rod perpendicularity is protected, vertical observation should be carried out on other direction using theodolite, that is, realizes " dual control " purpose, meanwhile, it is
Avoid drilling rod from being tilted in drilling process, no less than 2 times observation corrections should be carried out in drilling process.Normal rate of penetration
1~1.50m/min is can be controlled in, rate of penetration should at the uniform velocity be carried out neglecting and neglected soon slowly;In drilling process, such as find that drilling rod shakes
When rolling or difficult brill, drilling depth should be slowed down, stake holes deflection, displacement and drilling tool damage is prevented, deflection should be adjusted in time if finding, be adjusted
Drilling depth should be slowed down when whole, to ensure the perpendicularity of drilling.With the hole depth mark keyhole depth on drilling rod, drilling to design will
After the depth and soil layer asked, it is necessary to carry out the clear soil that dallies in former depths, then stop operating, carry brill.In view of the technique pile belongs to
In end-bearing friction pile stake, it should be carried out in construction after " dual control " i.e. drilling to designed elevation while to be unearthed to judge with reference to drilling
Whether enter design soil layer, if soil property is not inconsistent, should can be resolved through consultation with prospecting, design, be sure not blindly to construct.
It is pumped concrete pile:Before spudding in it is ensured that enough single pile consumption concrete marched into the arena and finish slump detection, concrete slump
It is required that 200 ± 20, it must be surveyed before concrete use of marching into the arena by car test, it is to avoid because the concrete stand-by period is long or because concrete itself workability is bad
Cause steel reinforcement cage underthrust difficult, not in place and useless stake phenomenon occur;Meanwhile, the sampling of 50m3 concretes is often poured into a mould in formation of pile and does 1
Group(3 pieces)Test block, test block size is that correspondence pile No. and pile date are indicated in 100mm × 100mm × 100mm, test block, in regulation
Send laboratory to carry out standard curing in time and determine its 28d compression strength.When drill hole of drilling machine reaches projected depth and to sweep bottom complete
Cheng Hou, starts concrete pump and concrete is conveyed into drilling tool, treat concrete be transported to drilling tool bottom drilling tool slowly above carries to 100-
300mm, by observing concrete conveyance pump pressure whether there is change, to judge whether drill bit both sides valve has already turned on, conveys concrete
After smooth, filling pile work can be pressed in Ti Zuan, forbids first to carry pumping concrete after pipe.
When pressure fills pile, drilling tool is allotted in pumping concrete;Carrying drilling speed degree will be adapted with rate of pumping, it is ensured that in central tube
All the time concrete is full of, drilling speed degree general control is carried in 1.5~2m/min during pile;Pressure is filled to carry boring in formation of pile and answered with pumping concrete
Close fit from beginning to end, drilling tool bottom discharging opening must not higher than stake material in hole liquid level, it is to avoid there is broken pile;In formation of pile
It should be carried out continuously, pressure fills pile must one-time continuous perfusion completion.Pressure fills pile stake top absolute altitude and should be higher than that design stake top absolute altitude(≥
500mm)And pour to flat with earth's surface one.
Cleaning product soil, fixed pile:Drilling, which is unearthed, to be concentrated mainly on around stake holes earth's surface, to ensure a level really and under reduction
Depth is inserted, spoir around stake holes should be gone to pile side with excavator week and artificial before steel reinforcement cage contraposition, decentralization is carried out
Coordinate and carry out aperture cleaning.
Underthrust steel reinforcement cage is to designed elevation:Bottom should be done with reference to the process characteristic, during fabrication of reinforcing cage coning, with
Facilitate cage body underthrust, should to be included in stake long for the conical section in construction.
Its tie hoop is with cage bar mainly using being welded to connect in manufacturing process for steel reinforcement cage, and vibrating arm is penetrating into reinforcing bar
Stirrup sealing-off problem is the common fault of the technique caused by cage, to avoid the occurrence of the cage bar off normal caused by stirrup sealing-off, reply
The steel reinforcement cage for having worn vibrating arm is carried out " secondary to check and accept ", and firm using iron wire colligation to sealing-off stirrup.
Vibrating arm is penetrated in steel reinforcement cage in ground level, sling steel reinforcement cage vertically using crane, by vibrating arm certainly
Steel reinforcement cage is kept vertical, placed in the middle again, transferred after should being corrected during decentralization by manual-alignment aperture, forbid cage body not just by force
Decentralization.
During underthrust steel reinforcement cage, decentralization first is realized by the deadweight of vibration hammer+vibrating arm+steel reinforcement cage, when can not be after by deadweight
During continuous insertion, open vibration hammering and realize that steel reinforcement cage is transferred by vibrating arm, the time for opening vibration hammer should be free in steel reinforcement cage
Decentralization will terminate preceding startup, it is unsuitable too early, be easily caused that a bottom concrete is closely knit to cause cage body underthrust difficult too early;Meanwhile, open
The time of vibration hammer also should not too late, if starting after the termination of steel reinforcement cage free releasing, in fact it could happen that because of vibration hammer own wt
Causing vibrating arm to tilt causes follow-up cage body underthrust difficult, influences construction speed, and serious is likely to occur cage body in vibrating arm
Guide in oblique insertion side wall soil layer and useless stake occur.
When steel reinforcement cage decentralization is close to projected depth, cage top mark height should be carried out copying survey by survey crew, it is contemplated that vibration force
Degree causes the uncontrollable of underthrust depth, therefore, should in advance on improve lever, underthrust depth performs " peaceful high not low " principle, cage top
Absolute altitude is controlled within+100mm.
Failure of oscillation and slowly continuously should not above it be carried during being carried on vibrating arm, meanwhile, vibrating arm bottom should be accomplished away from earth's surface 2m
Within when failure of oscillation, to realize the vibration compacting to concrete piles.
Survey is copied for ease of cage top mark height, there should be 1 cage bar to extend to ground off-balancesheet during fabrication of reinforcing cage and be not less than 100mm, should
Absolute altitude control muscle can also take later stage colligation or welding spreading.When it is implemented, the steel reinforcement cage uses following structures, such as Fig. 2 institutes
Show, including many cage bars 1 being uniformly arranged along the circumference of steel reinforcement cage and be spirally wound on along the circumference of steel reinforcement cage in main ribs 1
Tie hoop 2, the tie hoop 2 is weldingly fixed on the outside of main ribs 1, and one end of main ribs 1 is towards steel reinforcement cage
Axis direction bending, make the end steel reinforcement cage formation conical lower section;Have at least one main ribs 1 along the bottom of away from
The extension 3 that the direction in portion is set, when the steel reinforcement cage is inserted into designed elevation, the extension is higher by the top of stake holes.
Using said structure, when being inserted into designed elevation due to steel reinforcement cage, the extension is higher by the top of stake holes so that steel
Muscle cage in down process, all the time can to extension top carry out absolute altitude copy survey, due to extension upper end to cage top away from
From what is be to determine, it is possible to judge the actual elevation of steel reinforcement cage.So so that the whole down process and underthrust of steel reinforcement cage
Depth can be monitored, so as to ensure steel reinforcement cage being properly inserted in designed elevation, it is to avoid steel reinforcement cage was inserted
It is deep or excessively shallow, be conducive to improving the construction quality of engineering.
During implementation, the intersection of the tie hoop 2 and main ribs 1 is also banded with steel wire.
Its tie hoop is with cage bar mainly using being welded to connect in manufacturing process for traditional steel reinforcement cage, and vibrating arm is being penetrated
The problems such as stirrup sealing-off being easily caused in steel reinforcement cage.Using said structure, in tie hoop and the intersection of main ribs
Steel wire is also banded with, the cage bar off normal caused by stirrup sealing-off can be avoided, is conducive to improving the construction quality of engineering.
During implementation, the extension 3 is the reinforcing bar being welded in main ribs.
Because cage bar is generally using batch production, length is than more consistent, by the way of the independent welded reinforcement in cage bar,
It can improve the design of steel reinforcement cage again in the case where not influenceing the manufacture craft of original steel reinforcement cage, make it easy to absolute altitude
Copy survey.Meanwhile, the discarded reinforcement ratio of job site is more, can be made full use of, and can improve the utilization rate of material, saves
Cost.
During implementation, the pitch of the tie hoop 2 and the diameter ratio generally 1 of steel reinforcement cage:3.
Using above-mentioned setting, the intensity of steel reinforcement cage can either be ensured, the length of tie hoop can be shortened again, be conducive to section
Material saving and cost.
Second pouring concrete, vibration compacting:As vibrating arm proposes outside hole that 1m or so drops occur in concrete in hole, on the one hand
Be concrete itself it is closely knit caused by, be on the other hand caused by concrete is excessive caused by the vibrating arm underthrust;The drop part should treat that vibrating arm is carried
Pour concrete is supplemented after going out in time and vibrating head is used(Φ50)Vibration compacting.
Pile quality is detected:After pile 28d, engineering pile is carried out in proportion by drawing and Test Technology of Pile Foundation code requirement
Pile quality(Integrality)And vertical bearing capacity is examined, next step construction can be carried out after detection is qualified.
Above-mentioned construction method, by taking fluting piling method, saves the material usages such as concrete, reinforcing bar, meanwhile, because the duration carries
Before, reduce the input of administration fee, labour cost, machine and equipment leasing expense etc.;Compared with other pile-type, the construction period significantly subtracts
It is few, save labour cost, fee of material(Reinforcing bar, the saving of concrete materials are produced), machine and equipment leasing take and administration fee etc., with good
Good economic benefit.
My company undertakes the construction of Hebei province's residential area project, the Wan ㎡ of overall floorage 19.34, by ground, underground two parts
Composition, altogether including 33 monomers of size, wherein there is 11 17F small high-rises pile foundations to use long auger guncreting pile, stake footpath
600mm, the long 21.7m of stake, pile body concrete strength C30, concrete piles protective layer thickness 50mm, vertical ultimate bearing capacity of single pile standard value will
Ask and reach 2800KN, vertical bearing capacity of single pile characteristic value 1400KN.
This engineering is by effectively controlling rational technology utilization and emphasis link, and construction quality produces a desired effect, together
When, the construction period is saved, materials'use is reduced, reduces machinery cost, labour cost, administration fee input, achieve preferably
Economic benefit.
The foregoing is merely illustrative of the preferred embodiments of the present invention, is not limitation, all essences in the present invention with the present invention
Any modifications, equivalent substitutions and improvements made within refreshing and principle etc., should be included in the scope of the protection.
Claims (7)
1. a kind of long auger guncreting pile construction method, comprises the following steps, S1, measurement and positioning are provided according to Mapping departments
Control point carry out stake position throw survey, determine the position of guncreting pile hole to be drilled;S2, well cementing, utilize stake machine drill to predetermined stake holes
Guncreting after depth;Steel reinforcement cage, is inserted perpendicularly into stake to designed elevation, above carried by S3, underthrust steel reinforcement cage using vibrating arm
Vibrating arm;S4, second pouring concrete and vibration compacting;Characterized in that, in the step S3, first making steel of the bottom in cone
There is the extension set along the direction away from bottom on muscle cage, the steel reinforcement cage at least one cage bar, make the reinforcing bar
When cage is inserted into designed elevation, the extension is higher by the top of stake holes;In steel reinforcement cage down process, the extension to the steel reinforcement cage
The upper end in portion carries out absolute altitude and copies survey, according to the distance of the upper end of extension to cage top, judges the actual elevation of steel reinforcement cage.
2. long auger guncreting pile construction method as claimed in claim 1, it is characterised in that steel reinforcement cage is in down process
In, once steel reinforcement cage actual elevation higher than designed elevation and when being less than 100mm with the difference of designed elevation, above improve lever.
3. long auger guncreting pile construction method as claimed in claim 1, it is characterised in that steel reinforcement cage is operated in underthrust
When, first vibrating arm is penetrated in steel reinforcement cage, then sling steel reinforcement cage vertically using crane, steel reinforcement cage is made by vibrating arm deadweight
Keep vertical state, alignment aperture to be transferred after being corrected, during decentralization, first by vibration hammer, vibrating arm and steel reinforcement cage from
Realize again, when the subsidence velocity of steel reinforcement cage is close to zero, Vibration on Start-up hammer drives steel reinforcement cage vibration to transfer by vibrating arm,
It must not be hammered into shape in construction after steel reinforcement cage free-falling termination in Vibration on Start-up, so only can increase friction in down stroke.
4. long auger guncreting pile construction method as claimed in claim 1, it is characterised in that the steel reinforcement cage includes cage bar
(1)And tie hoop(2), the tie hoop(2)It is weldingly fixed on main ribs(1)Outside, the tie hoop(2)With
Main ribs(1)Intersection be also banded with steel wire.
5. long auger guncreting pile construction method as claimed in claim 1, it is characterised in that before measurement and positioning, is first carried out
Foundation trench is excavated, and the foundation trench bottom land absolute altitude is the superfilled absolute altitude of guncreting pile, and excavation planar dimension should ensure that reserved in foundation trench surrounding
There is the working face that 2~3m is wide, carry out clear bottom during excavation simultaneously, and survey, control flume are copied to the progress of bottom land absolute altitude during clear bottom
The bottom discrepancy in elevation is in -50mm~50mm.
6. long auger guncreting pile construction method as claimed in claim 1, it is characterised in that in the step S2, specifically
During drilling, it should ensure that overhead traveling crane center, gyrator center and stake position are centrally located on same vertical line, and pass through the water on drilling rod shaft
Leveling ruler is observed control to the perpendicularity of drilling rod, meanwhile, theodolite is also provided with the direction of visual lines perpendicular to driver
Perpendicularity to drilling rod is observed control.
7. long auger guncreting pile construction method as claimed in claim 1, it is characterised in that in the step S2, work as brill
After the completion of hole reaches projected depth and sweeps bottom, start concrete pump and concrete is conveyed into drilling tool, allot drilling tool in pumping, together
When make the pressure held stationary of concrete pump.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710253075.4A CN107100164A (en) | 2017-04-18 | 2017-04-18 | A kind of long auger guncreting pile construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710253075.4A CN107100164A (en) | 2017-04-18 | 2017-04-18 | A kind of long auger guncreting pile construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN107100164A true CN107100164A (en) | 2017-08-29 |
Family
ID=59658154
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710253075.4A Pending CN107100164A (en) | 2017-04-18 | 2017-04-18 | A kind of long auger guncreting pile construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN107100164A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111321730A (en) * | 2020-03-03 | 2020-06-23 | 云南建投第一勘察设计有限公司 | Foundation reinforcing method in superfluid cement soil pit |
CN113089651A (en) * | 2021-05-06 | 2021-07-09 | 北京城建勘测设计研究院有限责任公司 | Long spiral drilling pressure irrigation energy pile structure and construction method thereof |
CN114438997A (en) * | 2022-01-30 | 2022-05-06 | 广东巨源工程技术有限公司 | Hard stratum dry drilling soil-squeezing pore-forming post-grouting bored concrete pile construction method |
CN115059070A (en) * | 2022-05-31 | 2022-09-16 | 北京建材地质工程有限公司 | Construction method of collapse-free stratum foundation pit supporting pile based on solid waste utilization |
CN115387328A (en) * | 2022-07-26 | 2022-11-25 | 河南黄河河务局工程建设中心 | Construction method of beach area cast-in-place pile based on overlong spiral drilling machine |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101967825A (en) * | 2010-09-15 | 2011-02-09 | 中铁四局集团第五工程有限公司 | Reinforcement cage and manufacturing method thereof |
CN203594024U (en) * | 2013-12-03 | 2014-05-14 | 兖矿东华建设有限公司 | Cast-in-situ bored pile reinforcement cage elevation control rod |
JP2014088687A (en) * | 2012-10-29 | 2014-05-15 | Yokoyama Kiso Koji:Kk | Method for creating pile body |
-
2017
- 2017-04-18 CN CN201710253075.4A patent/CN107100164A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101967825A (en) * | 2010-09-15 | 2011-02-09 | 中铁四局集团第五工程有限公司 | Reinforcement cage and manufacturing method thereof |
JP2014088687A (en) * | 2012-10-29 | 2014-05-15 | Yokoyama Kiso Koji:Kk | Method for creating pile body |
CN203594024U (en) * | 2013-12-03 | 2014-05-14 | 兖矿东华建设有限公司 | Cast-in-situ bored pile reinforcement cage elevation control rod |
Non-Patent Citations (3)
Title |
---|
《施工技术》杂志社等: "《地基与基础工程施工新技术典型案例与分析》", 31 May 2011, 北京:机械工业出版社 * |
建设部工程质量安全监督与行业发展司等: "《土木建筑国家级工法汇编 2003-2004年度》", 31 January 2007, 北京:中国计划出版社 * |
王力宇: "《菜鸟入职与快速提升系列 建筑工程测量快速上手与提升》", 31 October 2016, 北京:中国电力出版社 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111321730A (en) * | 2020-03-03 | 2020-06-23 | 云南建投第一勘察设计有限公司 | Foundation reinforcing method in superfluid cement soil pit |
CN113089651A (en) * | 2021-05-06 | 2021-07-09 | 北京城建勘测设计研究院有限责任公司 | Long spiral drilling pressure irrigation energy pile structure and construction method thereof |
CN114438997A (en) * | 2022-01-30 | 2022-05-06 | 广东巨源工程技术有限公司 | Hard stratum dry drilling soil-squeezing pore-forming post-grouting bored concrete pile construction method |
CN115059070A (en) * | 2022-05-31 | 2022-09-16 | 北京建材地质工程有限公司 | Construction method of collapse-free stratum foundation pit supporting pile based on solid waste utilization |
CN115387328A (en) * | 2022-07-26 | 2022-11-25 | 河南黄河河务局工程建设中心 | Construction method of beach area cast-in-place pile based on overlong spiral drilling machine |
CN115387328B (en) * | 2022-07-26 | 2024-02-13 | 河南黄河河务局工程建设中心 | Beach cast-in-place pile construction method based on ultra-long spiral drilling machine |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107246006B (en) | The pile-filling method of concrete-pile | |
CN102277867B (en) | A construction method of collapsible loess foundation | |
CN107542108B (en) | A kind of reverse construction method of building basement structure | |
CN105887813A (en) | Large-diameter super-long pile construction method in karst area through full-casing pipe full rotating and rotary drilling | |
CN108517877B (en) | Supporting construction method combining consolidation grouting of hybrid filling ultra-deep foundation pit with double-row steel pipe piles | |
CN204491626U (en) | The foundation pit enclosure structure that Larsen steel sheet pile and prestressed anchor combine | |
CN107524142A (en) | A kind of holing with slurry wall protection cast-in-place pile construction method | |
CN107100164A (en) | A kind of long auger guncreting pile construction method | |
CN109372517A (en) | A construction method suitable for the tunnel under the upper-soft lower-hard composite stratum to penetrate the water supply pipe | |
CN101215834A (en) | Construction Method of Outrigger Type Diaphragm Wall | |
AU2021106928A4 (en) | Construction method for excavation of deep pit with triaxial mixing pile waterstop curtains and rotary bored cast-in-place pile supports | |
CN109555116A (en) | A kind of high density karst intense development area fully-sleeved filled pile construction method | |
CN108842819A (en) | A kind of urban track traffic cable run method for tunnel construction | |
CN102635113A (en) | Construction method for hydraulic vibrating sinking pipe cast-in-place piles | |
CN108842791A (en) | A kind of relief piled anchor multistage support structure and construction method | |
CN106988302A (en) | A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method | |
CN106088127A (en) | Open caisson construction method | |
CN206721870U (en) | A kind of long auger guncreting pile steel reinforcement cage | |
CN100532733C (en) | Diving casting cast-in-place pile construction method for constructing in scree layer and sand layer | |
CN113174958A (en) | Construction method for foundation pit of adjacent road under poor ground condition | |
CN104196014A (en) | Combined rock-embedded anchor cable slide-resistant pile where round steel is implanted and construction method thereof | |
CN103898914A (en) | Method for using prefabricated square pile as concrete supporting upright post | |
CN107503344A (en) | The construction method of turnover type merogenesis steel pile casting retaining wall manually digging hole filling pile | |
CN110042843A (en) | A kind of large deep foundation pit construction method of complex condition | |
CN109610473A (en) | A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20170829 |
|
RJ01 | Rejection of invention patent application after publication |