CN206308569U - It is a kind of to reinforce the road structure for punishing the solution cavity that underlies - Google Patents

It is a kind of to reinforce the road structure for punishing the solution cavity that underlies Download PDF

Info

Publication number
CN206308569U
CN206308569U CN201621377401.XU CN201621377401U CN206308569U CN 206308569 U CN206308569 U CN 206308569U CN 201621377401 U CN201621377401 U CN 201621377401U CN 206308569 U CN206308569 U CN 206308569U
Authority
CN
China
Prior art keywords
curtain
grouting
solution cavity
pile
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201621377401.XU
Other languages
Chinese (zh)
Inventor
何忠明
杨煜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changsha University of Science and Technology
Original Assignee
Changsha University of Science and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changsha University of Science and Technology filed Critical Changsha University of Science and Technology
Priority to CN201621377401.XU priority Critical patent/CN206308569U/en
Application granted granted Critical
Publication of CN206308569U publication Critical patent/CN206308569U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)

Abstract

本实用新型公开了一种加固处治下伏溶洞的路基结构,它主要包括路基(1)、加筋横梁(2)、帷幕注浆孔(3)、冲孔灌注桩(4)、溶洞(6)、帷幕加固区(7)、钢护筒(8);本实用新型首先采用袖阀管注浆法通过帷幕注浆孔(3)对溶洞(6)周围边界进行注浆加固处理,形成帷幕加固区(7)以此截断水流,起到防渗堵漏的目的;然后利用不同尺寸的冲孔灌注桩(4)对溶洞(6)进行浇筑加固,溶洞 (6) 区域内采用钢护筒(8)浇筑;最后冲孔灌注桩(4)和注浆后的帷幕注浆孔(3)的顶部通过加筋横梁(2)相连,形成以刚形桩与桩顶以上的加筋梁共同组成桩‑网复合地基;本实用新型可以有效处治路基下伏埋深大于10m的大型溶洞,并且可以对路基起到加固防护作用;该结构不仅施工便利,而且适用范围广。

The utility model discloses a subgrade structure for strengthening and treating an underlying karst cave, which mainly includes a subgrade (1), a reinforced beam (2), a curtain grouting hole (3), a punching grouting pile (4), and a karst cave (6 ), the curtain reinforcement area (7), and the steel casing (8); the utility model first adopts the sleeve valve pipe grouting method to perform grouting reinforcement on the surrounding boundary of the karst cave (6) through the curtain grouting hole (3) to form a curtain The reinforcement area (7) cuts off the water flow to prevent seepage and plugging; then use different sizes of punching piles (4) to reinforce the karst cave (6), and steel casings are used in the karst cave (6) area (8) pouring; the top of the final punching cast-in-place pile (4) and the curtain grouting hole (3) after the grouting are connected by a reinforced crossbeam (2), forming a joint between the rigid pile and the reinforced beam above the pile top. A pile-net composite foundation is formed; the utility model can effectively treat large-scale karst caves with a buried depth greater than 10m under the roadbed, and can reinforce and protect the roadbed; the structure is not only convenient for construction, but also has a wide range of applications.

Description

一种加固处治下伏溶洞的路基结构A subgrade structure for strengthening and treating underlying karst caves

技术领域technical field

本实用新型涉及土木工程中的道路工程技术领域,具体关于一种加固处治下伏溶洞的路基结构。The utility model relates to the technical field of road engineering in civil engineering, in particular to a subgrade structure for strengthening and treating underlying karst caves.

背景技术Background technique

我国地质条件复杂,岩溶分布极为广泛。随着公路建设的发展,高速公路路线不可避免的会穿越岩溶发育区域。岩溶路段大量存在的溶洞及土洞,给公路路基的建设和运营会带来潜在危害,溶洞在我国公路建设过程中已经成为普遍的不良的地质灾害,其可溶性岩石在水的作用下溶蚀作用下产生严重的塌陷,以此,解决采溶洞对公路建设产生的威胁迫在眉睫。my country's geological conditions are complex, and karst is widely distributed. With the development of highway construction, it is inevitable that the highway route will pass through the karst development area. There are a large number of karst caves and soil caves in karst road sections, which will bring potential hazards to the construction and operation of road subgrades. Karst caves have become common adverse geological disasters in the process of highway construction in my country. The soluble rocks are dissolved under the action of water. Serious subsidence occurs, so it is imminent to solve the threat of mining karst caves to road construction.

目前,解除溶洞对公路建设产生的威胁方式很多,其主要分为注浆填充和桩基础两大类;注浆填充对路基稳定性起到良好的作用,能够保持整个路基的稳定性,但其不适应于大的和深的溶洞,且注浆填充费用昂贵,施工复杂;桩基础加固能够为路基提供足够的承载力,其桩基础的位置和间距对路基稳定性起到关键作用,但是对于如何确定桩基础的位置和间距至今没有得到统一的认证,同时已有的桩基础往往不能支撑在水侵蚀作用下不断扩大的溶洞,不能保证路基长期的稳定性。At present, there are many ways to relieve the threat of karst caves to highway construction, which are mainly divided into two categories: grouting filling and pile foundation; grouting filling has a good effect on the stability of the roadbed and can maintain the stability of the entire roadbed, but its It is not suitable for large and deep karst caves, and the cost of grouting filling is expensive and the construction is complicated; pile foundation reinforcement can provide sufficient bearing capacity for the roadbed, and the position and spacing of the pile foundation play a key role in the stability of the roadbed, but for How to determine the position and spacing of pile foundations has not been uniformly certified. At the same time, the existing pile foundations are often unable to support the ever-expanding karst caves under the action of water erosion, and cannot guarantee the long-term stability of the subgrade.

发明内容Contents of the invention

针对以上问题,本实用新型公开了一种加固处治下伏溶洞的路基结构,采用以下技术方案:首先采用帷幕注浆法对溶洞临近边界进行加固处理,以防止溶洞的不断扩大,其次采用冲孔灌注桩对溶洞区进行加固,并在溶洞区域内浇筑冲孔灌注桩时,其部分段采用钢护筒进行浇筑,可节约大量的浆液,同时为顶层路基提供足够的支撑力,最后通过加筋横梁将冲孔灌注桩和浇筑后的帷幕注浆孔相互连接,形成稳定的桩-网复合地基,保证其路基的整体稳定性,该路基结构可以有效处治路基下伏埋深大于10m的大型溶洞。Aiming at the above problems, the utility model discloses a subgrade structure for strengthening and treating the underlying karst caves. The following technical scheme is adopted: firstly, the curtain grouting method is used to reinforce the adjacent boundary of the karst caves to prevent the continuous expansion of the karst caves; Cast-in-place piles are used to reinforce the karst cave area, and when pouring punched-in-place piles in the karst cave area, parts of the piles are poured with steel casings, which can save a lot of grout and provide sufficient support for the top roadbed, and finally through reinforcement The crossbeam connects the punched cast-in-place piles and the poured curtain grouting holes to form a stable pile-net composite foundation to ensure the overall stability of the subgrade. This subgrade structure can effectively treat large-scale karst caves with a buried depth greater than 10m under the subgrade .

所述的一种加固处治下伏溶洞的路基结构,其特征是,所述的帷幕注浆孔(3)成圆形布置,且包围整个溶洞,相邻帷幕注浆孔(3)之间的距离d为1.5m,帷幕注浆孔(3)距溶洞(6)四周边缘距离D不小于1.5m。The roadbed structure for strengthening and treating the underlying karst cave is characterized in that the curtain grouting holes (3) are arranged in a circle and surround the entire karst cave, and the gap between adjacent curtain grouting holes (3) The distance d is 1.5m, and the distance D between the curtain grouting hole (3) and the surrounding edges of the cave (6) is not less than 1.5m.

所述的一种加固处治下伏溶洞的路基结构,其特征是,对溶洞 (6) 区域浇筑冲孔灌注桩(4)时采用钢护筒(8)浇筑,且钢护筒(8)距离溶洞(6)上下底部不小于0.5m,灌注浆液采用强度不小于32.5MPa级,水灰比采用1:1.3~1:1.5,帷幕注浆孔采用水泥—水玻璃双浆液,其中水玻璃模数为2.4~3.4,浓度为50波美度以上。The subgrade structure for strengthening and treating the underlying karst cave is characterized in that, when pouring the perforated piles (4) in the karst cave (6) area, steel casings (8) are used for pouring, and the distance between the steel casings (8) The upper and lower bottom of the karst cave (6) shall not be less than 0.5m, the grout shall be grouted with a strength not less than 32.5MPa, the water-cement ratio shall be 1:1.3~1:1.5, and the cement-water glass double grout shall be used for the curtain grouting hole, where the water glass modulus It is 2.4~3.4, and the concentration is above 50 degrees Baume.

所述的一种加固处治下伏溶洞的路基结构,其特征是,帷幕注浆孔(3)和冲孔灌注桩(4)的低端均低于溶洞底部标高0.5m以上。The subgrade structure for strengthening and treating the underlying karst cave is characterized in that the lower ends of the curtain grouting holes (3) and the punching piles (4) are all lower than the bottom elevation of the karst cave by more than 0.5m.

本实用新型的有益效果:通过帷幕注浆法对溶洞临近边界进行加固处理,以此截断水流,起到防渗堵漏的目的,同时能够防止溶洞不再扩大;采用冲孔灌注桩能够为路基提供足够的承载力,在溶洞区采用钢护筒浇筑,可节约大量的浆液;通过加筋横梁将冲孔灌注桩和浇筑完成后的帷幕注浆孔相互连接以形成稳定的桩-网复合地基,保证其地基及路基工作区整体的稳定性,该结构不仅施工简单、经济适用、而且施工便利、适用范围广。The beneficial effects of the utility model: the curtain grouting method is used to reinforce the adjacent boundary of the karst cave, so as to cut off the water flow, achieve the purpose of preventing seepage and plugging, and at the same time prevent the karst cave from expanding; To provide sufficient bearing capacity, steel casings are used for pouring in the karst cave area, which can save a lot of grout; the punched cast-in-place piles and the poured curtain grouting holes are connected to each other through reinforced beams to form a stable pile-net composite foundation , to ensure the overall stability of its foundation and subgrade work area, the structure is not only simple in construction, economical and applicable, but also convenient in construction and wide in scope of application.

附图说明Description of drawings

图1为本实用新型的路基结构示意图。Fig. 1 is the roadbed structure schematic diagram of the present utility model.

图2为本实用新型铺设结构的俯视图。Fig. 2 is a top view of the laying structure of the present invention.

图中,1—路基、2—加筋横梁、3—帷幕注浆孔、4—冲孔灌注桩、5—大尺寸的冲孔灌注桩、6—溶洞、7—帷幕加固区、8—钢护筒。In the figure, 1—subgrade, 2—reinforced beam, 3—curtain grouting hole, 4—punched cast-in-place pile, 5—large-sized punched cast-in-place pile, 6—karst cave, 7—curtain reinforcement area, 8—steel Casing.

具体实施方式detailed description

下面结合附图对本实用新型结构组合方式和实施步骤做进一步的说明。Below in conjunction with the accompanying drawings, the structural combination and implementation steps of the present utility model will be further described.

如图1、图2所示,分别为实用新型路基结构的正视图和俯视图,它主要包括路基(1)、加筋横梁(2)、帷幕注浆孔(3)、冲孔灌注桩(4)、大尺寸冲孔灌注桩(5)、溶洞(6)、钢护筒(8);其中所述的路基(1)下方由加筋横梁(2) 相互交错连接,加筋横梁(2)均与冲孔灌注桩(4)、浇筑后的帷幕注浆孔(3)相互连接,在溶洞(6)周围边界采用袖阀管进行帷幕注浆。As shown in Figure 1 and Figure 2, they are the front view and top view of the utility model roadbed structure respectively, which mainly include roadbed (1), reinforced beam (2), curtain grouting hole (3), punching cast-in-place pile (4) ), large-size perforated piles (5), karst caves (6), and steel casings (8); the underside of the subgrade (1) is interlacedly connected by reinforced beams (2), and the reinforced beams (2) They are all connected to each other with punching cast-in-place piles (4) and cast-in-place curtain grouting holes (3), and sleeve valve pipes are used for curtain grouting around the boundary of the karst cave (6).

1、首先采用地质雷达法、高密度电法、工程地质钻探等多种勘测方法确定则溶洞的尺寸、范围,从而判定采用何种方法解决溶洞对路基的危害问题。1. Firstly, various survey methods such as geological radar method, high-density electrical method, and engineering geological drilling are used to determine the size and scope of the karst cave, so as to determine which method to use to solve the problem of the hazard of the karst cave to the subgrade.

2、根据溶洞的尺寸和范围,若是路基下伏埋深大于10m大型溶洞,可采取该路基结构,在路面进行设计规划冲孔灌注桩和帷幕注浆孔(3)的位置,利用钻孔机在溶洞区域制作减压孔。2. According to the size and scope of the karst cave, if it is a large karst cave with a buried depth greater than 10m under the roadbed, the roadbed structure can be used to design and plan the positions of the punching piles and curtain grouting holes (3) on the road surface, and use a drilling machine Create relief holes in the cave area.

3、施工场地先预先整平,并沿钻孔位置开挖沟槽和集水坑,注浆施工时,采用自动流量和压力记录仪,在溶洞临界边缘位置布设间距为d为1.5m的帷幕注浆孔(3),施工两排注浆孔,初拟分两次注浆,第一次注浆压力控制在0.3MPa,第二次注浆压力控制在0.8~1MPa,形成注浆帷幕。3. The construction site shall be leveled in advance, and trenches and sumps shall be excavated along the drilling position. During grouting construction, an automatic flow and pressure recorder shall be used, and curtains with a distance of d of 1.5m shall be arranged at the critical edge of the cave. Grouting hole (3), construct two rows of grouting holes, and initially plan to inject grouting twice, the first grouting pressure is controlled at 0.3MPa, and the second grouting pressure is controlled at 0.8~1MPa to form a grouting curtain.

4、在溶洞区注浆由四周向内侧采用间隔跳孔施工,在洞溶区浇筑时部分段采用钢护筒浇筑,其浇筑深度低于溶洞底部标高至少0.5m以上,且按梅花型布设。4. The grouting in the karst cave area shall be constructed by jumping holes at intervals from all sides to the inside. When pouring in the karst cave area, steel casings shall be used for pouring in sections. The pouring depth shall be at least 0.5m lower than the elevation of the bottom of the karst cave, and it shall be arranged in a plum blossom pattern.

5、注浆完成后通过加筋横梁(2)将冲孔灌注桩(4)和完成注浆的帷幕注浆孔(3)相互绑扎浇筑,其加筋横梁(2)采用预应力浇筑而成。本说明未详细描述的内容均属于本专业领域技术人员公知的现有技术。5. After the grouting is completed, the punched cast-in-situ pile (4) and the grouted curtain grouting hole (3) are bound and poured through the reinforced beam (2), and the reinforced beam (2) is made of prestressed pouring . The content not described in detail in this specification belongs to the prior art known to those skilled in the art.

Claims (4)

1. the road structure of the solution cavity that underlies is punished in a kind of reinforcing, including:Roadbed (1), reinforcement crossbeam (2), curtain-grouting hole (3), Punching Borehole Cast-in-place Concrete Pile (4), solution cavity (6), steel pile casting (8);It is characterized in that, described roadbed (1) is noted by the curtain after slip casting Slurry hole (3) and Punching Borehole Cast-in-place Concrete Pile (4) are connected with each other by reinforcement crossbeam (2), and described curtain-grouting hole (3) top and punching are filled Note stake (4) top keeps concordant, and its lower curtate is below solution cavity elevation of bottom, and described curtain-grouting hole (3) is positioned at solution cavity (6) Close on borderline region.
2. the road structure of the solution cavity that underlies is punished in a kind of reinforcing according to claim 1, it is characterized in that, described curtain note Slurry hole (3) circular arrangement, and it is 1.5m, curtain-grouting to surround the distance between whole solution cavity, adjacent curtain-grouting hole (3) d Hole (3) is not less than 1.5m away from solution cavity (6) edge apart from D.
3. the road structure of the solution cavity that underlies is punished in a kind of reinforcing according to claim 1, it is characterized in that, described curtain note Slurry hole (3) circular arrangement, and it is 1.5m, curtain-grouting to surround the distance between whole solution cavity, adjacent curtain-grouting hole (3) d Hole (3) is not less than 1.5m away from solution cavity (6) edge apart from D.
4. the road structure of the solution cavity that underlies is punished in a kind of reinforcing according to claim 1, it is characterized in that, curtain-grouting hole And the low side of Punching Borehole Cast-in-place Concrete Pile (4) is below more than solution cavity elevation of bottom 0.5m (3).
CN201621377401.XU 2016-12-15 2016-12-15 It is a kind of to reinforce the road structure for punishing the solution cavity that underlies Expired - Fee Related CN206308569U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201621377401.XU CN206308569U (en) 2016-12-15 2016-12-15 It is a kind of to reinforce the road structure for punishing the solution cavity that underlies

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201621377401.XU CN206308569U (en) 2016-12-15 2016-12-15 It is a kind of to reinforce the road structure for punishing the solution cavity that underlies

Publications (1)

Publication Number Publication Date
CN206308569U true CN206308569U (en) 2017-07-07

Family

ID=59253280

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201621377401.XU Expired - Fee Related CN206308569U (en) 2016-12-15 2016-12-15 It is a kind of to reinforce the road structure for punishing the solution cavity that underlies

Country Status (1)

Country Link
CN (1) CN206308569U (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107938649A (en) * 2017-11-29 2018-04-20 上海建工五建集团有限公司 A kind of solution cavity foundation reinforcement method
CN108729461A (en) * 2018-07-04 2018-11-02 中国水利水电第七工程局成都水电建设工程有限公司 For the constructing structure and construction method on aerial leakage stratum in deep hole impervious wall construction
CN109763391A (en) * 2019-03-11 2019-05-17 杭州昂创科技有限公司 Base and roadbed construction method are reinforced in disease road single hole combined casting
CN113073984A (en) * 2021-04-16 2021-07-06 中铁隧道勘察设计研究院有限公司 Construction method for grouting pre-reinforcement and pile-forming integration of tunnel penetrating through small karst cave groups
CN114875962A (en) * 2022-04-11 2022-08-09 中建路桥集团有限公司 Reinforced concrete slab structure spanning large karst cave and construction method
CN114892632A (en) * 2022-05-18 2022-08-12 中建路桥集团有限公司 A device and construction method for crossing a large-scale shallow karst cave in road construction
CN115162319A (en) * 2022-07-25 2022-10-11 福建冶地恒元建设有限公司 Water plugging treatment device and method for seepage holes in underground karst cave wall in cast-in-place pile construction
CN116220416A (en) * 2023-02-09 2023-06-06 中铁二十局集团南方工程有限公司 Ancient city gate protection support device

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107938649A (en) * 2017-11-29 2018-04-20 上海建工五建集团有限公司 A kind of solution cavity foundation reinforcement method
CN108729461A (en) * 2018-07-04 2018-11-02 中国水利水电第七工程局成都水电建设工程有限公司 For the constructing structure and construction method on aerial leakage stratum in deep hole impervious wall construction
CN109763391A (en) * 2019-03-11 2019-05-17 杭州昂创科技有限公司 Base and roadbed construction method are reinforced in disease road single hole combined casting
CN109763391B (en) * 2019-03-11 2021-01-15 浩祥(福建)建设有限公司 Construction method for reinforcing base course and roadbed by single-hole composite grouting of damaged road
CN113073984A (en) * 2021-04-16 2021-07-06 中铁隧道勘察设计研究院有限公司 Construction method for grouting pre-reinforcement and pile-forming integration of tunnel penetrating through small karst cave groups
CN114875962A (en) * 2022-04-11 2022-08-09 中建路桥集团有限公司 Reinforced concrete slab structure spanning large karst cave and construction method
CN114892632A (en) * 2022-05-18 2022-08-12 中建路桥集团有限公司 A device and construction method for crossing a large-scale shallow karst cave in road construction
CN115162319A (en) * 2022-07-25 2022-10-11 福建冶地恒元建设有限公司 Water plugging treatment device and method for seepage holes in underground karst cave wall in cast-in-place pile construction
CN115162319B (en) * 2022-07-25 2024-01-30 福建冶地恒元建设有限公司 Device and method for treating water seepage Kong Dushui of underground karst cave wall in construction of cast-in-place pile
CN116220416A (en) * 2023-02-09 2023-06-06 中铁二十局集团南方工程有限公司 Ancient city gate protection support device

Similar Documents

Publication Publication Date Title
CN206308569U (en) It is a kind of to reinforce the road structure for punishing the solution cavity that underlies
CN106499413B (en) A kind of Shallow-buried section tunnel stratum consolidation construction method
CN108442382B (en) In-situ protection and enclosure soil-retaining structure for pressure pipeline crossing deep foundation pit and construction method
CN103321244B (en) Sand foundation existing building sets up the construction method of basement
CN103696784B (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN113565525A (en) Construction protection system and construction method for newly-built shield tunnel super-close ultra-shallow buried upper-span existing tunnel
CN106930321B (en) A construction method for building underground structures with large diameter pipe jacking combined with hole piles
CN103122636A (en) Superficial layer groove wall reinforcing method of feeble stratum underground continuous wall
CN204401385U (en) A kind of road structure processing Deep Thick Soft Ground karst foundation
CN110374134A (en) A kind of combined member increased suitable for retaining wall and construction method
CN209040150U (en) A kind of rigid frame formula peg board retaining wall
CN105672450A (en) Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure
CN110344394A (en) A kind of surrounding deep foundation pit shallow embedding structure base ruggedized construction and construction method
CN110055973B (en) Foundation pit enclosure structure under high-speed railway bridge with limited construction space and water stopping method
CN109594575A (en) A kind of open caisson periphery grouting and reinforcing soil body construction method
CN110735436A (en) cutting rock slope reinforced structure
CN102235007B (en) Method for supporting deep foundation with upper nail-lower pile combination
CN212642730U (en) Collapsible loess area tunnel passes people's air defense structure
CN211500658U (en) Shallow tunnel supporting construction that nearly connects that buries suitable for sand ground
CN108330963A (en) A kind of constructing device for inside soil body existing pile foundation pile extension
CN111350106A (en) A kind of railway track temporary support structure and construction method thereof
CN110485230A (en) A kind for the treatment of structures and construction method of high water level weak soil Bridgehead by Blastig
CN106087996B (en) Manual digging pile construction method based on self leveling backpressure device
CN110939139B (en) Pile-sheet wall structure and construction method based on rigid contact of special-shaped retaining wall behind piles
CN217974480U (en) Reinforced concrete plate type structure spanning large karst cave

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20170707

Termination date: 20171215

CF01 Termination of patent right due to non-payment of annual fee