CN108729461A - For the constructing structure and construction method on aerial leakage stratum in deep hole impervious wall construction - Google Patents
For the constructing structure and construction method on aerial leakage stratum in deep hole impervious wall construction Download PDFInfo
- Publication number
- CN108729461A CN108729461A CN201810726870.5A CN201810726870A CN108729461A CN 108729461 A CN108729461 A CN 108729461A CN 201810726870 A CN201810726870 A CN 201810726870A CN 108729461 A CN108729461 A CN 108729461A
- Authority
- CN
- China
- Prior art keywords
- steel pipe
- construction
- wall
- deep hole
- guide groove
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 58
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 85
- 239000010959 steel Substances 0.000 claims abstract description 85
- 238000005553 drilling Methods 0.000 claims abstract description 28
- 239000004570 mortar (masonry) Substances 0.000 claims abstract description 10
- 239000002002 slurry Substances 0.000 claims abstract description 8
- 230000003014 reinforcing effect Effects 0.000 claims description 2
- 238000007569 slipcasting Methods 0.000 claims 8
- 229920002472 Starch Polymers 0.000 claims 3
- 235000019698 starch Nutrition 0.000 claims 3
- 238000000151 deposition Methods 0.000 claims 1
- 238000002347 injection Methods 0.000 claims 1
- 239000007924 injection Substances 0.000 claims 1
- 235000013336 milk Nutrition 0.000 claims 1
- 239000008267 milk Substances 0.000 claims 1
- 210000004080 milk Anatomy 0.000 claims 1
- 230000010412 perfusion Effects 0.000 claims 1
- 230000002787 reinforcement Effects 0.000 claims 1
- 239000008107 starch Substances 0.000 claims 1
- 238000009955 starching Methods 0.000 claims 1
- 230000015572 biosynthetic process Effects 0.000 abstract description 6
- 238000005516 engineering process Methods 0.000 abstract description 6
- 238000005755 formation reaction Methods 0.000 abstract description 6
- 239000004567 concrete Substances 0.000 abstract description 3
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 abstract description 3
- 239000007787 solid Substances 0.000 abstract description 2
- 230000002265 prevention Effects 0.000 abstract 1
- 239000002689 soil Substances 0.000 abstract 1
- 238000000034 method Methods 0.000 description 18
- 239000011440 grout Substances 0.000 description 8
- 238000002360 preparation method Methods 0.000 description 3
- 239000004576 sand Substances 0.000 description 3
- QVGXLLKOCUKJST-UHFFFAOYSA-N atomic oxygen Chemical compound [O] QVGXLLKOCUKJST-UHFFFAOYSA-N 0.000 description 2
- 238000009412 basement excavation Methods 0.000 description 2
- 238000010586 diagram Methods 0.000 description 2
- 229910052760 oxygen Inorganic materials 0.000 description 2
- 239000001301 oxygen Substances 0.000 description 2
- 239000011435 rock Substances 0.000 description 2
- 239000003381 stabilizer Substances 0.000 description 2
- 239000002699 waste material Substances 0.000 description 2
- 238000003466 welding Methods 0.000 description 2
- 235000008733 Citrus aurantifolia Nutrition 0.000 description 1
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 1
- 235000011941 Tilia x europaea Nutrition 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000011083 cement mortar Substances 0.000 description 1
- 239000004927 clay Substances 0.000 description 1
- 238000005056 compaction Methods 0.000 description 1
- 230000009918 complex formation Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 239000012530 fluid Substances 0.000 description 1
- 238000007689 inspection Methods 0.000 description 1
- 239000004571 lime Substances 0.000 description 1
- 239000005416 organic matter Substances 0.000 description 1
- 239000002245 particle Substances 0.000 description 1
- 238000004537 pulping Methods 0.000 description 1
- 230000005855 radiation Effects 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D19/00—Keeping dry foundation sites or other areas in the ground
- E02D19/06—Restraining of underground water
- E02D19/12—Restraining of underground water by damming or interrupting the passage of underground water
- E02D19/18—Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Environmental & Geological Engineering (AREA)
- Hydrology & Water Resources (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Bulkheads Adapted To Foundation Construction (AREA)
Abstract
深孔防渗墙施工中针对架空漏失地层的施工结构及施工方法,属于水利水电工程中混凝土防渗墙工程施工技术。它包括防渗墙和防渗墙轴线两侧的导向槽,其关键技术是在导向槽中心轴线上布置钢管桩孔,钢管桩孔内下设注浆钢管,注浆钢管内灌注砂浆形成钢管桩。其施工方法包括地层判断、钻孔、下设注浆钢管和钢管桩灌浆。本发明针对不同的地层,钢管桩布置密度、深度不同,钢管起到锁住孤石及沙土的作用,对地层薄弱环节能充分地起到填充、固结作用,预防、减少甚至避免防渗墙施工中槽孔坍塌、漏浆、管涌等事故发生,以达到防渗墙施工槽孔固壁保护的目的,提高防渗墙成槽工效,为防渗墙施工质量及稳定性提供了可靠保障。
The invention relates to a construction structure and a construction method for overhead leakage strata in the construction of deep hole anti-seepage walls, and belongs to the construction technology of concrete anti-seepage walls in water conservancy and hydropower projects. It includes the anti-seepage wall and the guide grooves on both sides of the axis of the anti-seepage wall. The key technology is to arrange steel pipe pile holes on the central axis of the guide groove, and to install grouted steel pipes in the steel pipe pile holes, and pour mortar into the grouted steel pipes to form Steel pipe piles. The construction method includes stratum judgment, drilling, grouting steel pipes and steel pipe pile grouting. The present invention is aimed at different formations, the steel pipe piles are arranged in different densities and depths, and the steel pipes play the role of locking boulders and sandy soil, fully filling and consolidating weak links in the formation, preventing, reducing or even avoiding seepage prevention Accidents such as slot collapse, slurry leakage, and piping occurred during the wall construction, so as to achieve the purpose of solid wall protection for the cut-off wall construction, improve the work efficiency of the cut-off wall, and provide a reliable guarantee for the construction quality and stability of the cut-off wall .
Description
技术领域technical field
深孔防渗墙施工中针对架空漏失地层的施工结构及施工方法,属于水利水电工程中混凝土防渗墙工程施工技术。The invention relates to a construction structure and a construction method for overhead leakage strata in the construction of deep hole anti-seepage walls, and belongs to the construction technology of concrete anti-seepage walls in water conservancy and hydropower projects.
背景技术Background technique
在水利水电工程中,混凝土防渗墙作为一种常用的基础防渗处理方式,在水电站工程基坑防渗处理中得到了广泛应用,但是在防渗墙施工中常常会遇见围堰水下填筑无法碾压密实回填层、架空漏失地层等复杂地层。在这类地层防渗墙施工中极易出现漏浆、塌孔、管涌等事故,尤其是在进行深孔50m及以上孔深防渗墙施工时,此类地层危害尤为巨大。一旦发生事故不仅直接对施工人员设备及槽段的安全造成极大影响,而且事故处理无限期地延长了防渗墙的成槽周期,严重影响施工正常进度,增大成本投入。In water conservancy and hydropower projects, concrete cut-off walls, as a commonly used foundation anti-seepage treatment method, have been widely used in the anti-seepage treatment of foundation pits of hydropower station projects, but in the construction of cut-off walls, cofferdams are often encountered underwater fill Complex formations such as dense backfill layers and overhead leakage formations cannot be rolled and compacted by construction. Accidents such as slurry leakage, hole collapse, and piping are very likely to occur in the construction of cutoff walls in such strata, especially in the construction of cutoff walls with deep holes of 50m and above, the hazards of such strata are particularly great. Once an accident occurs, it will not only directly have a great impact on the safety of the construction personnel's equipment and the groove section, but also the accident handling will indefinitely prolong the groove formation cycle of the cutoff wall, seriously affecting the normal progress of the construction and increasing the cost investment.
防渗墙施工出现事故后一般采用“回填法”进行处理,常用的“回填法”处理实用性较强,但施工效率极低;一般情况下,防渗墙施工中塌槽事故往往出现在导墙下部,而传统的“回填法”针对槽孔出现塌槽、漏失地层区域的处理方式为回填粘土加块石料,利用冲击钻机反复冲击挤压使槽孔壁密实,往往一个漏失坍塌区域,不仅要将已成槽部分全部回填至导墙部位而且需要反复施工几次以保证挤压密实,这对深孔(50m级以上)防渗墙施工极其不利,且在造孔冲击过程中扰动较大,槽孔也极易再次塌孔、漏浆。The "backfilling method" is generally used to deal with accidents in the construction of cutoff walls. The commonly used "backfilling method" is more practical, but the construction efficiency is extremely low; The lower part of the wall, while the traditional "backfilling method" for the collapse of the slot and the loss of the formation area is to backfill the clay and add stones, and use the impact drill to repeatedly impact and squeeze the wall of the slot to make the wall dense. It is necessary to backfill all the part of the formed groove to the guide wall and repeat the construction several times to ensure compaction, which is extremely unfavorable to the construction of cut-off walls in deep holes (above 50m level), and the disturbance is relatively large during the impact process of hole making , The slot hole is also very easy to collapse again and leak slurry.
发明内容Contents of the invention
本发明要解决的问题就是针对深孔(50m级以上)围堰水下填筑无法碾压密实回填层、架空漏失地层等复杂地层,提供一种能安全、快速地进行防渗墙施工的结构及施工方法。其技术方案如下:The problem to be solved by the present invention is to provide a structure that can safely and quickly carry out cut-off wall construction for complex strata such as deep hole (above 50m level) cofferdam underwater filling that cannot be rolled and compacted, dense backfill layer, overhead leakage stratum, etc. and construction methods. Its technical scheme is as follows:
它包括防渗墙和防渗墙轴线两侧的导向槽,其关键技术是在导向槽中心轴线上布置钢管桩孔,钢管桩孔内下设注浆钢管,注浆钢管内灌注砂浆形成钢管桩。It includes the anti-seepage wall and the guide grooves on both sides of the axis of the anti-seepage wall. The key technology is to arrange steel pipe pile holes on the central axis of the guide groove, and to install grouted steel pipes in the steel pipe pile holes, and pour mortar into the grouted steel pipes to form Steel pipe piles.
所述钢管桩孔的间距为1.5m~2m。The distance between the steel pipe pile holes is 1.5m-2m.
在注浆钢管壁上每间隔30cm~35cm加工梅花状孔洞。Process quincunx-shaped holes at intervals of 30cm to 35cm on the wall of the grouted steel pipe.
所述注浆钢管增加长度时采用丝扣连接。When the length of the grouting steel pipe is increased, the threaded connection is adopted.
其施工方法包括以下步骤:Its construction method includes the following steps:
1)地层判断;1) stratum judgment;
2)钻孔准备:待防渗墙导向槽开挖完成后导向槽浇筑前,沿防渗墙导向槽中心轴线按照设计间距布置钢管桩孔,钻机准备及就位;2) Drilling preparation: After the excavation of the guide groove of the cut-off wall is completed, before the pouring of the guide groove, the steel pipe pile holes are arranged along the central axis of the guide groove of the cut-off wall according to the designed spacing, and the drilling rig is prepared and in place;
3)钻孔:钻机就位后,首先将带扩孔套偏心钻头中心与标记定位的钢管桩孔进行对正,确保钻孔垂直度,然后进行跟管钻进至设计孔深;3) Drilling: After the drilling rig is in place, first align the center of the eccentric drill bit with the reaming sleeve with the steel pipe pile hole marked and positioned to ensure the verticality of the drilling hole, and then drill with the pipe to the designed hole depth;
4)下设注浆钢管:钻孔验收合格后,向钢管桩孔内下设注浆钢管,注浆钢管上口超出导向槽1底部50~60cm的高度;4) Set up grouted steel pipes: after the boreholes pass the inspection and acceptance, install grouted steel pipes into the steel pipe pile holes, and the upper opening of the grouted steel pipes exceeds the height of the bottom of the guide groove 1 by 50-60 cm;
5)钢管桩灌浆:注浆施工时无需加压,只需利用注浆泵将浆液输送至注浆钢管孔口即可,利用砂浆自重注入孔内,待浆液注满钢管桩孔,孔口浆面不再下降,停止注浆,形成钢管桩。5) Steel pipe pile grouting: No need to pressurize during grouting construction, just use the grouting pump to transport the grout to the hole of the grouted steel pipe, and use the mortar to inject the hole into the hole by its own weight. After the grout fills the steel pipe pile hole, the hole The grout level no longer drops, stop grouting, and form steel pipe piles.
与现有技术相比,本发明具有的有益效果是:Compared with prior art, the beneficial effect that the present invention has is:
1、与常规防渗墙在成槽过程中进行的围堰回填层、漏失架空层处理工艺相比较,本发明采用超前预灌砂浆钢管桩地层加固处理施工结构,通过钢管桩灌注砂浆,针对不同的地层,钢管桩布置密度、深度不同,钢管起到锁住孤石及沙土的作用,对地层薄弱环节能充分地起到填充、固结作用,提高地层整体性,预防、减少甚至避免防渗墙施工中槽孔坍塌、漏浆、管涌等事故发生,以达到防渗墙施工槽孔固壁保护的目的,提高防渗墙成槽工效,为防渗墙施工质量及稳定性提供了可靠保障。1. Compared with the cofferdam backfill layer and leakage overhead layer treatment process carried out during the trench formation process of the conventional anti-seepage wall, the present invention adopts advanced pre-filled mortar steel pipe piles to reinforce the construction structure, and pours mortar through the steel pipe piles. For different strata, steel pipe piles are arranged in different densities and depths. The steel pipes play the role of locking boulders and sand, and can fully fill and consolidate weak links in the stratum, improve the integrity of the stratum, prevent, reduce or even Avoid accidents such as slot collapse, slurry leakage, and piping in the construction of the cutoff wall, so as to achieve the purpose of solid wall protection in the construction of the cutoff wall, improve the work efficiency of the cutoff wall, and provide a guarantee for the construction quality and stability of the cutoff wall a reliable guarantee.
2、该结构预防、减少甚至避免了防渗墙施工中槽孔坍塌、漏浆、管涌等事故发生,所以减少了因处理事故造成的资源浪费,节约了施工成本。2. This structure prevents, reduces or even avoids the occurrence of accidents such as slot collapse, slurry leakage, and piping during the construction of the cut-off wall, so it reduces the waste of resources caused by handling accidents and saves construction costs.
3、该结构的采用,使得施工快速、安全可靠,加快了施工进度,降低了施工成本。3. The adoption of this structure makes the construction fast, safe and reliable, speeds up the construction progress and reduces the construction cost.
4、该结构适用于50m级以上深孔防渗墙施工。4. The structure is suitable for the construction of deep hole anti-seepage walls above 50m level.
附图说明Description of drawings
图1,是本发明平面结构示意图;Fig. 1 is a schematic diagram of the plane structure of the present invention;
图2,是图1A-A剖面结构示意图。Fig. 2 is a schematic cross-sectional structure diagram of Fig. 1A-A.
具体实施方式Detailed ways
下面结合具体实施方式对本发明作进一步说明,具体实施方式是对本发明原理的进一步说明,不以任何方式限制本发明,与本发明相同或类似技术均没有超出本发明保护的范围。The present invention will be further described below in conjunction with specific embodiment, and specific embodiment is a further description of the principle of the present invention, does not limit the present invention in any way, and the same or similar technologies as the present invention do not exceed the protection scope of the present invention.
参见图1、图2,本发明包括防渗墙和防渗墙轴线4两侧的导向槽1,其关键技术是在导向槽中心轴线2上布置钢管桩孔3,钢管桩孔3内下设注浆钢管5,注浆钢管5内灌注砂浆形成钢管桩。Referring to Fig. 1 and Fig. 2, the present invention includes the anti-seepage wall and guide grooves 1 on both sides of the anti-seepage wall axis 4, and its key technology is to arrange steel pipe pile holes 3 on the central axis 2 of the guide groove, and inside the steel pipe pile holes 3 A grouting steel pipe 5 is arranged below, and mortar is poured into the grouting steel pipe 5 to form a steel pipe pile.
所述钢管桩孔3的间距为1.5m~2m。The distance between the steel pipe pile holes 3 is 1.5m-2m.
所述注浆钢管5采用Φ89mm的钢管制成。The grouting steel pipe 5 is made of a Φ89mm steel pipe.
在注浆钢管壁上每间隔30cm~35cm使用氧气焊加工直径为2cm梅花状孔洞6,以便提高注浆效果,增加浆液辐射范围。Oxygen welding is used to process plum blossom-shaped holes 6 with a diameter of 2 cm on the wall of the grouting steel pipe at intervals of 30 cm to 35 cm, so as to improve the grouting effect and increase the radiation range of the grout.
所述注浆钢管5的长度根据施工孔深设定,一般单根长度为6m~8m。The length of the grouting steel pipe 5 is set according to the depth of the construction hole, and generally the length of a single steel pipe is 6m-8m.
所述上、下注浆钢管5采用丝扣连接来增加长度。The upper and lower grouting steel pipes 5 are connected with screws to increase the length.
所述注浆钢管5增加长度时的丝扣连接处外侧设置2道连接加强钢筋,以防止下设过程中管件脱落。When the length of the grouted steel pipe 5 is increased, two connecting reinforcing bars are provided outside the threaded connection to prevent the pipe fittings from falling off during the lowering process.
所述注浆钢管5上口超出导向槽1底部50~60cm的高度,后期注浆完成后浇筑在导向槽1中增加钢管桩的稳固性。The upper opening of the grouted steel pipe 5 exceeds the height of the bottom of the guide groove 1 by 50-60 cm, and is poured in the guide groove 1 after the grouting in the later stage to increase the stability of the steel pipe pile.
深孔防渗墙施工中针对架空漏失地层的施工方法包括以下步骤:The construction method for overhead leakage stratum in the construction of deep hole cutoff wall includes the following steps:
1)地层判断:前期根据施工部位围堰填筑性质以及设计勘探资料确定施工地层性状,判定需预先处理的施工区域,根据具体的地质情况确定桩间距及孔深;1) Stratum judgment: In the early stage, according to the nature of the cofferdam filling at the construction site and the design and exploration data, the properties of the construction stratum are determined, the construction area that needs to be pre-treated is determined, and the pile spacing and hole depth are determined according to the specific geological conditions;
2)钻孔准备:待防渗墙导向槽开挖完成后导向槽浇筑前,沿防渗墙导向槽中心轴线2按照设计间距1.5m~2m布置钢管桩孔3,钻孔中心采用石灰进行标记定位,钻机准备及就位;2) Drilling preparation: After the excavation of the guide groove of the cut-off wall is completed, before the pouring of the guide groove, the steel pipe pile holes 3 are arranged along the central axis 2 of the guide groove of the cut-off wall according to the design interval of 1.5m ~ 2m, and the drilling center is made of lime. Mark positioning, drilling rig preparation and positioning;
3)钻孔设备:为提高施工效率,选用阿特拉斯A66CBT型全液压履带式钻机配英格索兰XHP900WCAT空压机进行钻孔施工;3) Drilling equipment: In order to improve the construction efficiency, Atlas A66CBT full-hydraulic crawler drilling rig and Ingersoll Rand XHP900WCAT air compressor are selected for drilling construction;
4)孔径:采用Φ127mm的偏心钻头配合Φ140mm套管钻进成孔;4) Aperture diameter: Use Φ127mm eccentric drill bit with Φ140mm casing to drill into the hole;
5)偏心式钻孔工艺钻孔:钻机就位后,首先将φ127mm带扩孔套偏心钻头中心与标记定位的钢管桩孔3进行对正,利用水平尺校核,确保钻孔垂直度,然后进行跟管钻进,利用“重锤式”测斜仪在钻进中进行孔斜检测,发现钻孔偏斜马上进行纠偏,如此循环钻进至设计孔深;5) Drilling by eccentric drilling process: After the drilling rig is in place, first align the center of the φ127mm eccentric drill bit with a reaming sleeve with the marked steel pipe pile hole 3, and check with a level ruler to ensure the verticality of the drilling. Then drill with the pipe, use the "hammer type" inclinometer to detect the hole inclination during drilling, and correct the deviation immediately if the drilling deviation is found, and drill in this way to the design hole depth;
6)下设注浆钢管:钻孔验收合格后,根据深度不同,对中校正上、下两根注浆钢管5的垂直度,偏斜率符合要求后,采用吊车或人工在现场向钢管桩孔3内下设注浆钢管5;注浆钢管上口超出导向槽1底部50~60cm的高度,后期注浆完成后注浆钢管浇筑在导向槽1中增加钢管桩的稳固性;6) Underlying grouted steel pipes: After the boreholes are qualified, according to the depth, the verticality of the upper and lower two grouted steel pipes 5 is corrected. A grouted steel pipe 5 is set in the hole 3; the upper opening of the grouted steel pipe exceeds the height of the bottom of the guide groove 1 by 50-60 cm, and the grouted steel pipe is poured in the guide groove 1 after the grouting is completed in the later stage to increase the stability of the steel pipe pile;
所述注浆钢管5采用Φ89mm的钢管制成,单根长度一般为6m。The grouting steel pipe 5 is made of a Φ89mm steel pipe, and the length of a single pipe is generally 6m.
在注浆钢管壁上每间隔30cm~35cm使用氧气焊加工直径为2cm梅花状孔洞6。Oxygen welding is used to process quincunx-shaped holes 6 with a diameter of 2 cm at intervals of 30 cm to 35 cm on the grouted steel pipe wall.
为达到注浆钢管5长度所及,可以将注浆钢管5首、尾端采用丝扣连接增加其长度。In order to reach the length of the grouting steel pipe 5, the 5 head and tail ends of the grouting steel pipe can be connected with screws to increase its length.
为防止下设过程中管件脱落,在增加注浆钢管5长度的丝扣连接处外侧设置2道连接加强钢筋紧固。In order to prevent the pipe fittings from falling off during the lowering process, 2 connecting reinforcing steel bars are arranged on the outside of the threaded joint that increases the length of the grouted steel pipe 5 for fastening.
7)钢管桩灌浆:采用J-400高速制浆机1台拌制高流态砂浆,注浆使用的砂石为质地坚硬的天然或机制中细砂,粒径不大于2.5mm,细度模数不大于2.0,其含泥量不大于3%,SO3含量小于1%,有机物含量不大于3%;注浆设备采用TTB100/20中压变量注浆泵输送水泥沙浆,注浆施工时无需加压,只需利用注浆泵将浆液输送至注浆钢管孔口即可,利用砂浆自重注入孔内,以避免压力过大导致浆液扩散半径过大,造成不必要的资源浪费,待浆液注满钢管桩孔,孔口浆面不再下降,停止注浆,形成钢管桩。7) Steel pipe pile grouting: One J-400 high-speed pulping machine is used to mix high-fluid mortar. The sand used for grouting is hard natural or machine-made medium-fine sand, with a particle size of not more than 2.5mm and a fineness of The modulus is not more than 2.0, the mud content is not more than 3%, the SO3 content is less than 1%, and the organic matter content is not more than 3%; the grouting equipment uses TTB100/20 medium pressure variable grouting pump to transport cement mortar, no need for grouting construction Pressurization, just use the grouting pump to transport the grout to the hole of the grouting steel pipe, and inject the grout into the hole by its own weight to avoid excessive pressure and cause the grout to spread too much, causing unnecessary waste of resources. When the steel pipe pile hole is full, the grout level of the hole will no longer drop, and the grouting will be stopped to form a steel pipe pile.
所述的偏心式跟管钻具成孔法的钻进形式为冲击回转形式,偏心式钻孔工艺的钻具由三件套钻具组成(稳杆器、中心钻头、偏心钻头)。钻进过程是依靠中心钻头冲击底部岩石钻进,偏心钻头对孔壁周围的岩石破碎进行扩孔,稳杆器带动外壁套管跟进的原理成孔;钻进至设计深度后,反向回转钻杆,收回偏心钻头,提取钻杆、钻具成孔。The drilling method of the eccentric follow-through drilling method is the impact rotary form, and the drilling tool of the eccentric drilling process is composed of three sets of drilling tools (rod stabilizer, center drill bit, and eccentric drill bit). The drilling process is to rely on the center drill bit to drill into the bottom rock, the eccentric drill bit breaks the rock around the hole wall to ream the hole, and the rod stabilizer drives the outer wall casing to follow up to form a hole; after drilling to the design depth, reverse rotation Drill pipe, retract the eccentric drill bit, extract the drill pipe and drill tool to form a hole.
Claims (9)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810726870.5A CN108729461A (en) | 2018-07-04 | 2018-07-04 | For the constructing structure and construction method on aerial leakage stratum in deep hole impervious wall construction |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201810726870.5A CN108729461A (en) | 2018-07-04 | 2018-07-04 | For the constructing structure and construction method on aerial leakage stratum in deep hole impervious wall construction |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN108729461A true CN108729461A (en) | 2018-11-02 |
Family
ID=63926207
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201810726870.5A Pending CN108729461A (en) | 2018-07-04 | 2018-07-04 | For the constructing structure and construction method on aerial leakage stratum in deep hole impervious wall construction |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN108729461A (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110645858A (en) * | 2019-10-12 | 2020-01-03 | 中国水电基础局有限公司 | Pretreatment method for grooving construction of anti-seepage wall of dam plug body |
| CN110747848A (en) * | 2019-10-24 | 2020-02-04 | 湖北盛达泰水利水电工程有限公司 | Construction method of gravel layer foundation deep cement mixing pile diaphragm wall |
| CN111424653A (en) * | 2020-04-23 | 2020-07-17 | 中国建筑第四工程局有限公司 | Construction method and structure of thin-walled karst cave composite pipe pile |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104404960A (en) * | 2014-11-26 | 2015-03-11 | 中建三局第二建设工程有限责任公司 | Grouting device for joint of underground diaphragm wall and construction method |
| CN105350569A (en) * | 2015-09-24 | 2016-02-24 | 中国水利水电第七工程局成都水电建设工程有限公司 | Diaphragm wall parallel drilling method grooving process |
| CN206308569U (en) * | 2016-12-15 | 2017-07-07 | 长沙理工大学 | It is a kind of to reinforce the road structure for punishing the solution cavity that underlies |
| CN107268603A (en) * | 2017-08-15 | 2017-10-20 | 广东省水利水电第三工程局有限公司 | The karst cave treatment structure and processing method of a kind of diaphram wall |
| CN208917856U (en) * | 2018-07-04 | 2019-05-31 | 中国水利水电第七工程局成都水电建设工程有限公司 | For the constructing structure on aerial leakage stratum in deep hole impervious wall construction |
-
2018
- 2018-07-04 CN CN201810726870.5A patent/CN108729461A/en active Pending
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN104404960A (en) * | 2014-11-26 | 2015-03-11 | 中建三局第二建设工程有限责任公司 | Grouting device for joint of underground diaphragm wall and construction method |
| CN105350569A (en) * | 2015-09-24 | 2016-02-24 | 中国水利水电第七工程局成都水电建设工程有限公司 | Diaphragm wall parallel drilling method grooving process |
| CN206308569U (en) * | 2016-12-15 | 2017-07-07 | 长沙理工大学 | It is a kind of to reinforce the road structure for punishing the solution cavity that underlies |
| CN107268603A (en) * | 2017-08-15 | 2017-10-20 | 广东省水利水电第三工程局有限公司 | The karst cave treatment structure and processing method of a kind of diaphram wall |
| CN208917856U (en) * | 2018-07-04 | 2019-05-31 | 中国水利水电第七工程局成都水电建设工程有限公司 | For the constructing structure on aerial leakage stratum in deep hole impervious wall construction |
Non-Patent Citations (1)
| Title |
|---|
| 陈卫等: "预灌浓浆在糯扎渡电站防渗墙施工中的应用", 《人民长江》, vol. 40, no. 24, pages 46 - 47 * |
Cited By (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN110645858A (en) * | 2019-10-12 | 2020-01-03 | 中国水电基础局有限公司 | Pretreatment method for grooving construction of anti-seepage wall of dam plug body |
| CN110645858B (en) * | 2019-10-12 | 2024-02-02 | 中国水电基础局有限公司 | Pretreatment method for dam body impervious wall grooving construction |
| CN110747848A (en) * | 2019-10-24 | 2020-02-04 | 湖北盛达泰水利水电工程有限公司 | Construction method of gravel layer foundation deep cement mixing pile diaphragm wall |
| CN111424653A (en) * | 2020-04-23 | 2020-07-17 | 中国建筑第四工程局有限公司 | Construction method and structure of thin-walled karst cave composite pipe pile |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN103628912B (en) | The construction method of filling grouting is processed in a kind of goaf | |
| CN106988302B (en) | A kind of high inclination-angle competent bed rotary digging pile driving construction engineering method | |
| CN108119143B (en) | A joint grouting method of cement-sodium silicate double liquid and chemical grout double-circle curtain in shaft working face | |
| CN105863648B (en) | A kind of tunneling is shallow to cover large-section tunnel construction method | |
| CN101173516B (en) | Method of grouting curtain method to prevent grout leakage and hole collapse of large-diameter deep-hole bored piles | |
| CN106640120A (en) | Ground-surface fixed-point deep hole layered grouting construction method | |
| CN104612179B (en) | Through the construction method of the diaphram wall of super thick silty sand ground | |
| CN108166483A (en) | Bored pile construction method | |
| CN106837382A (en) | A kind of subway tunnel country rock pre grouting from the surface reinforcement process | |
| CN108756809B (en) | A kind of sealing method for shield tunnel geological exploration borehole | |
| CN106758759B (en) | A kind of trestle pile foundation and its anchoring process for deep water drift net riverbed | |
| CN116181375A (en) | A fixed-point control method for wellbore seepage water in inclined wells in water-rich formations | |
| CN112281880A (en) | A kind of construction method of long spiral guide hole inserting and locking steel pipe pile cofferdam in complex stratum | |
| CN108729461A (en) | For the constructing structure and construction method on aerial leakage stratum in deep hole impervious wall construction | |
| CN111236214A (en) | Construction method for constructing secant pile by lengthening protective cylinder of rotary drilling rig | |
| CN110469332A (en) | A kind of advance support consolidation method passing through Debris Flow Deposition body tunnel | |
| CN110424971A (en) | The method for handling jacked piles with small section landslide | |
| CN114991818B (en) | Advanced grouting construction method for tunnel penetrating fault | |
| CN105221157B (en) | WSS grouting and reinforcings assist gas pressure cutter replacing method in shield tunnel | |
| CN115573725A (en) | Stratum reinforcing method for comprehensive pipe gallery tunnel to penetrate existing subway shield | |
| CN207406345U (en) | Rich water sand-pebble layer shield tunnel end horizontal grouting ruggedized construction | |
| CN108071110A (en) | Rotary drilling rig Pile method under complex geological condition | |
| CN208917856U (en) | For the constructing structure on aerial leakage stratum in deep hole impervious wall construction | |
| CN207080242U (en) | Cup-type horizontal reinforcement structure of bamboo reinforcement grouting anchor rod at the end of shield tunnel | |
| CN206477240U (en) | A kind of trestle pile foundation for deep water drift net riverbed |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20181102 |