CN205576638U - Consolidate roadbed structure who handles newly -built railway karst foundation - Google Patents

Consolidate roadbed structure who handles newly -built railway karst foundation Download PDF

Info

Publication number
CN205576638U
CN205576638U CN201620278194.6U CN201620278194U CN205576638U CN 205576638 U CN205576638 U CN 205576638U CN 201620278194 U CN201620278194 U CN 201620278194U CN 205576638 U CN205576638 U CN 205576638U
Authority
CN
China
Prior art keywords
girder
plate
karst
pile
reinforcing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201620278194.6U
Other languages
Chinese (zh)
Inventor
王祥
晏军
陈占
顾湘生
熊林墩
李小和
倪岳艳
席亚丽
赵新益
熊朝辉
田浩萍
李添翼
陈世刚
王勇刚
杨松
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Siyuan Group Engineering Construction Co Ltd
Original Assignee
China Railway Siyuan Survey and Design Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Siyuan Survey and Design Group Co Ltd filed Critical China Railway Siyuan Survey and Design Group Co Ltd
Priority to CN201620278194.6U priority Critical patent/CN205576638U/en
Application granted granted Critical
Publication of CN205576638U publication Critical patent/CN205576638U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
  • Railway Tracks (AREA)

Abstract

The utility model discloses a consolidate roadbed structure who handles newly -built railway karst foundation, a serial communication port, including setting up at the plate -girder at weak soil layer top, laying the road bed at the plate -girder top, the plate -girder below is equipped with the fore -and -aft many gang drill hole bored concrete pile in way along the line, all pierce through weak soil layer, hard stratum to karst layer at the bottom of the stake of drilling bored concrete pile, drilling bored concrete pile pile bolck forms the stake plate structure with plate -girder bottom fixed connection, stake plate structure both sides karst foundation 's hard stratum is equipped with the fore -and -aft continuous slip casting in way along the line with the karst stacking department of closing and consolidates the district. The utility model discloses a roadbed structure consolidates karst foundation and upper portion soil property overburden, has improved the foundation bearing capacity, the effective control road bed post -construction settlement.

Description

A kind of road structure of consolidation process newly built railway karst foundation
Technical field
This utility model relates to Geotechnical Engineering field, newly-built in particular to a kind of consolidation process The road structure of railway karst foundation.
Background technology
Karst is that the solublerock such as limestone, dolomite produces under the long-term corrosion of water Raw various geological form, effect and phenomenon.Karst foundation deformation failure principal mode has Foundation bearing capacity deficiency, differential settlement, concrete foundation slide, earth's surface cave in.And along with Socioeconomic development, railway construction is increasingly faster, and increasing railway engineering is at rock Molten area is launched, and the regularity and stability of road structure is directly connected to railway operation peace Entirely, thus high-speed railway has extremely strict requirements to base stabilization and settlement Control.Cause This builds high-speed railway on karst foundation, it is necessary to process karst foundation, takes Effectively reinforcement measure controls the settlement after construction of roadbed, to ensure the long-term steady of track structure Fixed.
At present, the treatment measures of karst foundation are mainly filled out pad method, slip casting method, high pressure Churning method etc..Fill out pad method and be primarily adapted for use in bare karst and shallow embedding karst, and inapplicable In covered karst, buried karst;Slip casting method is the most frequently used karst treatment method, but The stability of karst foundation can only be ensured, and can not well control settlement after construction;High pressure Churning method includes the experience of construction all to construction technology, the plant equipment of construction and material There is very high request, and uneconomical, so non-large-scale promotion uses.
Therefore for overcoming above-mentioned many defects, it is necessary to provide one can not only ensure karst Foundation stability, simultaneously also can effectively control settlement after construction, reasonable, economic consolidation process The road structure of newly built railway karst foundation.
Summary of the invention
The purpose of this utility model seeks to solve the deficiency of above-mentioned background technology, it is provided that a kind of The road structure of consolidation process newly built railway karst foundation, carries out drill-pouring to karst foundation Stake is reinforced and slip casing by pressure processes, and not only ensure that the steady in a long-term of karst foundation, the most effectively Control settlement after construction, meet stability and the change of karst foundation high-speed railway subgrade simultaneously The requirement that shape controls.
The technical solution of the utility model is: a kind of consolidation process newly built railway karst foundation Road structure, it is characterised in that include being arranged on the plate-girder at Soft Soil Layer top, being laid on plate The roadbed in back portion, is provided with the multiple rows of cast-in-situ bored pile along circuit longitudinal direction below described plate-girder, All penetrating Soft Soil Layer, hard stratum to karst layer at the bottom of described Pile, described boring fills Note stake stake top is fixedly connected to form pile slab structure, described pile slab structure both sides rock bottom plate-girder The continuous grouting that the hard stratum of molten ground and karst layer junction are provided with along circuit is longitudinal is reinforced District.
Preferably, described cast-in-situ bored pile, plate-girder pour with employing armored concrete and form, Described Pile top extends upwardly into bottom plate-girder 10-15cm and cast-in-situ bored pile and plate The steel bar stress welding colligation of beam.
Preferably, in described multiple rows of cast-in-situ bored pile between adjacent two row hole drilling bored concrete piles away from From equal, for 4-5m;Adjacent two cast-in-situ bored piles side by side in described every row hole drilling bored concrete pile Between distance equal, for 4-5m.
Preferably, described Pile footpath is equal, for 1.0-1.5m.
Preferably, described plate-girder along circuit longitudinally disposed time, pre-between longitudinally adjacent two boards beam Leave expansion joint, in described expansion joint, be packed with Colophonium hemp cut.
Preferably, described plate-girder along circuit laterally by the small-sized plate-girder of polylith with central lines of track pair Title is formed by connecting.
Preferably, described grouting and reinforcing district thickness model in the above hard stratum of interface of stone and earth Enclosing for 3-5m, in interface of stone and earth following karst layer, thickness is in the range of 6-7m, described The total thickness in grouting and reinforcing district is 9-12m.
Preferably, in described grouting and reinforcing district, injected hole presses equilateral triangle or quadrate array cloth Put, injected hole pitch of holes 5-6m.
Preferably, the reinforcing scope in pile slab structure both sides grouting and reinforcing district is from flushing in same side plate Beam lateral ends rises, and the reinforcing scope in grouting and reinforcing district, embankment location is along circuit the most extremely The outer 5.0m of embankment toe, the reinforcing scope in grouting and reinforcing district, cutting location is along circuit laterally outward To lateral sulcus platform outward flange.
Principle of the present utility model is:
The Deep Thick Soft Ground of base table layer uses cast-in-situ bored pile to carry out basement process, stake the most over the ground Long Soft Soil Layer, the hard stratum to karst layer of penetrating, is formed and has globality, water stability and certain The composite foundation of intensity, thus improve foundation bearing capacity, reduce uneven settlement of foundation and work Rear sedimentation, reaches the purpose of reinforcement of soft soil ground.Then, to the rock under deep soft soil foundation Molten interface of stone and earth uses grouting and reinforcing, has reached the process to Deep Thick Soft Ground karst foundation, Ensure long-time stability and the settlement request of roadbed.
The beneficial effects of the utility model are:
By pile slab structure, karst foundation and top soil property cover layer are reinforced, improved Foundation bearing capacity, effectively controls post-construction settlement of subgrade;It is filled with rock by slip casing by pressure Molten crack, solution cavity, plug groundwater activities space, forms water barrier, thus prevents The karst collapse caused because of groundwater level fluctuation, it is ensured that karst foundation steady in a long-term Property.And this foundation reinforcing structure form uncomplicated, economical rationality, can extensively apply from now on In high-speed railway karst foundation is reinforced.
Accompanying drawing explanation
Fig. 1 is this utility model along the horizontal structural representation of circuit
Fig. 2 is that this utility model injected hole equilateral triangle arrangement arranges schematic diagram
Fig. 3 is that this utility model injected hole square arrangement arranges schematic diagram
Wherein: 1. roadbed 2. Soft Soil Layer 3. hard stratum 4. karst layer 5. interface of stone and earth 6. note Slurry stabilization zone 7. cast-in-situ bored pile 8. plate-girder 9. injected hole.
Detailed description of the invention
With specific embodiment, this utility model is made the most below in conjunction with the accompanying drawings Bright.
As it is shown in figure 1, this utility model provides a kind of consolidation process newly built railway karst foundation Road structure, the karst foundation structure at place includes karst layer 4, is positioned on karst layer 4 Side hard stratum 3, be positioned at the Soft Soil Layer 2 above hard stratum 3, road structure include arrange Plate-girder 8 at Soft Soil Layer 2 top, it is laid on the roadbed 1 at plate-girder 8 top, plate-girder 8 edge Circuit is longitudinally and with the lateral symmetry setting of central lines of track, and central lines of track is roadbed center Line, plate-girder 8 transverse ends lays respectively between curb and the toe of roadbed 1 homonymy (such as plate The left side lateral ends of beam 8 is positioned between the curb on the left of roadbed 1 and toe, the right side of plate-girder 8 Side lateral ends is in like manner).Soft Soil Layer 2 bottom plate-girder 8 is provided with along circuit longitudinal many Row hole drilling bored concrete pile 7, all penetrate at the bottom of cast-in-situ bored pile 7 Soft Soil Layer 2, hard stratum 3 to Karst layer 4, cast-in-situ bored pile 7 top is fixedly connected to form pile slab structure bottom plate-girder 8, Hard stratum 3 and karst layer 4 junction of pile slab structure both sides karst foundation are provided with indulges along circuit To continuous grouting stabilization zone 6.It is horizontal that central lines of track in this utility model refers to circuit Kernel of section line.
Cast-in-situ bored pile 7, plate-girder 8 pour with employing armored concrete and form, drill-pouring 7 tops of stake extend upwardly into bottom plate-girder 8 10-15cm and cast-in-situ bored pile 7 and plate-girder 8 Steel bar stress welding colligation.7 footpaths of cast-in-situ bored pile are equal, and diameter d is 1-1.5m, stake Space D is 4-5m, effective length 18-22m, depending on visual on-the-spot Exploring Cavern situation, And meet sedimentation inspection calculation requirement.Plate-girder 8 in the present embodiment is laterally by thick 1-1.2m, laterally A size of 14m, longitudinal size is that two blocks of small-sized plate-girders of 7.2m connect formation, along circuit The expansion joint of wide 2cm is stayed, filling Colophonium fiber crops in seam between longitudinally adjacent two blocks of small-sized plate-girders Muscle, expansion joint position is preferably located at the centre position of two campsheds.Phase in multiple rows of cast-in-situ bored pile 7 Distance between adjacent two row hole drilling bored concrete piles 7 is equal, for 4-5m, every row hole drilling bored concrete pile 7 In distance between adjacent cast-in-situ bored pile 7 equal, for 4-5m.The present embodiment is adjacent with row Cast-in-situ bored pile 7 pile spacing 5.0m, spacing 4.0m of adjacent row cast-in-situ bored pile 7, i.e. The horizontal 5.0m of pile spacing, longitudinal 4.0m.
The grouting and reinforcing district 6 thickness range in interface of stone and earth more than 5 hard stratum 3 is 3-5m, in interface of stone and earth less than 5 karst layer 4, thickness is in the range of 6-7m, slip casting The total thickness of stabilization zone 6 is 9-12m.In grouting and reinforcing district 6, injected hole 9 is by positive three Dihedral or arranged in squares as Figure 2-3, injected hole 9 pitch of holes 5-6m.Plate-girder both sides The reinforcing scope in grouting and reinforcing district 6 from flushing in homonymy plate-girder 8 lateral ends along circuit Laterally outward extending (away from line direction), this structure is suitable for and embankment location and road simultaneously Moat location: when for embankment location, the reinforcing scope in grouting and reinforcing district 6 along circuit laterally to Outward to the outer 5.0m of embankment toe, when for cutting location, the reinforcing scope in grouting and reinforcing district 6 Along circuit laterally outward to lateral sulcus platform outward flange.
The road structure Specific construction process of above-mentioned consolidation process karst foundation is:
A. use armored concrete cast in situs along multiple rows of cast-in-situ bored pile 7 of circuit longitudinal direction, bore Hole pouring pile 7 pile body typically uses C35 armored concrete cast in situs, has once irrigated, Must not stop over.With arranging adjacent cast-in-situ bored pile 7 pile spacing 5.0m, adjacent row boring fills Spacing 4.0m of note stake 7, i.e. the horizontal 5.0m of pile spacing, longitudinal 4.0m.Cast-in-situ bored pile 7 footpaths are equal, for 1.0-1.5m, effective length 18-22m (the present embodiment preferred stake footpath 1.2m, Effective length 20m), as met solution cavity, cast-in-situ bored pile 7 should enter rock stratum through solution cavity No less than 2m, and stake bed rock layer thickness is not less than 3m, concrete visual on-the-spot Exploring Cavern feelings Depending on condition, and to meet sedimentation inspection calculation requirement.Above cast-in-situ bored pile 7, Soft Soil Layer 2 pushes up The plate-girder 8 of C35 armored concrete is longitudinally laid in portion along circuit, and plate-girder 8 is with central lines of track Lateral symmetry setting, cast-in-situ bored pile 7 pile body stretches into 10-15cm (this enforcement in plate-girder 8 The preferred 15cm of example) and cast-in-situ bored pile 7 weld colligation with the steel bar stress of plate-girder 8, adopt With the formation pile slab structure that is rigidly connected.Plate-girder 8 laterally directly laid by a monoblock along circuit or The small-sized plate-girder of polylith is formed by connecting with central lines of track symmetry, and the plate-girder 8 in the present embodiment is horizontal To by thick 1-1.2m, lateral dimension is 14m, and longitudinal size is two pieces of compact board of 7.2m Beam connects formation, stays stretching of wide 2cm between the longitudinally adjacent two blocks of small-sized plate-girders of circuit Seam, filling Colophonium hemp cut in seam, expansion joint position is preferably located at the centre position of two campsheds.
B. pile slab structure both sides karst foundation uses slip casing by pressure to reinforce, to interface of stone and earth 5 Carry out sealing treatment, form grouting and reinforcing district 6 (water barrier).Grouting and reinforcing district 6 gross thickness Not less than 9m, wherein in interface of stone and earth more than 5 hard stratum 3, thickness is not less than 3m, with Not less than 6m in lower karst layer 4.Grouting and reinforcing district 6, is filled with Karst Fissures, solution cavity, Plug groundwater activities space, it is possible to prevent because groundwater level fluctuation causes karst collapse. Injected hole 9 equilateral triangle or arranged in squares as Figure 2-3 (in Fig. 2-3 left and right to for Along circuit longitudinally, upward and downward is horizontal along circuit), (the present embodiment is preferred for pitch of holes 5-6m 5.0m), from flushing in homonymy plate-girder 8 lateral ends, embankment location reinforcing scope is to setting About 5.0m outside the roadbed 1 embankment toe of meter, outside cutting location reinforcing scope to lateral sulcus platform Edge.The grouting and reinforcing degree of depth discloses karsts developing area situation according to guide's exploratory hole, and general reinforcing is deep Degree for interface of stone and earth less than 5 6m, as in the range of 6m Karst roof rock crushing or Meet solution cavity and karst when growing very much, slip casting thickness should be strengthened, should to below solution cavity base plate not Less than 1m;Slip casting sleeve pipe embeds basement rock 0.5m, is consolidated into one by cement mortar.Slip casting When hole runs into empty or bigger crack, medium coarse sand material etc. is used to be backfilled to depending on concrete condition molten Slip casting just can be carried out after the filling of hole.Slip casting terminates grouting port and uses C15 concrete backfill in time Close.
C. plate-girder 8 top is by design roadbed paving 1, and plate-girder 8 transverse ends lays respectively at homonymy Between curb and the toe of roadbed 1.
In sum, by pile slab structure, karst foundation and top soil property cover layer are carried out Reinforce, improve foundation bearing capacity, effectively control post-construction settlement of subgrade;Noted by pressure Slurry is filled with Karst Fissures, solution cavity, plugs groundwater activities space, forms water barrier, Thus prevent the karst collapse caused because of groundwater level fluctuation, it is ensured that karst foundation Long-time stability.And this foundation reinforcing structure and form of construction work uncomplicated, economical rationality, Can be widely applied to from now in the reinforcing of high-speed railway karst foundation.

Claims (9)

1. the road structure of a consolidation process newly built railway karst foundation, it is characterised in that Including being arranged on the plate-girder (8) at Soft Soil Layer (2) top, being laid on plate-girder (8) top Roadbed (1), described plate-girder (8) lower section is provided with the multiple rows of cast-in-situ bored pile along circuit longitudinal direction (7), Soft Soil Layer (2), hard stratum (3) are all penetrated at the bottom of described cast-in-situ bored pile (7) stake To karst layer (4), described cast-in-situ bored pile (7) stake top is fixing with plate-girder (8) bottom even Connect formation pile slab structure, the hard stratum (3) of described pile slab structure both sides karst foundation and rock Soluble layer (4) junction is provided with the continuous grouting stabilization zone (6) along circuit longitudinal direction.
2. road structure as claimed in claim 1, it is characterised in that described drill-pouring Stake (7), plate-girder (8) pour with employing armored concrete and form, described cast-in-situ bored pile (7) stake top extend upwardly into plate-girder (8) bottom 10-15cm and cast-in-situ bored pile (7) with The steel bar stress welding colligation of plate-girder (8).
3. road structure as claimed in claim 1, it is characterised in that multiple rows of described boring In bored concrete pile (7), the distance between adjacent two row hole drilling bored concrete piles (7) is equal, for 4-5m; Often arrange in described cast-in-situ bored pile (7) between adjacent two cast-in-situ bored piles (7) side by side Apart from equal, for 4-5m.
4. road structure as claimed in claim 1, it is characterised in that described drill-pouring Stake (7) stake footpath is equal, for 1.0-1.5m, effective length 18-22m.
5. road structure as claimed in claim 1, it is characterised in that described plate-girder (8) Along circuit longitudinally disposed time, be reserved with expansion joint between longitudinally adjacent two boards beam (8), institute Colophonium hemp cut it is packed with in stating expansion joint.
6. road structure as claimed in claim 1, it is characterised in that described plate-girder (8) Laterally it is formed by connecting with central lines of track symmetry by the small-sized plate-girder of polylith along circuit.
7. road structure as claimed in claim 1, it is characterised in that described grouting and reinforcing The district (6) thickness range in interface of stone and earth (5) above hard stratum (3) is 3-5m, In interface of stone and earth (5) following karst layer (4), thickness is in the range of 6-7m, described note The total thickness of slurry stabilization zone (6) is 9-12m.
8. road structure as claimed in claim 1, it is characterised in that described grouting and reinforcing In district (6), injected hole (9) is to arrange by equilateral triangle or quadrate array, injected hole (9) Pitch of holes 5-6m.
9. road structure as claimed in claim 1, it is characterised in that pile slab structure both sides The reinforcing scope in grouting and reinforcing district (6) from flushing in homonymy plate-girder (8) lateral ends, The reinforcing scope in grouting and reinforcing district, embankment location (6) along circuit laterally outward to embankment toe Outer 5.0m, the reinforcing scope in grouting and reinforcing district, cutting location (6) is along circuit the most extremely Lateral sulcus platform outward flange.
CN201620278194.6U 2016-04-06 2016-04-06 Consolidate roadbed structure who handles newly -built railway karst foundation Active CN205576638U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201620278194.6U CN205576638U (en) 2016-04-06 2016-04-06 Consolidate roadbed structure who handles newly -built railway karst foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201620278194.6U CN205576638U (en) 2016-04-06 2016-04-06 Consolidate roadbed structure who handles newly -built railway karst foundation

Publications (1)

Publication Number Publication Date
CN205576638U true CN205576638U (en) 2016-09-14

Family

ID=56865094

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201620278194.6U Active CN205576638U (en) 2016-04-06 2016-04-06 Consolidate roadbed structure who handles newly -built railway karst foundation

Country Status (1)

Country Link
CN (1) CN205576638U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105696427A (en) * 2016-04-06 2016-06-22 中铁第四勘察设计院集团有限公司 Construction method for reinforcing newly-built railway karst foundation and roadbed structure thereof
CN106638168A (en) * 2017-01-17 2017-05-10 马鞍山钢铁股份有限公司 Device for treating metallurgy railroad bed defects through reinforcing and grouting and construction method

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105696427A (en) * 2016-04-06 2016-06-22 中铁第四勘察设计院集团有限公司 Construction method for reinforcing newly-built railway karst foundation and roadbed structure thereof
CN105696427B (en) * 2016-04-06 2017-11-03 中铁第四勘察设计院集团有限公司 The construction method and its road structure of a kind of consolidation process newly built railway karst foundation
CN106638168A (en) * 2017-01-17 2017-05-10 马鞍山钢铁股份有限公司 Device for treating metallurgy railroad bed defects through reinforcing and grouting and construction method

Similar Documents

Publication Publication Date Title
CN105696427B (en) The construction method and its road structure of a kind of consolidation process newly built railway karst foundation
CN107503257B (en) One kind being close to mountain high-filled subgrade stabilization and Deformation control structure and construction method
CN106759473B (en) The constructing structure and its construction method of underground pipe gallery and road
CN206308569U (en) It is a kind of to reinforce the road structure for punishing the solution cavity that underlies
CN102071607A (en) Railroad bed repair method without affecting existing running conditions
CN207109475U (en) It is close to mountain high-filled subgrade stabilization and Deformation control structure
CN204401385U (en) A kind of road structure processing Deep Thick Soft Ground karst foundation
CN104895055A (en) Building grouting pile foundation construction method
CN114109394B (en) Method for determining pile length of tunnel shallow-buried weak surrounding rock high-pressure jet grouting pile method ground surface reinforcement
CN110144908A (en) A kind of deep layer grouting and reinforcing landslide construction and its construction method
CN111395060B (en) Design and construction method for widening roadbed structure of existing cutting in karst area
CN103074882A (en) Construction method for reinforcing island-type perennial frozen-soil foundation by adopting gravel piles
CN106049195A (en) Method for strengthening subgrade basement of existing high speed railway line
CN110219359A (en) A kind of Submersed type inspection well and its construction method
CN104532714B (en) Roadbed structure for treating deep soft soil karst foundation
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN105926391B (en) A kind of curb method for widening of existing railway roadbed
CN207525567U (en) A kind of pile plate composite structure suitable for Steep Slope Embankment
CN205116204U (en) Roadbed structure of crowded native bored concrete pile stake board of two -way spiral
CN107841908A (en) For eliminating the road structure of the high embankment lateral variation sedimentation in high-speed railway abrupt slope
CN205576638U (en) Consolidate roadbed structure who handles newly -built railway karst foundation
CN102296591A (en) Rapid drainage solidifying treatment method of soft soil foundation
CN102493485B (en) Method for building slope protection retaining wall during filling
CN108487234B (en) Construction method of cast-in-situ pile plate type platform wall
CN205576990U (en) Cross section and wear bridge pier tunnel slip casting supporting construction

Legal Events

Date Code Title Description
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20180403

Address after: 430063 Wuchang, Hubei, Yang Park, Peace Avenue, No. 745

Patentee after: In the fourth group of geotechnical engineering limited liability company

Address before: 430063 Wuchang, Hubei, Yang Park, Peace Avenue, No. 745

Patentee before: The forth Survey and Design Institute (Group) Co., Ltd. Of CRCC

TR01 Transfer of patent right
CP01 Change in the name or title of a patent holder

Address after: 430063 No. 745 Heping Avenue, Wuchang, Hubei, Wuhan

Patentee after: China Railway Siyuan Group Engineering Construction Co., Ltd

Address before: 430063 No. 745 Heping Avenue, Wuchang, Hubei, Wuhan

Patentee before: GEOTECHNICAL ENGINEERING CO., LTD. OF CHINA RAILWAY SIYUAN SURVEY AND DESIGN GROUP Co.,Ltd.

CP01 Change in the name or title of a patent holder