CN115573725A - Stratum reinforcing method for comprehensive pipe gallery tunnel to penetrate existing subway shield - Google Patents

Stratum reinforcing method for comprehensive pipe gallery tunnel to penetrate existing subway shield Download PDF

Info

Publication number
CN115573725A
CN115573725A CN202211192656.9A CN202211192656A CN115573725A CN 115573725 A CN115573725 A CN 115573725A CN 202211192656 A CN202211192656 A CN 202211192656A CN 115573725 A CN115573725 A CN 115573725A
Authority
CN
China
Prior art keywords
grouting
tunnel
reinforcement
pipe gallery
shield
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202211192656.9A
Other languages
Chinese (zh)
Inventor
吴振宇
石超
刘治文
任江磊
郑东平
周平
刘冬祥
熊春林
范佰通
许强锋
廖振威
刘龙展
柴德华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shenzhen Metro Group Co ltd
Sichuan Nanjiao Tangchen Civil Engineering Technology Co ltd
Shield Engineering Branch Of China Railway 25th Bureau Group Co ltd
Southwest Jiaotong University
China Railway 25th Bureau Group Co Ltd
Original Assignee
Shenzhen Metro Group Co ltd
Sichuan Nanjiao Tangchen Civil Engineering Technology Co ltd
Shield Engineering Branch Of China Railway 25th Bureau Group Co ltd
Southwest Jiaotong University
China Railway 25th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shenzhen Metro Group Co ltd, Sichuan Nanjiao Tangchen Civil Engineering Technology Co ltd, Shield Engineering Branch Of China Railway 25th Bureau Group Co ltd, Southwest Jiaotong University, China Railway 25th Bureau Group Co Ltd filed Critical Shenzhen Metro Group Co ltd
Priority to CN202211192656.9A priority Critical patent/CN115573725A/en
Publication of CN115573725A publication Critical patent/CN115573725A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/001Improving soil or rock, e.g. by freezing; Injections
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Soil Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a stratum reinforcing method for a comprehensive pipe gallery tunnel to pass through an existing subway shield, which relates to the field of tunnel construction and comprises the steps of strengthening the bearing and anti-permeability capacity of a soil body by ground grouting reinforcement, reducing the deformation and seepage influence of the existing subway by pre-reinforcement in a subway tunnel, improving the self-stability of the front soil body and reducing the water permeability of the soil body by shield advanced grouting, controlling the deformation and water plugging of surrounding rocks by grouting reinforcement in the pipe gallery tunnel, and forming a complete prevention and control system by the connection of the four steps. Compared with the traditional grouting filling, the invention has more comprehensive safety prevention and control capability. In addition, the grouting range is optimized according to the stress characteristics of the existing subway with different sections, the large deformation and torsion risks of the existing shield interval are effectively prevented and controlled, the defect of time-consuming consumable materials of large-range whole reinforcement is avoided, and the construction benefit is greatly improved.

Description

一种综合管廊隧道下穿既有地铁盾构的地层加固方法A Ground Reinforcement Method for a Comprehensive Pipe Gallery Tunnel Passing Under an Existing Subway Shield

技术领域technical field

本发明涉及隧道施工领域,尤其是涉及一种综合管廊隧道下穿既有地铁盾构的地层加固方法。The invention relates to the field of tunnel construction, in particular to a ground reinforcement method for a comprehensive pipe gallery tunnel passing under an existing subway shield.

背景技术Background technique

目前城市地下工程建设快速发展,合理的规划使用地下空间尤为重要。综合管廊就是集电力、通信、燃气、供热、给排水等各种工程管线于一体,实现统一规划、统一设计、统一建设和管理。然而,随着各大城市地铁建设发展,在城区内修建大断面综合管廊隧道时常会穿越各种既有地铁盾构区间。新建综合管廊隧道开挖产生的地层扰动给近接盾构区间带来巨大的安全隐患。当盾构掘进下穿带来地层损失和应力扰动,间接诱发上部既有地铁结构位移影响超出一定范围时,将会对新建和既有隧道结构,甚至周围地层环境造成严重破坏。轻则衬砌结构开裂、不均匀沉降与倾斜,重则地层塌陷,结构坍塌,威胁人民的生命财产安全。At present, urban underground engineering construction is developing rapidly, and it is particularly important to plan and use underground space reasonably. The comprehensive pipe gallery integrates various engineering pipelines such as electric power, communication, gas, heating, water supply and drainage, and realizes unified planning, unified design, unified construction and management. However, with the development of subway construction in major cities, the construction of large-section comprehensive pipe corridor tunnels in urban areas often passes through various existing subway shield sections. The stratum disturbance caused by the excavation of the newly-built comprehensive utility gallery tunnel has brought huge safety hazards to the section close to the shield. When the shield excavation leads to stratum loss and stress disturbance, and indirectly induces the displacement of the upper existing subway structure beyond a certain range, it will cause serious damage to the new and existing tunnel structures, and even the surrounding stratum environment. In the slightest, the lining structure cracks, uneven settlement and inclination, and in severe cases, the ground subsides and the structure collapses, threatening the safety of people's lives and properties.

主动防控新建综合管廊隧道施工对上方既有盾构区间的安全影响至关重要。现有措施大部分仅考虑单一形式的加固方式,并不能有效控制地下盾构施工安全和近接地铁结构安全。此外,现有加固体系并未考虑隧道重叠段的特殊形式,多为相互交叉穿越工况。再者,为安全考虑,多为大范围的注浆加固,这导致工程经济效益低。因此,研发一种有效防控既有盾构区间沉降大变形和扭转风险且减少非必要的大范围加固,对盾构隧道后续施工安全防控和经济效益是具有一定的工程意义。It is very important to actively prevent and control the safety impact of the construction of the new comprehensive utility gallery tunnel on the existing shield section above. Most of the existing measures only consider a single form of reinforcement, which cannot effectively control the safety of underground shield construction and the safety of structures close to the subway. In addition, the existing reinforcement system does not consider the special form of the overlapping section of the tunnel, and most of them are cross-crossing conditions. Furthermore, for the sake of safety, most of them are reinforced by large-scale grouting, which leads to low economic benefits of the project. Therefore, the development of a large-scale reinforcement that can effectively prevent and control the large deformation and torsional risk of settlement in the existing shield section and reduce unnecessary large-scale reinforcement has certain engineering significance for the safety prevention and economic benefit of the subsequent construction of the shield tunnel.

发明内容Contents of the invention

本发明的目的是为了解决上述技术中存在的缺点,提供了一种综合管廊隧道下穿既有地铁盾构的地层加固方法,该加固方法能够有效防控既有盾构区间大变形和扭转风险且避免大范围加固的不经济性。The purpose of the present invention is to solve the shortcomings in the above-mentioned technologies, and to provide a ground reinforcement method in which the comprehensive utility tunnel passes through the existing subway shield tunnel, and the reinforcement method can effectively prevent and control the large deformation and torsion of the existing shield section risk and avoid the diseconomy of large-scale reinforcement.

为实现上述目的,本发明采用的技术方案是:In order to achieve the above object, the technical scheme adopted in the present invention is:

一种综合管廊隧道下穿既有地铁盾构的地层加固方法,包括:A ground reinforcement method for a comprehensive utility gallery tunnel passing under an existing subway shield, comprising:

地面注浆加固措施,通过地面注浆孔向地层注入双液浆形成多面加固墙,达到土体承载和抗渗能力的加强;Ground grouting reinforcement measures, through the ground grouting hole to inject double liquid grout into the ground to form a multi-faceted reinforcement wall, to achieve the strengthening of soil bearing and anti-seepage capacity;

地铁隧道洞内预加固措施,通过地铁洞内注浆管向地层注浆形成底部加固区,降低既有地铁变形和渗流影响;The pre-reinforcement measures in the subway tunnel are to form the bottom reinforcement area by grouting the grouting pipe in the subway tunnel to the ground to reduce the deformation and seepage effects of the existing subway;

新建综合管廊盾体超前注浆措施,通过盾体超前注浆孔向盾构前上方土体注浆,达到盾构前方土体自稳并减小土体透水性;The advanced grouting measures for the shield body of the newly-built comprehensive pipe gallery are grouted to the soil above the front of the shield through the advanced grouting holes of the shield body, so as to achieve the self-stabilization of the soil in front of the shield and reduce the water permeability of the soil;

新建管廊洞内注浆加固,通过管廊洞内注浆管向地层注浆形成拱顶加固区,达到围岩变形控制和堵水;The grouting in the newly-built pipe gallery is reinforced, and the vault reinforcement area is formed by grouting the grouting pipe in the pipe gallery to the formation, so as to control the deformation of the surrounding rock and block water;

所述地面注浆加固、地铁隧道洞内预加固、盾体超前注浆和管廊洞内注浆加固是相辅相成,共同联系形成完整的加固防控体系。The ground grouting reinforcement, the subway tunnel pre-reinforcement, the shield body advance grouting, and the tunnel tunnel grouting reinforcement are complementary to each other, and they are connected together to form a complete reinforcement prevention and control system.

进一步的,所述地面注浆孔,布置在既有地铁隧道中心线2m和5m位置,在地面上垂直钻孔,钻孔深度为隧道结构上下3m至地表范围内,注浆孔间距为3m,呈梅花形布置。Further, the ground grouting holes are arranged at positions 2m and 5m from the centerline of the existing subway tunnel, and are drilled vertically on the ground. The drilling depth is within the range of 3m from the top and bottom of the tunnel structure to the surface, and the distance between the grouting holes is 3m. Arranged in plum blossom shape.

进一步的,所述地面注浆孔,包括远侧地面注浆孔和近侧地面注浆孔;注浆孔钻孔完成后管廊区间下穿前,在孔内预先填充中粗砂。Further, the ground grouting holes include far-side ground grouting holes and near-side ground grouting holes; after the grouting holes are drilled, medium-coarse sand is pre-filled in the holes before the pipe gallery section is passed down.

进一步的,所述地面注浆加固措施,当管廊区间下穿过程中,地铁既有线变形超过4mm,采用WSS钻注一体机进行后退式注浆加固,用于对地表及地铁隧道下方土体进行加固。Further, in the ground grouting reinforcement measures, when the existing subway line is deformed by more than 4mm during the down-passing process of the pipe gallery section, the WSS drilling and injection machine is used to carry out retreat grouting reinforcement, which is used to repair the soil on the surface and under the subway tunnel. For reinforcement.

进一步的,所述地面注浆加固措施,包括外侧穿越、重叠穿越、内侧穿越三种加固型式,避免了大范围加固的不经济性。Further, the ground grouting reinforcement measures include three types of reinforcement: outer crossing, overlapping crossing, and inner crossing, which avoids the uneconomical effect of large-scale reinforcement.

进一步的,所述地面注浆孔,在远侧区间采用与综合管廊延伸方向平行的布孔方案,在近侧区间存在重叠段采用与近侧区间隧道延伸方向平行的布孔方案。Further, the ground grouting holes adopt a hole arrangement scheme parallel to the extension direction of the comprehensive pipe gallery in the far section, and adopt a hole arrangement plan parallel to the extension direction of the tunnel in the near section where overlapping sections exist in the near section.

进一步的,所述地铁隧道洞内预加固,为避免注浆加固造成隧道水平位移,每一环注浆针对5点位和7点位同步对称进行。Further, for the pre-reinforcement in the subway tunnel, in order to avoid the horizontal displacement of the tunnel caused by grouting reinforcement, each ring of grouting is synchronously and symmetrically carried out at the 5 o'clock and 7 o'clock positions.

进一步的,所述盾体超前注浆,设计的是Φ50钻孔直径,18-20m钻孔深度,13°外插角。在施工作业中,中盾预留超前注浆孔到刀盘的长度约6m,实际有效注浆深度约14m,管片环宽1.5m,即8.7环,为保障前后两次的注浆面的咬合,每推进6环做一次循环。Further, the advance grouting of the shield is designed with a diameter of Φ50 drilling, a drilling depth of 18-20m, and an extrapolation angle of 13°. During the construction work, the length from the advanced grouting hole to the cutter head is about 6m reserved by Zhongshi, the actual effective grouting depth is about 14m, and the segment ring width is 1.5m, which is 8.7 rings. Bite, and do a cycle every 6 rings.

进一步的,所述新建管廊洞内注浆加固,在外侧穿越段采取在距离地铁隧道较近一端的1点或2点位管片手孔采用打设钢花管方式径向注入水泥-水玻璃双液浆;在重叠穿越段采取在管廊隧道1点或2点和10点或11点位垂直向上注浆。在内侧穿越段采取在管廊隧道1点或2点和10点或11点位径向注浆。Further, the grouting in the newly-built pipe corridor is reinforced, and the cement-sodium silicate double-layer cement-sodium silicate is radially injected into the hand hole of the segment at 1 or 2 points near the end of the subway tunnel in the outer crossing section by laying steel flower pipes. Slurry: Grout vertically upward at 1 or 2 points and 10 or 11 points of the pipe gallery tunnel in the overlapping crossing section. Radial grouting at 1 point or 2 points and 10 points or 11 points of the pipe gallery tunnel is carried out in the inner crossing section.

本发明的有益效果是:The beneficial effects of the present invention are:

(1)本发明综合考虑了地面注浆加固、地铁隧道洞内预加固、盾体超前注浆和管廊洞内注浆加固相结合的完整防控体系,相对于传统注浆方案具有更强的安全防控能力;(1) The present invention comprehensively considers a complete prevention and control system that combines ground grouting reinforcement, subway tunnel pre-reinforcement, shield body advance grouting, and pipe gallery grouting reinforcement. Compared with traditional grouting schemes, it has more advantages. Strong security prevention and control capabilities;

(2)本发明基于新建管廊下穿地铁隧道不同情况的受力特征,分别设计有注浆方案,有效防控既有盾构区间大变形和扭转风险,且避免了大范围全部加固的耗时耗材缺点,大大提升了施工效益。(2) Based on the stress characteristics of different situations of subway tunnels passing under the newly-built pipe gallery, the present invention designs grouting schemes respectively to effectively prevent and control the risk of large deformation and torsion in the existing shield section, and avoids the time-consuming time-consuming reinforcement of a large area The shortcomings of consumables have greatly improved the construction efficiency.

附图说明Description of drawings

图1为本发明近接隧道地层加固地面注浆孔布置平面图;Fig. 1 is a layout plan view of the grouting holes on the ground near the tunnel strata of the present invention;

图2为本发明近接隧道地层加固地面注浆孔位置关系图;Fig. 2 is a positional relationship diagram of the grouting holes on the ground near the tunnel strata of the present invention;

图3为本发明A断面外侧穿越段地层加固体系示意图;Fig. 3 is a schematic diagram of the stratum reinforcement system of the outer crossing section of section A of the present invention;

图4为本发明B断面重叠穿越段地层加固体系示意图;Fig. 4 is a schematic diagram of the stratum reinforcement system of the B-section overlap crossing section of the present invention;

图5为本发明C断面内侧穿越段地层加固体系示意图;Fig. 5 is a schematic diagram of the stratum reinforcement system of the inner crossing section of the C section of the present invention;

图6为本发明新建管廊隧道盾体超前注浆加固示意图;Fig. 6 is a schematic diagram of advanced grouting reinforcement of the shield body of the new pipe gallery tunnel of the present invention;

图中:1-远侧既有地铁区间,2-近侧既有地铁区间,3-新建综合管廊,4-远侧地面注浆孔,5-近侧地面注浆孔,6-盾构机,7-地铁洞内注浆管,8-管廊洞内注浆管,9-盾体超前注浆孔,10-超前注浆范围。In the figure: 1- the existing subway section on the far side, 2- the existing subway section on the near side, 3- the newly built comprehensive pipe gallery, 4- the far side ground grouting hole, 5- the near side ground grouting hole, 6- shield tunneling Machine, 7-grouting pipe in the subway cave, 8-grouting pipe in the tunnel gallery, 9-advance grouting hole in the shield body, 10-advance grouting range.

具体实施方式detailed description

为了使本发明的目的、技术方案及优点更加清楚明白,下面结合附图及具体实施方法对本发明作进一步说明。In order to make the object, technical solution and advantages of the present invention clearer, the present invention will be further described below in conjunction with the accompanying drawings and specific implementation methods.

如图1-6所示,一种综合管廊隧道下穿既有地铁盾构的地层加固方法,包括:As shown in Figure 1-6, a ground reinforcement method for a comprehensive utility gallery tunnel passing under an existing subway shield, including:

地面注浆加固措施,其是通过远侧地面注浆孔4和近侧地面注浆孔5向地层注入双液浆形成多面加固墙,达到土体承载和抗渗能力的加强;Ground grouting reinforcement measures, which are to inject double liquid grout into the formation through the far side ground grouting hole 4 and the near side ground grouting hole 5 to form a multi-faceted reinforcement wall, so as to achieve the strengthening of soil bearing and anti-seepage capacity;

地铁隧道洞内预加固措施,其是通过地铁洞内注浆管7向地层注浆形成底部加固区,降低既有地铁变形和渗流影响;The pre-reinforcement measures in the subway tunnel are to form the bottom reinforcement area by grouting the grouting pipe 7 in the subway tunnel to the ground to reduce the deformation and seepage effects of the existing subway;

新建综合管廊3盾体超前注浆措施,其是通过盾体超前注浆孔9向盾构机6前上方土体注浆,达到盾构机6前方土体自稳并减小土体透水性;The advanced grouting measures for the shield body of the newly-built comprehensive pipe gallery 3 are grouting to the soil above the shield machine 6 through the shield body advanced grouting hole 9, so as to achieve the self-stabilization of the soil in front of the shield machine 6 and reduce the soil permeability sex;

新建综合管廊3洞内注浆加固,其是通过管廊洞内注浆管8向地层注浆形成拱顶加固区,达到围岩变形控制和堵水;The grouting reinforcement in the 3rd hole of the newly-built comprehensive pipe gallery is to form the vault reinforcement area by grouting the grouting pipe 8 in the pipe gallery hole to the ground, so as to control the deformation of the surrounding rock and block water;

所述地面注浆加固、地铁隧道洞内预加固、盾体超前注浆和管廊洞内注浆加固是相辅相成,共同联系形成完整的防控加固体系。The ground grouting reinforcement, the subway tunnel pre-reinforcement, the shield body advance grouting, and the tunnel tunnel grouting reinforcement are complementary and jointly connected to form a complete prevention and control reinforcement system.

在施工时,具体施工步骤是:During construction, the specific construction steps are:

步骤一:在新建综合管廊3盾构机6将要穿越时,提前在既有地铁隧道中心线外2m和5m位置进行垂直钻孔,注浆孔间距为3m,呈梅花形布置。在远侧既有地铁区间1采用与新建综合管廊3延伸方向平行的布孔方案,在近侧既有地铁区间2存在重叠段采用与近侧既有地铁区间2隧道延伸方向平行的布孔方案。钻孔深度为既有隧道结构上下3m至地表范围内。注浆孔钻孔完成后,新建综合管廊3下穿前,在孔内预先填充中粗砂。Step 1: When the shield machine 6 of the newly-built comprehensive pipe gallery 3 is about to pass through, vertical drilling shall be carried out at positions 2m and 5m outside the center line of the existing subway tunnel in advance, and the grouting hole spacing shall be 3m, arranged in a plum blossom shape. In the existing subway section 1 on the far side, the hole layout scheme parallel to the extension direction of the newly-built comprehensive pipe gallery 3 is adopted, and in the overlapping section of the existing subway section 2 on the near side, the hole layout plan parallel to the extension direction of the tunnel in the existing subway section 2 on the near side is adopted. Program. The drilling depth is within 3m above and below the existing tunnel structure to the surface. After the grouting holes are drilled, the holes are pre-filled with medium-coarse sand before the new integrated pipe gallery 3 is drilled down.

步骤二:在新建综合管廊3下穿过程中,地铁既有线变形超过4mm,采用WSS钻注一体机进行后退式注浆加固,用于对地表及地铁隧道下方土体进行加固。地表注浆采用水泥-水玻璃双液浆,采用P·O42.5普通硅酸盐水泥单液浆,水灰比1:1,水玻璃(波美度39)与水按体积比1:1稀释,水泥浆-稀释后水玻璃体积比为1:1,采用现场试配,该液浆的初凝时间为60s,注浆压力控制在0.5-1MPa。值得注意的是:在外侧穿越时,仅对近侧既有地铁区间2外侧两排进行注浆;当重叠穿越时,仅对近侧既有地铁区间2内外侧四排进行注浆;在内侧穿越时,对近侧既有地铁区间2内外侧和远侧既有地铁区间1内侧六排进行注浆。Step 2: During the underpassing process of the newly built comprehensive pipe gallery 3, the deformation of the existing subway line exceeds 4mm, and the WSS integrated drilling and injection machine is used for retreat grouting reinforcement, which is used to reinforce the surface and the soil below the subway tunnel. Surface grouting adopts cement-sodium silicate double slurry, P O42.5 ordinary portland cement single slurry, water-cement ratio 1:1, water glass (baume degree 39) and water by volume ratio 1:1 Dilution, cement slurry-diluted water glass volume ratio is 1:1, using on-site trial preparation, the initial setting time of the slurry is 60s, and the grouting pressure is controlled at 0.5-1MPa. It is worth noting that: when crossing on the outside, grouting is only performed on the two outer rows of the existing subway section 2 on the near side; When crossing, grouting is performed on the inner and outer sides of the existing subway section 2 on the near side and the inner side of the existing subway section 1 on the far side.

步骤三:在近侧既有地铁区间2内利用管片上预留的地铁洞内注浆管7对近侧既有地铁区间2管片壁后进行注浆加固,采用两台注浆机同时分别对同一环管片的5点位和7点位进行注浆加固,根据管片错缝拼装原则,采用跳环注浆方式。具体注浆加固过程分两步,第一步为预注浆,每隔3环在5点位和7点位位置进行一次预注浆加固。第二步为跟踪注浆,为避免预注浆堵塞跟踪注浆钢花管,须待预注浆加固全部完成后,对第一步注浆位置预留的中间环5点位和7点位开始开孔并预埋4m长钢花管,后续随盾构机6掘进及自动化监测数据进行跟踪注浆。为避免注浆加固造成既有隧道水平位移,每一环注浆针对5点位和7点位同步进行。其中,预埋地铁洞内注浆管7采用直径Φ25mm钢花管,钢花管埋入深度为4米。注浆压力0.4-0.5MPa。浆液采用水泥-水玻璃双液浆,每一注浆段应反复注浆2-3次,保证注浆质量。Step 3: In the existing subway section 2 on the near side, use the grouting pipe 7 in the subway hole reserved on the segment to perform grouting reinforcement on the wall of the adjacent existing subway section 2 segment, and use two grouting machines to separate the wall at the same time. The 5 o'clock and 7 o'clock positions of the same ring segment are reinforced by grouting, and the jump ring grouting method is adopted according to the principle of segment staggered assembly. The specific grouting reinforcement process is divided into two steps. The first step is pre-grouting, and pre-grouting reinforcement is performed at the 5 o'clock and 7 o'clock positions every three rings. The second step is tracking grouting. In order to avoid the pre-grouting from blocking the tracking grouting steel flower pipe, after the pre-grouting reinforcement is completed, start at the 5 o'clock and 7 o'clock positions of the middle ring reserved for the first step grouting position. Drill holes and pre-embed 4m long steel flower pipes, followed by tracking grouting with shield machine 6 tunneling and automatic monitoring data. In order to avoid the horizontal displacement of the existing tunnel caused by grouting reinforcement, the grouting of each ring is carried out synchronously for the 5 o'clock and 7 o'clock positions. Among them, the pre-buried grouting pipe 7 in the subway cave adopts a steel flower pipe with a diameter of Φ25mm, and the embedded depth of the steel flower pipe is 4 meters. The grouting pressure is 0.4-0.5MPa. The grout adopts cement-sodium silicate double-fluid grout, and each grouting section should be grouted repeatedly 2-3 times to ensure the quality of grouting.

步骤四:考虑后续施工在对上软下硬地层或软弱地层掘进的坍塌风险,利用盾构机6上盾体超前注浆孔9对盾构机6刀盘前上方2~12m 范围土体进行注浆加固,注浆浆液采用双液浆,注浆原则为注浆压力和注浆量双控。主要目的是密实盾构施工区域刀盘前上方土体,保证土体具有一定自稳性,同时,尽可能减小土体透水性,提高盾构机6刀盘前上方土体整体稳定性。其中,施工钻孔采用钻头:Φ50,钻杆:Φ42*2m,钻孔深度:18-20m,外插角:13°。在施工作业中有效钻孔深度20m,实施中以20m为例,其中,中盾预留盾体超前注浆孔9到刀盘的长度约6m,实际有效注浆深度约14m,管片还宽1.5m,即8.7环,为保障前后两次的注浆面的咬合,每推进6环做一次循环。此外,超前注浆所用的浆液及磷酸配比为:水玻璃:水=1:2,磷酸:水=1:30,干水泥:水=10(包):1m3,水玻璃:水泥(混)=1:1,水玻璃:磷酸(混)=1:1。浆液的配比可根据现场实际情况进行调配,开始注时可将浆液的初凝时间控制在50s左右,随着退杆长度的增加,初凝逐渐缩短时间,控制在30s-40s之间,注浆压力控制在1MPa以内,磷酸的初凝时间控制在25s-30s之间。Step 4: Considering the risk of collapse in the subsequent construction when excavating the upper soft and lower hard strata or weak strata, use the advanced grouting hole 9 on the upper shield body of the shield machine 6 to carry out grouting on the soil in the range of 2 to 12m above the front and upper part of the shield machine 6 cutterhead. Grouting reinforcement, the grouting grout adopts double liquid grouting, and the grouting principle is dual control of grouting pressure and grouting volume. The main purpose is to compact the soil above the cutter head in the shield construction area to ensure a certain degree of self-stability of the soil. At the same time, reduce the water permeability of the soil as much as possible and improve the overall stability of the soil above the cutter head of the shield machine 6. Among them, the construction drilling adopts drill bit: Φ50, drill pipe: Φ42*2m, drilling depth: 18-20m, extrapolation angle: 13°. The effective drilling depth is 20m in the construction operation, and 20m is taken as an example in the implementation. Among them, the length from the advanced grouting hole 9 reserved in the shield body to the cutter head is about 6m, the actual effective grouting depth is about 14m, and the segment is still wide 1.5m, that is, 8.7 rings, in order to ensure the occlusion of the two grouting surfaces before and after, a cycle is made every time 6 rings are advanced. In addition, the ratio of grout and phosphoric acid used in advance grouting is: water glass: water = 1:2, phosphoric acid: water = 1:30, dry cement: water = 10 (bag): 1m3, water glass: cement (mixed) =1:1, water glass: phosphoric acid (mixed) =1:1. The ratio of the slurry can be adjusted according to the actual situation on site. The initial setting time of the slurry can be controlled at about 50s at the beginning of injection. The slurry pressure is controlled within 1MPa, and the initial setting time of phosphoric acid is controlled between 25s-30s.

步骤五:在新建综合管廊3隧道内部加强二次补浆,同时在隧道拱顶打设管廊洞内注浆管8注浆加固地铁隧道底部土体。在A或者A’断面外侧穿越段,如图3所示,新建综合管廊3隧道侧穿近侧既有地铁区间2的这段范围内,应采取在距离近侧既有地铁区间2较近一端的1点或2点位管片手孔采用打设钢花管方式注入水泥-水玻璃双液浆。在B或者B’断面重叠穿越段,如图4所示,新建综合管廊3隧道与近侧既有地铁区间2平面完全重叠,此段范围内采取在管廊隧道1点或2点和10点或11点位管片手孔采用垂直向上打设钢花管方式注入水泥-水玻璃双液浆。在C断面内侧穿越段,如图5所示,新建综合管廊3隧道位于远侧和近侧既有地铁区间2之间,此段范围内采取在管廊隧道1点或2点和10点或11点位管片手孔采用打设钢花管方式径向注入水泥-水玻璃双液浆。根据管片错缝拼装原则,注浆加固采用跳环钻孔注浆方式,从新建综合管廊3隧道下穿前30m先对已施工的管片进行注浆加固,后续施工过程中,随管片脱出盾尾及时跟进注浆加固措施。Step 5: Strengthen the secondary grouting inside the tunnel of the newly-built comprehensive pipe gallery 3, and at the same time drill the grouting pipe 8 in the tunnel vault to reinforce the soil at the bottom of the subway tunnel. In the outer crossing section of the A or A' section, as shown in Figure 3, within the range where the newly built comprehensive pipe corridor 3 tunnel passes through the existing subway section 2 on the near side, it should be closer to the existing subway section 2 on the near side. The 1-point or 2-point segment hand hole at one end is injected with cement-sodium silicate double liquid slurry by drilling a steel flower tube. In the overlap crossing section of B or B' section, as shown in Figure 4, the newly-built comprehensive utility corridor 3 tunnel completely overlaps with the plane of the existing subway section 2 on the near side. Point or 11 o'clock segment segment hand hole is drilled vertically upwards to set up a steel flower tube to inject cement-sodium silicate double liquid slurry. In the inner crossing section of the C section, as shown in Figure 5, the newly-built integrated utility corridor 3 tunnel is located between the far side and the near side of the existing subway section 2, and within the scope of this section, points 1 or 2 and point 10 of the utility corridor tunnel are adopted. Or the hand hole of the 11 o'clock segment is radially injected with cement-sodium silicate double slurry by drilling a steel flower tube. According to the principle of staggered assembly of segments, the grouting reinforcement adopts the method of jump ring drilling and grouting, and the constructed segments are reinforced by grouting 30m before the tunnel of the newly built comprehensive pipe gallery 3. If the piece comes out of the tail of the shield, follow up the grouting reinforcement measures in time.

该加固方法实施方式中的地面注浆加固、地铁隧道洞内预加固、盾体超前注浆和管廊洞内注浆加固可以根据施工变形监测情况适当调整。当地层变形小于规范预警值60%时,采用盾体超前注浆+地铁隧道洞内预加固组合;当地层变形处于规范预警值60%-80%时,采用盾体超前注浆+地铁隧道洞内预加固+地面注浆加固组合;当地层变形大于规范预警值时,采用盾体超前注浆+地铁隧道洞内预加固+地面注浆加固+管廊洞内注浆加固组合。The ground grouting reinforcement, the pre-reinforcement in the subway tunnel, the advance grouting of the shield body and the grouting reinforcement in the tunnel of the tunnel in the embodiment of the reinforcement method can be appropriately adjusted according to the construction deformation monitoring situation. When the formation deformation is less than 60% of the standard warning value, the combination of advanced grouting of the shield body + pre-reinforcement in the subway tunnel hole is adopted; when the formation deformation is 60%-80% of the standard warning value, the advanced grouting of the shield body + subway tunnel hole is used Internal pre-reinforcement + ground grouting reinforcement combination; when the formation deformation is greater than the standard warning value, the shield body advance grouting + subway tunnel pre-reinforcement + ground grouting reinforcement + grouting reinforcement combination in the tunnel tunnel is adopted.

从施工整体上来说,该加固方法综合考虑了地面注浆加固、地铁隧道洞内预加固、盾体超前注浆和管廊洞内注浆加固相结合的完整防控体系,相对于传统注浆方案具有更强的安全防控能力;并且,该加固方法基于新建管廊下穿地铁隧道不同情况的受力特征,分别设计有注浆方案,有效防控既有盾构区间大变形和扭转风险,且避免了大范围全部加固的耗时耗材缺点,大大提升了施工效益。From the perspective of construction as a whole, this reinforcement method comprehensively considers a complete prevention and control system that combines ground grouting reinforcement, subway tunnel pre-reinforcement, shield body advance grouting, and pipe tunnel grouting reinforcement. The grouting scheme has stronger safety prevention and control capabilities; moreover, this reinforcement method is based on the stress characteristics of different situations of the subway tunnel under the new pipe gallery, and the grouting scheme is designed respectively to effectively prevent and control the large deformation and torsion risk of the existing shield section , and avoid the time-consuming and consumable shortcomings of large-scale reinforcement, which greatly improves the construction efficiency.

以上结合附图及实施例对本发明进行了详细说明,本领域中普通技术人员可根据上述说明对本发明做出种种变化例。因而,实施例中的某些细节不应构成对本发明的限定,本发明将以所附权利要求书界定的范围作为本发明的保护范围。The present invention has been described in detail above with reference to the accompanying drawings and embodiments, and those skilled in the art can make various changes to the present invention according to the above description. Therefore, some details in the embodiments should not be construed as limiting the present invention, and the present invention will take the scope defined by the appended claims as the protection scope of the present invention.

Claims (8)

1. A stratum reinforcing method for a comprehensive pipe gallery tunnel to pass through an existing subway shield is characterized by comprising the following steps:
ground grouting reinforcement measures are adopted, and double-liquid slurry is injected into the stratum through a far-side ground grouting hole (4) and a near-side ground grouting hole (5) to form a multi-surface reinforced wall;
pre-reinforcing in the subway tunnel, and forming a bottom reinforcing area by grouting the stratum through a grouting pipe (7) in the subway tunnel;
establishing a shield advanced grouting measure of the comprehensive pipe gallery, and grouting soil body above the front of the shield through a shield advanced grouting hole (9);
grouting and reinforcing in the newly-built pipe gallery hole, and grouting the stratum through a grouting pipe (8) in the pipe gallery hole to form a vault reinforcing area;
the ground grouting reinforcement, the pre-reinforcement in the subway tunnel, the shield body advanced grouting and the pipe gallery grouting reinforcement are complementary and are connected together to form a complete prevention and control reinforcement system.
2. The method for reinforcing the stratum of the underground existing subway shield penetrating through the comprehensive pipe gallery tunnel according to claim 1, wherein the far-side ground grouting holes (4) and the near-side ground grouting holes (5) are vertically drilled from the ground to the stratum at positions 2m and 5m outside the center line of the existing subway tunnel, the drilling depth ranges from the upper part to the lower part of the tunnel structure to the ground surface, the distance between the grouting holes is 3m, and the grouting holes are arranged in a quincunx shape.
3. The stratum reinforcing method for the underground tunnel penetrating existing subway shield of the comprehensive pipe gallery according to claim 1, wherein ground grouting reinforcement measures are adopted, and when the deformation of the existing subway line exceeds 4mm in the process of penetrating the newly-built comprehensive pipe gallery (3), backward grouting reinforcement is carried out by adopting a WSS drilling and grouting integrated machine.
4. The method for reinforcing the stratum of the underground through existing subway shield of the comprehensive pipe gallery tunnel according to claim 1, wherein the ground grouting reinforcement measures comprise an outside crossing reinforcement type, an overlapping crossing reinforcement type and an inside crossing reinforcement type.
5. The method for reinforcing the stratum of the underground tunnel penetrating the existing subway shield of the utility tunnel according to claim 1, wherein the ground grouting holes are distributed in a manner parallel to the extending direction of the newly-built utility tunnel (3) in the far-side existing subway section (1) and in a manner parallel to the extending direction of the tunnel in the near-side existing subway section (2).
6. The method for reinforcing the stratum of the existing underground tunnel shield penetrating through the comprehensive pipe gallery tunnel according to claim 1, wherein the underground tunnel is pre-reinforced, and in order to avoid horizontal tunnel displacement caused by grouting reinforcement, each ring of grouting is synchronously and symmetrically performed aiming at 5-point location and 7-point location.
7. The method for reinforcing the stratum of the underground existing subway shield penetrating through the comprehensive pipe gallery tunnel according to claim 1, wherein the shield body is subjected to advanced grouting by adopting a phi 50 drilling diameter, a drilling depth of 18-20m and an external inserting angle of 13 degrees; in the construction operation, the length from the advanced grouting hole (9) of the shield body to the cutter head of the middle shield is about 6m, the actual effective grouting depth is about 14m, the ring width of the duct piece is 1.5m, namely 8.7 rings, and in order to ensure the occlusion of the grouting surfaces of the front and the back twice, circulation is performed once when 6 rings are pushed.
8. The method for reinforcing the stratum of the existing subway shield penetrating under the comprehensive pipe gallery tunnel according to claim 1, characterized in that grouting reinforcement is performed in a hole of the newly-built comprehensive pipe gallery (3), and cement-water glass double-liquid slurry is radially injected in an outer penetrating section by adopting a mode of drilling a grouting pipe (8) in the hole of the pipe gallery at a 1 point or 2 point of a pipe segment of the newly-built comprehensive pipe gallery (3) at the end close to the subway tunnel; grouting vertically upwards at 1 point or 2 points and 10 points or 11 points of a tunnel of a newly-built comprehensive pipe gallery (3) at the overlapping crossing section; radial grouting is adopted at 1 point or 2 point and 10 points or 11 points of the tunnel of the newly-built comprehensive pipe gallery (3) at the inner side crossing section.
CN202211192656.9A 2022-09-28 2022-09-28 Stratum reinforcing method for comprehensive pipe gallery tunnel to penetrate existing subway shield Pending CN115573725A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202211192656.9A CN115573725A (en) 2022-09-28 2022-09-28 Stratum reinforcing method for comprehensive pipe gallery tunnel to penetrate existing subway shield

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202211192656.9A CN115573725A (en) 2022-09-28 2022-09-28 Stratum reinforcing method for comprehensive pipe gallery tunnel to penetrate existing subway shield

Publications (1)

Publication Number Publication Date
CN115573725A true CN115573725A (en) 2023-01-06

Family

ID=84582228

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202211192656.9A Pending CN115573725A (en) 2022-09-28 2022-09-28 Stratum reinforcing method for comprehensive pipe gallery tunnel to penetrate existing subway shield

Country Status (1)

Country Link
CN (1) CN115573725A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116591697A (en) * 2023-07-17 2023-08-15 中铁九局集团第四工程有限公司 Construction method for normal-pressure cutter changing based on shield in coastal region

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116591697A (en) * 2023-07-17 2023-08-15 中铁九局集团第四工程有限公司 Construction method for normal-pressure cutter changing based on shield in coastal region
CN116591697B (en) * 2023-07-17 2023-10-13 中铁九局集团第四工程有限公司 Construction method for normal-pressure cutter changing based on shield in coastal region

Similar Documents

Publication Publication Date Title
CN103089275B (en) Control method of surrounding rocks in water-rich very-broken surrounding rock tunnel collapse sections
CN102678134B (en) Collapse and sink intrusion limit construction method for treating wind accumulated sand loess tunnel through stride shed pipe
CN109098733B (en) Rapid grouting reinforcement method for large-section tunnel in fracture zone rock stratum
CN103898916B (en) Mini stake Composite Braced Retaining Structure and construction method
CN106948843A (en) A kind of double-deck multiple-limb concordant bored grouting transformation dual limestone aquifer method of roof and floor
CN108915736A (en) The water damage control method of digging laneway under the strong weak cementing water-bearing layer of rich water
CN103899323A (en) Construction method of shield passing through railway yard
CN103628894A (en) Water-rich fault fracture zone collapsed roadway repairing method based on angle-variable umbrella-shaped advancing grouting
CN103362117A (en) Full-section grouting method for grouting section
CN108979644A (en) A kind of rich water tunnel solution cavity collapses processing and tunnel excavation construction method
CN106522981B (en) Pass through the method for protecting support in goaf tunnel
CN114483109B (en) Curtain grouting advanced large pipe shed through construction method for crossing tunnel fault fracture zone
CN115573725A (en) Stratum reinforcing method for comprehensive pipe gallery tunnel to penetrate existing subway shield
CN110273700A (en) It is a kind of to control red shale tunnel strength bolt-grouting support structure and its construction method
CN108729461A (en) For the constructing structure and construction method on aerial leakage stratum in deep hole impervious wall construction
CN211202006U (en) A tunnel arch structure with advanced locking feet to reinforce weak soil layers
CN105040705A (en) Ground foundation treatment construction technology under multi-karst-cave geological conditions
CN110847206B (en) Construction method for newly-built subway tunnel to penetrate existing bridge piles
CN105178355B (en) The stratum pre-reinforcement processing method of underground space construction
CN207829905U (en) A kind of drift-sand stratum bored tunnel three-dimensional supporting construction in advance
CN105862725A (en) Underground construction preliminary grouting waterproof and anti-seepage supporting technology
CN112065449B (en) Advanced grouting support method for tunnel
CN205296194U (en) Rich irrigated land layer undercut tunnel interlock pipe curtain
CN207080242U (en) Cup-type horizontal reinforcement structure of bamboo reinforcement grouting anchor rod at the end of shield tunnel
CN112664206B (en) Milling and excavating method for soft and weak cladding shallow-buried large-section tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination