CN103982185A - Mechanical sublevel filling mining method adopting vertical hole and horizontal hole cooperative recovery - Google Patents

Mechanical sublevel filling mining method adopting vertical hole and horizontal hole cooperative recovery Download PDF

Info

Publication number
CN103982185A
CN103982185A CN201410257493.7A CN201410257493A CN103982185A CN 103982185 A CN103982185 A CN 103982185A CN 201410257493 A CN201410257493 A CN 201410257493A CN 103982185 A CN103982185 A CN 103982185A
Authority
CN
China
Prior art keywords
recovery
hole
unit
sublevel
back production
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410257493.7A
Other languages
Chinese (zh)
Other versions
CN103982185B (en
Inventor
李启月
王卫华
尹土兵
张瑞华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central South University
Original Assignee
Central South University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central South University filed Critical Central South University
Priority to CN201410257493.7A priority Critical patent/CN103982185B/en
Publication of CN103982185A publication Critical patent/CN103982185A/en
Application granted granted Critical
Publication of CN103982185B publication Critical patent/CN103982185B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Drilling And Exploitation, And Mining Machines And Methods (AREA)

Abstract

The invention discloses a mechanical sublevel filling mining method adopting vertical hole and horizontal hole cooperative recovery. According to mine sublevel recovery, vertical hole recovery and horizontal hole recovery are cooperatively performed in a sublevel recovery unit; a vertical hole comprises a pre-splitting hole and an ore breaking hole, most of the ore in the unit is recovered in the vertical ore breaking hole, a unit ejector plate is formed by horizontal hole recovery, two outlines of the unit are controlled by the vertical pre-splitting hole, the ore is discharged cooperatively by a common scraper and a remote control scraper after recovery canopy guard, a unit goaf is filled at a time, and a drilling space is reserved for the upper recovery next sublevel. The operation is cycled until the whole one-step stope recovery is finished. The characteristics of high strength, high efficiency and low cost of sublevel recovery are exerted, the two outlines of the sublevel recovery unit are controlled by utilizing pre-splitting blasting, and the outline of a recovery unit ejector plate is controlled through the horizontal hole recovery. The method has the advantages of safety, high efficiency, simple process, low loss and dilution and high mechanical degree.

Description

The mechanization sublevel cut and fill method of the collaborative back production of upright opening and lateral aperture
Technical field
The present invention relates to a kind of mining codes, particularly relate to the mechanization sublevel cut and fill method of the collaborative back production of a kind of upright opening and lateral aperture, be applicable to that ore deposit rock moderately stable is above, inclination or Slowly inclined large and thick ore body, the safety of high-dipping middle thickness orebody, high-efficiency mining.
Background technology
Updating and developing along with mining technique and plant equipment, the shortcomings such as stratified filling method production efficiency when exploitation big thick ore body is low, cost of winning is high, two rate index height expose gradually, filling method develops out sublevel fill stoping method and Mass filling method day by day, and Mass filling method is comparatively strict to the requirement of orebody occurrence, so sublevel fill stoping method is more adopted by mine.
For sublevel fill stoping method, in exploitation process, have the problem of roof safety, traditional sublevel fill stoping method adopts the mode on pre-control top conventionally, and the method complex process, cost is higher, and concussion of blasting easily damages supporting.
Summary of the invention
Technical problem to be solved by this invention is to provide a kind of assurance under the prerequisite of job safety, realizes the upright opening of safe and efficient low-cost exploitation and the mechanization sublevel cut and fill method of the collaborative back production of lateral aperture of big thick ore body.
In order to solve the problems of the technologies described above, the mechanization sublevel cut and fill method of the collaborative back production of upright opening provided by the invention and lateral aperture, ore body is divided into stage casing in short transverse, in stage casing, be further subdivided into segmentation, according to ore-rock stability, determine rational mineral building length and width, using this as a back production unit; Adopt the outer trackless of arteries and veins to adopt standard, by stope connection roadway, slice drift, segmentation, join lane by ore body and stage haulage way or ramp UNICOM; In the first segmentation bottom, form pulling end space and construct artificial false bottom, for the rock drilling space that upright opening is provided is exploited in this segmentation; By back production dividing elements, be upright opening and two back production regions of lateral aperture, the most of ore body in back production unit, vertical Luo Kuang hole, unit top board is pressed to adopt by lateral aperture and is formed, and unit two helps profile to be controlled by vertical pre-ceasma; Pressure is protected top operation after adopting end, adopts subsequently Common LHD and remote-controlled scraper to work in coordination with ore removal, goaf, unit primary filling, and on adopt next segmentation and leave rock drilling space, so circulation, until a whole step stope mining is complete.
Further, two of two back production regions of upright opening and lateral aperture help profile to be controlled by vertical pre-ceasma onepull, and upright opening, pre-ceasma detonate with vertical Luo Kuang hole homogeneous simultaneously.
Adopt the upright opening of technique scheme and the mechanization sublevel cut and fill method of the collaborative back production of lateral aperture, the problems referred to above that exist in recovery process for sublevel fill stoping method, the mechanization sublevel cut and fill method of the collaborative back production of upright opening and lateral aperture is creatively proposed, guaranteeing under the prerequisite of job safety, realizing the safe and efficient low-cost exploitation of big thick ore body.
Adopt the present invention, beneficial effect is:
1. stoping safety is high
By back production dividing elements, be upright opening and two back production regions of lateral aperture, the miner that falls does the major part that upright opening region completes this segmentation, and by presplit blasting, control back production unit two and help profile, lateral aperture back production region is pressed and is adopted operation on upright opening shrink heap, and by controlled blasting controlroof profile.
2. back production efficiency is high, production capacity is large
Segmentation is exploited, and has greatly improved back production efficiency and the production capacity of stope,
3. mechanization degree is high, labour intensity is low
Trackless is adopted standard, and the use of the advanced trackless extractive equipments such as jumbo, remote-controlled scraper, electric truck, rock bolting jumbo, whitewashing chassis has greatly improved the mechanization degree of producing, and has greatly reduced workman's labour intensity.
4. adopt cost low, resources loss is few
Accurate cutting is adopted in segmentation, substoping, and sublevel fill stoping, technique is simple, and cost is low; Can serialization exploit, resources loss is few.
The present invention had both brought into play the high strength, high efficiency of minute section mining, feature cheaply, utilized again presplit blasting to control the profile that substoping unit two is helped, and was pressed and was adopted the profile of having controlled back production unit top board simultaneously by lateral aperture.That the present invention has is safe and efficient, technique is simple, the little and high advantage of mechanization degree of loss and dilution.
In sum, the present invention is a kind of assurance under the prerequisite of job safety, realizes the upright opening of safe and efficient low-cost exploitation and the mechanization sublevel cut and fill method of the collaborative back production of lateral aperture of big thick ore body.
Accompanying drawing explanation
Fig. 1 is mining methods structure perspective view of the present invention.
Fig. 2 is the II of accompanying drawing 1--II section.
Fig. 3 is the III of accompanying drawing 1--III section.
Fig. 4 is the IV of accompanying drawing 1--IV section.
In figure: 1-stage haulage way; 2-drop shaft; 3-drop shaft connecting taxiway; 4-slice drift; 5-cemented fill; 6-artificial false bottom; 7-fore-set; 8-pulling end space; 9-vertical Luo Kuang hole; 10-vertical pre-ceasma; 11-broken ore; 12-upright opening back production region; 13-lateral aperture back production region.
The specific embodiment
The mechanization sublevel cut and fill method of the collaborative back production of upright opening provided by the invention and lateral aperture, technical scheme is as follows:
(1), ore body is divided into stage casing along short transverse, in stage casing, be further subdivided into segmentation, ore body across pitch or capwise are arranged to mineral building, according to ore-rock stability, determine rational mineral building length and width, using this as a back production unit;
(2), segmentation tunnel is arranged on parallel ore bodies border, each segmentation tunnel connects by segmentation connecting taxiway and ramp respectively, stope communicates with segmentation tunnel by stope connection roadway, and stage haulage way, by drop shaft and slice drift UNICOM, is adopted Barebone thereby form the outer trackless of arteries and veins;
, in the first segmentation bottom driving tunnel that undercuts, then expand side and form pulling end space, and construct artificial false bottom, pulling end space is for this substoping provides rock drilling space and compensation space;
, by back production dividing elements, be upright opening and two back production regions of lateral aperture, adopt after accurate cutting, Drilling upright opening upwards, vertical Luo Kuang hole completes the ore deposit operation that falls in this region, vertical pre-ceasma is controlled two of back production unit and is helped profile; The back production in lateral aperture back production region, enters stope and adopts horizontal shallow hole pressure to adopt in ore deposit heap from the stope connection roadway of upper segmentation, by controlled blasting controlroof profile;
(5), after explosion ventilates, protect top operation, adopt subsequently Common LHD and remote-controlled scraper to work in coordination with a large amount of ore removals;
(6), carry out immediately primary filling after this segmentation ore removal, and be the rock drilling space of the reserved certain altitude of upper sectional vertical hole back production, so circulation is until a whole step stope mining is complete and carry out filling and connect top.
Below with reference to figure and instantiation, the present invention is described in further detail:
Embodiments of the invention: take certain gold mine-580m~-620m stage casing is example.
Concrete implementation step is as follows:
, vertical orebody trend divides mineral building ore pillar, the wide 8m of mineral building, the wide 7m of ore pillar, 8~10 mineral building ore pillars are as a panel.Back production in two steps in panel, the room of first digging up mine, then the post of digging up mine, during two step back production, stope two helps to be cemented fill.Along short transverse, divide stage casing, be further subdivided into segmentation in stage casing, miding level height is 50m, and height of lift is 10.5m, all back production from bottom to top in segmentation.
(2), segmentation tunnel is arranged on parallel ore bodies lower wall border, each segmentation tunnel connects by connecting taxiway and main ramp respectively, stope communicates with segmentation tunnel by stope connection roadway, and stage haulage way, by ore pass and slice drift UNICOM, is adopted Barebone thereby form the outer trackless of arteries and veins; As shown in accompanying drawing 1, accompanying drawing 2, accompanying drawing 3 and accompanying drawing 4, in figure: 1-stage haulage way; 2-drop shaft; 3-drop shaft connecting taxiway; 4-slice drift; 5-cemented fill; 6-artificial false bottom; 7-fore-set; 8-pulling end space; 9-vertical Luo Kuang hole; 10-vertical pre-ceasma; 11-broken ore; 12-upright opening back production region; 13-lateral aperture back production region.
(3), at first segmentation bottom driving 3.5m * 3.5m, cut lane, then will cut lane expansion and help to 8.8m, and the thick ore body of working to the rise 1.5m, making to control heights of roofs is 5m.In mineral building bottom, build artificial false bottom, thereby form pulling end space, using this rock drilling space as this segmentation upright opening region.
, form in stope after pulling end space, Drilling upright opening upwards, once by the high ore avalanche of 7m, and adopts the mode of presplit blasting to control two of whole back production unit to help profile.Then from upper segmentation, enter stope and adopt horizontal shallow hole to press in ore deposit heap and adopt the high ore body of 3.5m, controlled blasting makes top board form 1/4 basket handle arch.Wherein, during upright opening explosion, the hole depth in Luo Kuang hole is 7m, and the hole depth of pre-ceasma is 10m, thereby realize upright opening Advance presplitting, with level of control hole, presses and adopts two and help profile.
(5), after explosion ventilates, on the heap of ore deposit, adopt anchor pole to protect top, local Area cracked adopts anchor pole+wire lath+whitewashing combined supporting.
(6), adopt the collaborative a large amount of ore removals of Common LHD and remote-controlled scraper.
(7), carry out immediately consolidated fill one time after segmentation ore removal, and be the rock drilling space of the reserved certain altitude of upper sectional vertical hole back production, so circulation, until a whole step stope mining is complete.

Claims (2)

1. the mechanization sublevel cut and fill method of the collaborative back production of a upright opening and lateral aperture, it is characterized in that: ore body is divided into stage casing in short transverse, in stage casing, be further subdivided into segmentation, according to ore-rock stability, determine rational mineral building length and width, using this as a back production unit; Adopt the outer trackless of arteries and veins to adopt standard, by stope connection roadway, slice drift, segmentation, join lane by ore body and stage haulage way or ramp UNICOM; In the first segmentation bottom, form pulling end space and construct artificial false bottom, for the rock drilling space that upright opening is provided is exploited in this segmentation; By back production dividing elements, be upright opening and two back production regions of lateral aperture, the most of ore body in back production unit, vertical Luo Kuang hole, unit top board is pressed to adopt by lateral aperture and is formed, and unit two helps profile to be controlled by vertical pre-ceasma; Pressure is protected top operation after adopting end, adopts subsequently Common LHD and remote-controlled scraper to work in coordination with ore removal, goaf, unit primary filling, and on adopt next segmentation and leave rock drilling space, so circulation, until a whole step stope mining is complete.
2. upright opening according to claim 1 and lateral aperture are worked in coordination with the mechanization sublevel cut and fill method of back production, it is characterized in that: two of two back production regions of upright opening and lateral aperture help profile to be controlled by vertical pre-ceasma onepull, and vertical pre-ceasma detonates with vertical Luo Kuang hole homogeneous simultaneously.
CN201410257493.7A 2014-06-11 2014-06-11 Upright opening and lateral aperture work in coordination with the mechanization sublevel cut and fill method of back production Expired - Fee Related CN103982185B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410257493.7A CN103982185B (en) 2014-06-11 2014-06-11 Upright opening and lateral aperture work in coordination with the mechanization sublevel cut and fill method of back production

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410257493.7A CN103982185B (en) 2014-06-11 2014-06-11 Upright opening and lateral aperture work in coordination with the mechanization sublevel cut and fill method of back production

Publications (2)

Publication Number Publication Date
CN103982185A true CN103982185A (en) 2014-08-13
CN103982185B CN103982185B (en) 2016-01-13

Family

ID=51274327

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410257493.7A Expired - Fee Related CN103982185B (en) 2014-06-11 2014-06-11 Upright opening and lateral aperture work in coordination with the mechanization sublevel cut and fill method of back production

Country Status (1)

Country Link
CN (1) CN103982185B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106869931A (en) * 2017-02-14 2017-06-20 广西高峰矿业有限责任公司 A kind of barren rock and cementing layering wedging mining with stowing technique and its structure
CN111550248A (en) * 2020-05-20 2020-08-18 长沙矿山研究院有限责任公司 Pre-roof-protecting sublevel open-stoping subsequent filling mining method
CN112012744A (en) * 2020-09-18 2020-12-01 陕西华源矿业有限责任公司 Comprehensive mechanized ore breaking layered filling mining method
CN114562268A (en) * 2022-02-23 2022-05-31 长沙矿山研究院有限责任公司 Partitioned unloading and sublevel filling mining method based on rhombic stoping structure

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO1980000361A1 (en) * 1978-08-03 1980-03-06 Graenges Ab A method of selective underground mining and stabilization of rock cavities
US4309059A (en) * 1978-01-11 1982-01-05 Walsh Myles A Mining method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4309059A (en) * 1978-01-11 1982-01-05 Walsh Myles A Mining method
WO1980000361A1 (en) * 1978-08-03 1980-03-06 Graenges Ab A method of selective underground mining and stabilization of rock cavities

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
姚银佩: "新城金矿二步矿房采矿方法优选研究", 《矿业研究与开发》, vol. 30, no. 5, 31 October 2010 (2010-10-31) *
赵国彦: "机械化盘区上向分层充填采矿法试验研究", 《金属矿山》, no. 276, 30 June 1999 (1999-06-30) *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106869931A (en) * 2017-02-14 2017-06-20 广西高峰矿业有限责任公司 A kind of barren rock and cementing layering wedging mining with stowing technique and its structure
CN106869931B (en) * 2017-02-14 2019-09-20 广西高峰矿业有限责任公司 A kind of barren rock and cementing layering wedging mining with stowing technique and its structure
CN111550248A (en) * 2020-05-20 2020-08-18 长沙矿山研究院有限责任公司 Pre-roof-protecting sublevel open-stoping subsequent filling mining method
CN111550248B (en) * 2020-05-20 2021-06-01 长沙矿山研究院有限责任公司 Pre-roof-protecting sublevel open-stoping subsequent filling mining method
CN112012744A (en) * 2020-09-18 2020-12-01 陕西华源矿业有限责任公司 Comprehensive mechanized ore breaking layered filling mining method
CN114562268A (en) * 2022-02-23 2022-05-31 长沙矿山研究院有限责任公司 Partitioned unloading and sublevel filling mining method based on rhombic stoping structure

Also Published As

Publication number Publication date
CN103982185B (en) 2016-01-13

Similar Documents

Publication Publication Date Title
CN105041314B (en) A kind of combined mining method of deep afterwards rooming-slicing ore pillar
CN107339104B (en) Security personnel's curtain wall recovery method
CN108661646B (en) False roof pillar type shrinkage and post filling mining method
CN102619513B (en) Room and pillar type medium-length hole filling mining method using bottom ore withdrawal structures simultaneously arranged in original rock
CN104806244B (en) Filling mining method for slant middle-thick ore body
CN101737052B (en) Sublevel fill-mining method
CN101858217B (en) House pillar changeable panel upward demix filling mining method
CN102635356B (en) Medium-length hole mining method in multiple blasting free faces of high dipping thin veins
CN104481543B (en) Stage shrink caved stopes
CN102953732A (en) Room-and-pillar major-diameter longhole inverted-step-like segmented lateral caving subsequent filling mining method
CN102168579A (en) Rib-pillar-free continuous sublevel filling method for mining preparation in medium-thickness slope crushed ore body vein
CN111828007B (en) Stoping method for residual studs in underground mine goaf
CN102678121A (en) Layered top-controlling filling mining method for residual ores in deep hole in diskless area
CN103590831A (en) Novel mining method of gently-inclined thin and medium thickness ore bodies
CN101818643A (en) Stepped non-pillar continuous filling mining method for deep well super high large breaking ore body panel
CN102155228A (en) Fully-segmented presplitting squeezing primary-blasting mining method
CN104695960B (en) Air column becomes well back coming afterwards filling mining method
CN110295909A (en) Only stay mining methods under the obturation of tooth form ore pillar
CN103089267A (en) Thin-ore-body shallow hole shrinkage method without sill pillar
CN107165635A (en) A kind of oblique pinpoint blasting mining codes for slight slope and thin ore body
CN104453900A (en) Filling mining method of near-horizontal ore body
CN103982185B (en) Upright opening and lateral aperture work in coordination with the mechanization sublevel cut and fill method of back production
CN106640080A (en) Deep part high-stress environment self-stabilizing arched stope arrangement mining method
CN107503748A (en) A kind of overhand slicing mining methods of extremely thick big firm ore body
CN101725351A (en) Filling stope pillar recovery mining method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160113

Termination date: 20200611