CN103938649A - 一种超高层建筑空腔基础的施工方法 - Google Patents

一种超高层建筑空腔基础的施工方法 Download PDF

Info

Publication number
CN103938649A
CN103938649A CN201410117481.4A CN201410117481A CN103938649A CN 103938649 A CN103938649 A CN 103938649A CN 201410117481 A CN201410117481 A CN 201410117481A CN 103938649 A CN103938649 A CN 103938649A
Authority
CN
China
Prior art keywords
concrete
cavity
construction
reinforcing bar
conducted
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201410117481.4A
Other languages
English (en)
Other versions
CN103938649B (zh
Inventor
王生玉
马明国
程群
孔康伟
林贵顺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd
Original Assignee
Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd filed Critical Sixth Construction Co Ltd of China Construction Fourth Engineering Division Co Ltd
Priority to CN201410117481.4A priority Critical patent/CN103938649B/zh
Publication of CN103938649A publication Critical patent/CN103938649A/zh
Application granted granted Critical
Publication of CN103938649B publication Critical patent/CN103938649B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

本发明公开了一种超高层建筑电梯井基坑空腔基础的施工方法,采用对大体积混凝土四周放坡喷锚支护形式作为模板,通过运用槽钢垫在垫层上作为马镫支撑来保证来保证了钢筋骨架不变形,尺寸准确,并且对混凝土浇筑采用二次浇筑施工,第一次浇筑底层实心底板,第二次浇筑空腔结构。混凝土浇筑施工完成对其进行保温养护处理,防止表面温度散失过快,出现混凝土裂缝。采用空腔设计能够很好地减小混凝土有效截面积,从而控制温度裂缝的产生,同时结构自重轻、缩短了施工工期,节约了材料。

Description

一种超高层建筑空腔基础的施工方法
技术领域
本发明涉及建筑工程中基础工程技术领域,属于一种超高层建筑电梯井基坑空腔基础的施工方法。
背景技术
随着经济建设规模的迅速发展,现代建筑业向着高、大、深以及复杂结构方向拓展,其中常涉及到大体积混凝土,如高层建筑或大型设备基础,桩基础的超厚超大承台,水工结构等。它的主要特点是体积大,水泥水化热量大,极易引起混凝土由于内外部温度差超过25°C而开裂,影响结构的安全使用,延长施工工期。目前在现有技术中还没有什么理想的施工处理方法。
发明内容
本发明的目的在于提供一种承载力高,成本低的超高层建筑电梯井基坑空腔基础的施工方法,以解决建筑工程施工过程中大基础施工过程中的难题,从而确保施工安全和施工质量,及克服现有技术的不足。
本发明采用的技术方案:
一种超高层建筑空腔基础的施工方法,按以下步骤实施:
1、定位放线及垫层防水施工,采用对大体积混凝土四周放坡喷锚支护形式作为模板;
2、底层实心结构钢筋骨架支设;
3、底层实心结构钢筋绑扎,基础的底板钢筋直径大、层数多,且底板厚钢筋间间距大,底板钢筋支撑采用16号槽钢制作的马镫制作支撑,对于采用槽钢作为钢筋支架横梁和立柱时,横梁的间距和立柱的的间距设置3m一道,钢架立柱与钢梁采用焊接处理来增加整体性;
4、底层实心结构首次砼浇筑,浇筑方法采用“斜向分层,薄层浇筑,循序退浇,一次到底”连续施工的方法,采用斜面分段分层踏步式浇捣方法,分层厚度不大于500mm,坡度为1:8左右,分层浇捣使新混凝土沿斜坡流一次到顶,使混凝土充分散热,从而减少混凝土的热量,且混凝土振捣后产生的泌水沿浇灌混凝土斜坡排走,在第一次振捣之后20-30分钟进行第二次复振;
5、空腔结构钢筋马镫支设;
6、空腔结构钢筋绑扎;
7、空腔结构模板支设,对基础空腔内搭设满堂支撑架,立杆在搭设时纵横向的距离要均匀,立杆底部均应加设垫板,立杆接长采用对接扣件连接,对接接头交错布置,相邻立杆不得设置在同一位置,水平杆接长宜采用对接扣件连接或者采用搭接,对接扣件交错布置,模板支撑架水平杆在与已施工完成的墙体相遇时,需与墙体顶紧,每根水平杆与立杆交汇处必须用直角扣件扣紧,同时在空腔顶部预留500洞口作为模板材料传出口;
8、空腔结构砼浇筑,砼浇时,先对称浇筑空腔外墙部分,然后对称浇筑内墙及顶板,顶板砼浇筑时,应由中心向四周分层进行浇筑;
9、空腔结构砼养护,混凝土浇筑完毕后在砼结构表面满铺一层塑料薄膜,防止水分蒸发过快而使混凝土失水,再在薄膜上盖2层麻袋,最后在麻袋上载铺一层后薄膜,用于防止外部雨水淋湿麻袋。
与现有技术相比,本发明在无施工方法和经验借鉴的情况下,采用空腔基础施工方法,很好地解决了建筑工程中大体积混凝土施工工程中水化热大,裂缝控制难的难题。本发明技术简单,现场施工效率高,质量可靠,施工工期短,劳动力强度低,可安排劳动力同时进行施工;材料可于材料加工场内进行加工,现场可直接进行拼装工作,节省了工期;施工质量到达了设计要求。
附图说明
图1是本发明的结构示意图。
图2是本发明的施工工艺图。
图3是本发明的基础示意图。
附图标号为:1-钢管,2-槽钢,3-钢筋,4-止水钢板,5-混凝土,
6-桩,7-塑料薄膜,6-麻袋。
具体实施方式
下面结合附图对本发明作进一步的详细说明,但不作为对本发明的任何限制。
一种超高层建筑空腔基础的施工方法,按以下步骤实施:
1、定位放线及垫层防水施工,采用对大体积混凝土四周放坡喷锚支护形式作为模板;
2、底层实心结构钢筋骨架支设;
3、底层实心结构钢筋绑扎,基础的底板钢筋直径大、层数多,且底板厚钢筋间间距大,底板钢筋支撑采用16号槽钢制作的马镫制作支撑,对于采用槽钢作为钢筋支架横梁和立柱时,横梁的间距和立柱的的间距设置3m一道,钢架立柱与钢梁采用焊接处理来增加整体性;
4、底层实心结构首次砼浇筑,浇筑方法采用“斜向分层,薄层浇筑,循序退浇,一次到底”连续施工的方法,采用斜面分段分层踏步式浇捣方法,分层厚度不大于500mm,坡度为1:8左右,分层浇捣使新混凝土沿斜坡流一次到顶,使混凝土充分散热,从而减少混凝土的热量,且混凝土振捣后产生的泌水沿浇灌混凝土斜坡排走,在第一次振捣之后20-30分钟进行第二次复振;
5、空腔结构钢筋马镫支设;
6、空腔结构钢筋绑扎;
7、空腔结构模板支设,对基础空腔内搭设满堂支撑架,立杆在搭设时纵横向的距离要均匀,立杆底部均应加设垫板,立杆接长采用对接扣件连接,对接接头交错布置,相邻立杆不得设置在同一位置,水平杆接长宜采用对接扣件连接或者采用搭接,对接扣件交错布置,模板支撑架水平杆在与已施工完成的墙体相遇时,需与墙体顶紧,每根水平杆与立杆交汇处必须用直角扣件扣紧,同时在空腔顶部预留500洞口作为模板材料传出口;
8、空腔结构砼浇筑,砼浇时,先对称浇筑空腔外墙部分,然后对称浇筑内墙及顶板,顶板砼浇筑时,应由中心向四周分层进行浇筑;
9、空腔结构砼养护,混凝土浇筑完毕后在砼结构表面满铺一层塑料薄膜,防止水分蒸发过快而使混凝土失水,再在薄膜上盖2层麻袋,最后在麻袋上载铺一层后薄膜,用于防止外部雨水淋湿麻袋。

Claims (1)

1.一种超高层建筑空腔基础的施工方法,其特征在于,按以下步骤实施:
1、定位放线及垫层防水施工,采用对大体积混凝土四周放坡喷锚支护形式作为模板;
2、底层实心结构钢筋骨架支设;
3、底层实心结构钢筋绑扎,基础的底板钢筋直径大、层数多,且底板厚钢筋间间距大,底板钢筋支撑采用16号槽钢制作的马镫制作支撑,对于采用槽钢作为钢筋支架横梁和立柱时,横梁的间距和立柱的的间距设置3m一道,钢架立柱与钢梁采用焊接处理来增加整体性;
4、底层实心结构首次砼浇筑,浇筑方法采用“斜向分层,薄层浇筑,循序退浇,一次到底”连续施工的方法,采用斜面分段分层踏步式浇捣方法,分层厚度不大于500mm,坡度为1:8左右,分层浇捣使新混凝土沿斜坡流一次到顶,使混凝土充分散热,从而减少混凝土的热量,且混凝土振捣后产生的泌水沿浇灌混凝土斜坡排走,在第一次振捣之后20-30分钟进行第二次复振;
5、空腔结构钢筋马镫支设;
6、空腔结构钢筋绑扎;
7、空腔结构模板支设,对基础空腔内搭设满堂支撑架,立杆在搭设时纵横向的距离要均匀,立杆底部均应加设垫板,立杆接长采用对接扣件连接,对接接头交错布置,相邻立杆不得设置在同一位置,水平杆接长宜采用对接扣件连接或者采用搭接,对接扣件交错布置,模板支撑架水平杆在与已施工完成的墙体相遇时,需与墙体顶紧,每根水平杆与立杆交汇处必须用直角扣件扣紧,同时在空腔顶部预留500洞口作为模板材料传出口;
8、空腔结构砼浇筑,砼浇时,先对称浇筑空腔外墙部分,然后对称浇筑内墙及顶板,顶板砼浇筑时,应由中心向四周分层进行浇筑;
9、空腔结构砼养护,混凝土浇筑完毕后在砼结构表面满铺一层塑料薄膜,防止水分蒸发过快而使混凝土失水,再在薄膜上盖2层麻袋,最后在麻袋上载铺一层后薄膜,用于防止外部雨水淋湿麻袋。
CN201410117481.4A 2014-03-26 2014-03-26 一种超高层建筑空腔基础的施工方法 Active CN103938649B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410117481.4A CN103938649B (zh) 2014-03-26 2014-03-26 一种超高层建筑空腔基础的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410117481.4A CN103938649B (zh) 2014-03-26 2014-03-26 一种超高层建筑空腔基础的施工方法

Publications (2)

Publication Number Publication Date
CN103938649A true CN103938649A (zh) 2014-07-23
CN103938649B CN103938649B (zh) 2016-06-29

Family

ID=51186504

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410117481.4A Active CN103938649B (zh) 2014-03-26 2014-03-26 一种超高层建筑空腔基础的施工方法

Country Status (1)

Country Link
CN (1) CN103938649B (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105401580A (zh) * 2014-09-16 2016-03-16 天津二十冶建设有限公司 地下通廊混凝土浇筑施工方法
CN105625459A (zh) * 2016-03-01 2016-06-01 沈阳建筑大学 一种用混凝土槽浇筑的独立住宅一字形混凝土基础
CN106284355A (zh) * 2016-08-03 2017-01-04 中国航天建设集团有限公司 钢板预埋件封顶的大体积混凝土技术设施施工方法
CN109024685A (zh) * 2018-09-20 2018-12-18 北京建工国际投资有限责任公司 一种大体积混凝土底板钢筋支撑体系及其施工方法
CN113026802A (zh) * 2021-03-31 2021-06-25 中国中材国际工程股份有限公司 一种用于立式磨机的混凝土设备基础及其施工方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007002425A (ja) * 2005-06-21 2007-01-11 Hitachi Ltd 鉄筋コンクリート基礎、テンプレート架台及び鉄筋コンクリート基礎の構築方法
CN102359118A (zh) * 2011-08-02 2012-02-22 北京健安诚岩土工程有限公司 地下连续墙环形基础及其建造方法
CN102400469A (zh) * 2011-08-02 2012-04-04 北京健安诚岩土工程有限公司 咬合桩圆桶型基础及其建造方法
CN103321257A (zh) * 2013-06-18 2013-09-25 浙江海天建设集团有限公司 超长大体积混凝土结构地下室抗裂防渗施工方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2007002425A (ja) * 2005-06-21 2007-01-11 Hitachi Ltd 鉄筋コンクリート基礎、テンプレート架台及び鉄筋コンクリート基礎の構築方法
CN102359118A (zh) * 2011-08-02 2012-02-22 北京健安诚岩土工程有限公司 地下连续墙环形基础及其建造方法
CN102400469A (zh) * 2011-08-02 2012-04-04 北京健安诚岩土工程有限公司 咬合桩圆桶型基础及其建造方法
CN103321257A (zh) * 2013-06-18 2013-09-25 浙江海天建设集团有限公司 超长大体积混凝土结构地下室抗裂防渗施工方法

Non-Patent Citations (6)

* Cited by examiner, † Cited by third party
Title
刘新福等: "《岩溶隧道安全施工与灾害防治研究》", 31 January 2014, 中国铁道出版社 *
北京土木建筑学会: "《混凝土工程现场施工处理方法与技巧》", 31 March 2009, 机械工业出版社 *
北京城建集团: "《路桥、市政工程施工工艺标准》", 31 July 2004, 中国计划出版社 *
李继业等: "《脚手架基础知识与施工技术》", 31 March 2012, 中国建材工业出版社 *
焦桐善等: "《城市轨道交通首届中青年专家论坛文集》", 31 October 2002, 兵器工业出版社 *
王日丰: "特殊人工挖孔桩的设计和施工新探", 《铁道标准设计》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105401580A (zh) * 2014-09-16 2016-03-16 天津二十冶建设有限公司 地下通廊混凝土浇筑施工方法
CN105625459A (zh) * 2016-03-01 2016-06-01 沈阳建筑大学 一种用混凝土槽浇筑的独立住宅一字形混凝土基础
CN106284355A (zh) * 2016-08-03 2017-01-04 中国航天建设集团有限公司 钢板预埋件封顶的大体积混凝土技术设施施工方法
CN109024685A (zh) * 2018-09-20 2018-12-18 北京建工国际投资有限责任公司 一种大体积混凝土底板钢筋支撑体系及其施工方法
CN109024685B (zh) * 2018-09-20 2023-09-15 北京建工国际投资有限责任公司 一种大体积混凝土底板钢筋支撑体系及其施工方法
CN113026802A (zh) * 2021-03-31 2021-06-25 中国中材国际工程股份有限公司 一种用于立式磨机的混凝土设备基础及其施工方法
CN113026802B (zh) * 2021-03-31 2022-07-01 中国中材国际工程股份有限公司 一种用于立式磨机的混凝土设备基础及其施工方法

Also Published As

Publication number Publication date
CN103938649B (zh) 2016-06-29

Similar Documents

Publication Publication Date Title
CN103938649B (zh) 一种超高层建筑空腔基础的施工方法
CN105839836B (zh) 一种预制混凝土剪力墙构件及其施工方法
CN107724680A (zh) 一种高层建筑框架结构梁柱节点施工方法
CN108505805B (zh) 膨胀加强带控裂大型现浇水池及其施工方法
CN104405123B (zh) 现浇钢筋砼薄壁矩形小截面空心柱用模板组件及其施工方法
CN105178427B (zh) 房屋的一体成型建造方法
CN105178603A (zh) 一种eps聚苯免拆模板混凝土楼盖板施工工艺方法
CN105178244A (zh) 一种现浇防浪墙快速立模施工方法
CN101487293A (zh) 梁柱节点不同强度等级混凝土浇筑方法
CN104631677A (zh) 超厚混凝土空心地坪分次施工工艺
CN106351376B (zh) 车库顶板施工方法
CN206174120U (zh) 一种预制构造柱及其结构
CN105113706A (zh) 带保温层的钢筋桁架石膏板、新型免拆模板及施工方法
CN103061509B (zh) 以后浇带劲性钢管支撑体系实现后浇带浇筑的施工工艺
CN102535841A (zh) 一种预制墙板施工工艺
CN104532990A (zh) 桁架钢筋双层纤维石膏板、免拆模板墙体结构及施工方法
CN105201204B (zh) 一种防止浇筑钢筋混凝土柱柱脚时烂根的方法及结构
CN104164951A (zh) 楼梯休息平台及其施工方法
CN105926656B (zh) 大体积混凝土基础的施工方法
CN102605988B (zh) 烟囱内衬外砼同步施工方法
CN104947853B (zh) 一种内置支架式现浇钢筋混凝土柱子及施工方法
EP3006639B1 (en) Module for slabs and metho to make said module
CN211007647U (zh) 现浇钢筋混凝土水池底板支模体系
CN104234432B (zh) 车库顶板结构施工方法
CN212176547U (zh) 一种建筑物内楼层卫生间降板施工模板装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: 230000 building 3, 262 Heping Road, Yaohai District, Hefei City, Anhui Province

Patentee after: No 6 Construction Co.,Ltd. of China Construction Fourth Engineering Bureau

Address before: 230011 science and Technology Department of No.6 company of China Construction Fourth Bureau, Dongfang Building, intersection of Changjiang East Street and Mingguang Road, Yaohai District, Hefei City, Anhui Province

Patentee before: CHINA CONSTRUCTION 4TH ENGINEERING BUREAU, 6TH Co.,Ltd.

CP03 Change of name, title or address