CN104631677A - 超厚混凝土空心地坪分次施工工艺 - Google Patents

超厚混凝土空心地坪分次施工工艺 Download PDF

Info

Publication number
CN104631677A
CN104631677A CN201510029398.6A CN201510029398A CN104631677A CN 104631677 A CN104631677 A CN 104631677A CN 201510029398 A CN201510029398 A CN 201510029398A CN 104631677 A CN104631677 A CN 104631677A
Authority
CN
China
Prior art keywords
concrete
girt strip
floor
mould
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201510029398.6A
Other languages
English (en)
Other versions
CN104631677B (zh
Inventor
黄健
廖志钻
陈春光
罗伟坤
龚成文
胡进福
郑超选
戴伟权
肖金水
洪派钦
李易谦
叶波
官海斌
吴多跃
洪宏鉴
林培
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Construction Engineering Group Co Ltd
Original Assignee
Guangdong Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Construction Engineering Group Co Ltd filed Critical Guangdong Construction Engineering Group Co Ltd
Priority to CN201510029398.6A priority Critical patent/CN104631677B/zh
Publication of CN104631677A publication Critical patent/CN104631677A/zh
Application granted granted Critical
Publication of CN104631677B publication Critical patent/CN104631677B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

本发明提出一种超厚混凝土空心地坪分次施工工艺,包括步骤1)砖模与垫层施工;2)底板及肋梁钢筋绑扎安装;3)浇筑底板混凝土;4)箱模安装及预压;5)楼板上部钢筋绑扎安装;6)肋梁及面板混凝土浇筑养护;实质性特点在于:步骤5)中楼板上部钢筋绑扎完毕后,在每个箱模顶和楼板上部钢筋之间加设垫块,压住箱模,并在每个箱模四角,用拉筋将箱模与楼板上部钢筋及肋梁底筋拉结,确保内模不移位;本发明的实质性特点是将地坪混凝土分两次浇筑,通过首次浇筑的混凝土底板与肋梁钢筋骨架有效结合,将超厚地坪空心内模浮力转移到已与底板混凝土牢固结合的肋梁上,取消了专用抗浮锚固钢筋施工,简化了施工工序,节省了材料,施工质量容易保证。

Description

超厚混凝土空心地坪分次施工工艺
技术领域
    本发明涉及混凝土空心地坪施工技术。
背景技术
近年来新开发的现浇混凝土空心楼盖,可广泛适用于大跨度、大空间、大荷载的建筑中。现浇混凝土空心楼板是采用轻质填充体为内模,永久填埋于现浇混凝土楼板中,置换部分混凝土以达到减轻结构自重的楼板类型。该技术对节能减材、提高经济效益有着明显的效果。
与普通梁板结构相比较,空心楼盖有以下几个优势:
1、保温隔音效果好,节能环保;
2、减少材料量,节省材料,降低综合造价;
3、减轻结构自重。
但是将空心板引入地坪施工在国内尚不多见,由于空心板地坪尤其是超厚地坪施工时存在梁柱节点施工复杂、抗浮措施困难、混凝土浇筑时空心内模易移位等问题,在推广应用中受到较大限制。
空心板地坪施工是由于混凝土比重大,浇筑期间对空心内模产生较大浮力,而地坪下面为垫层,无法像楼板一样采取下拉的抗浮措施,通常的思路是考虑锚入承台的大直径抗浮钢筋固定内模,施工工艺复杂且效果难以保证;此外空心内模在混凝土浇筑期间容易移位倾侧,混凝土板的厚度和钢筋位置难以保证。
发明内容
本发明的目的是提出一种超厚混凝土空心地坪分次施工工艺,其可避免了混凝土浇筑期间空心内模移位侧倾问题并实现了空心板体系的自平衡,保证了抗浮效果,同时避免空心内模的扰动,保证了施工效果。
本发明的目的可通过如下技术方案来实现。
超厚混凝土空心地坪分次施工工艺,包括如下步骤:
(1) 砖模与垫层施工
砖模砌筑,垫层施工且标高满足设计要求,并按设计图纸完成主梁、肋梁的定位放线。
(2) 底板及肋梁钢筋绑扎安装
按设计图,依主梁、肋梁、底板的顺序安装绑扎钢筋,钢筋绑扎完毕后,按每米设两个垫块保证钢筋保护层满足要求。
(3)底板混凝土浇筑
浇筑底板混凝土,混凝土面标高应与内模底面标高相等,有高低差的空心板,在交接处设置收口网;浇筑混凝土时避免混凝土过量导致内模无法放置。
(4)箱模安装及预压
底板混凝土浇筑完毕后,按照布箱图,在每个肋梁空格内依次摆放箱模,在混凝土终凝前对箱模进行预压。
(5)楼板上部钢筋绑扎安装
箱模安放完成后,即可开始绑扎楼板上部钢筋,楼板上部钢筋应与肋梁上部钢筋位于同一层,并与肋梁钢筋绑扎牢固;
楼板上部钢筋绑扎完毕后,在每个箱模顶和楼板上部钢筋之间加设垫块,压住箱模,并保证箱模上部混凝土厚度,如果成品箱模已设置隔离筋,则可不用再增加垫块;
在每个箱模四角,用拉筋将箱模与楼板上部钢筋及肋梁底筋拉结,确保内模不移位。
(6)肋梁及面板混凝土浇筑养护
在肋梁及面板混凝土浇筑前,先将垫层、箱模浇水湿透;
浇筑肋梁及面板混凝土,浇筑沿楼板跨度方向从一侧开始,顺序依次进行,布料尽量均匀,避免砼在同一位置堆积过高损坏箱模;
用振捣棒沿肋梁位置顺浇筑方向依次振捣,振捣时间较普通楼板长,确保混凝土密实;在混凝土浇筑后,及时对混凝土进行养护,养护时间不少于7天。
本发明具有如下突出的实质性特点和显著的进步。
1.本发明结合超厚地坪施工难点和设计要点,将地坪混凝土分两次浇筑,通过首次浇筑的混凝土底板与肋梁钢筋骨架有效结合,将超厚地坪空心内模浮力转移到已与底板混凝土牢固结合的肋梁上,取消了专用抗浮锚固钢筋施工,简化了施工工序,节省了材料,施工质量容易保证。
2.本发明将空心内模(模箱)在底板混凝土浇筑后初凝前放置并通过预压措施,避免了空心内模(模箱)在二次混凝土浇筑时移位、标高难以准确控制等质量通病。
附图说明
图1—5为本发的施工流程示意图。
图6为本发明空心地坪结构示意图。
具体实施方式
 下面用一具体实施例对本发明作进一步说明:
参考图1—6,本发明提出一种超厚混凝土空心地坪分次施工工艺,包括如下步骤:
(1) 砖模与垫层施工
砖模砌筑,垫层施工且标高满足设计要求,并按设计图纸完成主梁、肋梁的定位放线。
(2) 底板及肋梁钢筋绑扎安装
按设计图,依顺序安装绑扎主梁钢筋(图中未示)、肋梁钢筋2和底板钢筋1(如图1),绑扎箍筋时,应确保箍筋与纵向受力筋垂直;绑扎钢筋时,应控制肋梁网格不移位,确保网格尺寸;绑扎完毕后,按每米设两个垫块保证钢筋保护层满足要求。
(3)浇筑底板混凝土
浇筑底板混凝土3,混凝土面标高应与内模底面标高相等,有高低差的空心板,在交接处设置收口网;浇筑混凝土时避免混凝土过量导致内模无法放置,浇筑后的底板如图2和图6所示。
(4)内模安装及预压
底板混凝土3浇筑完毕后,按照布箱图,在每个肋梁空格内依次摆放箱模4(如图3),箱模放置平整,前后左右对齐、对正;在底板混凝土3终凝前对箱模4进行预压,控制预压力度,以模箱4边缘混凝土不向外凸出为限。
(5)楼板上部钢筋绑扎安装
空心箱模4安放完成后,即可开始绑扎楼板上部钢筋5,楼板上部钢筋5应与肋梁上部钢筋位于同一层,并与肋梁钢筋绑扎牢固(如图4);为保证抗浮点的有效,将楼板上部钢筋5要压在肋梁上部钢筋下或专门设置上部钢筋抗浮点与下层钢筋抗浮点对应连接;
楼板上部钢筋5绑扎完毕后,在每个空心箱模4顶和楼板上部钢筋5之间加设垫块6(如图4),压住箱模4,并保证箱模4上部混凝土厚度,如果成品模箱已设置隔离筋,则可不用再增加垫块;
在每个模箱四角,用直径为6mm 的拉筋(图中未示)将箱模4与楼板上部钢筋5及肋梁底筋2拉结,确保模箱4不移位。
(6)肋梁及面板混凝土浇筑、养护
肋梁及面板混凝土骨料碎石粒径为16~20,不超过25,混凝土拌合物的坍落度不小于150mm;
在肋梁及面板混凝土浇筑前,先将垫层6、箱模4浇水湿透;
沿楼板跨度方向从一侧开始,顺序依次进行肋梁混凝土7及面板混凝土8浇筑,布料尽量均匀,避免砼在同一位置堆积过高损坏箱模;
用振捣棒沿肋梁位置顺浇筑方向依次振捣;适当加大振捣时间和振捣点数量;振捣同时观察空心箱模4四周,直至不再有气泡冒出,表示箱模4底部混凝土已密实;振捣棒应避免直接触碰空心箱模;振捣时振捣器应避免触碰内模、钢筋、定位马凳;混凝土振捣时采用50及30棒配合使用,对较小的肋梁应采用30棒振捣,面板混凝土8可采用平板振动器振捣,振捣时间应较普通楼板适当延长,确保混凝土密实;浇筑后的肋梁和面板如图5所示。
在肋梁及面板混凝土浇筑后,及时对混凝土进行养护,优先采用薄膜覆盖养护,养护时间不少于7天,浇筑养护后的底板10、肋梁20和面板50如图6所示。

Claims (1)

1.超厚混凝土空心地坪分次施工工艺,包括如下步骤:
(1)砖模与垫层施工
砖模砌筑,垫层施工且标高满足设计要求,并按设计图纸完成主梁、肋梁的定位放线;
(2)底板及肋梁钢筋绑扎安装
按设计图,依主梁、肋梁、底板的顺序安装绑扎钢筋,钢筋绑扎完毕后,按每米设两个垫块保证钢筋保护层满足要求;
(3)浇筑底板混凝土
浇筑底板混凝土,混凝土面标高应与内模底面标高相等,有高低差的空心板,在交接处设置收口网;浇筑混凝土时避免混凝土过量导致内模无法放置;
(4)箱模安装及预压
底板混凝土浇筑完毕后,按照布箱图,在每个肋梁空格内依次摆放箱模,在混凝土终凝前对箱模进行预压;
(5)楼板上部钢筋绑扎安装
箱模安放完成后,开始绑扎楼板上部钢筋,楼板上部钢筋应与肋梁上部钢筋位于同一层,并与肋梁钢筋绑扎牢固;
楼板上部钢筋绑扎完毕后,在每个箱模顶和楼板上部钢筋之间加设垫块,压住箱模,并保证箱模上部混凝土厚度,如果成品箱模已设置隔离筋,则可不用再增加垫块;
在每个箱模四角,用拉筋将箱模与楼板上部钢筋及肋梁底筋拉结,确保内模不移位;
(6)肋梁及面板混凝土浇筑养护
在混凝土浇筑前,先将垫层、箱模浇水湿透;
浇筑肋梁及面板混凝土,浇筑沿楼板跨度方向从一侧开始,顺序依次进行,布料尽量均匀,避免砼在同一位置堆积过高损坏箱模;
用振捣棒沿肋梁位置顺浇筑方向依次振捣,振捣时间较普通楼板长,确保混凝土密实;在混凝土浇筑后,及时对混凝土进行养护,养护时间不少于7天。
CN201510029398.6A 2015-01-21 2015-01-21 超厚混凝土空心地坪分次施工工艺 Active CN104631677B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201510029398.6A CN104631677B (zh) 2015-01-21 2015-01-21 超厚混凝土空心地坪分次施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201510029398.6A CN104631677B (zh) 2015-01-21 2015-01-21 超厚混凝土空心地坪分次施工工艺

Publications (2)

Publication Number Publication Date
CN104631677A true CN104631677A (zh) 2015-05-20
CN104631677B CN104631677B (zh) 2017-04-05

Family

ID=53210872

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201510029398.6A Active CN104631677B (zh) 2015-01-21 2015-01-21 超厚混凝土空心地坪分次施工工艺

Country Status (1)

Country Link
CN (1) CN104631677B (zh)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105908883A (zh) * 2016-06-12 2016-08-31 中国十七冶集团有限公司 一种防止复合楼盖轻质芯模上浮的施工方法
CN106836597A (zh) * 2017-03-21 2017-06-13 中国航空规划设计研究总院有限公司 一种空心楼板芯模固定装置及其施工方法
CN106939663A (zh) * 2017-05-04 2017-07-11 广东省第四建筑工程有限公司 一种混凝土空心双层楼板及其施工方法
CN107165320A (zh) * 2016-03-07 2017-09-15 王清 一种用于现浇空心楼盖内置填充的特种收口网状箱形空腔构件
CN108756034A (zh) * 2018-05-11 2018-11-06 中冶建工集团有限公司 架空结构地坪及其施工方法
CN113367121A (zh) * 2021-05-18 2021-09-10 戴伟权 一种具有防泄漏密封功能的体液储存装置
CN113481960A (zh) * 2021-07-26 2021-10-08 苏交科集团股份有限公司 一种高填方场地地坪沉降处理方法及处理结构
CN114351926A (zh) * 2022-03-21 2022-04-15 中铁九局集团第四工程有限公司 一种金属方箱现浇混凝土空心楼板抗浮施工工法

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108222350A (zh) * 2017-12-28 2018-06-29 上海二十冶建设有限公司 一种地下室现浇空心楼盖钢网箱体施工工艺

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040237439A1 (en) * 2003-05-02 2004-12-02 Powell David W. Method and system for prefabricated construction
CN103388402A (zh) * 2013-08-16 2013-11-13 中国建筑第八工程局有限公司 密肋梁空腹楼板施工方法
CN103397729A (zh) * 2013-07-19 2013-11-20 中建五局第三建设有限公司 Nz内模抗浮施工方法
CN103590602A (zh) * 2013-10-22 2014-02-19 重庆建工第三建设有限责任公司 现浇混凝土空心楼盖的施工方法
CN103806656A (zh) * 2012-11-06 2014-05-21 南通卓强建设工程有限公司 现浇混凝土无梁板内置薄壁空心盒体的施工方法
CN103924784A (zh) * 2014-04-17 2014-07-16 中国建筑第二工程局有限公司 一种无密肋梁空心板抗浮侧移施工方法

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20040237439A1 (en) * 2003-05-02 2004-12-02 Powell David W. Method and system for prefabricated construction
CN103806656A (zh) * 2012-11-06 2014-05-21 南通卓强建设工程有限公司 现浇混凝土无梁板内置薄壁空心盒体的施工方法
CN103397729A (zh) * 2013-07-19 2013-11-20 中建五局第三建设有限公司 Nz内模抗浮施工方法
CN103388402A (zh) * 2013-08-16 2013-11-13 中国建筑第八工程局有限公司 密肋梁空腹楼板施工方法
CN103590602A (zh) * 2013-10-22 2014-02-19 重庆建工第三建设有限责任公司 现浇混凝土空心楼盖的施工方法
CN103924784A (zh) * 2014-04-17 2014-07-16 中国建筑第二工程局有限公司 一种无密肋梁空心板抗浮侧移施工方法

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107165320A (zh) * 2016-03-07 2017-09-15 王清 一种用于现浇空心楼盖内置填充的特种收口网状箱形空腔构件
CN105908883A (zh) * 2016-06-12 2016-08-31 中国十七冶集团有限公司 一种防止复合楼盖轻质芯模上浮的施工方法
CN106836597A (zh) * 2017-03-21 2017-06-13 中国航空规划设计研究总院有限公司 一种空心楼板芯模固定装置及其施工方法
CN106836597B (zh) * 2017-03-21 2019-02-26 中国航空规划设计研究总院有限公司 一种空心楼板芯模固定装置及其施工方法
CN106939663A (zh) * 2017-05-04 2017-07-11 广东省第四建筑工程有限公司 一种混凝土空心双层楼板及其施工方法
CN108756034A (zh) * 2018-05-11 2018-11-06 中冶建工集团有限公司 架空结构地坪及其施工方法
CN113367121A (zh) * 2021-05-18 2021-09-10 戴伟权 一种具有防泄漏密封功能的体液储存装置
CN113481960A (zh) * 2021-07-26 2021-10-08 苏交科集团股份有限公司 一种高填方场地地坪沉降处理方法及处理结构
CN114351926A (zh) * 2022-03-21 2022-04-15 中铁九局集团第四工程有限公司 一种金属方箱现浇混凝土空心楼板抗浮施工工法

Also Published As

Publication number Publication date
CN104631677B (zh) 2017-04-05

Similar Documents

Publication Publication Date Title
CN104631677A (zh) 超厚混凝土空心地坪分次施工工艺
CN105317137B (zh) 预制墙体、墙板及其施工方法以及预制墙板生产方法
CN106592426B (zh) 横向预应力全宽钢筋混凝土桥面板预制模板体系的施工方法
CN107268878B (zh) 预制夹芯墙板的制作安装方法
CN201649459U (zh) 坡屋面现浇混凝土结构
CN105133768A (zh) 一种采用大截面bdf箱体的现浇空心楼板及其施工方法
CN205669281U (zh) 一种现浇整体式混凝土框架填充墙体系
CN104295003A (zh) 一种构造柱施工方法
CN103046465A (zh) 一种泡沫芯模预制空心板梁的加固施工方法
CN104532990A (zh) 桁架钢筋双层纤维石膏板、免拆模板墙体结构及施工方法
CN108638322B (zh) 一种装配式建筑中预制柱混凝土浇筑方法
CN110374234A (zh) 一种装配式墙体与建筑框架的空腔节点结构及施工方法
CN105064500A (zh) 一种阳台梁板内侧填充墙体与主体结构整体浇筑施工方法
CN204435616U (zh) 桁架钢筋双层纤维石膏板、免拆模板墙体结构
CN109630364B (zh) 风力发电机组的风机基础及其制造方法、风力发电机组
CN207919848U (zh) 地下车库顶板用塑料模盒组合装置
CN113059685B (zh) 一种预制梁施工系统及施工方法
CN205224044U (zh) 一种钢衬底板混凝土浇筑装置
CN112411560A (zh) 一种深大基坑内支撑体系梁板结构分步快速施工方法
CN211200460U (zh) 装配整体式地下空间基础构件
CN104234432B (zh) 车库顶板结构施工方法
CN206477251U (zh) 横向预应力全宽钢筋混凝土桥面板预制模板体系
CN110748221A (zh) 一种预制装配式水池导流墙
CN115262916B (zh) 一种房建地板结构、地板成型工艺及其顶升装置
CN104912189A (zh) 配筋砌块框架结构及其施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant