CN104295003A - 一种构造柱施工方法 - Google Patents

一种构造柱施工方法 Download PDF

Info

Publication number
CN104295003A
CN104295003A CN201410499085.2A CN201410499085A CN104295003A CN 104295003 A CN104295003 A CN 104295003A CN 201410499085 A CN201410499085 A CN 201410499085A CN 104295003 A CN104295003 A CN 104295003A
Authority
CN
China
Prior art keywords
concrete
column
constructional
structural column
constructional column
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410499085.2A
Other languages
English (en)
Inventor
游靓
游兴荣
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Original Assignee
Second Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd filed Critical Second Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Priority to CN201410499085.2A priority Critical patent/CN104295003A/zh
Publication of CN104295003A publication Critical patent/CN104295003A/zh
Pending legal-status Critical Current

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

本发明公开了一种构造柱施工方法。该方法包括以下步骤:1)将钢筋框架柱或剪力墙钢筋与构造柱钢筋同时绑扎;2)将泡沫板固定在构造柱钢筋的底部;3)支设模板;4)构造柱混凝土与梁板柱混凝土一起浇筑;5)在砌墙之前将构造柱底部的泡沫凿去,用细石混凝土对构造柱底部进行填充;6)混凝土填充完毕,进行砌体拉结钢筋植筋并做拉拨试验。本发明有效地克服了传统方法施工中遇到的种种困难,而且还具有能保证工程质量。不出现二次施工、将施工最困难的二次结构与主体结构同步完成,该方法降低工人劳动强度、提高工效、不浪费材料的优点。适用于多层、框剪结构等工程构造柱较多的地方。

Description

一种构造柱施工方法
 
技术领域
本发明涉及建筑施工方法,尤其涉及一种构造柱施工方法。
背景技术
为提高多层建筑砌体结构的抗震性能,规范要求应在房屋的砌体内适宜部位设置钢筋混凝土柱并与圈梁连接,共同加强建筑物的稳定性。这种钢筋混凝土柱通常就被称为构造柱。构造柱主要不是承担竖向荷载的,而是抗击剪力、抗震等横向荷载的。
根据国家标准《砌体结构设计规范》第2.1.14条规定:在多层砌体房屋墙体的规定部位,按构造配筋,并按先砌墙后浇灌混凝土柱的施工顺序制成的混凝土柱,通常称为混凝土构造柱,简称构造柱。
以上条文规定了构造柱是先砌筑砖墙后浇筑混凝土,而且在一般情况下构造柱是不允许与主体混凝土一起浇筑的,这就存在以下问题:
1)钢筋绑扎困难。由于是先绑扎构造柱钢筋,待砖墙砌筑好之后,直接插上。因为要与下层预留构造柱主筋连接就存在着搭接,搭接长度的钢筋就浪费了。
2)由于先砌筑砖墙,后绑扎钢筋、支设模板、浇筑混凝土。就导致在构造柱顶部约200mm的混凝土是不密实的,同时浇筑构造柱混凝土比较麻烦,因为振捣棒无法插入,仅仅在模板外部进行振捣,混凝土密实度控制不好,拆模后出现大量的蜂窝、麻面,甚至漏筋的现象,不仅费工,而且混凝土质量无法保证。
3)现在比较成熟的构造柱做法是在构造柱上部约200mm处,将模板支成为楔形,在浇筑混凝土完毕,将多余的混凝土凿去。这样虽然比传统方法在质量上有保障,但存在着浪费混凝土,浪费人工的问题。
4)为了避免上述问题,有些施工队将构造柱按照框架柱进行施工,在浇筑混凝土时,将构造柱与梁板柱混凝土一起浇筑,以为这样既满足施工需要,又节省了人工,其实存在着重大安全隐患。因为设计时,构造柱不是作为支撑支座进行计算的,现将构造柱按框架柱进行施工,整个楼板的支撑体系就改变了,有些钢筋不是按照设计受力,在现场是绝对禁止的,有些甚至都要下令停工。
发明内容
本发明要解决的技术问题是提供一种构造柱施工方法。
为了解决上述技术问题,本发明采用的技术方案是,一种构造柱施工方法,包括以下步骤:
(1)绑扎框架柱或剪力墙钢筋时,同时将构造柱钢筋绑扎完毕;避免构造柱钢筋插入时与下层钢筋的搭接现象,减少钢筋使用量,不存在二次施工,降低了工人的劳动强度;
(2)在距离构造柱钢筋底部约100mm处焊接固定点,将泡沫板固定在固定点上;
(3)支设模板,按照正常的施工工序,构造柱钢筋绑扎完毕,将模板支设完毕,即进行加固;
(4)在浇筑梁板柱混凝土时,将构造柱混凝土与梁板柱混凝土一起浇筑,振捣密实,不会出现漏振;
(5)在砌墙之前将构造柱底部的泡沫凿去,然后用高一强度等级的细石混凝土对底部进行填充;
(6)混凝土填充完毕,按照砌体规范要求,每500mm高进行植筋,做拉拨试验,试验完成后就可继续砌筑工程的施工。
本发明的有益效果是:
采用本发明施工方法的构造柱,有效地克服了工程中遇到的种种困难,而且还具有能保证工程质量。不出现二次施工、将施工最困难的二次结构与主体结构同步完成,该方法降低工人劳动强度、提高工效、不浪费材料的优点。适用于多层、框剪结构等工程构造柱较多的地方。
具体实施方式
一种构造柱施工方法,包括以下步骤:
(1)绑扎框架柱或剪力墙钢筋时,同时将构造柱钢筋绑扎完毕;避免构造柱钢筋插入时与下层钢筋的搭接现象,减少钢筋使用量,不存在二次施工,降低了工人的劳动强度;
(2)在距离构造柱钢筋底部约100mm处焊接固定点,将泡沫板固定在固定点上;
(3)支设模板,按照正常的施工工序,构造柱钢筋绑扎完毕,将模板支设完毕,即进行加固;
(4)在浇筑梁板柱混凝土时,将构造柱混凝土与梁板柱混凝土一起浇筑,振捣密实,不会出现漏振;
(5)在砌墙之前将构造柱底部的泡沫凿去,然后用高一强度等级的细石混凝土对底部进行填充;
(6)混凝土填充完毕,按照砌体规范要求,每500mm高进行植筋,做拉拨试验,试验完成后就可继续砌筑工程的施工。
以上所述的本发明实施方式,并不构成对本发明保护范围的限定。任何在本发明的精神和原则之内所作的修改、等同替换和改进等,均应包含在本发明的权利要求保护范围之内。

Claims (3)

1.一种构造柱施工方法,其特征在于包括以下步骤:
(1)绑扎框架柱或剪力墙钢筋时,同时将构造柱钢筋绑扎完毕; 
(2)在构造柱钢筋的底部设置固定点,通过固定点将泡沫板固定在构造柱钢筋的底部;
(3)支设模板,按照正常的施工工序,构造柱钢筋绑扎完毕,将模板支设完毕,即进行加固;
(4)在浇筑梁板柱混凝土时,将构造柱混凝土与梁板柱混凝土一起浇筑,并振捣密实;
(5)在砌墙之前将构造柱底部的泡沫凿去,然后用高一强度等级的细石混凝土对构造柱底部进行填充;
(6)混凝土填充完毕,按照砌体规范要求,在间隔设定的高度进行植筋,做拉拨试验,试验完成后就可继续砌筑工程的施工。
2.根据权利要求1所述的构造柱施工方法,其特征在于:步骤(2)中是将固定点焊接在距离构造柱钢筋底部100mm处。
3. 根据权利要求1所述的构造柱施工方法,其特征在于:步骤(6)中所述设定的高度为500mm。
CN201410499085.2A 2014-09-26 2014-09-26 一种构造柱施工方法 Pending CN104295003A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410499085.2A CN104295003A (zh) 2014-09-26 2014-09-26 一种构造柱施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410499085.2A CN104295003A (zh) 2014-09-26 2014-09-26 一种构造柱施工方法

Publications (1)

Publication Number Publication Date
CN104295003A true CN104295003A (zh) 2015-01-21

Family

ID=52314927

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410499085.2A Pending CN104295003A (zh) 2014-09-26 2014-09-26 一种构造柱施工方法

Country Status (1)

Country Link
CN (1) CN104295003A (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104878853A (zh) * 2015-04-02 2015-09-02 中国十七冶集团有限公司 砌筑墙体与混凝土结构交接面处拉结筋设置方法
CN105525753A (zh) * 2015-06-05 2016-04-27 中建四局第一建筑工程有限公司 一种构造柱与主体结构同时施工的方法及结构
CN105604339A (zh) * 2015-12-22 2016-05-25 中国一冶集团有限公司 二次结构构造柱加固方法
CN107675871A (zh) * 2017-07-25 2018-02-09 浙江省建工集团有限责任公司 一种在建高层大跨度外架连墙件施工方法
CN109162363A (zh) * 2018-06-19 2019-01-08 浙江省建工集团有限责任公司 一种加快高大结构砌体工程进度及整体稳定性的结构及其工艺
CN113565263A (zh) * 2021-07-23 2021-10-29 华北冶建工程建设有限公司 构造柱施工方法
CN114809769A (zh) * 2022-05-18 2022-07-29 龙元建设集团股份有限公司 提升砌体结构填充墙施工速度的方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09268648A (ja) * 1996-03-27 1997-10-14 Riyoukan Consultant:Kk 鉄骨鉄筋コンクリート造柱と大梁及びその構築方法と軸組
CN201581648U (zh) * 2009-12-24 2010-09-15 上海市第七建筑有限公司 一种钢筋混凝土柱预留插筋结构
CN102518258A (zh) * 2011-12-26 2012-06-27 北京工业大学 格构式单排配筋t形截面混凝土柱及作法
CN102936964A (zh) * 2012-11-04 2013-02-20 西安建筑科技大学 一种高延性混凝土嵌入式构造柱的施工方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09268648A (ja) * 1996-03-27 1997-10-14 Riyoukan Consultant:Kk 鉄骨鉄筋コンクリート造柱と大梁及びその構築方法と軸組
CN201581648U (zh) * 2009-12-24 2010-09-15 上海市第七建筑有限公司 一种钢筋混凝土柱预留插筋结构
CN102518258A (zh) * 2011-12-26 2012-06-27 北京工业大学 格构式单排配筋t形截面混凝土柱及作法
CN102936964A (zh) * 2012-11-04 2013-02-20 西安建筑科技大学 一种高延性混凝土嵌入式构造柱的施工方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
王淮北: "构造柱施工工艺的改进", 《建筑工人》, no. 2, 15 February 2014 (2014-02-15) *

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104878853A (zh) * 2015-04-02 2015-09-02 中国十七冶集团有限公司 砌筑墙体与混凝土结构交接面处拉结筋设置方法
CN105525753A (zh) * 2015-06-05 2016-04-27 中建四局第一建筑工程有限公司 一种构造柱与主体结构同时施工的方法及结构
CN105604339A (zh) * 2015-12-22 2016-05-25 中国一冶集团有限公司 二次结构构造柱加固方法
CN105604339B (zh) * 2015-12-22 2017-12-15 中国一冶集团有限公司 二次结构构造柱加固方法
CN107675871A (zh) * 2017-07-25 2018-02-09 浙江省建工集团有限责任公司 一种在建高层大跨度外架连墙件施工方法
CN109162363A (zh) * 2018-06-19 2019-01-08 浙江省建工集团有限责任公司 一种加快高大结构砌体工程进度及整体稳定性的结构及其工艺
CN113565263A (zh) * 2021-07-23 2021-10-29 华北冶建工程建设有限公司 构造柱施工方法
CN114809769A (zh) * 2022-05-18 2022-07-29 龙元建设集团股份有限公司 提升砌体结构填充墙施工速度的方法

Similar Documents

Publication Publication Date Title
CN104295003A (zh) 一种构造柱施工方法
CN104895092B (zh) 一种内支撑临时格构柱用作永久结构柱的方法
CN102383628B (zh) 筒仓结构后施工减压锥的施工装置及施工方法
CN108035438A (zh) 一种高强高延性混凝土装配式框架结构体系及连接方法
CN103410317A (zh) 采用墙体预制构件现场拼装并浇筑的整体墙体施工方法
CN110777983A (zh) 一种混凝土填充墙与现浇结构同步施工结构及方法
CN103953114B (zh) 钢框架-配筋砌体剪力墙组合结构及其施工方法
CN105525753A (zh) 一种构造柱与主体结构同时施工的方法及结构
CN205421616U (zh) 具有钢管砼边缘构件的装配整体式剪力墙
CN103603359A (zh) 一种深基坑斜撑支护结构拆除方法
CN101487293A (zh) 梁柱节点不同强度等级混凝土浇筑方法
CN106320704A (zh) 型钢混凝土结构模板套筒螺杆拉结施工方法
CN103088830A (zh) 超深地下室复合外墙结构的施工方法
CN111218983A (zh) 一种格构式结构混凝土框架房屋
CN104929047A (zh) 一种v型墩外支撑施工方法
CN207919747U (zh) 一种高强高延性混凝土装配式框架结构体系
CN108625531A (zh) 一种浇筑构造柱混凝土免拆模板的施工方法
CN103696437A (zh) 一种切割格构柱的施工方法
CN207110214U (zh) 一种预制内填充混凝土墙板
CN211499326U (zh) 一种混凝土填充墙与现浇结构同步施工结构
CN108775086A (zh) 附加闭合连接钢筋的装配整体式梁柱节点结构及施工方法
CN204715764U (zh) 一种构造柱与主体结构同时施工的结构
CN101929245A (zh) 薄腹梁立式施工方法
CN108755938B (zh) 一种装配式混凝土框架的钢核心区节点
CN106193120A (zh) 地下室悬挑底板逆作结构及施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150121