CN105908883A - 一种防止复合楼盖轻质芯模上浮的施工方法 - Google Patents
一种防止复合楼盖轻质芯模上浮的施工方法 Download PDFInfo
- Publication number
- CN105908883A CN105908883A CN201610406507.6A CN201610406507A CN105908883A CN 105908883 A CN105908883 A CN 105908883A CN 201610406507 A CN201610406507 A CN 201610406507A CN 105908883 A CN105908883 A CN 105908883A
- Authority
- CN
- China
- Prior art keywords
- concrete
- construction
- core
- construction method
- composite floor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/16—Load-carrying floor structures wholly or partly cast or similarly formed in situ
- E04B5/32—Floor structures wholly cast in situ with or without form units or reinforcements
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/16—Load-carrying floor structures wholly or partly cast or similarly formed in situ
- E04B5/32—Floor structures wholly cast in situ with or without form units or reinforcements
- E04B5/36—Floor structures wholly cast in situ with or without form units or reinforcements with form units as part of the floor
Abstract
本发明公开了一种防止复合楼盖施工中芯模上浮的施工方法,其施工步骤为:在复合楼盖板底钢筋和肋梁钢筋绑扎及预埋管线安装完成后,进行隐蔽工程验收,然后浇筑第一层混凝土;待第一层混凝土振捣完成后立即进行芯模安装;板面钢筋绑扎;待隐蔽工程验收合格后浇筑第二层混凝土。浇筑完成后对混凝土表面进行收光、压实处理。上述防止复合楼盖施工中轻质芯模上浮的施工方法工序简单,无需额外的芯模固定工序,能有效解决芯模上浮、底板蜂窝、麻面及漏筋等问题,提高施工效率,保证现浇混凝土复合楼盖施工质量满足国家相关规范及设计要求。
Description
技术领域
本发明涉及一种建筑施工方法,更具体的说,是涉及一种防止复合楼盖轻质芯模上浮的施工方法。
背景技术
随着建筑行业的高速发展,现浇混凝土复合楼盖技术日趋成熟。但其中仍存在一些质量通病,如混凝土浇筑产生的浮力引起的轻质芯模上浮问题及芯模下部混凝土振捣不实引起的板底蜂窝、麻面、漏筋等问题。现有复合楼盖芯模抗浮方法工序复杂且难以对上述问题进行有效控制,施工质量及施工效率较低。
发明内容
本发明针对现有技术的不足,而提供一种防止复合楼盖轻质芯模上浮的施工方法。
本发明的一种防止复合楼盖轻质芯模上浮的施工方法,其特征在于,包括以下施工步骤:
步骤一,在复合楼盖板底钢筋和肋梁钢筋绑扎及预埋管线安装完成后,进行隐蔽工程验收,然后浇筑第一层混凝土;混凝土浇筑至待安装芯模的底面高度,浇筑厚度由板底钢筋保护层厚度、板底钢筋直径及其与芯模的间隙共同确定;一次浇筑,振捣密实;
步骤二,待第一层混凝土振捣完成后立即进行芯模安装;芯模直接安放在第一层混凝土上,两侧放置混凝土垫块,以保证芯模与肋梁间距;
步骤三,板面钢筋绑扎;绑扎板面钢筋时,板面纵向分布筋从肋梁顶部受力筋下部穿过,且二者绑扎牢固;板面钢筋与芯模之间放置混凝土垫块,保证二者的间距;
步骤四,待隐蔽工程验收合格后浇筑第二层混凝土;第二层混凝土直接浇筑至楼板设计标高;浇筑时从肋梁钢筋之间输送混凝土,边浇筑边振捣,确保各处混凝土均振捣密实、无空洞;浇筑完成后对混凝土表面进行收光、压实处理;
所述步骤2、步骤3及隐蔽工程验收须在第一层混凝土初凝前完成,或应进行分段施工,各段分别按以上步骤完成;各施工段之间应留设垂直施工缝,并施工缝处采取增加插筋、封堵及修凿。
所述步骤一中第一层混凝土初凝时间不宜小于4h。
本发明的有益效果是:施工工序简单,不需要额外采取芯模固定措施即可防止芯模的上浮问题,同时能防止板底出现蜂窝、麻面等问题,在确保现浇混凝土复合楼盖芯模安装施工质量满足国家规范及设计要求的同时能显著提高施工效率。
附图说明
图1为本发明的结构示意图;
图2是本发明的的施工工序流程图;
图中:第一层浇筑混凝土1-1、第二层浇筑混凝土1-2、板底钢筋1-3、板面纵向分布筋1-4、板面横向分布筋1-5、混凝土垫块1-6、芯模1-7、肋梁箍筋1-8、肋梁顶部受力筋1-9、楼盖底部模板1-10、两次浇筑混凝土的分界线1-11。
具体实施方式
下面结合附图对本发明作进一步的描述。
在图中,本发明的一种防止复合楼盖轻质芯模上浮的施工方法,包括以下施工步骤:
步骤1,在复合楼盖板底钢筋1-1和肋梁钢筋1-8及肋梁顶部受力筋1-9绑扎及预埋管线安装完成后,进行隐蔽工程验收,然后浇筑第一层混凝土1-1。第一层浇筑混凝土1-1初凝时间不宜小于4h,以保证后续工作在第一层浇筑混凝土1-1初凝前完成。第一层浇筑混凝土1-1浇筑厚度h为板底钢筋1-3保护层厚度、板底钢筋1-3的直径及其与芯模1-7的间距之和,一次浇筑,振捣密实。
步骤2,待第一层混凝土1-1振捣完成后立即进行芯模1-7安装。芯模1-7直接安放在第一层混凝土1-1上,两侧放置混凝土垫块1-6,以保证芯模1-7与肋梁箍筋1-8的间距。
步骤3,板面纵向分布筋1-4及板面横向分布筋1-5绑扎。绑扎板面纵向分布筋1-4时,板面纵向分布筋1-4从肋梁顶部受力筋1-9下部穿过,且二者应绑扎牢固。板面横向分布筋1-5与芯模1-7之间放置混凝土垫块1-6,保证二者的间距。
步骤4,待隐蔽工程验收合格后浇筑第二层浇筑混凝土1-2。第二层浇筑混凝土1-2直接浇筑至楼板设计标高。浇筑时从肋梁顶部受力筋1-9及肋梁箍筋1-8之间输送混凝土,边浇筑边振捣,确保各处混凝土均振捣密实、无空洞。浇筑完成后对第二层浇筑混凝土1-2表面进行收光、压实处理。
在现浇混凝土复合楼盖施工中按照本发明提出的施工方法可以有效解决芯模上浮、底板蜂窝、麻面及漏筋等问题。此方法施工工艺简单,施工效率高且具有较强的实用性。
以上所述仅为本发明的实施例,并非因此限制本发明的专利范围,凡是利用本发明说明书及附图内容所作的等效结构或等效流程变换,或直接或间接运用在其他相关的技术领域,均同理包括在本发明的专利保护范围内。
Claims (2)
1.一种防止复合楼盖轻质芯模上浮的施工方法,其特征在于,包括以下施工步骤:
步骤一,在复合楼盖板底钢筋和肋梁钢筋绑扎及预埋管线安装完成后,进行隐蔽工程验收,然后浇筑第一层混凝土;混凝土浇筑至待安装芯模的底面高度,浇筑厚度由板底钢筋保护层厚度、板底钢筋直径及其与芯模的间隙共同确定;一次浇筑,振捣密实;
步骤二,待第一层混凝土振捣完成后立即进行芯模安装;芯模直接安放在第一层混凝土上,两侧放置混凝土垫块,以保证芯模与肋梁间距;
步骤三,板面钢筋绑扎;绑扎板面钢筋时,板面纵向分布筋从肋梁顶部受力筋下部穿过,且二者绑扎牢固;板面钢筋与芯模之间放置混凝土垫块,保证二者的间距;
步骤四,待隐蔽工程验收合格后浇筑第二层混凝土;第二层混凝土直接浇筑至楼板设计标高;浇筑时从肋梁钢筋之间输送混凝土,边浇筑边振捣,确保各处混凝土均振捣密实、无空洞;浇筑完成后对混凝土表面进行收光、压实处理;
根据权利要求1所述的一种防止复合楼盖轻质芯模上浮的施工方法,其特征在于,所述步骤2、步骤3及隐蔽工程验收须在第一层混凝土初凝前完成,或应进行分段施工,各段分别按以上步骤完成;各施工段之间应留设垂直施工缝,并施工缝处采取增加插筋、封堵及修凿。
2.根据权利要求1所述的一种防止复合楼盖轻质芯模上浮的施工方法,其特征在于,所述步骤一中第一层混凝土初凝时间不宜小于4h。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610406507.6A CN105908883A (zh) | 2016-06-12 | 2016-06-12 | 一种防止复合楼盖轻质芯模上浮的施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201610406507.6A CN105908883A (zh) | 2016-06-12 | 2016-06-12 | 一种防止复合楼盖轻质芯模上浮的施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN105908883A true CN105908883A (zh) | 2016-08-31 |
Family
ID=56750025
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201610406507.6A Pending CN105908883A (zh) | 2016-06-12 | 2016-06-12 | 一种防止复合楼盖轻质芯模上浮的施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN105908883A (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106836597A (zh) * | 2017-03-21 | 2017-06-13 | 中国航空规划设计研究总院有限公司 | 一种空心楼板芯模固定装置及其施工方法 |
CN107338895A (zh) * | 2017-08-21 | 2017-11-10 | 深圳市道同创新科技开发有限公司 | 有肋梁带芯模的装配式空心楼盖及其施工方法 |
CN114351926A (zh) * | 2022-03-21 | 2022-04-15 | 中铁九局集团第四工程有限公司 | 一种金属方箱现浇混凝土空心楼板抗浮施工工法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007023714A (ja) * | 2005-07-21 | 2007-02-01 | Jfe Engineering Kk | 形鋼を用いた合成床版、合成床版橋又は合成桁橋、及び、その施工方法 |
CN104631677A (zh) * | 2015-01-21 | 2015-05-20 | 广东省建筑工程集团有限公司 | 超厚混凝土空心地坪分次施工工艺 |
CN104695707A (zh) * | 2015-02-13 | 2015-06-10 | 中国建筑第二工程局有限公司 | 一种现浇混凝土楼板空心管抗浮施工方法 |
CN204753935U (zh) * | 2015-06-17 | 2015-11-11 | 青岛海川建设集团有限公司 | 一种薄壁方箱抗浮施工定位结构 |
CN204960084U (zh) * | 2015-08-21 | 2016-01-13 | 上海宝冶集团有限公司 | 一种采用大截面bdf箱体的现浇空心楼板 |
CN105442736A (zh) * | 2015-12-03 | 2016-03-30 | 荣盛建设工程有限公司 | 现浇混凝土空心楼盖分段式组合装置抗浮施工方法 |
-
2016
- 2016-06-12 CN CN201610406507.6A patent/CN105908883A/zh active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2007023714A (ja) * | 2005-07-21 | 2007-02-01 | Jfe Engineering Kk | 形鋼を用いた合成床版、合成床版橋又は合成桁橋、及び、その施工方法 |
CN104631677A (zh) * | 2015-01-21 | 2015-05-20 | 广东省建筑工程集团有限公司 | 超厚混凝土空心地坪分次施工工艺 |
CN104695707A (zh) * | 2015-02-13 | 2015-06-10 | 中国建筑第二工程局有限公司 | 一种现浇混凝土楼板空心管抗浮施工方法 |
CN204753935U (zh) * | 2015-06-17 | 2015-11-11 | 青岛海川建设集团有限公司 | 一种薄壁方箱抗浮施工定位结构 |
CN204960084U (zh) * | 2015-08-21 | 2016-01-13 | 上海宝冶集团有限公司 | 一种采用大截面bdf箱体的现浇空心楼板 |
CN105442736A (zh) * | 2015-12-03 | 2016-03-30 | 荣盛建设工程有限公司 | 现浇混凝土空心楼盖分段式组合装置抗浮施工方法 |
Non-Patent Citations (3)
Title |
---|
国振喜等: "《简明建筑工程施工手册 新规范 第2版》", 30 September 2003, 机械工业出版社 * |
张晏清: "《建筑结构材料》", 29 February 2016, 同济大学出版社 * |
沈右禄: "《建筑施工1000问:第2版》", 30 April 2009, 机械工业出版社 * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN106836597A (zh) * | 2017-03-21 | 2017-06-13 | 中国航空规划设计研究总院有限公司 | 一种空心楼板芯模固定装置及其施工方法 |
CN106836597B (zh) * | 2017-03-21 | 2019-02-26 | 中国航空规划设计研究总院有限公司 | 一种空心楼板芯模固定装置及其施工方法 |
CN107338895A (zh) * | 2017-08-21 | 2017-11-10 | 深圳市道同创新科技开发有限公司 | 有肋梁带芯模的装配式空心楼盖及其施工方法 |
CN114351926A (zh) * | 2022-03-21 | 2022-04-15 | 中铁九局集团第四工程有限公司 | 一种金属方箱现浇混凝土空心楼板抗浮施工工法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106522440A (zh) | 基于聚苯颗粒纤维混凝土夹芯保温的叠合楼板及施工方法 | |
CN108086113A (zh) | 一种适用于南方湿热地区的路面预制拼装快速修补方法 | |
CN107083817A (zh) | 一种现浇混凝土竹芯楼板结构及其施工工艺 | |
CN103643795B (zh) | 扣合式木模板圆柱混凝土浇筑施工方法 | |
CN108035438A (zh) | 一种高强高延性混凝土装配式框架结构体系及连接方法 | |
CN108638324A (zh) | 一种预制箱梁的施工方法 | |
CN108343150A (zh) | 一种加腋双向张拉预应力混凝土复杂梁柱节点施工方法 | |
CN106930194B (zh) | 柱间系梁与墩柱整体成型施工方法及所用模板支架 | |
CN108661225B (zh) | 一种可调节高度的预制混凝土叠合楼板 | |
CN110080454A (zh) | Lpm轻质填充体现浇混凝土空心楼盖施工方法 | |
CN106760050A (zh) | 剪力墙与后浇筑混凝土框架梁的连接结构及贯通式处理方法 | |
CN105908883A (zh) | 一种防止复合楼盖轻质芯模上浮的施工方法 | |
CN110004791A (zh) | 一种无粘结预应力装配式道路及其施工方法 | |
CN104831932A (zh) | 一种高标号混凝土柱脚的施工工艺 | |
CN104975614B (zh) | 型钢组合式单侧支模加固施工工法 | |
CN206408515U (zh) | 预制桥墩节段拼装结构 | |
CN104074141A (zh) | 一种小半径曲线鱼腹式连续箱梁的施工方法 | |
CN103938871B (zh) | 一种采用钢筋混凝土环梁节点的钢管混凝土柱有粘结预应力框架梁结构的施工方法 | |
CN106337530B (zh) | 一种框架梁施工缝封堵的施工方法 | |
CN108775085A (zh) | 梁端连接的装配整体式混凝土框架结构及其施工方法 | |
CN106193120A (zh) | 地下室悬挑底板逆作结构及施工方法 | |
CN206917031U (zh) | 一种现浇混凝土竹芯楼板结构 | |
CN206233405U (zh) | 剪力墙与后浇筑混凝土框架梁的连接结构 | |
CN108396900A (zh) | 一种双层壳体屋面板及其施工方法 | |
CN107724241A (zh) | 一种配重施工斜拉桥桥面附属结构的施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WD01 | Invention patent application deemed withdrawn after publication | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20160831 |