CN102979312A - 一种室内蜂窝铝板吊顶反向安装工艺 - Google Patents

一种室内蜂窝铝板吊顶反向安装工艺 Download PDF

Info

Publication number
CN102979312A
CN102979312A CN2011104180955A CN201110418095A CN102979312A CN 102979312 A CN102979312 A CN 102979312A CN 2011104180955 A CN2011104180955 A CN 2011104180955A CN 201110418095 A CN201110418095 A CN 201110418095A CN 102979312 A CN102979312 A CN 102979312A
Authority
CN
China
Prior art keywords
ceiling
bolt
angle steel
board
suspended ceiling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2011104180955A
Other languages
English (en)
Other versions
CN102979312B (zh
Inventor
刘国舟
梁涛
刘子成
林朋朋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Bureau Decoration Engineering Co Ltd
Original Assignee
China Construction Eighth Engineering Division Decoration Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Decoration Co Ltd filed Critical China Construction Eighth Engineering Division Decoration Co Ltd
Priority to CN201110418095.5A priority Critical patent/CN102979312B/zh
Publication of CN102979312A publication Critical patent/CN102979312A/zh
Application granted granted Critical
Publication of CN102979312B publication Critical patent/CN102979312B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Floor Finish (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明公开了一种室内蜂窝铝板吊顶反向安装工艺,其特征包含如下步骤:1、施工平台搭设,2、测量放线,3、安装连接件及吊杆角钢,4、安装主龙骨,5、安装次龙骨,6、安装蜂窝板配套龙骨,7、反向安装蜂窝板。采用本发明具备安装效率高、施工周期短、便于调节、安全可靠且对现场文明施工、安全生产和施工质量等方面均有良好的保证。

Description

一种室内蜂窝铝板吊顶反向安装工艺
技术领域
本发明涉及到建筑工程领域的室内蜂窝铝板吊顶工程,特别涉及一种室内蜂窝铝板吊顶反向安装工艺。
背景技术
长期以来,建筑装饰工程设计追求实用、安全、经济、美观的原则在进行,并且随着国民经济的发展,装饰这一特殊性作品已经成为反映一个时代的社会经济技术水平及文化理念的载体。同时,超大超高空间的金属吊顶方式与通常吊顶有着更大的吊装难度和质量要求。
蜂窝铝板吊顶工程相对于整个装饰工程来讲,所占工程造价的比重是非常大的,传统施工方法是搭设满堂脚手架,从上到下逐层施工,施工人员在吊顶面层下方操作,吊顶完工后进行墙地面工程施工;然而采用这种传统施工方法不仅工程造价高、施工工期长,而且不能立体交叉作业,对墙地面等分部工程的交叉影响大。
发明内容
本发明的目的是解决在不搭设满堂脚手架的情况下反向安装蜂窝铝板材施工难的问题。
本发明解决其技术问题所采用的技术方案是:一种室内蜂窝铝板吊顶反向安装工艺,其特征包含如下步骤:
步骤1:施工平台搭设:在网架上悬挂电动吊篮作为操作平台;吊篮与网架采用抱箍拧固的方式连接;
步骤2:测量放线,包含以下4步:
1、利用水平仪、经纬仪或全站仪将结构轴线进行复核并施放到结构螺栓上或自控基点面上,作为原始控制线;
2、将控制线利用经纬仪向上导到螺栓球面上,用拉通钢丝的形式形成控制线;
3、根据吊顶标高控制线,弹出图纸上要求的本轴线吊顶标高线,在结构上焊接一根角钢用以固定钢丝线,使用红外线水平仪在两端螺栓球间拉一道水平定位钢丝线的另一个端点,用这条水平钢丝线来控制檩条的标高;
4、将球型网架螺栓球吊杆与控制线的误差进行分区控制,避免误差积累;
步骤3:安装连接件及吊杆角钢:连接件采用镀锌角钢,与檩托板下的高强螺栓连接;
步骤4:安装主龙骨:主龙骨与吊杆角钢通过螺栓连接,主龙骨间连接通过内置连接件用螺栓连接;
步骤5:安装次龙骨:次龙骨间连接通过内置连接件用螺栓连接,次龙骨与主龙骨通过螺栓连接,并且在每个檩条间加设两个拉杆,防止C型檩条上翼缘失稳;所有檩条搭设完成后,将施工跳板放置在次龙骨上,形成一个完整的操作平台;
步骤6:安装蜂窝板配套龙骨:蜂窝板配套龙骨由角钢吊杆与蜂窝板配套龙骨组成,角钢吊杆用螺栓与次龙骨连接,蜂窝板配套龙骨再与角钢吊杆用螺栓连接,并通过腰形孔调整龙骨的水平度;
步骤7:反向安装蜂窝板,包含以下2步:
a、安装铝型材特制吊件与压块,铝合金预埋型材与铝型材特制吊件、压块有机配合,吊件可在面板预埋型材长度方向任意定位;
b、蜂窝板材的安装,每一块吊顶板为一个安装单元,在吊顶板的边缘处设4~6个吊装点;刚刚起吊时保持板面与地面垂直,当上端到安装高度时,将另一边拉起,起吊边应选择长边,将吊顶板吊至所需高度后,用吊板挂件勾住吊顶龙骨,暂时不要将螺钉锁死,当反向安装好一排吊顶板后,通过吊顶上方高度调节螺钉将吊顶板调整到同一高度,高度调节完毕后将侧边用螺钉锁死;,所有吊顶板调整完成后,在型材的凹槽里注满封胶,然后加密封条。
根据步骤1,所述施工平台的施工荷载不超过2吨,所述网架应能够满足施工平台的施工荷载要求。
根据步骤2,所述次龙骨的间距应小于1.5m;
根据步骤6,所述水平度应控制不超过4mm;
根据步骤7的a部分,所述特制吊件上方预制螺纹孔,面板挂装在面板龙骨后,可用螺栓进行精确微调,方便了面板的水平调平。
本发明的有益效果是:采用本发明具备以下几个优势:
1、采用反向安装,提高了蜂窝铝板高空吊顶安装作业的效率,使得制作过程更加方便快捷,大大节省了施工时间,避免了脚手架的搭设和拆除,也减少了对其他施工作业的影响,具有明显的经济效益。
2、由于连接角钢上开长腰型孔,整个龙骨系统可自行调节龙骨的高度和水平平直度,方便安装,特别适合大面积水平安装。内部构件均进行热镀锌处理,龙骨表面加工相应的工艺孔,不需焊接,不需进行二次防锈处理,用螺栓直接连接,适合大型公共场所的安装要求。
3、铝合金预埋型材与铝型材特制吊件、压块的有机配合,吊件可在面板预埋型材长度方向任意定位,不受面板龙骨(L50X5镀锌角钢)位置误差的影响,保证了吊件与面板龙骨的良好吊装和精确定位,同时,压块的作用保证了吊件与蜂窝面板的吊装稳固、安全,提供了结构安全的双层保险,整套吊装系统科学、合理、操作方面快捷。
4、特制吊件上方预制螺纹孔,面板挂装在面板龙骨后,可用螺栓进行精确微调,方便了面板的水平调整。
5、反向法施工对于大跨度、高空间的项目有明显的优越性,且该施工方法对现场文明施工、安全生产和施工质量等方面均有良好的保证。
附图说明
图1是网架球节点连接示意图;
图2是主龙骨连接示意图;
图3是次龙骨连接示意图;
图4是蜂窝板安装示意图。
具体实施方式
现在结合附图对本发明作进一步详细的说明。这些附图均为简化的示意图,仅以示意方式说明本发明的基本结构,因此其仅显示与本发明有关的构成。
一种室内蜂窝铝板吊顶反向安装工艺,其特征包含如下步骤:
步骤1:施工平台搭设:在网架结构上悬挂电动吊篮作为操作平台;吊篮网架采用抱箍拧固的方式连接;所述施工平台的施工荷载不超过2吨,所述网架应能够满足施工平台的施工荷载要求;
步骤2:测量放线,包含以下4步:
1、利用水平仪、经纬仪或全站仪将结构轴线进行复核并施放到结构螺栓上或自控基点面上,作为原始控制线;
2、将控制线利用经纬仪向上导到螺栓球面上,用拉通钢丝的形式形成控制线;
3、根据吊顶标高控制线,弹出图纸上要求的本轴线吊顶标高线,在结构上焊接一根角钢用以固定钢丝线,使用红外线水平仪在两端螺栓球间拉一道水平定位钢丝线的另一个端点,用这条水平钢丝线来控制檩条的标高;
4、将球型网架螺栓球吊杆与控制线的误差进行分区控制,避免误差积累;
步骤3:安装连接件及吊杆角钢:连接件采用L110×150×7镀锌角钢,长度为200mm,与檩托板下的高强螺栓连接(如图1所示);
步骤4:安装主龙骨:主龙骨为C160×70×2.5C型钢,长度同网架球间距,主龙骨与吊杆角钢通过M12×50螺栓连接,主龙骨间连接通过内置连接件用M12x25螺栓连接(如图2所示);
步骤5:安装次龙骨:(如图3所示)次龙骨为C140×70×20×2.5C型钢,间距为1500mm,次龙骨间连接通过内置连接件用M12×25螺栓连接,次龙骨与主龙骨通过M12×50螺栓连接,并且在每个檩条间加设两个拉杆,防止C型檩条上翼缘失稳;所有檩条搭设完成后,将施工跳板放置在次龙骨上,形成一个完整的操作平台;所述次龙骨的间距应小于1.5m;
步骤6:安装蜂窝板配套龙骨:蜂窝板配套龙骨由角钢吊杆(L50×5)与蜂窝板配套龙骨(L40×4)组成,角钢吊杆用螺栓与次龙骨连接,蜂窝板配套龙骨再与角钢吊杆用螺栓连接,并通过腰形孔调整龙骨的水平度;所述水平度应控制不超过4mm;
步骤7:反向安装蜂窝板(如图4所示),包含以下2步:
a、安装铝型材特制吊件与压块,铝合金预埋型材与铝型材特制吊件、压块有机配合,吊件可在面板预埋型材长度方向任意定位;所述特制吊件上方预制螺纹孔,面板挂装在面板龙骨后,可用螺栓进行精确微调,方便了面板的水平调平;
b、蜂窝板材的安装,每一块吊顶板为一个安装单元,在吊顶板的边缘处设4~6个吊装点;刚刚起吊时保持板面与地面垂直,当上端到安装高度时,将另一边拉起,起吊边应选择长边,将吊顶板吊至所需高度后,用吊板挂件勾住吊顶龙骨,暂时不要将螺钉锁死,当反向安装好一排吊顶板后,通过吊顶上方高度调节螺钉将吊顶板调整到同一高度,高度调节完毕后将侧边用螺钉锁死;,所有吊顶板调整完成后,在型材的凹槽里注满封胶,然后加密封条。

Claims (5)

1.一种室内蜂窝铝板吊顶反向安装工艺,其特征包含如下步骤:
步骤1:施工平台搭设:在网架结构上悬挂电动吊篮作为操作平台;吊篮与网架采用抱箍拧固的方式连接;
步骤2:测量放线,包含以下4步:
1、利用水平仪、经纬仪或全站仪将结构轴线进行复核并施放到结构螺栓上或自控基点面上,作为原始控制线;
2、将控制线利用经纬仪向上导到螺栓球面上,用拉通钢丝的形式形成控制线;
3、根据吊顶标高控制线,弹出图纸上要求的本轴线吊顶标高线,在结构上焊接一根角钢用以固定钢丝线,使用红外线水平仪在两端螺栓球间拉一道水平定位钢丝线的另一个端点,用这条水平钢丝线来控制檩条的标高;
4、将球型网架螺栓球吊杆与控制线的误差进行分区控制,避免误差积累;
步骤3:安装连接件及吊杆角钢:连接件采用镀锌角钢,与檩托板下的高强螺栓连接;
步骤4:安装主龙骨:主龙骨与吊杆角钢通过螺栓连接,主龙骨间连接通过内置连接件用螺栓连接;
步骤5:安装次龙骨:次龙骨间连接通过内置连接件用螺栓连接,次龙骨与主龙骨通过螺栓连接,并且在每个檩条间加设两个拉杆,防止C型檩条上翼缘失稳;所有檩条搭设完成后,将施工跳板放置在次龙骨上,形成一个完整的操作平台;
步骤6:安装蜂窝板配套龙骨:蜂窝板配套龙骨由角钢吊杆与蜂窝板配套龙骨组成,角钢吊杆用螺栓与次龙骨连接,蜂窝板配套龙骨再与角钢吊杆用螺栓连接,并通过腰形孔调整龙骨的水平度;
步骤7:反向安装蜂窝板,包含以下两部分:
a、安装铝型材特制吊件与压块,铝合金预埋型材与铝型材特制吊件、压块有机配合,吊件可在面板预埋型材长度方向任意定位;
b、蜂窝板材的安装,每一块吊顶板为一个安装单元,在吊顶板的边缘处设4~6个吊装点;刚刚起吊时保持板面与地面垂直,当上端到安装高度时,将另一边拉起,起吊边应选择长边,将吊顶板吊至所需高度后,用吊板挂件勾住吊顶龙骨,暂时不要将螺钉锁死,当反向安装好一排吊顶板后,通过吊顶上方高度调节螺钉将吊顶板调整到同一高度,高度调节完毕后将侧边用螺钉锁死,且在所有吊顶板调整完成后,在型材的凹槽里注满封胶,然后密封条。
2.根据权利要求1所述的一种室内蜂窝铝板吊顶反向安装工艺,其特征在于,步骤1中所述施工平台的施工荷载不超过2吨,所述网架应能够满足施工平台的施工荷载要求。
3.根据权利要求1所述的一种室内蜂窝铝板吊顶反向安装工艺,其特征在于,步骤2中所述次龙骨的间距应小于1.5m。
4.根据权利要求1所述的一种室内蜂窝铝板吊顶反向安装工艺,其特征在于,步骤6中所述水平度应控制不超过4mm。
5.根据权利要求1所述的一种室内蜂窝铝板吊顶反向安装工艺,其特征在于,步骤7的a部分中所述特制吊件上方预制螺纹孔,面板挂装在面板龙骨后,可用螺栓进行精确微调,方便面板的水平调平。
CN201110418095.5A 2011-12-14 2011-12-14 一种室内蜂窝铝板吊顶反向安装工艺 Active CN102979312B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110418095.5A CN102979312B (zh) 2011-12-14 2011-12-14 一种室内蜂窝铝板吊顶反向安装工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110418095.5A CN102979312B (zh) 2011-12-14 2011-12-14 一种室内蜂窝铝板吊顶反向安装工艺

Publications (2)

Publication Number Publication Date
CN102979312A true CN102979312A (zh) 2013-03-20
CN102979312B CN102979312B (zh) 2015-01-28

Family

ID=47853634

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110418095.5A Active CN102979312B (zh) 2011-12-14 2011-12-14 一种室内蜂窝铝板吊顶反向安装工艺

Country Status (1)

Country Link
CN (1) CN102979312B (zh)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103395200A (zh) * 2013-07-24 2013-11-20 苏州凯尔博精密机械有限公司 一种生物菌培养膜焊接机用热熔装置
CN104499729A (zh) * 2014-11-28 2015-04-08 芜湖银星汽车零部件有限公司 一种拆卸台
CN105133840A (zh) * 2015-05-28 2015-12-09 南京长岛建设工程有限公司 一种双曲面吊顶的施工方法
CN108425455A (zh) * 2018-03-05 2018-08-21 中国建筑第二工程局有限公司 一种用于冷库板吊顶反装施工工艺节点及施工工法
CN108999404A (zh) * 2018-09-30 2018-12-14 中建八局装饰工程有限公司 用于高大空间中格栅吊顶的施工方法
CN110468960A (zh) * 2019-08-12 2019-11-19 兰州理工大学 一种可调节网架结点位移的支撑结构及施工方法
CN111945878A (zh) * 2020-09-08 2020-11-17 中国建筑第四工程局有限公司 一种钢网架球下挂吊重组件
CN113027140A (zh) * 2021-03-15 2021-06-25 中铁建工集团建筑安装有限公司 一种反向吊顶铝板安装方法及系统
CN114086712A (zh) * 2021-11-12 2022-02-25 中铁建设集团(杭州)建设有限公司 高大空间拼接铝单板交替式施工方法
CN114232878A (zh) * 2021-12-07 2022-03-25 上海市建筑装饰工程集团有限公司 一种无脚手架施工的超大板块蜂窝铝板吊顶安装方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07331883A (ja) * 1994-06-13 1995-12-19 Yamato:Kk 屋根の施工方法
US6082058A (en) * 1996-10-07 2000-07-04 Deng; Genghou Lifting method of building construction from top to bottom
JP2002356863A (ja) * 2001-06-01 2002-12-13 Toda Constr Co Ltd 逆打ち工法における1階床先行構築方法

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07331883A (ja) * 1994-06-13 1995-12-19 Yamato:Kk 屋根の施工方法
US6082058A (en) * 1996-10-07 2000-07-04 Deng; Genghou Lifting method of building construction from top to bottom
JP2002356863A (ja) * 2001-06-01 2002-12-13 Toda Constr Co Ltd 逆打ち工法における1階床先行構築方法

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
冯绍安: "铝合金板吊顶的施工工艺", 《广东建材》 *
卢希: "铝蜂窝板在国家数字图书馆工程中的应用", 《中国建设信息》 *
尹振宇: "长沙南站高大空间弧形吊顶单元式安装技术", 《施工技术》 *
陈成意等: "青岛体育馆屋面设计与施工技术", 《施工技术》 *

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103395200A (zh) * 2013-07-24 2013-11-20 苏州凯尔博精密机械有限公司 一种生物菌培养膜焊接机用热熔装置
CN104499729A (zh) * 2014-11-28 2015-04-08 芜湖银星汽车零部件有限公司 一种拆卸台
CN104499729B (zh) * 2014-11-28 2016-12-07 芜湖银星汽车零部件有限公司 一种拆卸台
CN105133840A (zh) * 2015-05-28 2015-12-09 南京长岛建设工程有限公司 一种双曲面吊顶的施工方法
CN108425455B (zh) * 2018-03-05 2019-12-27 中国建筑第二工程局有限公司 一种用于冷库板吊顶反装施工工艺节点及施工工法
CN108425455A (zh) * 2018-03-05 2018-08-21 中国建筑第二工程局有限公司 一种用于冷库板吊顶反装施工工艺节点及施工工法
CN108999404A (zh) * 2018-09-30 2018-12-14 中建八局装饰工程有限公司 用于高大空间中格栅吊顶的施工方法
CN110468960A (zh) * 2019-08-12 2019-11-19 兰州理工大学 一种可调节网架结点位移的支撑结构及施工方法
CN110468960B (zh) * 2019-08-12 2020-12-22 甘肃一安建设科技集团有限公司 一种可调节网架结点位移的支撑结构及施工方法
CN111945878A (zh) * 2020-09-08 2020-11-17 中国建筑第四工程局有限公司 一种钢网架球下挂吊重组件
CN113027140A (zh) * 2021-03-15 2021-06-25 中铁建工集团建筑安装有限公司 一种反向吊顶铝板安装方法及系统
CN113027140B (zh) * 2021-03-15 2022-04-12 中铁建工集团建筑安装有限公司 一种反向吊顶铝板安装方法及系统
CN114086712A (zh) * 2021-11-12 2022-02-25 中铁建设集团(杭州)建设有限公司 高大空间拼接铝单板交替式施工方法
CN114232878A (zh) * 2021-12-07 2022-03-25 上海市建筑装饰工程集团有限公司 一种无脚手架施工的超大板块蜂窝铝板吊顶安装方法

Also Published As

Publication number Publication date
CN102979312B (zh) 2015-01-28

Similar Documents

Publication Publication Date Title
CN102979312B (zh) 一种室内蜂窝铝板吊顶反向安装工艺
CN107558723B (zh) 一种斜屋面用吊篮悬挂支架制作及安装的方法
CN105804305B (zh) 波浪形金属板吊顶系统及其安装方法
CN104563494A (zh) 一种用于承插盘扣式钢管支撑架的转换支撑体系及施工工法
CN204475846U (zh) 一种用于承插盘扣式钢管支撑架的转换支撑体系
CN213329955U (zh) 一种花篮斜拉杆式悬挑脚手架
CN205742671U (zh) 一种可调解式铝板连接结构
CN205171782U (zh) 石材装饰柱间的框架幕墙系统
CN104878867A (zh) 吊顶龙骨与双层施工平台的一体化结构及其制作方法
CN102995907B (zh) 装配式单元骨架安装方法
CN204728554U (zh) 吊顶龙骨与双层施工平台的一体化结构
CN211200882U (zh) 一种钢结构转换层吊顶
CN207794379U (zh) 具有悬挑结构的单元式幕墙系统
CN103291042B (zh) 一种可三维调节的幕墙挂件
CN206844617U (zh) 一种悬挑脚手架
CN105421656A (zh) 嵌入式钢结构装配住宅外墙板安装结构
CN206636168U (zh) 一种悬挑式脚手架体系
CN215594561U (zh) 用于网架结构的超大曲面吊顶结构
CN204959995U (zh) 一种屋梁的模块化结构
CN211523694U (zh) 一种小单元体铝板竖向线条幕墙钢架系统
CN204609092U (zh) 一种组合式转换层连接件
CN203569833U (zh) 一种新型建筑外装饰保温一体化板干挂系统
CN113605581A (zh) 一种单元板块玻璃幕墙屋面及其施工方法
CN205777023U (zh) 转换层双曲面吊顶龙骨可移动定位器及吊顶系统
CN203867063U (zh) 拼装式房梁结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address

Address after: 200120 unit 06, 07, No. 28, No. 1568, Century Avenue, free trade test area, Pudong New Area, Shanghai, China (Shanghai)

Patentee after: Zhongjian eight bureau Decoration Engineering Co., Ltd.

Address before: 200136 Shanghai City Road No. 289 building 16 M.

Patentee before: China Construction Eight Engineering Division Decoration Co., Ltd.