CN102877884B - The difficult to understand grey top transformation of a kind of mine based on km directional drilling technology and construction method - Google Patents
The difficult to understand grey top transformation of a kind of mine based on km directional drilling technology and construction method Download PDFInfo
- Publication number
- CN102877884B CN102877884B CN201210348377.7A CN201210348377A CN102877884B CN 102877884 B CN102877884 B CN 102877884B CN 201210348377 A CN201210348377 A CN 201210348377A CN 102877884 B CN102877884 B CN 102877884B
- Authority
- CN
- China
- Prior art keywords
- boring
- slip casting
- understand
- directional drilling
- grey
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Investigation Of Foundation Soil And Reinforcement Of Foundation Soil By Compacting Or Drainage (AREA)
Abstract
The present invention relates to a kind of mine based on km directional drilling technology grey top difficult to understand remodeling method.It comprises the probing work using km directional drilling machine to implement mine grey top difficult to understand grout transformation, and boring is that concordant is nonlinear, and boring arranges that form can be " a hole perforate, porous bifurcated ", adopts protrusive slip casting.Austria of the present invention grey top remodeling method, solves when mining more than artesian aquifer, the safe working problem in impermeable layer thickness, insufficient strength situation.The structure of shutoff Ordovician limestone karst growth on a large scale and Hidden Fault Structures under coal mining or driving face condition can not taken, change aquiclude by the certain limit of grey for Austria top into by pervious layer, reach mineral resources that liberation threatens by artesian water and driving and back production can be implemented continuously in such circumstances, do not stay or stay less anti-(every) water coal column, improve the object of resource recovery.
Description
Technical field
The present invention relates to the difficult to understand grey top transformation of a kind of mine based on km directional drilling technology and construction method, belong to the underground construction water damage prevention and control field such as mine down-hole.
Background technology
At present in Deep Confined seam mining waterborne, the thin layer aquifer on to ash difficult to understand is had to carry out the case of grout transformation, but along with mining depth increases, hydraulic pressure constantly increases, when impermeable layer thickness when between mined bed and the Ordovician period huge thick limestone aquifer is less than safe thickness, grow because of Ordovician limestone karst and be difficult to carry out Draining hook, there is no effective safe working method at present; Have the case adopting filling method to reduce ore deposit pressure collapse dept raising effective water-resisting layer thickness, but the method still needs reserved Impermeable basement, causes ample resources to waste; Traditional tunnel or the transformation of exploiting field base plate, the number of openings is large, and hole utilization rate is low, and technical matters is complicated, and is difficult to use in the Regional of concordant on a large scale to high pressure aquifer in Ordovician limestone.
Summary of the invention
The object of the invention is for overcoming above-mentioned the deficiencies in the prior art, a kind of mine based on km directional drilling technology grey top difficult to understand remodeling method is provided, realize transforming the pre-grouting at the grey top of Austria under can realizing not taking driving and exploitation work plane condition, shutoff grey top difficult to understand karsts developing area structure and Hidden Fault Structures, increase base plate mechanical strength, the ash of the Austria in certain limit rock stratum is made to become aquiclude from pervious layer, increase water proof base plate thickness, reach the requirement that mine geological hazards specifies about water bursting coefficient, thus improve lower group coal mining rate.Meanwhile, boring the number of openings is significantly reduced, the reduction of erection time.
For achieving the above object, the present invention adopts following technical proposals:
A kind of mine based on km directional drilling technology grey top remodeling method (as Fig. 1 and Fig. 2) difficult to understand, comprising: (1) uses km directional drilling machine to implement floor grouting transformation probing, holes in the soleplate.(2) boring is that concordant is nonlinear as shown in Figure 1, can according to Practical Project Demand Design.(3) hole A, boring A-1, boring A-2, boring A-3 and A-4 as shown in Figure 1, and boring arranges that form is " a hole perforate, porous bifurcated ", and perforate order is by inside the lateral in transformation district; (4) slip casting process adopts protrusive slip casting.
Described boring is that concordant is nonlinear, can carry out radian and experiment material according to actual condition to boring, as boring A-1 ~ A-4.
Described boring arranges that form can be many bifurcateds, and every bar bifurcated drillable length can be determined according to actual condition.Spacing as the boring of Fig. 2 bifurcated is determined by grouting serous fluid dilation angle and actual condition.
Described protrusive slip casting is, in boring, water burst occurs and retreats brill, carry out slip casting.
Described boring method for arranging is a point sequence (Fig. 2), and a sequence boring of first constructing, two sequences of then constructing supplement boring, and two sequences supplement the effect that slip casting inspection and after-teeming are played in boring.Two sequence drilling constructions order (Fig. 2,1-1 → 1-6,2-1 → 2-5) are to be implemented inside the lateral in transformation region Ordovician limestone.
Described boring method for arranging, should make boring can penetrate the permeable structures such as tomography by intersect with large-angle.
The present invention also discloses a kind of mine based on km directional drilling technology grey top difficult to understand rebuilding construction method, the steps include:
(1) probing chamber position and boring position of opening is determined;
(2) water proof base plate safe thickness is calculated according to mine geological hazards relevant regulations;
(3) main borehole and bifurcated boring is designed according to grout transformation technical scheme and water proof safe thickness;
(4) design non-linear concordant data of holes drilled, data of holes drilled comprises drillable length, bifurcated and radian etc.;
(5) orifice tube is installed, and carries out pressure testing according to corresponding specification; ;
(5) drilling operation is carried out according to by the order inside lateral;
(6) in aquifer, grey top difficult to understand, all slip casting operations adopt protrusive slip casting, carry out next drilling construction after all completing to one borehole probing slip casting;
(7) use km directional drilling machine to check slip casting effect, and carry out supplementary slip casting as required.
Protrusive slip casting in the present invention is prior art, and relevant art index obtains by document, does not repeat them here.
The invention has the beneficial effects as follows: can realize not taking driving or exploiting work plane to the grout transformation at the grey top of Austria, shutoff grey top difficult to understand karsts developing area structure and Hidden Fault Structures, increase base plate mechanical strength, thus make aquifer in Ordovician limestone change water barrier into reach safe thickness, organize coal deep mining problem under solving North China type coalfield.
Accompanying drawing explanation
Fig. 1 is the base plate transformation generalized section of technical system of the present invention.
Fig. 2 is the base plate transformation floor map of technical system of the present invention.
Detailed description of the invention
Certain colliery is deep-well flood mine, and buried depth is more than 700m, and hydrostatic hydraulic pressure reaches 6Mpa, and its exploiting field floor strata (Fig. 1) is respectively: lower group coal 1, fluid-tight shale layer 2, Ordovician limestone 3.The not enough problem of the base plate safe thickness that blocks water is faced with to carry out lower group of coal mining.Grow in stope region simultaneously and have two groups of water conductive fault (water conductive fault 9,10).For carrying out grout transformation to Ordovician limestone aquifer and permeable structure, under the prerequisite ensureing Safety of Coal Mine Production, adopting technical scheme of the present invention to transform in advance exploiting field base plate, having liberated mineral resources.Implementation process is as follows:
(1) as Fig. 2, require in district dip tunnel, lay probing chamber according to engineering, to drill slip casting to stope region base plate aquifer in Ordovician limestone.
(2) slip casting adopts cement grout, design dilation angle 10 ~ 15m.A bifurcated sequence whole hole (1-1 ~ 1-6) line space design of holing of holing is between 20m ~ 30m.As shown in Figure 2, boring and water conductive fault 9 and 10 should meet intersect with large-angle and penetrate tomography in design and construction boring.
(3) after a sequence drilling construction completes, carry out two sequences and supplement drilling construction, as slip casting inspection eye and the after-teeming hole of a sequence boring.
The sequence of construction of (4) two sequence borings is carries out inside the lateral in transformation district, and a sequence the 1st is holed to the 6th boring 1-1 → 1-6; Two sequences the 1st are supplemented boring and are supplemented boring to the 5th.
(5) after each boreholes drilling slip casting all completes, next drilling construction is carried out.
(6) after probing slip casting all completes, after slurries setting and harden 7d, km directional drilling machine is adopted to carry out slip casting effect inspection according to related specifications.
(7), in borehole inspection process, single hole water yield meets mine geological hazards associated specifications, and grout transformation reaches re-set target.
Claims (3)
1., based on a mine grey top difficult to understand rebuilding construction method for km directional drilling technology, the steps include:
(1) probing chamber position and boring position of opening is determined;
(2) water proof base plate safe thickness is calculated;
(3) main borehole and bifurcated boring is designed according to grout transformation technical scheme and water proof safe thickness;
(4) design non-linear concordant data of holes drilled, parameter comprises drillable length, bifurcated and radian;
(5) orifice tube is installed, and carries out pressure testing;
(5) drilling operation is carried out according to by the order inside lateral;
(6) in aquifer, grey top difficult to understand, all slip casting operations adopt protrusive slip casting, carry out next drilling construction after all completing to one borehole probing slip casting;
(7) use km directional drilling machine to check slip casting effect, and carry out supplementary slip casting as required.
2. construction method as claimed in claim 1, is characterized in that, boring arranges that form is " a hole perforate, porous bifurcated ".
3. construction method as claimed in claim 1, it is characterized in that, boring can penetrate water conductive fault by intersect with large-angle.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210348377.7A CN102877884B (en) | 2012-09-13 | 2012-09-13 | The difficult to understand grey top transformation of a kind of mine based on km directional drilling technology and construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210348377.7A CN102877884B (en) | 2012-09-13 | 2012-09-13 | The difficult to understand grey top transformation of a kind of mine based on km directional drilling technology and construction method |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102877884A CN102877884A (en) | 2013-01-16 |
CN102877884B true CN102877884B (en) | 2016-03-16 |
Family
ID=47479374
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210348377.7A Active CN102877884B (en) | 2012-09-13 | 2012-09-13 | The difficult to understand grey top transformation of a kind of mine based on km directional drilling technology and construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102877884B (en) |
Families Citing this family (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103867229B (en) * | 2014-03-12 | 2016-05-11 | 河北煤炭科学研究院 | A kind of coal mine large-mining is dark prevents and treats comprehensive treatment method for water with lower group of coal mining |
CN104929617A (en) * | 2014-12-18 | 2015-09-23 | 安徽恒源煤电股份有限公司 | Water filling pressure test method for grouting pipelines |
CN104847379B (en) * | 2015-03-20 | 2016-01-13 | 山东科技大学 | The method of a kind of Austria grey top grouting and reinforcing floor undulation |
CN104989403B (en) * | 2015-06-02 | 2017-05-10 | 国投新集能源股份有限公司 | Method for reconstructing floor limestone aquifer into natural-artificial composite integrated aquiclude |
CN106593300A (en) * | 2016-12-02 | 2017-04-26 | 淮北矿业股份有限公司 | Thin-layer limestone ground directional drilling horizontal multi-stage branch grouting drill hole |
CN106703692A (en) * | 2016-12-02 | 2017-05-24 | 淮北矿业股份有限公司 | Method using surface orientation bedding drilling grouting to reinforce laminar limestone |
CN106948843B (en) * | 2017-03-21 | 2018-11-23 | 山东省邱集煤矿 | A kind of bilayer multiple-limb concordant bored grouting transformation dual limestone aquifer method of roof and floor |
CN108952776A (en) * | 2018-08-27 | 2018-12-07 | 山东省邱集煤矿有限公司 | A kind of method of the equidistant horizontal orientation concordant bored grouting transformation dual limestone of roof and floor |
CN110017155B (en) * | 2019-05-23 | 2020-11-06 | 合肥工业大学 | Grouting reinforcement water-proof method for water-rich gravel layer of top plate of coal face |
CN110566118B (en) * | 2019-09-09 | 2021-03-26 | 中煤科工集团西安研究院有限公司 | Advanced grouting transformation method for combined directional hole of underground deep-buried aquifer bottom plate of coal mine |
CN110486022B (en) * | 2019-09-11 | 2020-12-22 | 中煤科工集团西安研究院有限公司 | Method for determining treatment mode classification of advanced region of coal seam floor aquifer |
CN111236940B (en) * | 2020-01-14 | 2021-06-01 | 山西晋城无烟煤矿业集团有限责任公司 | Method for safely and efficiently passing reverse fault group on fully mechanized coal mining face |
CN114837556A (en) * | 2022-05-11 | 2022-08-02 | 冀中能源峰峰集团有限公司 | Double-layer water damage treatment method based on regional treatment |
CN114934757A (en) * | 2022-05-31 | 2022-08-23 | 彬县水帘洞煤炭有限责任公司 | Water spraying treatment process for underground tunneling roadway of coal seam immediate roof aquifer |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101050709A (en) * | 2006-04-03 | 2007-10-10 | 郭国政 | High water pressure releasing and blocking mining method for mining area |
CN101608552A (en) * | 2008-06-18 | 2009-12-23 | 郭国政 | The seat earth aquifer reinforces and protects the method for water barrier in reinforcing process |
CN101864763A (en) * | 2010-05-29 | 2010-10-20 | 中国二十二冶集团有限公司 | Foundation integrated processing construction method of cover type karst area |
CN102134967A (en) * | 2011-01-25 | 2011-07-27 | 煤炭科学研究总院西安研究院 | Construction method of consolidating horizontal directional drilling hole by grouting coal seam baseboard |
CN102518464A (en) * | 2011-12-09 | 2012-06-27 | 中国神华能源股份有限公司 | Method for extracting gas at corner on recovery working face in coal mine |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US8196677B2 (en) * | 2009-08-04 | 2012-06-12 | Pioneer One, Inc. | Horizontal drilling system |
-
2012
- 2012-09-13 CN CN201210348377.7A patent/CN102877884B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101050709A (en) * | 2006-04-03 | 2007-10-10 | 郭国政 | High water pressure releasing and blocking mining method for mining area |
CN101608552A (en) * | 2008-06-18 | 2009-12-23 | 郭国政 | The seat earth aquifer reinforces and protects the method for water barrier in reinforcing process |
CN101864763A (en) * | 2010-05-29 | 2010-10-20 | 中国二十二冶集团有限公司 | Foundation integrated processing construction method of cover type karst area |
CN102134967A (en) * | 2011-01-25 | 2011-07-27 | 煤炭科学研究总院西安研究院 | Construction method of consolidating horizontal directional drilling hole by grouting coal seam baseboard |
CN102518464A (en) * | 2011-12-09 | 2012-06-27 | 中国神华能源股份有限公司 | Method for extracting gas at corner on recovery working face in coal mine |
Non-Patent Citations (1)
Title |
---|
注浆改造技术在矿井防治煤层底板承压水中的应用;刘义永;《煤炭技术》;20050910;第1节和第3节 * |
Also Published As
Publication number | Publication date |
---|---|
CN102877884A (en) | 2013-01-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102877884B (en) | The difficult to understand grey top transformation of a kind of mine based on km directional drilling technology and construction method | |
CN110242301B (en) | Two-step grouting modification water-retention coal mining method for roof aquifer | |
CN102080526B (en) | Method for extracting gas from bedding level fractured well of ground coal seam roof | |
CN103557002B (en) | A kind of mechanized concentrates drop shaft filling-up method | |
CN101575983B (en) | Directional fracturing permeability improvement outburst elimination method in coal mine and device thereof. | |
CN102080518B (en) | Method for extracting gas from coal seam roof complex branched well | |
CN102635392B (en) | Co-extraction method for pillar-less coal and gas of advanced entry-retaining construction extraction engineering | |
CN112593853B (en) | Construction method for coal mine waste filling and water-reducing mining | |
CN103835729B (en) | Deep distance roadway surrounding rock pre grouting from the surface reinforcement process | |
CN100560937C (en) | A kind of thin basic rock shallow buried coal seam longwall face water retaining exploitation method | |
CN102392678A (en) | Gas drainage method combining surface and underground fracturing and permeability improvement | |
CN104863629A (en) | Method for extracting gas from separation layer below overlying strata, draining water and grouting through combined drill hole | |
CN106321025B (en) | A kind of coal and the green harmonic extraction system of oil gas and application process | |
CN112879011B (en) | Method for controlling height of water guide crack zone by hard overburden rock pre-cracking weakening under aquifer | |
CN104694746A (en) | Ion-adsorption-type rare earth in-situ leaching method and leaching system thereof | |
CN105257334A (en) | Surface drilling pressure relief gas extraction and overlying strata isolated grouting filling synchronous implementing method | |
CN103867229A (en) | Coal mine large-mining-depth and next-group coal exploitation water control comprehensive treatment method | |
CN108843343B (en) | A kind of coal mine waits for covering the grouting method of burnt rock water seal curtain on mining face | |
CN104975868A (en) | Top plate high-position boring large-diameter long-drill-hole gas extraction method based on directional drilling | |
CN104370508A (en) | Coal mine floor rock mass grouting reinforcement method and grouting slurry | |
CN106761750B (en) | Slot type recovery method is built in the longwell plane milling of half-edge coal seam longitudinal direction | |
CN104895531A (en) | Single thick coal seam ground mining well extraction process | |
CN105351001A (en) | Gas extraction method for region reinforcement of gob-side entry retaining | |
CN102226412B (en) | Underground dark mining drilling well gas extraction method | |
CN104763466A (en) | Method for detecting active diffusion radius of covered rock separation grouting filling slurry |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |